HARTNELL COLLEGE Construction Update Prepared by Joseph Reyes, Director, Maintenance CURRENT PROJECTS 1. 2. Technical Training Building (813028) – 2010 – Hartnell issued a request for qualifications (RFQ) for architectural services related to the design of the Technical Training Building on the Alisal Campus. A total of eight firms submitted a RFQ. A group of faculty and staff (the users of the building) met and shortlisted a total of 5 firms for interviews. The users then interviewed the firms and they selected NTD based off of previous similar project experience and cost. May 2010 Approved NTD architect firm of Salinas. January 2012 Plans submitted to (DSA) Division of State Architects. August 23, 2012 Project out for rebid. October 2, 2012 Board awarded contract to Dilbeck and Sons of Salinas, CA PE Field House (865003) – 2011 - Locker rooms, restrooms, a classroom, a training room, and concessions area. Matching funds raised by the Hartnell College Foundation. April 2011 Board awarded contract to Belli Architectural Group Firm of Salinas December 2011 Plans submitted to (DSA) Division of State Architects. July 25, 2012 Board awarded contract to Tombleson Inc of Salinas, CA August 13, 2012 . Construction started. Measure H ($1,604.000) & Foundation ($700K) Raised to date $820,000 3. CAB Building First Floor/North Remodel ( 814001) – Accommodate the following Programs, Human Resources, Vice President Academic Affairs, Deans, Trio program, and Supporting Staff. 4. CAB Elevator (814001) – will be installed on CAB north side of the building. There is currently an elevator in CAB south but it is not reliable and often breaks down. The new elevator will tie into the CAB ADA compliance work and make it easier for students coming from the main entrance, 411 Central, of the campus to get to the second and third floor of CAB. Page 1 of 3 5. CAB ADA Compliance (814001) - The area on the west side of CAB will get a complete ADA upgrade to all of the pathways. In addition the mote, which is between the Student Center and CAB will be filled which will allow for better access between two buildings. 6. Campus Signage (843003) - The campus maps for all three campuses will be updated and labeled. Once that map is completed all the building, both inside and outside, will get signage which matches maps. 7. Annex Demolition (813026)-In accordance with Facilities Master Plan, it is proposed that the existing Library/Annex 7 be demolished to provide space for a future Science Building. 7 7 . 8. Science Building (813026), 56,690 SF Building, State of the Art Classrooms, Labs, and Technology. State of the Art Planetarium. Page 2 of 3 OCCUPIED PROJECTS IN FINAL STAGES OF COMPLETION Alisal Campus Additional Parking Alisal Campus Center for Applied Technology(In DSA close out process) Student Center ( In DSA close out process) CALL Building (In DSA close out process) COMPLETED PROJECTS* Date Closed Out October 2004 November 2005 June 2006 December 2008 February 2009 September 2010 September 2010 December 2010 June 2010 January 2011 April 2011 August 2011 September 2011 September 2011 December 2011 December 2011 January 2012 Project Name Campus Infrastructure Phase I Parking Structure Learning Resource Center (LRC) CAB Refresh #1 CAB Refresh #2 Lighting Phase II CAB Refresh #3 Pool Renovation NE Landscape Project CAB Refresh #4 Alisal Landscape Project City Sidewalk Replacement City Sidewalk Phase II Alisal Campus Sign Alisal Campus Bus Turnaround CAB Boiler/Chiller and Roof Replasement Campus Infrastructure II *Completed means that all of the claims and paperwork have been submitted and no further action/claims on this project will be forthcoming from the District. FUTURE PROJECTS CAB Building First Floor/South Merrill Hall Remodel Keyless Entry Page 3 of 3