Pennfield MS Modular Additions and Renovations October 22, 2014 Electri-Tech, Inc. Change Order No. EC-1 Summary: COR EC-01 Electrical Service Revision In accordance with approval from PP&L electric company, change the new underground electrical service to an overhead aerial service with drop to service pole in accordance with Electri-Tech, Inc. proposal EC-01 dated 6/4/2014 in the amount of a DEDUCT of $18,525.55 COR EC-02 Additional Fire Alarm Devices & Wiring in Modular Classroom Wing In accordance with coordination with Hatfield Township, provide additional fire alarm devices and associated wiring in the new modular classroom wing per Bulletin EC-02 dated 7/21/2014 as documented by Bonnett Associates, Inc. and in accordance with Electri-Tech, Inc. proposal EC-02 dated 9/19/2014 in the amount of $1,908.37 COR EC-03 Additional Emergency Lighting & Wiring in Modular Classroom Wing In accordance with coordination with Hatfield Township, provide additional fire alarm devices and associated wiring in the new modular classroom wing per Bulletin EC-02 dated 7/21/2014 as documented by Bonnett Associates, Inc. and in accordance with Electri-Tech, Inc. proposal EC-02 dated 9/19/2014 in the amount of $2,228.61 Material Allowance Credit Credit for material allowance values not used on the project in the amount of a DEDUCT of $7,035.80. Change Order EC-1 Total: DEDUCT: $21,424.37 82 Tuckahoe Road Dorothy, NJ 08317 (Tel) 609.476.0822 (Fax) 609.476.0662 06/09/14 License #34EB01289300 To: North Penn School District Arch Job# Education Services Center Date: 401 East Hancock Street ETI Job# 06/06/14 Attention: Peter Medica, Steve Gribb, Don Schildd Lansdale. PA 19446 Re: Add. & Renov. To Pennfield M.S. Mod. Classrooms WE ARE SENDING YOU Attached _ Under separate cover via _______________________________ following items: _ Shop Drawings _ Prints _ Copy of letter X_ Change Copies Date 1 06/06/14 _ Plans Order _ Samples __See _ Specifications Detail Listed Below No. Description Change Order Request #EC-01 THESE ARE TRANSMITTED as checked below: X For approval For your use As requested _ Approved as submitted _ Approved as noted _ Returned for corrections For review and comment _ Resubmit ______________ copies for approval _ Submit _______________ copies for distribution _ Return ________________ corrected prints. _ For bids due ___________________________ 20XX _ Prints returned after loan to us REMARKS: COPY TO: 1008 SIGNED: Bill Blystone 82 TUCKAHOE ROAD DOROTHY, NJ 08317 (TEL) 609-476-0822 (FAX) 609-476-0662 LICENSE # M 832 DATE PROJECT # ETI PROJECT# CHANGE ORDER REQUEST #: EC-01 PROJECT: ADD. & RENOV. TO MODULAR CLASSROOMS AT PENNFIELD ELEMENTARY SCHOOL 06/04/14 2012129.02 1008 ADDRESS: 726 FORTY FOOT RD HATFIELD, PA 19440 ESTIMATED BY: BILL BLYSTONE SCOPE OF WORK: BULLETIN # EC-01 CHANGE UNDERGROUND PRIMARY SERVICE TO OVERHEAD AERIAL SERVICE BY PP&L. DELETE UNDERGROUND SERVICE SECONDARY AND CHANGE TO A AERIAL DROP TO SERVICE MAST BY PP&L. DEDUCT AMOUNT UNIT MATERIAL DESCRIPTION Material Per Attached Backup UNIT COST $ Sub Total Materials Sales Tax Sub Total Materials & Sales Tax Overhead & Profit @ 15 % Exempt Material Total HOURS -80 -67 LABOR CLASSIFICATION Project Manager Project Superintendent Electrical Foreman Electrical Journeymen Apprentice/Laborer Sub Total Labor Social Security & Medicare Unemployment Taxes Workman's Compensation Insurance Total Labor (PRIOR TO MARKUP) Overhead & Profit @ 15% HOURS EQUIPMENT DESCRIPTION > $300. - SEE ATTACHED LIST Sub Total Equipment Sales Tax @ 6 % Sub Total Equipment & Sales Tax Overhead & Profit @ 15 % HR. RATE TOTAL 0.00% 0.00% 0.00% $0.00 $0.00 $0.00 ($5,600.80) ($3,755.95) ($9,356.75) $0.00 $0.00 $0.00 15% TOTAL LABOR ($9,356.75) $0.00 ($9,356.75) $70.01 $56.06 RENTAL RATE TOTAL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 SUBCONTRACTS PP&L Additional Costing Sub Total Subcontracts Overhead & Profit @ 0 % TOTAL SUBCONTRACTS SUMMARY Total Material Total Labor Total Equipment Total Subcontracts SUB TOTAL LESS DEDUCTS SUB TOTAL Bond Public Liability Insurance 1.20% 0.000% TOTAL $6,411.00 $0.00 $6,411.00 $0.00 $6,411.00 ($15,579.80) ($9,356.75) $0.00 $6,411.00 ($18,525.55) $0.00 ($18,525.55) $0.00 TOTAL PROPOSAL Harold H. Stoyer / President ($15,579.80) $0.00 ($15,579.80) $0.00 ($15,579.80) TOTAL EQUIPMENT HOURS TOTAL (15,579.80) ($18,525.55) ETI Confidential Item Desc PVC SCH 40 UGRD GRC 36 GRC LG RAD ELBOW PVC COUPLING PVC END BELLS PVC ADPT/FEMALE LOCKNUT BONDING BUSHINGS-INS COPPER GROUND ROD GROUND ROD CLAMP HOLE DRILL & PATCH NYLON LINE C. Y. EXCAV-ROCKY C. Y. BACKFILL 3'' WARNING TAPE MAG. PRIMARY VAULT 7'X8'X5D HOLE/MANHOLE MANHOLE-BCKFLL&TAMP MANHOLE-GRAVEL/MH PVC SCH 40 UGRD GRC 90 ELBOW PVC END BELLS PVC ADPT/FEMALE LOCKNUT BONDING BUSHINGS-INS NYLON LINE 3/0 THHN STR CU THHN STR CU 3/0 WIRE TERM-LABOR ONLY WIRE TERM-LABOR ONLY INTERMEDIATE SPACER BASE SPACER C. Y. EXCAV-ROCKY C. Y. BACKFILL 3'' WARNING TAPE MAG. GRAND TOTAL 6/5/2014 Qty 380 40 2 4 2 2 4 2 2 2 10 420 190 190 190 1 1 1 1 240 8 8 8 16 8 400 250 1,000.00 5 20 30 30 30 30 30 Page 2 UOM FEET FEET EACH EACH EACH EACH EACH EACH EACH EACH EACH FEET CYD CYD FEET EACH EACH EACH EACH Mat Unit $ 1.57 $ 9.86 $ 352.20 $ 1.57 $ 15.81 $ 1.77 $ 2.22 $ 50.02 $ 37.34 $ 3.24 $ 4.00 $ 0.02 $ 7.50 $ $ 0.25 $ 4,000.00 $ $ $ - Mat Ext $ 596.60 $ 394.40 $ 704.40 $ 6.28 $ 31.62 $ 3.54 $ 8.88 $ 100.04 $ 74.68 $ 6.48 $ 40.00 $ 8.40 $ 1,425.00 $ $ 47.50 $ 4,000.00 $ $ $ - FEET EACH EACH EACH EACH EACH FEET FEET FEET EACH EACH EACH EACH CYD CYD FEET $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 376.80 $ 408.16 $ 126.48 $ 14.16 $ 35.52 $ 400.16 $ 8.00 $ 595.00 $ 5,760.00 $ $ $ 87.60 $ 87.60 $ 225.00 $ $ 7.50 1.57 51.02 15.81 1.77 2.22 50.02 0.02 2.38 5.76 2.92 2.92 7.50 0.25 $ 15,579.80 Lbr Unit Lbr Adj Lbr Ext 147 82 TUCKAHOE ROAD DOROTHY, NJ 08317 (TEL) 609-476-0822 (FAX) 609-476-0662 LICENSE # M 832 09/19/14 DATE PROJECT # ETI PROJECT# CHANGE ORDER REQUEST #: EC-02 PROJECT: ADD. & RENOV. TO MODULAR CLASSROOMS AT PENNFIELD ELEMENTARY SCHOOL 2012129.02 1008 ADDRESS: 726 FORTY FOOT RD HATFIELD, PA 19440 ESTIMATED BY: BILL BLYSTONE SCOPE OF WORK: Add Fire Alarm devices & wiring per A/E ADD AMOUNT UNIT MATERIAL DESCRIPTION Material Per Attached Backup UNIT COST $ Sub Total Materials Sales Tax Sub Total Materials & Sales Tax Overhead & Profit @ 15 % Exempt Material Total HOURS 6 LABOR CLASSIFICATION Project Manager Project Superintendent Electrical Foreman Electrical Journeymen Apprentice/Laborer Sub Total Labor Social Security & Medicare Unemployment Taxes Workman's Compensation Insurance Total Labor (PRIOR TO MARKUP) Overhead & Profit @ 15% HOURS EQUIPMENT DESCRIPTION > $300. - SEE ATTACHED LIST Sub Total Equipment Sales Tax @ 6 % Sub Total Equipment & Sales Tax Overhead & Profit @ 15 % TOTAL 1,125.00 $1,125.00 $0.00 $1,125.00 $168.75 $1,293.75 HR. RATE TOTAL 7.65% 10.89% 0.00% $0.00 $0.00 $0.00 $420.06 $0.00 $420.06 $32.13 $45.74 $0.00 15% TOTAL LABOR $497.94 $74.69 $572.63 $70.01 $56.06 RENTAL RATE TOTAL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTAL EQUIPMENT HOURS SUBCONTRACTS TOTAL Sub Total Subcontracts Overhead & Profit @ 0 % TOTAL SUBCONTRACTS $0.00 $0.00 $0.00 $0.00 $0.00 SUMMARY Total Material Total Labor Total Equipment Total Subcontracts SUB TOTAL LESS DEDUCTS SUB TOTAL Bond Public Liability Insurance 1.20% 1.05% $22.40 $19.60 TOTAL PROPOSAL Harold H. Stoyer / President $1,293.75 $572.63 $0.00 $0.00 $1,866.38 $0.00 $1,866.38 $1,908.37 82 Tuckahoe Road Dorothy, NJ 08317 (Tel) 609.476.0822 (Fax) 609.476.0662 License #00000832 ESTIMATE SHEET Project Name: Pennfield Modular Classrooms ETI Project No.: 1008 Arch Project No.: 2012129.02 Address: 726 Forty Foot Road CM Project No.: Hatfield, PA Estimated By: Harold H. Stoyer Date: September 19, 2014 Page 1 of 1 Scope of Work: Electri-Tech, Inc. Change Order Proposal EC-02 for / Fire Alarm Adds Description Material ¾” conduit & fittings QTY Unit Price 30’ 60 Per 00 L Labor Amount 60 00 1065 00 $ 1,125 00 QTY Hour Per Total 1 HR L 6 Wiremold & MC cable Pull Stations 3 Stobe 1 TOTAL MISCELLANEOUS AMOUNT TOTAL JOB SUMMARY TOTAL 6 82 TUCKAHOE ROAD DOROTHY, NJ 08317 (TEL) 609-476-0822 (FAX) 609-476-0662 LICENSE # M 832 09/19/14 DATE PROJECT # ETI PROJECT# CHANGE ORDER REQUEST #: EC-03 PROJECT: ADD. & RENOV. TO MODULAR CLASSROOMS AT PENNFIELD ELEMENTARY SCHOOL 2012129.02 1008 ADDRESS: 726 FORTY FOOT RD HATFIELD, PA 19440 ESTIMATED BY: BILL BLYSTONE SCOPE OF WORK: Add Emergency Lighting per A/E ADD AMOUNT UNIT MATERIAL DESCRIPTION Material Per Attached Backup UNIT COST $ Sub Total Materials Sales Tax Sub Total Materials & Sales Tax Overhead & Profit @ 15 % Exempt Material Total HOURS 12 LABOR CLASSIFICATION Project Manager Project Superintendent Electrical Foreman Electrical Journeymen Apprentice/Laborer Sub Total Labor Social Security & Medicare Unemployment Taxes Workman's Compensation Insurance Total Labor (PRIOR TO MARKUP) Overhead & Profit @ 15% HOURS EQUIPMENT DESCRIPTION > $300. - SEE ATTACHED LIST Sub Total Equipment Sales Tax @ 6 % Sub Total Equipment & Sales Tax Overhead & Profit @ 15 % TOTAL 899.40 $899.40 $0.00 $899.40 $134.91 $1,034.31 HR. RATE TOTAL 7.65% 10.89% 0.00% $0.00 $0.00 $0.00 $840.12 $0.00 $840.12 $64.27 $91.49 $0.00 15% TOTAL LABOR $995.88 $149.38 $1,145.26 $70.01 $56.06 RENTAL RATE TOTAL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTAL EQUIPMENT HOURS SUBCONTRACTS TOTAL Sub Total Subcontracts Overhead & Profit @ 0 % TOTAL SUBCONTRACTS $0.00 $0.00 $0.00 $0.00 $0.00 SUMMARY Total Material Total Labor Total Equipment Total Subcontracts SUB TOTAL LESS DEDUCTS SUB TOTAL Bond Public Liability Insurance 1.20% 1.05% $26.15 $22.89 TOTAL PROPOSAL Harold H. Stoyer / President $1,034.31 $1,145.26 $0.00 $0.00 $2,179.57 $0.00 $2,179.57 $2,228.61 82 Tuckahoe Road Dorothy, NJ 08317 (Tel) 609.476.0822 (Fax) 609.476.0662 License #00000832 ESTIMATE SHEET Project Name: Pennfield Modular Classrooms ETI Project No.: 1008 Arch Project No.: 2012129.02 Address: 726 Forty Foot Road CM Project No.: Hatfield, PA Estimated By: Harold H. Stoyer Date: September 19, 2014 Page 1 of 1 Scope of Work: Electri-Tech, Inc. Change Order Proposal EC-03 for / Emergency Lighting Adds Description Material QTY Unit Price Per Labor Amount 12-4 MC Cable w/ ground 500’ 0 86 E 430 00 12-2 MC Cable w/ ground 100’ 0 38 E 38 00 431 40 $ 899 40 Emergency Lighting & Exits 7 TOTAL MISCELLANEOUS AMOUNT TOTAL QTY Hour Per Total 1 HR L 12 JOB SUMMARY TOTAL 12