Construction Update
Prepared by Joseph Reyes, Director, Maintenance
Presented to the Board: February 4, 2014
CURRENT PROJECTS
1.
Building-S Science Building (813026)- 2013 56,690 sq. ft. Building, State of the Art Classrooms, Labs, and
Technology. State of the Art Planetarium.
October 11, 2013
December10, 2013
January 14, 2014
(FRP) Request for Proposal
Project out to rebid
Rebid Opening
2.
Building-D Elevator (840104) – 2013 An elevator will be installed on CAB north side of the building.
Currently, the elevator in CAB south is not reliable and often breaks down. The new elevator will tie into
the CAB ADA compliance work and make it easier for students coming from the main entrance, 411 Central
Avenue, to get to the second and third floors of CAB.
3.
Building-D ADA Compliance (840103)- 2013 The area on the west side of CAB will get a complete ADA
upgrade to all of the pathways. In addition, the moat, which is between the Student Center and CAB, will be
filled allowing better access between two buildings.
OCCUPIED PROJECTS IN FINAL STAGES OF COMPLETION
Alisal Building-D Technical Training Building
Alisal Campus Center for Applied Technology Building-A (in DSA close out process)
Student Services Building B (in DSA close out process)
COMPLETED PROJECTS*
Date Closed Out
October 2004
November 2005
June 2006
December 2008
February 2009
September 2010
September 2010
December 2010
June 2010
January 2011
Project Name
Campus Infrastructure Phase I
Parking Structure
Learning Resource Center (LRC)
Building-D&E Classrooms Refresh #1
Building- D&E Classrooms Refresh #2
Lighting Phase II
Building-D&E Classrooms Refresh #3
U- Pool Renovation
NE Landscape Project
Building-D&E Classrooms Refresh #4
Page 1 of 2
April 2011
August 2011
September 2011
September 2011
December 2011
December 2011
January 2012
January 2013
January 2013
April 2013
June 2013
June 2013
June 2013
June 2013
July 2013
Alisal Landscape Project
City Sidewalk Replacement
City Sidewalk Phase II
Alisal Campus Sign
Alisal Campus Bus Turnaround
Building-D & E B Boiler/Chiller and Roof
Replacement
Campus Infrastructure II
Alisal Campus Additional Parking
Student Center
Building- S Annex Demolition
Campus Safety & Security Improvements
Campus Maps & Directional Signage
Building-P PE Field House
Solar Canopy Structures, Alisal Campus
Building-D First Floor/ North Remodel
*Completed means that all of the claims and paperwork have been submitted and no further action/claims on this
project will be forthcoming from the District.
Future Projects
Building-E 1ST Floor /South
Building-N Remodel
Keyless Entry
Safety Cameras
Project
1) Building-S Science
Building
2) Building-D Elevator
Budget
% Completed
Funding Source
$28,065,000
0%
Measure H
$491,500
0%
Measure H
$541,500
0%
Measure H
3) Building-D ADA
Page 2 of 2