Construction is underway for Charlotte-Mecklenburg Storm
Water Services’ Wilora Lake Rehabilitation Project. Construction is
approximately 40% complete and on schedule.
United Construction has completed the sanitary sewer
replacement. Grading of the new pond (shaping the pond bottom
and shore) should be completed soon. In the next few months, the
old dam will be removed and replaced with a new dam. After that
the pond will be allowed to refill and disturbed areas revegetated.
For more information, please visit our website at
http://stormwater.charmeck.org and click on Storm Water
Projects, Storm Water Projects again and then Wilora Lake.
Wilora Lake pit shown with old
spillway that will be replaced with
new one.
Engineering & Property Management
Storm Water Services Division
600 East Fourth Street
Charlotte, North Carolina 28202
Wilora Lake Project Update
HIGHLIGHTS
If you have any questions, please contact one of the following
team members:
On-site Construction Inspector:
Heather O. Broome: 704-634-1039
Email: hbroome@charlottenc.gov
Construction Manager:
Gary Stansbury: 704-336-2667
E-mail: gstansbury@charlottenc.gov
Project Manager:
Greg Cole: 704-336-4647
Email: gcole@charlottenc.gov
A construction inspector will be on site daily to address any