storm drainage improvement project
YOUR STORM WATER FEES AT WORK
June 3, 2010
Dear Resident,
Charlotte-Mecklenburg Storm Water Services held a public
meeting on May 3 at Cornerstone Baptist Church for the
Robinhood/Dooley Storm Drainage Improvement Project.
During the meeting proposed improvements for the previously
identified existing storm water issues were discussed. Meeting
highlights:
• Monica Kruckow, Storm Water Services Project Manager,
introduced the project team, provided general project
information and briefly reviewed the project scope and goals.
• Will Wilhelm, Project Manager for our design consultant
Kimley-Horn and Associates, Inc., reviewed the existing
drainage conditions in the entire project area and mentioned
that the problems will be addressed by maintaining the
existing characteristics of the drainage infrastructure.
• Mr. Wilhelm also discussed the proposed improvements:
o Culverts
o Pipe Systems and inlets
o Driveway pipes and ditches
o Stream channel
•
•
•
Ms. Kruckow discussed the project’s next steps which
is moving into the design phase and developing the
construction drawings for the alternative selected. These
plans are to include many details, such as pipe sizes and
locations, channel/ditch widths, utility relocations and
easement locations.
Project updates will be mailed quarterly to keep citizens
informed of progress.
A question and answer session was held.
For more information about this project or detailed meeting
minutes, please visit our website at
http://stormwater.charmeck.org and click on Storm Water
Projects, Storm Water Projects again, then Robinhood/Dooley.
If you have any questions about this project, please contact
Project Manager, Monica Kruckow at mkruckow@charlottenc.gov
or 704-336-4722.
Engineering & Property Management
Storm Water Services Division
600 East Fourth Street
Charlotte, North Carolina 28202
Robinhood/Dooley Project Update
HIGHLIGHTS FROM PUBLIC MEETING
Download