ECE 6300 TRANSMISSION SYSTEMS CONTROL SPRING 2016 PROJECT #3 DUE 03/28/2016 The single-line diagram of a 10-bus three-phase power system is shown in Fig. 1. The power system has 7 generation units, 2 345-kV lines, 7 230-kV lines, and 4 transformers. The per-unit transformer leakage reactances, transmission-line series impedances, real power generation, and real and reactive loads during heavy load periods, all on a 100 MVA system base, are given on the diagram. Fixed transformer tap settings are also shown. During light load periods, the real and reactive loads (and generation) are 25% of those shown. Bus 1 is swing/slack bus. Additional data are given in Table 1. 1 G6 3.0 2 1:1.048 G2 3.0 G7 4 7 10 1:1 6 0.013 + j0.139 0.025 + j0.151 0.031 + j0.188 0.026 + j0.159 B = 1.687 3 8 B = 0.366 B = 0.294 j0.021 j0.015 1:1.048 1:1 B = 0.309 1.21 1.94 4.0 2.5 2.0 2.0 G4 2.0 G5 0.013 + j0.139 G1 G3 B = 1.687 j0.021 0.054 + j0.325 j0.015 22 kV Buses: 2, 3 230 kV Buses: 1, 5, 6, 7, 8, 9 345 kV Buses: 4, 10 System Base = 100 MVA (3-phase) Bus 1: Swing Bus V1 = 1.0/0o p.u. Constant Voltage Magnitude Busses Bus2: V = 1.0 p.u.; -1.45 < QG < +1.45 p.u. Bus3: V = 1.0 p.u.; -1.45 < QG < +1.45 p.u. Bus8: V = 1.0 p.u.; -1.95 < QG < +1.95 p.u. B = 0.632 5 9 0.034 + j0.203 0.03 + j0.181 0.025 + j0.148 B = 0.395 B = 0.352 0.48 1.0 1.7 B = 0.287 0.97 3.5 Fig. 1 Single-line Diagram for 10-Bus Power System 2.0 0.726 1.5 Table 1 Constant Voltage Magnitude Buses Bus Voltage (p.u.) 2 3 8 1.0 1.0 1.0 System Base Quantities: (a) (b) (c) (d) (e) (f) (g) QG (p.u.) Minimum -1.45 -1.45 -1.45 Maximum +1.45 +1.45 +1.45 Sbase = 100 MVA (three-phase) Convert, where necessary, all the load, line, and voltage data into per unit using the appropriate base quantities. Determine the per-unit bus impedance matrices. Determine the per-unit bus admittance matrices. Using ETAP Simulator, create input data files: generator data, bus input data, line input data, and transformer input data. Bus 1 is the slack bus (swing bus) Using the ETAP Simulator, perform an initial power-flow solution to verify the base case system operation. Using the ETAP Simulator, determine (i) The amount of shunt power compensation required at 230- and 345-kV busses such that the voltage magnitude 0.99 < V < 1.02 p.u. at all buses during both light and heavy loads. Find two settings for the compensation, one for light and heavy loads. (ii) The amount of series compensation required during heavy loads on each 345kV line such that there is a maximum of 40o angular displacement between bus 4 and bus 10. Assume that one 345-kV line is out of service. Also assume that the series compensation is effectively distributed such that the net series reactance of each 345-kV line is reduced by the percentage compensation. Determine the percentage series compensation to within +10%. (i) A 3 single-phase AC-DC rectifiers are connected to bus 6; the original load (1.0 + j0.48 p.u.) is removed. The load carried by each rectifier (in each phase) is 100 Ω. (ii) An inductive load of 0.1 + j2.5 p.u. is connected to bus 7 (original load is removed). Using ETAP Simulator identify the magnitude of current harmonics at all the generator buses and the reactive power at bus 7. 1) Design static compensator to improve the power factor at bus 7 to 0.95, and 2) Design harmonic compensators (installed at the generator buses) to reduce the total harmonic distortion of the current at all the generator buses to 5%. Use ETAP Simulator in your design.