BT Group plc Cost Transformation Teach-in 5 December 2011 Agenda Introduction Tony Chanmugam Benchmarking and approach Shahzad Saleem Case studies – Broadband faults Andy Wells – Global Customer Service Ops Buchi Onwugbonu – Consumer Lead to Cash Arthur Yu Close Q&A 2 © British Telecommunications plc Tony Chanmugam BT Group plc Tony Chanmugam, Group Finance Director Cost transformation phases Phase 1 Initial phase Phase 2 Forensic phase Phase 2 Forensic phase Phase 3 Pan-BT phase Customer service delivery 4 © British Telecommunications plc Capex Labour costs including contractors Reduction in consultancy spend Supplier renegotiations Overhead Value Analysis Right First Time process re-engineering BT centric Insourcing Output based pricing Cost transformation Investing for the future A better business Cost base reduction Opex £1,243m £571m £364m Capex £1,087m £3,088m £57m £2,533m £2,590m Further cost saving opportunities £377m opex reduction in H1 2012 £16,545m H1 2012 costs £14,563m included c.£55m milestone acceleration and £35m FX/disposals £15,650m 2009 Opex Capex FX & acq'ns 2010 Opex Capex 2011 c.£2.8bn reduction in costs over two years 5 © British Telecommunications plc 2011 cost base Around a third of the cost base1 is labour cost, both direct and indirect Cost savings were made across all categories in 2011 Net labour costs 28% 33% POLOs Property & energy 5% 8% Network & IT Other 26% 1 operating costs before specific items, depreciation & amortisation and other operating income 6 © British Telecommunications plc Benchmarking Benchmarking identifies that we have further cost reduction opportunities Overall we have seen some improvement – In FY 2009, overall costs were worse than peer average – In FY 2011, overall costs were better than average, but there remains a significant gap to best – overall, BT is at lower end of second quartile Even in areas where we benchmark well, there remain many opportunities for improvement Marketing Sales Technical Network Customer services care (connectivity) operations IT services Facilities Benchmarking quartile1 1st quartile 1 FY 2011 benchmarking against telecoms peers 7 © British Telecommunications plc 2nd quartile 3rd quartile 4th quartile General & Total BT admin Cost transformation team Team objective: to deliver cost transformation by improving the efficiency and effectiveness of everything we do across the business in order to maximise long term cash generation 2005 2011 BT Retail Centric 10 internal ‘consultants’ Pan BT 30 internal ‘consultants’ Six of the original team are BT division/LoB CFOs Helen Miles Claire Watt CFO Openreach CFO Innovate & Design Shahzad Saleem Matt Davies Group Cost Transformation Director Finance Director, BT Consumer Samantha Booth Edward Briggs FD Service Infrastructure & Service Mgt Finance Director, Customer Service, Billing & Support 8 © British Telecommunications plc Dedicated cost transformation recruits Trained in consultancy tools and techniques 2-3 year assignments Strong learning & development culture – MBAs, Six Sigma, McAlinden BT Group plc Shahzad Saleem, Group Cost Transformation Director Cost transformation team model Team has evolved from a line of business focus to a team that operates across the business, with more than a third of resources focussed on end to end pan-BT activities Assignments come in from a variety of sources - Group CFO, LoB CEOs, LoB CFOs, MDs, referrals and self sourced by team Team is renowned for delivering forensic analysis within a framework which has been developed in-house over several years Improving customer service and sustainable cost reduction are at the centre of what the team does Consultants move through a four tier model as their experience grows It is an industry best model which does not have a close parallel Consultants Tier 4 Tier 3 Tier 2 Tier 1 Low/Med Med Med/High High Stakeholders & sponsors Direct report to MD MD/ direct report to MD MD Board/MD Consultant savings target £10m £15m £25m £40m Complexity & savings 10 © British Telecommunications plc Tools & techniques Root Cause Analysis Sample based testing and detailed process mapping to understand root cause of failure Benefits: increase in productivity, revenue protection, potential ‘Right First Time’ improvement Overhead Value Analysis Detailed activity-based review of an organisation Benefits: increase in productivity, removal of process inefficiency, scaleable cost base for future growth 11 © British Telecommunications plc Time of Day Analysis Quantitative analysis of inbound call volume profiles Benefits: increase in productivity, eliminates unproductive time Cost Transformation Project ‘Right First Time’ Process Review End to end process redesign, identifying improvement opportunities Benefits: increase in productivity, revised processes, ‘Right First Time’ improvement Call Handling Time Review Reduces call handling time through step by step analysis of major call types Benefits: increase in productivity, reduced call handling time, ‘Right First Time’ improvement Benchmarking Implementation Review against internal & external benchmarks to identify performance vs best practice Agree detailed implementation plan with business and monitor progress BT Group plc Broadband faults process Andy Wells Broadband faults objective & scope Objective: To identify the common capabilities and duplications of the end-toend broadband faults process to deliver pan-BT cost savings, without impacting customer service Project scope: Wholesale Retail Consumer Contact Centre Business Contact Centre Contact Centre Openreach Contact Centre Field Engineers Total c.£120m cost per annum 13 © British Telecommunications plc Operate Field Engineers Broadband faults original process Other CPs 2 Faults Customer reports fault Retail Contact Centre Faults 1 Wholesale Contact Centre 3 Faults 4 5 Openreach Contact Centre Fault Investigation Engineers Openreach Contact Centre BB Boost Engineers Operate support team Operate Engineers 6 Broadband Boost (trial) Operate home engineers Issues identified 1. Unnecessary dispatch of engineers 2. Faults sent to Wholesale in error (such as faults within customer’s own premises) 3. High volumes of internal communication due to unnecessary and ineffective status updates 14 © British Telecommunications plc 4. Insufficient engineering notes and manual process in contact centre supporting engineers 5. Multiple engineering solutions with different repeat rates 6. Inefficient communication medium (reliance on voice for updates) Broadband faults revised process Other CPs Complex faults Customer reports fault Wholesale Contact Centre Network testing call Retail Contact Centre Engineer appointing Other CPs Openreach Contact Centre BB Boost/ Fault Investigation Engineers Process improvements 1. Utilise additional procedures to actively monitor faults before engineer dispatch 2. Make Wholesale advanced diagnostic testing and profile reset functionalities available to CPs 3. Keep customer better informed by updating platform to include reliable progress status & information on major service outages 4. Standardise engineering note format 5. Allow CPs to directly appoint an engineering solution (e.g. Broadband Boost, which can resolve in-house broadband line issues) 6. Save time by switching update calls to e-chat Total forecast saving >£50m per annum 15 © British Telecommunications plc Broadband faults results & next steps Customer experience improved due to fewer initial engineering visits and lower repeat engineering visits Next steps: – Apply same revised process to Wholesale Managed Service Contracts and Global Services broadband faults – Pan-BT project on provision process started using same approach, with initial focus on bundled products 16 © British Telecommunications plc BT Group plc Global Customer Service Operations (GCSO) Buchi Onwugbonu GCSO objective & scope Objective: To identify opportunities to improve the customer experience, reduce the cost of failure and reduce the overall cost of servicing the customer Project scope: Global Customer Service Operations (GCSO) provides end to end IT management services to our customers on a global basis. This ranges from single product offerings for SME customers, to full IT management for multinationals GCSO Bespoke customer sites Standard shared services 10+ sites in scope 18 © British Telecommunications plc Service management (not in current scope) Support functions (not in current scope) GCSO approach Plan Gather Data • Agree on scope, key issues, timeline and project governance • Agree project participants, roles and responsibilities • Establish baseline headcount, including recent and planned movements • Gather volume data, reports, metrics/KPIs • Visit sites, review processes with operations team 19 © British Telecommunications plc Analyse • Analyse the teams’ activities and volumetric data • Analyse productivity, performance and other measures • Develop hypothesis and identify key issues Recommend and get signoff • Identify opportunities to improve productivity through consolidation and process improvement • Calculate total labour resource and labour cost impact • Validate with operational lead and sponsor to get sign-off GCSO high level findings & recommendations Issues Recommendations Varied approach to running diagnostics on customer queries – more time spent on low severity incidents with no impact on agreed service level Introduce job notes for running diagnostic with straightforward ‘step by step’ guide Teams working in ‘silos’ leading to excessive management and admin cover Create a centralised service desk with more bespoke 2nd and 3rd line support. Ten separate 1st line support desks combined into one Limited segregation of duties between agents or defined activities – leading to highly skilled & experienced staff carrying out low skilled standard activities Well defined responsibilities across 1st, 2nd and 3rd line agents – better alignment of skills to issues Huge disparity between productivity levels of staff Implement performance management tool to drive efficiency Multiple sites carrying out the same activities with material variation in average unit costs Consolidate and reduce number of sites – reduced from nine to two 20 © British Telecommunications plc GCSO results & next steps Improved customer service and cost reduction Reduced processing time by eliminating non value-added processes Reduced overall number of sites by consolidating work into fewer sites Introduction of automation: – Reduction in manual intervention – Quicker and easier to spot issues on customer networks and resolve them Next steps: – Complete end to end review of major customer contracts – Conduct productivity analysis of global standard/shared service operations Total saving to date >£10m per annum 21 © British Telecommunications plc BT Group plc Consumer Lead to Cash Arthur Yu Consumer Lead to Cash objective & scope Lead to Cash: The end to end process from sale through to provision Objective: To improve the Consumer Lead to Cash process by eliminating cost of failure across lines of business, reducing the cost base and, at the same time, enhancing customer service Project scope: Wholesale Retail Consumer Sales My Order Contact Centre Openreach Service Mgt Centre Service Delivery Total c.£450m cost per annum 23 © British Telecommunications plc Operate Operate Engineers Consumer Lead to Cash original process 1 2 Other CPs Broadband orders Wholesale BT Retail customer Orders Retail Consumer Sales Service Mgt Centre PSTN orders No visit required 3 Visit Openreach required Openreach Openreach Provision Workflow Systems Engineers 6 7 5 Retail – My Order 4 Faults, cancellations, system feedback Openreach Service Mgt Centre 8 Operate Engineers Issues identified 1. Broadband & PSTN order process separate 2. Wholesale unnecessarily act as ‘middle men’ in order process 3. Openreach and CP address systems not aligned 4. Unnecessary system generated updates 24 © British Telecommunications plc 5. Multiple Openreach systems/tools to manage orders 6. Unnecessary field visits due to CP ordering process 7. Too many ineffective engineering visits 8. Multiple engineering visits by both Operate & Openreach engineers Order close Consumer Lead to Cash revised process Other CPs Orders Orders BT Retail customer Orders Retail Consumer Sales Wholesale Service Mgt Centre No visit required Visit required Openreach Openreach Systems Workflow Openreach Provision Engineers Order close No touches Retail – My Order Openreach Service Mgt Centre Process improvements 5. Introduce single system order interface in Openreach 6. Work with CPs to improve order management Minimise number of Wholesale ‘touches’ processes to avoid unnecessary visits Create unified address matching capability 7. Improve Openreach engineering practice and job allocation process to reduce ineffective in Openreach to offer access to all CPs visits Improve quality of updates from 8. Openreach engineers to provide additional Openreach to CPs, and reduce value-added services, removing need for unnecessary system generated messages additional engineering visits 1. Re-design broadband and PSTN order process to enable efficient bundle sales 2. 3. 4. 25 Operate Engineers © British Telecommunications plc Consumer Lead to Cash customer experience With successful implementation, process improvements will have customer experience benefits Cycle time measures time taken to complete process >2.5m cycle time days Reduced cycle time means customer orders are saved per year completed more quickly, improving customer satisfaction Process improvements will mean fewer unnecessary and unsuccessful engineering visits Customer complaints roughly halved Re-design of sales process will enable more efficient bundle sales and lead to a better customer experience >250k fewer inbound calls per year Customers will call to check order progress if the sales process is not proceeding efficiently A more efficient sales process will lead to fewer calls Reduced churn Customers less likely to churn if their original order has been processed efficiently 26 © British Telecommunications plc Consumer Lead to Cash next steps >£50m annualised benefit to be delivered over 24 months Detailed implementation plan in place Cross line of business governance team will monitor progress against implementation plan 27 © British Telecommunications plc BT Group plc Tony Chanmugam, Group Finance Director Key points £2.8bn cost savings delivered in 2010 & 2011 £377m opex savings in H1 2012 Cost transformation team focussing on end to end processes and delivering significant cost savings Further opportunities for improvement across the business More to do 29 © British Telecommunications plc Financial strategy 2011 2013 Improve revenue trends Grow EBITDA Grow free cash flow Invest in business 30 © British Telecommunications plc Reduce net debt Support pension fund Progressive dividends BT Group plc Q&A