Energy and Appellate Alert June 2008 Authors: John L. Longstreth john.longstreth@klgates.com 202.661.6271 Donald A. Kaplan don.kaplan@klgates.com 202.661.6266 K&L Gates comprises approximately 1,500 lawyers in 25 offices located in North America, Europe and Asia, and represents capital markets participants, entrepreneurs, growth and middle market companies, leading FORTUNE 100 and FTSE 100 global corporations and public sector entities. For more information, visit www. klgates.com. www.klgates.com Supreme Court Reaffirms The “Mobile-Sierra” Presumption That Wholesale Electricity And Gas Contracts Are Just And Reasonable On June 26, 2008, the United States Supreme Court clarified in Morgan Stanley Capital Group Inc. v. Public Utility District No. 1 of Snohomish County the standards that the Federal Energy Regulatory Commission (FERC) must apply in determining whether to abrogate or revise contracts entered into by wholesale purchasers and sellers of natural gas or electricity. The case construed two Supreme Court decisions from 1956 that have come to be known as the “Mobile-Sierra” doctrine, and that recognize the importance of contract certainty under the Natural Gas Act (NGA) and the Federal Power Act (FPA). The Court rejected two limitations on the Mobile-Sierra doctrine that had been applied by a federal appeals court, holding that the doctrine applied: (1) to purchasers as well as sellers seeking relief from a contract, and (2) even if FERC had not reviewed the terms of the contract at the time it was made to determine if the terms were just and reasonable. The Court thus determined that a single standard applied under the doctrine: FERC must presume that the rate set out in a freely negotiated wholesale energy contract meets the “just and reasonable” requirement imposed by law, and that presumption may be overcome only if FERC concludes that the contract seriously harms the public interest. This strict “public interest” test is extremely protective of contracts and prohibits a party from seeking to avoid a contract simply because it determines that it made an improvident bargain or claims it is not getting a fair return. The Contracts at Issue The Supreme Court was reviewing cases that arose out of the California energy crisis of 2000 and 2001, when prices in the electricity spot market spiked due to a combination of natural, economic, and regulatory factors. Seeking relief from high spot market prices, buyers entered into long-term contracts whose prices were high by historical standards, but much lower than the prevailing spot market prices. When spot market prices came down, the buyers argued they should be relieved of their bargains because the contract prices were much higher than the subsequently prevailing market price or a reasonable measure of the sellers’ marginal cost, and because the market in which the contracts were entered into was “dysfunctional” as a result of the chaotic market conditions and manipulation of the spot markets by some sellers. The Ninth Circuit largely agreed, holding that Mobile-Sierra should not apply unless FERC makes an inquiry into “the market conditions in which the contracts at issue were formed,” and that market “dysfunction” is a ground for finding a contract not to be just and reasonable. The Ninth Circuit also held that a purchaser, as opposed to a seller, need show only that the price is outside a “zone of reasonableness,” and not that it is contrary to the public interest. Energy and Appellate Alert The Supreme Court Rejects the Ninth Circuit’s Limitations on the Mobile-Sierra Presumption The Supreme Court rejected the Ninth Circuit’s first limitation that Mobile-Sierra should apply only when FERC has made a prior review of market conditions. The Court held that the doctrine applies “regardless of when the contract is reviewed” because “sophisticated businesses enjoying presumptively equal bargaining power” could be expected to “negotiate a ‘just and reasonable’ rate as between the two of them.” The Court also noted that it would be anomalous to hold that the doctrine should not be enforced when there is volatility in the market, because that would discourage parties from entering into long-term contracts that could be expected to stabilize such volatility. Finally, the Court noted that “a presumption of validity that disappears when the rate is above marginal cost is no presumption of validity at all, but a reinstitution of cost-based rather than contract-based regulation.” The Court also rejected the Ninth Circuit’s second limitation – that a “zone of reasonableness” test rather than the Mobile-Sierra presumption should apply to a buyer’s challenge. In the Supreme Court’s view, the “zone of reasonableness” concept “fails to accord an adequate level of protection to contracts,” and the “standard for a buyer’s challenge must be the same, generally speaking, as the standard for a seller’s.” The Court noted that the Ninth Circuit’s limitation on the presumption gave short shrift to the fact that “contract stability ultimately benefits consumers, even if shortterm rates for a subset of the public might be high by historical standards.” The Court further found that the Ninth Circuit’s rule would be unworkable, as it would require FERC to determine the reasonableness, based on cost and other factors, of filed contracts, rather than limiting its review to the extraordinary circumstances where the public interest is affected. The Supreme Court Remands to FERC for Consideration of Two Points Although the Court disagreed with much of the Ninth Circuit’s ruling, it did agree that FERC should reconsider two points. First, it was unclear whether FERC considered only the rate the buyers were paying before the contracts went into effect, or also considered the disparity between the contract rate and the rates consumers would have paid (but for the contracts) further down the line, when the open market was no longer dysfunctional. If that disparity amounted to an “excessive burden,” then the contract challenge could be shown to have met the Mobile-Sierra public interest test. Second, FERC is to determine whether there was unfair dealing at the contract formation stage – for instance, considering traditional grounds for contract abrogation such as fraud or duress. In addition, if the “dysfunctional” market conditions under which the contract was formed were caused by the illegal action of one of the parties to the contract, the Supreme Court indicated that FERC should not apply the MobileSierra presumption. However, “the mere fact of a party’s engaging in unlawful activity in the spot market does not deprive its forward contracts of the benefit of the Mobile-Sierra presumption” – FERC must also find “a causal connection between unlawful activity and the contract rate.” Implications of the Decision The Morgan Stanley decision is striking in its endorsement of the benefits of contract stability to energy markets. The message is clear – while FERC has a role in determining if contracts are just and reasonable, its inquiry is limited to those circumstances where the public interest is plainly affected, or where one party to the contract engages in misconduct that directly affects the bargaining between the buyer and seller. There is also no support in the decision for imposing remedies against all sellers in a market based on the misconduct of certain sellers. Rather, the Court has made clear that it is the individual contracting parties’ conduct, not general market-wide conditions, that should govern FERC’s determination. This view is consistent with traditional rules of fault and liability as well as with the concern for contract stability that seemed of greatest importance to the Court. A copy of the court’s opinions is attached at the link below. The majority opinion was written by Justice Scalia (joined by Justices Kennedy, Thomas, and Alito), Justice Ginsburg concurred, and Justices Stevens and Souter dissented. http://www.supremecourtus.gov/opinions/07pdf/06-1457.pdf June 2008 | 2 Energy and Appellate Alert K&L Gates comprises multiple affiliated partnerships: a limited liability partnership with the full name Kirkpatrick & Lockhart Preston Gates Ellis LLP qualified in Delaware and maintaining offices throughout the U.S., in Berlin, in Beijing (Kirkpatrick & Lockhart Preston Gates Ellis LLP Beijing Representative Office), and in Shanghai (Kirkpatrick & Lockhart Preston Gates Ellis LLP Shanghai Representative Office); a limited liability partnership (also named Kirkpatrick & Lockhart Preston Gates Ellis LLP) incorporated in England and maintaining our London and Paris offices; a Taiwan general partnership (Kirkpatrick & Lockhart Preston Gates Ellis) which practices from our Taipei office; and a Hong Kong general partnership (Kirkpatrick & Lockhart Preston Gates Ellis, Solicitors) which practices from our Hong Kong office. K&L Gates maintains appropriate registrations in the jurisdictions in which its offices are located. A list of the partners in each entity is available for inspection at any K&L Gates office. This publication/newsletter is for informational purposes and does not contain or convey legal advice. The information herein should not be used or relied upon in regard to any particular facts or circumstances without first consulting a lawyer. Data Protection Act 1998—We may contact you from time to time with information on Kirkpatrick & Lockhart Preston Gates Ellis LLP seminars and with our regular newsletters, which may be of interest to you. We will not provide your details to any third parties. Please e-mail london@klgates.com if you would prefer not to receive this information. ©1996-2008 Kirkpatrick & Lockhart Preston Gates Ellis LLP. All Rights Reserved. June 2008 | 3