HABITAT IMPROVEMENT PROJECT Fishery Division ottoa :rot ....4.1t410094 SAME COMMISS101 OREGON STATE GAME COMMISSION 1634 S. W. Alder Portland 5, Oregon NUMBER 2 STATE OF OREGON OREGON STATE GAME COMMISSION P. W. Schneider, Director FEEERAL AID TO FISH RESTORATION COMPLETION REPORT Illinois Falls Fish Ladder By Donald M. Jacobson Project Engineer Robert L. Borovicka Coordinating Biologist State Oregon Project No. Date F-55-E61 March 1963 COMPLETION REPORT Illinois Falls Fish Ladder Period Covered: April 22, 1960 to June 30, 1963 ABSTRACT The construction of Illinois Falls fish ladder on the Illinois River in Oregon was completed in November 1961. Final cleanup and rock removal was completed in the fall the winter of 1961-62. of 1962. The ladder was opened and operated during The ladder was installed on a natural barrier where fish passage was delayed by low and moderately high river levels. The facility installed was a concrete vertical baffle-type fishway patterned after the Hells Gate fishway in use on the Fraser River in Canada. Since the ladder has been installed, salmon and steelhead have arrived at upper river areas much earlier than previously recorded. Concentrations of fish have not been observed below the falls. Site Location and Access Illinois Falls is approximately 12 miles northwest of Selma and is reached by a narrow access road from Highway 199. one-half mile downstream from the falls. was the only access to the falls. A road crosses the Illinois River about A trail on the south side of the river As part of the contract, it was necessary for the contractor to build an access road over large boulders and exposed bedrock to the primary work area. The road was laid over the flood plain of the river and requires annual maintenance because of water erosion. The project area is on U. S. Forest Service land in the SWi, Section 33, Township 37 South, Range 9 Wbst, W.M., within a federal power site withdrawal. A Special Use Permit was given by the U. S. Forest Service and approval was obtained from the Federal Power Commission to build on the site. Problem at the Natural Barrier Illinois Falls is on a bend of the river forming a barrier about 17.5 feet The forebay behind the falls is a deep pool and the bottom is about the high. same level as the stream bed below the falls. The pool extends upstream for approximately 600 feet where a small cascade is apparent during low flows. At the falls location, a large block of rock forms an island with the main falls on the north bank of the river and a side channel on the south. The two channels press against steep sides of the canyon with the center island some 13 to 14 feet above the low water level. Daring extremely low flows, fish arriving at the falls were attracted to and jumped at the main falls. The side channel did not pass sufficient water at low stages so the fish were blocked. start to take more water. At moderate flow the velocities and turbulence stopped fish movement until higher flows. channel was about equal. As the flows increased, the side channel would At a flow of 2,000 c.f.s.9 the flow in each Above this quantity the side channel would take slightly more water than the main channel. During these periods the fish were observed to completely ignore the main falls and pass over the side channel. The river flows vary from a low of 56 c.f.s. to a momentary high of 489600 c,f,s. From the developed hydrograph it was determined that fish passage should be aided through a range of 9,000 c,f,s. The possibility of blasting out the plug formed by the main falls and building a fishway upstream was investigated. Further engineering studies indicated that the wider area as now exists slows the velocity of the river where removing the falls would increase it through the new cut. The tail water of the falls fluctuates more than the forebay surface during 2 periods of increasing flows. surfaces. At low water there are 17.5 feet between the two At 9,000 c.f.s. the forebay rises 8 feet while the tail water rises 13.5 feet, with a difference of 12 feet. Silver salmon reach the falls about the middle of October and are followed by fall chinook, fall steelhead, and finally winter steelhead which pass as late as the middle of April. Passage is needed during most of the period. delays to migrant fish were experienced at the falls. Serious Heavy concentrations of fish in the stream below the falls caused an enforcement problem and unusually high angling success in open areas. Design Solutions A vertical baffle fishway patterned after the Hells Gate fishway on the Fraser River in Canada was designed for the falls. The high fluctuation of water levels at both the entrance and the fish exit and the velocity within the fishway would remain fairly constant through wide ranges of water levels with the vertical baffle type fishway. The location chosen for the facility was the island side of the side channel to obtain the best velocity of water for the approaching fish. A new channel was planned to be cut between the entrance of the fishway and the area just below the main falls. flow of the falls. The channel would enter at a 90. angle with the The flow from the new side channel would tend to divert most of the fish from the main falls and cause them to enter the fishway system directly. At low flows the fishway was designed to take approximately one-half of the total flow of the river. As the fish normally entered the side channel at the higher flows under the existing conditions, this was further support for the chosen location. Auxiliary water would be added to the entrance pool for attraction waters at all river flows. 3 The fishway was designed forming three sections with expansion joint materii,,I. between the sections. Sections A and C were single formed about one-half the height of the wall with dowels into the rock at this level. The remaining portions of the wall were designed as vertical beams spanning from this level to the top of the structure where the reaction was taken by an integral top beam tied into lateral beams at the baffle sections. metal grating. Roofs of the sections were covered with Section B was designed as vertical beams spanning from the floor slab to the roof slab with an integral top beam tied into lateral beams at top of the baffles. Access ports were placed in the roof slab at each pool in Section Bo This section would be submerged during moderate flows to allow more water to pass through this area of the side channel. The 24-inch auxiliary water pipe was designed to be placed below the floor slabs of Sections B and C, entering a diffusion chamber under the first pool. The floor of the first pool is metal grating, passing water at a velocity of 1/4 foot per second. Geology of the Falls LI The principal rock type in the vicinity of the Illinois River Falls is a metamorphosed basic lava, probably a basalt. There are associated interbedded metavolcanic and metasedimentary rocks including tuffs, agglomerates, sandstones, and conglomerates in the vicinity but not at the actual construction site. All of the rocks are hardened and partly recrystallized so that they have similar physical properties. ,i Report by: H. G. Schlicker and Len Ramp, visited May 18, 19600 Ublls, F. G., and others, Preliminary Geologic Map of the Kerby Quadrangle: State of Oregon, Department of Geology and Mineral Industries Map, 1948. Preliminary Geologic of Southwestern Oregon: MF 38, 1955. U. S. Geologic Survey Map The basalt at the falls is amygdaloidal and quite hard and fresh. Alteration by low-grade metamorphism appears to be mainly chloritization,silicification, and possibly saussuritization. Both calcite and quartz have been deposited in fractures. The metabasalt is massive and has a well-developed joint pattern. Closely spaced joints of varying strength cut the rock in many directions so that it breaks It was estimated that into angular blocks from 1 inch to 8 inches in dimension. overbreak would require approximately 25 per cent to 35 per cent additional concrete in floor or single-form wall construction. The joint pattern as measured is listed with the most frequent attitude and strongest direction first: Strike of Joint N N N N N N W to N 45" W to N 55. E to N 10' E to N - S 25' 60' 75' 30' 212 60' to 80' NE Vertical 60" to 85' NW 75' to 90' SE Vertical Vertical W (most frequent) W (strongest) E E - W A more detailed study of the joint pattern could probably relate the jointing to the transverse compressional stresses that caused folding in the area. The predominant trend of the fold axes is N 30° E. Construction The plans were advertized the latter part of April 1960, to be opened May 25, 1960. A site inspection trip was made May 18, 1960 by the Game Commission engin- eers, two State of Oregon geologists, and interested contractors. The proposed layout was explained on the ground as to locations, depths of rock cut, etc. by the engineers. Geologists explained the character of rock formations and what could be expected during blasting operations during excavation. Eight bids were received and the low four are listed below: Mann Construction Co. .island Construction Co. F. L. Somers Edwin Maery Redmond, Oregon Grants Pass, Oregon Medford, Oregon Salem, Oregon $83,700.00 92,960.00 93,200.00 93,500.00 The low bid of Mann Construction Company was accepted and work started June 13, 1960. The first concrete was poured in the floor slab of Section A on September 129 1960. Section A was nearly complete and the walls of Section B poured when high water breached the cofferdam and closed operations on November 16, 1960. Work was resumed the middle of August 1961 and continued to November 20, 1961. The main fishway was completed except for loose rock and debris in the lower entrance channel. The ladder was opened and operated during the winter of 196162. The contractor returned to the site in October 1962 and completed the project. Fish Passage No facilities were installed to enumerate or check the movement of fish through the new fishway. The ladder is isolated on the island during higher flows and difficult to check. Steelhead and silver salmon were found in the upper river areas at earlier dates than in previous observations. The concentration of fish below the falls that occurred before the ladder was completed no longer exist. Angler success has dropped to the lowest level ever recorded in the one-half-mile section immediately below the falls. These observations indicate that the fish are using the new facility and are not now delayed in their annual migration. Financial Statement Project approval Estimated expenditures $122,650.35 94,500.00 Submitted by: Approved by tames W. Goin (r. (' Federal Aid Coordinator Donald M. Jaz son Project Engineer Robert L. Borovxcka Coordinating Biologist 6 General view of fishway and Illinois Falls Fishway entrance A W. S. 82.03' ,5 10 - 2 3 - 5a 6RAvEL .0 r -t rr-N ?) .6 .1 \L ILLINOIS RJVEk INDEX TO DRAWINGS TITLE ATP a 13.5 SHEET SITE EA CONTOURS DAILY HYDROGRAPH EXCAVATION PROFILES 2 PLAN- SECTION "A" 6" El" PLAN-SECTION .8.8C 4 5 SECTION "A" DETAILS SECTION A. DETAILS 7 3 FISH EXIT DETAILS SECTION"Er DETAILS 6 SECTION "C" DETAILS 10 9 SECT1014-C-DETAILS B AUXILIARY WATER CHAMBER_ I I AUXILIARY PIPELINE B GRATINGS 12 IS MISCELLANEOUS METALWORK MISCELLANEOUS METALWORK 14 W.5. 85. c154,7 to 2 3 -58 e H L - AREA W5.5. TACK, W/R113 NJ oF OAK TREE. INDEX FOR TRIANGULATION P0113T5 &S. F. 5. Abast. E DISTANCE A AL 5.5, 5 I I 5' - 4" Cr 00' A 5 SCC L 5 5. 21' 13 (.' 0" STATION ". A C A C A 0 -rm. A Eva.w. A L11.02 119%2" L 96'50 Onto R 8r54' 5 L I14 52' E AAJ 11452 E 81, I." 149,0 2050' 212TACK W/RED FL A64,04 IN FOL.. 4106A TAU E F ALL STATIONS ALT W ITN WAIL IN COLIC. EXCEPT b. INDEX FOR REFERENCE POINTS STATION &S. F.S. ANGLE A B G G A D'135. Woo' 44:79. G Vas- H B C G PPE° 00' L4749. A B H L62659. 14 A G L69.12. H 0 hum LI17°30. H A I UAW DISTANT 93'2" SITE ILLINOIS FALLS 3Ci-4*" B13-91i 22-2" 73.10/c imr-sSi L15642. Imre IS ANY POINT ON It OF SECTION .C. OF FISH WAY. Oregon State Game Commission - Portland, Oregon CONTOUR. INTERVAL 2 FEET SCALE I nK1.1 20 FEET DRAWN 10-29-58 EN DtAJ ENGINEER CNICIWI IT AWT. SWICTO,.e./efre4 APR W IT MOM' PLATE" 14 i OF PLATES 1015 16 Si' POUR TO RCCK CUT 10 100 'STING BEAM C-2 12CONC.CAP SEE CCAP 2"C sct-iraEL4.11 6"M11.4.6 COMPACTED BACKFILL USE EXCAVATED MATERIAL JWALL SECTION ABOVE CONSTRUCTION JOINT MAY BE SINGLE FO AT CONTRACTORS 0 44912 45-12T.C. 44 6 -MIND CCM- SEE ethnot. RICTED BACK- JOINT 'T7 DOWELS 018"C-C. LENG,181N ROCK 4.-61.0NG, arm 1. VO.c. 31-0 WALL SECTION BELOW CONST- 0 RUCTION JOINT MUST 8E SINGLE FORMED. ACCESS NING W/STOFLCG CLOSURE ROCK FACE MUST BE FREE OF 15,3.X6.,STOFLOGS REQUIRED ALL LOOSE MATERIAL AT TIME OF POUR. &Dam Go SEE SHEET 0 AS VERT. 440IiCC 2 1110111101.1.11.6. 70 6"C.C. 401.2t.C. METAL PIPE,ASFNALT DIPPED. 2 24 fbei6GA.CORRUGATED S STOPLOGS REQUIRED Ir BAFFLE STOPLOGS -To BE INSTALLED 3X 6" TEIG, 3'..6" LONG, 15 PER BAFFLE, 240 TOTAL. 8 TYPICAL BAFFLE BAFFLE TO BE STORED 3X6 TELG, 2.9"LONG, 25 TOTAL. 2" TYPICAL BAFFLE 81 SECTION e) SCALE SCALE siI'-o" A asELET-TO BE STORED X 4.CHMENSiON, 5'.-24LONG, 75 TOTAL. 2P5 NOTE: 2N6*TBG , 2'-5"LONG, 20 TOTAL. BAFFLE STOPLOGS TO BE DOUGLAS FIR CONSTRUCTION GRADE. 2'4 BEAM C-1 TR)PLOG GUIDES ARE INSTALLED WITH ,5 FLUSH SHELLS. HOLD DOWN BRACKET FOR STOPLOGS INSTALLED WITH V'BOLT B THREADED INSERT, IONABOVE OPENING. HEIGHT 81.5 16.- 79.5 78.5 16'. lir 17'-0* 17=4' 60.5 Zsf BEAM C-3 I 2.3'7 FISH ENTRANCE To BE STORED 9.,,, 4. 1 440 IZCC. 3 ..0. 12' . teEACH i V LEG Ste. EACH LEG J. IL 4,!7.111 ILLINOIS FALLS FISHWAY SECTION "C" DETAILS SCALE TYPICAL BAFFLE SCALE ./2- Oregon State Game Commission - Portland, Oregon DINO OD. IONINI AS SHOWN DRAWN 3.17.60 BY KSL ENGINEER /4..ta)), grr',DoCry as iVtitei..4/ arer777,W, Liat;giSt PLATE OF 10 PLATES 1015