Value of Flexibility Dr. Richard de Neufville Professor of Engineering Systems and Civil and Environmental Engineering Massachusetts Institute of Technology Garage Case – Flexible Design / RdN © Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage Developed from “Valuing Options by Spreadsheet: Parking Garage Case Example,” ASCE J. of Infrastructure Systems, 2006 R. de Neufville, S. Scholtes, and T. Wang Garage Case – Flexible Design / RdN © Intended “Take-Aways” y Design for fixed objective (mission or specifications) is engineering base case y Recognizing variability => different design (because of system non-linearities) y Recognizing flexibility => even better design (it avoids costs, expands only as needed) Garage Case – Flexible Design / RdN © Value at Risk and Gain y Value at Risk and Gain (VARG) recognizes fundamental reality: value of any design can only be known probabilistically y Because of inevitable uncertainty in Future demands on system 4 Future performance of technology 4 Many other market, political factors 4 Garage Case – Flexible Design / RdN © Value at Risk and Gain Definition y Value at Risk definition: A loss that will not be exceeded at some specified confidence level 4 “We are p percent certain that we will not lose more than V dollars for this project.” 4 y Value at Gain similar – on the upside y VARG easy to see on cumulative probability distribution (see next figure) Garage Case – Flexible Design / RdN © Cumulative Probability CDF 100% 80% 60% 40% 20% 0% -400 -200 0 200 NPVA NPVB NPV 90%VAR for NPVB 10% Probability 400 600 90% VAR for NPVA y Look at distribution of NPV of designs A, B: 90% VARisk for NPVA,B are -$91, $102 4 20% VAGain for NPVA is around $210 4 Garage Case – Flexible Design / RdN © Notes y Cumulative distribution function (CDF) shows the probability that the value of a variable is < or = to quantity on x axis y VARG can be found on the CDF curve: 90% VARisk => 10% probability the value is less or equal 4 NPV corresponding to the 10% CDF is 90% VARisk 4 NPV for 90% CDF is 10% Value at Gain 4 Garage Case – Flexible Design / RdN © VAR and Flexibility y VAR is a common financial concept y It stresses downside losses, risks y However, designers also need to look at upside potential: “Value of Gain” y Flexible design provides value by both: Decreasing downside risk 4 Increasing upside potential 4 See next figure 4 Garage Case – Flexible Design / RdN © Sources of value for flexibility Cut downside ; Expand Upside Cumulative Probability Expand upside potential Original distribution Distribution with flexibility Cut downside risks Value Garage Case – Flexible Design / RdN © Excel Analysis Sequence to illustrate value of flexibility 1: Examine situation without flexibility 4 This is Base case design 2: Introduce variability (simulation) => a different design (in general) 3: Introduce flexibility => a even different and better design Garage Case – Flexible Design / RdN © Parking Garage Case y Garage in area where population expands y Actual demand is necessarily uncertain y Design Opportunity: Stronger structure enables future addition of floor(s) (flexibility) 4 Requires extra features (bigger columns, etc) 4 May cost less !!! Because can build smaller 4 y Design issue: is flexibility worthwhile? Garage Case – Flexible Design / RdN © Parking Garage Case details y Demand At start is for 750 spaces 4 Over next 10 years is expected to rise exponentially by another 750 spaces 4 After year 10 may be 250 more spaces 4 could be 50% off the projections, either way; 4 Annual volatility for growth is 10% 4 y Average annual revenue/space used = $10,000 y The discount rate is taken to be 12% Garage Case – Flexible Design / RdN © Parking Garage details (Cont) y Costs 4 annual operating costs (staff, cleaning, etc.) = $2,000 /year/space available (note: spaces used is often < spaces available) 4 Annual lease of the land = $3.6 Million 4 construction cost = $16,000/space + 10% for each level above the ground level y Site can accommodate 200 cars per level Garage Case – Flexible Design / RdN © Step 1: Set up base case Demand growth as predicted, no variability Year Demand Capacity Revenue Recurring Costs Operating cost Land leasing cost Cash flow Discounted Cash Flow Present value of cash flow Capacity costs for up to two levels Capacity costs for levels above 2 Net present value 0 $3,600,000 1 2 3 750 893 1,015 1,200 1,200 1,200 $7,500,000 $8,930,000 $10,150,000 $2,400,000 $3,600,000 $1,500,000 $1,339,286 $2,400,000 $3,600,000 $2,930,000 $2,335,778 $2,400,000 $3,600,000 $4,150,000 $2,953,888 19 20 1,688 1,696 1,200 1,200 $12,000,000 $12,000,000 $2,400,000 $3,600,000 $6,000,000 $696,641 $2,400,000 $3,600,000 $6,000,000 $622,001 $32,574,736 $6,400,000 $16,336,320 $6,238,416 Garage Case – Flexible Design / RdN © Optimal design for base case (no uncertainty) is 6 floors 10 5 0 2 3 4 5 6 7 8 9 -5 -10 -15 NUMBER OF LEVELS TRADITIONAL NPV Garage Case – Flexible Design / RdN © Step 2: Simulate uncertainty Lower demand => Loss 600 Higher demand => Gain limited by garage size 5-floor design 500 Frequency Sim ulated Mean 400 6-floor design 300 Determ inistic Result 200 100 0 -17.8 -15.6 -13.5 -11.3 -9.2 -7.0 -4.9 -2.7 -0.6 1.6 3.7 5.9 8.0 Garage Case – Flexible Design / RdN © NPV Cumulative Distributions Compare Actual (5 Fl) with unrealistic fixed 6 Fl design 1 0.9 Probability 0.8 0.7 0.6 CDF for Result of 0.5 Simulation Analysis (5- 0.4 floor) Implied CDF for 0.3 Result of 0.2 Deterministic NPV A 0.1 0 -20 -15 -10 -5 0 5 l i (6 fl 10 Garage Case – Flexible Design / RdN © ) Recognizing uncertainty => different design: 5 floors 10 5 0 2 3 4 5 6 7 8 9 -5 -10 -15 NUMBER OF LEVELS TRADITIONAL NPV RECOGNIZING UNCERTAINTY Garage Case – Flexible Design / RdN © Step 3: Introduce flexibility into design (expand when needed) Year Demand Capacity Decision on expansion Extra capacity Revenue Recurring Costs Operating cost Land leasing cost Expansion cost Cash flow Discounted Cash Flow Present value of cash flow Capacity cost for up to two levels Capacity costs for levels above 2 Price for the option Net present value 0 1 820 800 $8,000,000 2 3 924 1,044 800 1,200 expand 400 $8,000,000 $10,440,000 $1,600,000 $3,600,000 $3,600,000 $2,400,000 $3,600,000 $3,200,000 $3,600,000 $3,200,000 $3,600,000 $4,440,000 $3,160,304 $8,390,000 $974,136 $9,200,000 $953,734 $1,600,000 $3,600,000 $8,944,320 $2,800,000 -$6,144,320 $2,500,000 -$4,898,214 19 1,519 1,600 20 1,647 1,600 $15,190,000 $16,000,000 $30,270,287 $6,400,000 $7,392,000 $689,600 $12,878,287 Including Flexibility => Another, better design: 4 Fl with stronger structure enabling expansion Garage Case – Flexible Design / RdN © Summary of design results from different perspectives Perspective Deterministic Recognizing Uncertainty Simulation No Yes Option Embedded No No Incorporating Flexibilty Yes Yes Design 6 levels 5 levels 4 levels with strengthened structure Estimated Expected NPV $6,238,416 $3,536,474 $10,517,140 Why is the optimal design much better when we design with flexibility? Garage Case – Flexible Design / RdN © Sources of value for flexibility: 1) Minimize exposure to downside risk 1 0.9 Probability 0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1 0 -20 -15 -10 -5 5-Floor Design 0 5 10 4-Floor Design Garage Case – Flexible Design / RdN © Sources of value for flexibility: 2) Maximize potential for upside gain 100.0% 90.0% Mean for NPV without Flexibility 80.0% CDF for NPV with Flexibility Probability 70.0% 60.0% 50.0% 40.0% CDF for NPV without Flexibility 30.0% Mean for NPV with Flexibility 20.0% 10.0% 0.0% -20 -15 -10 -5 0 5 10 15 20 25 30 35 Garage Case – Flexible Design / RdN © Comparison of designs with and without flexibility Design Initial Investment Expected NPV Minimum Value Maximum Value Design with Flexibility Thinking Design without Flexibility thinking (4 levels, strengthened structure) (5 levels) $18,081,600 $21,651,200 $10,517,140 $3,536,474 -$13,138,168 -$18,024,062 $29,790,838 $8,316,602 Comparison Better with options Better with options Better with options Better with options Wow! Everything is better! How did it happen? Root cause: change the framing of design problem From: focus on a (mythical) forecast or set of specs To: managing (realistic) uncertainties by flexibility Garage Case – Flexible Design / RdN © Summary y Flexibility Adds great value y Sources of value for flexibility 4 Cut downside risk; Expand upside potential y VARG chart is a neat way to represent the sources of value for flexibility y Spreadsheet with simulation is a powerful tool for estimating value of flexibility Garage Case – Flexible Design / RdN ©