storm drainage improvement project
Dear Resident,
July 11, 2014
Charlotte-Mecklenburg Storm Water Services held its
first public meeting for the Lilly Mill Storm Drainage
Improvement Project on June 12, 2014 at St. Sarkis
Armenian Apostolic Church. The purpose of the meeting
was to discuss the real estate phase and describe the
easement process.
Meeting highlights:
• Project Manager Jackie Bray introduced the project
team, gave a brief overview of the different phases
and described the Lilly Mill channel improvements
including widening the channel, stabilization and
existing conditions.
• Greg VanHoose, engineering consultant with
Dewberry, discussed the real estate phase and the
easement packets homeowners will be receiving.
Engineering & Property Management
Storm Water Services Division
600 East Fourth Street
Charlotte, North Carolina 28202
Lilly Mill Court Project Update
HIGHLIGHTS FROM PUBLIC MEETING
YOUR STORM WATER FEES AT WORK
• VanHoose expressed the importance of easements
and let homeowners know that a contract agent
will review easements in the real estate package
with them.
• A question and answer session was held.
For more information about this project or detailed
meeting minutes, please visit our website at
stormwater.charmeck.org and click on Storm Water
Projects drop down menu in the green bar, then Active
Projects and Lilly Mill.
If you have any questions, please contact Project
Manager Jackie Bray at jbray@charlottenc.gov or
704-336-6770.