Hinsdale/Tinkerbell your storm water fees at work

advertisement
Hinsdale/Tinkerbell
s t o r m
Dear Resident:
d r a i n a g e
Meeting highlights:
• Project Manager Greg Cole introduced the project
team and gave a presentation on the project history,
boundaries and how the Hinsdale project was
selected.
• This project is in the planning phase. The phases of
the project were explained (Planning, Design, Real
Estate, Bid, Construction).
• The engineering consultant for this project is
Armstrong Glen, PC (AG).
•
•
•
AG reviewed the results of their stormwater modeling
using maps.
A question/answer session was held.
Three break-out groups were created to answer
specific questions.
For more information or detailed meeting summary, visit
our website: http://stormwater.charmeck.org. Click on
the Storm Water Projects drop down menu in the green
bar, then Active Projects and Hinsdale/Tinkerbell.
If you have any questions about this project, please
contact the Project Manager, Greg Cole at
704-336-4824 or email gcole@charlottenc.gov.
Engineering & Property Management
Storm Water Services Division
600 East Fourth Street
Charlotte, North Carolina 28202
Hinsdale/Tinkerbell Project Update
HIGHLIGHTS FROM PUBLIC MEETING
p r o j e c t
your storm water fees at work
April 19, 2013
Charlotte-Mecklenburg Storm Water Services held
a public meeting for the Hinsdale/Tinkerbell Storm
Drainage Improvement Project on March 28 at the Church
of Charlotte. The project goals are to update existing
infrastructure, reduce flooding in structures and streets,
increase channel stability and reduce erosion.
i m p r o v e m e n t