Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013 WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Agenda: • Introduce the Design-Build Team • Current Project Schedule • Design • • Project Overview (review purpose, goals & scope) • Developments since last public meeting Construction • Construction phasing\sequence, Staging Areas • Hours of work • Mitigation of Impacts • Communications program • Contact Information WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Design-Build Team Construction Contractors: Walsh Construction and McCourt Construction formed the Walsh-McCourt Joint Venture (JV1) With lead designer subconsultant HNTB Corporation Specialty Subconsultants include: • Green International Affiliates, Inc. – Survey, drainage, structural design • Shadley Associates, P.C. – Landscape Architecture • Regina Villa Associates, Inc. – Public outreach • Public Archaeology Laboratory - Cultural resources • Genesis Structures, Inc. – Erection & demolition engineering WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Current Project Schedule WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT DESIGN Project Overview & Design Developments WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Project Description & Purpose • Replace the structurallydeficient John Greenleaf Whittier Bridge carrying I95 over the Merrimack River • Improve I-95 from Exit 57 (Rte. 113) to Exit 60 by widening the roadway, improving ramp geometry, upgrading drainage & lighting systems WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Project Goals Improve safety Provide bridge that meets all current standards Improve traffic flow Improve air quality by reducing congestion Support non-motorized modes of transportation WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Overall Project Map WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT New Whittier Bridge • Network tied arch main spans • Two new parallel structures, each carrying 4 lanes plus shoulders • Shared Use Path (SUP) on NB structure with connections along approaches WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Shared Use Path WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Pine Hill (Ferry Rd) Bridge WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Evans Place (Main St) Bridge WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Rte. 110 Bridge WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Abandoned RR Bridges WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Design Changes & Refinements Since Last Public Meeting CCTV Cameras along SUP Evans Place Bridge - Alternative Superstructure Type & Span Whittier Bridge Pier Configuration Transparent barrier on NB Whittier SUP barrier Proposal to replace existing fan wall with new modular wall WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Base Technical Concept Pier Configuration Piers with vertical columns and arch supported on cantilevered cap beam WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Revised Pier Design Piers with sloping columns to provide support directly beneath arches WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Transparent Fence on Shared Use Path Barrier on the Whittier Bridge WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Relocation of Existing Wall adjacent to Laurel Road WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Existing Fan Wall Adjacent to Laurel Road WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Comparision of Alternatives WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Retaining Wall Finish WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT CONSTRUCTION Phasing/sequence, Hours of Work, Mitigation of Impacts WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Construction • Construction Phasing/Sequencing • Staging Areas • Hours of Work • Mitigation of Impacts a. Traffic\Real Time Traffic Management System b. Environmental c. Construction Noise d. Navigation channel WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Traffic Maintenance Requirements I-95 NB & SB 3 lanes to be provided during peak travel times For I-95 NB: a. Single lane closure, Monday-Thursday 7:00 PM – 5:00 PM b. Two lane closure, Monday-Thursday 10:00 PM – 7:00 AM For I-95 SB: a. Single lane closure, Monday-Thursday 9:00 AM – 6:00 AM b. Two lane closure, Monday-Thursday 9:00 PM – 6:00 AM No lane closures during holiday weekends and summer weekends WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Traffic Maintenance Requirements, cont’d Route 110 Single lane closure allowed: Monday-Friday 9:00 AM – 3:00 PM Monday-Thursday 8:00 PM – 6:00 AM All weekend (Saturday & Sunday) & holiday closures require MassDOT approval Evans Place Alternating traffic (with flaggers) allowed: Monday-Friday 9:00 AM – 3:00 PM Route 110/I-95 NB On-Ramp Shall remain open between Memorial Day & Labor Day Pine Hill Road Alternating traffic in single lane, using temporary traffic signals, until new bridge constructed (There will be exceptions to the above, which will require MassDOT approval & public notifications will be issued prior to any changes) WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Real Time Traffic Management System WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Real Time Traffic Management System WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Erection of the Whittier Bridge Approach spans become supply path for arch erection WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Erection of the Whittier Bridge Arch deck erected with Mi-Jacks Arch ribs erected with small cranes WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Erection of the Whittier Bridge Approach spans – Mi-Jacks Arch span – Mi-Jack, cranes WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Erection of the Whittier Bridge Approach spans become supply path for arch erection WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Erection of the Whittier Bridge Arch deck erected with Mi-Jacks Arch ribs erected with small cranes WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT COMMUNICATIONS PROGRAM WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Communications Program Update stakeholders on project progress • Website • E-blast updates/advisories • Social media • Press advisories • Business coordination, as necessary • Abutter/coordination meetings and briefings as necessary WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Project Website WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Project Contact Information Project website: www.mass.gov/massdot/whittierbridge Stephanie Boundy, MassDOT Public Outreach Coordinator e-mail: office phone: Stephanie.Boundy@state.ma.us (857) 368-8904 WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Thank You for Attending!