UNDER CONSTRUCTION
NorthPark Pond
restoration
project
Dear Resident:
December 2014
Construction continues for Charlotte-Mecklenburg Storm Water
Services NorthPark Pond Restoration Project, with contractor
Ferebee Corporation completing pond improvements, including:
• Installing a new pond outlet control structure.
• Installing a new 54-inch diameter drainage pipe.
• Grading the remainder of the pond’s embankment.
• Maintaining the pond in a dewatered state as grading
work and installation of the new pond outlet control
structure continues.
Construction is expected to be complete by March 2015, after
which vegetation will be established in the disturbed areas.
For more information about this project, visit our website to view
project updates and exhibits at: stormwater.charmeck.org. Click
on Storm Water Projects drop down menu in the green bar, then
Active Projects and NorthPark Pond.
If you have any questions, please contact one of the following
project team members:
Installation of a 54-inch drainage pipe discharging
into the existing stream.
On-site Construction Inspector (New): Project Manager:
John Keene: 704-432-5216
Joel Hardison: 704-299-1994
Email: jkeene@charlottenc.gov
Email: jdhardison@charlottenc.gov
Construction Supervisor:
Frank Cantrell: 704-336-7034
Email: flcantrell@charlottenc.gov
A construction inspector is on site daily to address any questions or concerns.
Please note efforts are taken to minimize disruption to nearby properties.
Engineering & Property Management
Storm Water Services Division
600 East Fourth Street
Charlotte, North Carolina 28202