Welcome Public Meeting #5 November 21, 2011 Today’s Agenda Open House Project Overview, Schedule & Budget THE CONCEPTUAL ALTERNATIVES: AT-GRADE & SINGLE BRIDGE The Alternatives and Perspectives MEASURES OF EVALUATION Methodology and Evaluation TRAFFIC, TRAFFIC, TRAFFIC Summary of the Findings and The Simulations Next Steps Accelerated Bridge Program Opportunity • • • Current Bridge Condition Available Funding Schedule and Opportunity PLANNING STUDY 2011 DESIGN 2012 DEMOLITION AND CONSTRUCTION 2013 2014 2015 Community Involvement Throughout Project Select Alternative Design Review Construction Staging & Traffic Management Phasing Meetings 2016 The Partnership MassDOT – Highway and Transit Department of Conservation & Recreation (DCR) City of Boston Consultant Team Working Advisory Group (WAG) Planning & Design Process Public Process – Objectives & Schedule Planning Study Schedule PUBLIC MEETINGS 1 2 EXISTING CONDITIONS APR 3 SELECTION CRITERIA & INITIAL CONCEPTS MAY CONCEPT DEVELOPMENT JUN 5 4 JUL ALTERNATIVES EVALUATION AUG SEP Working Group Meetings = 20 6 Draft ALTERNATIVES OCT NOV DEC Planning Study Meeting Schedule Meeting 1 Project Purpose, Goals and Existing Conditions Meeting 2 Issues & Opportunities, Evaluation Criteria, 2035 Traffic Projections, Framework for Design Elements Meeting 3 Development of Design Concepts, Refinement of Evaluation Criteria Meeting 4 Develop Draft Alternatives, Finalize Evaluation Criteria (MOEs) Meeting 5 Conceptual Alternatives, Applied MOEs and Traffic Analysis Meeting 6 Recommended Alternative and Next Steps Visualizing the Future Perspectives View 1 Arborway Yard towards Courthouse VIEW 1 EXISTING View 1 Arborway Yard towards Courthouse AT GRADE BRIDGE View 2 Southwest Corridor Park towards Forest Hills Station VIEW 2 EXISTING View 2 Southwest Corridor Park towards Forest Hills Station AT GRADE BRIDGE View 3 New Washington Street corridor looking east VIEW 3 EXISTING View 3 New Washington Street corridor looking east AT GRADE BRIDGE View 4 South Street towards Arnold Arboretum VIEW 4 EXISTING View 4 South Street towards Arnold Arboretum AT GRADE BRIDGE View 5 New Washington Street Corridor – Easterly between Hyde Park Avenue and Shea VIEW 5 EXISTING View 5 New Washington Street Corridor – Easterly between Hyde Park Avenue and Shea AT GRADE BRIDGE View 6 Corner of Morton and Hyde Park Avenue – Northwest toward SW Corridor Park VIEW 6 EXISTING View 6 Corner of Morton and Hyde Park Avenue – Northwest toward SW Corridor Park AT GRADE BRIDGE Livability: Objectives and Experience Changing Looking-Out to …. Today, the orientation is looking away from the corridor. With the removal of the Casey Overpass we face a choice: Replace it with an at-grade solution or put back a bridge. Look at some local Boston examples where elevated infrastructure was removed and the transformation that has occurred. Two urban design concepts that are common to examples. …. Looking-In The opportunity is here to change that and to create a center for Forest Hills. Object versus Space Change the focus from the viaduct to the surrounding area. City Square, Charlestown The elevated Orange Line and the approach to the Mystic Bridge discouraged redevelopment in City Square. City Square, Charlestown Removing the elevated created the opportunity for redevelopment around City Square. City Square, Charlestown Today, City Square is an inviting and welcoming asset to the neighborhood. It did not happen all at once and is still going on. Central Artery – Downtown Boston One of the lessdesirable locations in the downtown. Central Artery – Downtown Boston Properties abutting the artery corridor are reorienting toward it and activating its edges. Central Artery – Downtown Boston Properties abutting the artery corridor are reorienting toward it and activating its edges. Spaces that were once considered left over, are now programmed with active uses. Washington Street, South End The aging infrastructure was a blight to the neighborhood. Washington Street, South End Removal of the elevated Orange Line created the opportunity for redevelopment. With the object in the center gone, the edges became what defined the space… … And helped create a vibrant street life. Forest Hills Like some of the examples shown – the elevated infrastructure in Forest Hills is going The elevated Orange Line and Commuter Rail tracks have been relocated. The last elevated structure – the Casey Overpass – is coming down. We have seen some example of how the effects of bridges over public spaces can be mitigated, but… No one says, “Let’s put a bridge in that space to improve it.” Spaces under bridges are not inherently places people flock to. They are places people pass through but do not congregate in. An at-grade solution will provide the opportunity for a transformation process similar to what we have seen in other locations. With a bridge alternative that transformation is unlikely to ever happen. The Conceptual Alternatives At-Grade and Single Bridge At-Grade Conceptual Alternative DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED The Experience - New Washington Street Relocated Orange Line Head house Olmsted tree line boulevard Off street bike lanes connect to and cross at intersections Area for community gathering Bus #39 remains at current location passenger loading at intersection On street bike lanes Area for crossings – approx 20’ wide for bikes and pedestrians Landscaped median allows for minimal plantings in this section At-Grade Alternative – To further explore in 25% design Examine adding flexibility for Bus #39 by using Plaza area in front of Forest Hills station DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED At-Grade Alternative – To further explore in 25% design Allocation of uses for taxi and drop off areas (space preserved) DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED At-Grade Alternative – To further explore in 25% design Landscaping & Lighting Treatments DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED At-Grade Alternative – To further explore in 25% design Non-Peak Hour Treatments (e.g., signalization) Signalization, right turn lanes (pedestrian and transit), and detailed intersection geometry DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED At-Grade Alternative – To further explore in 25% design Bike accommodations on Washington Street – northern side of Ukraine DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED At-Grade Alternative – To further explore in 25% design Treatment of Asticou and Forest Hills Street DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED Interchangeable with Shea Circle design Bridge Conceptual Alternative DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED The Experience - New Washington Street Bus #39 remains at current location passenger loading at intersection Regional vehicular traffic located above Area for community gathering Off street Bike lanes connect to and cross at intersections On street bike lanes Usable contiguous open space connections Area for crossings – approx 20’ wide for bikes and pedestrians Bridge Alternative – To further explore in 25% design: Design of piers, under bridge area, and lighting DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED Bridge Alternative – To further explore in 25% design: Examine adding flexibility for Bus #39 by using Plaza area in front of station DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED Bridge Alternative – To further explore in 25% design: Landscaping and lighting treatments DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED Bridge Alternative – To further explore in 25% design: Treatment of Forest Hills Road Signalization,and rightintersection turn lanes Signalization (pedestrian and transit), and turning movements detailed intersection geometry DESIGNER GENERAL’S WARNING: THE DESIGN SHOWN HERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE HARD LINE FINISHED STYLE RESULTING FROM THE SOFTWARE PROGRAMS USED Measures of Evaluation (MOEs) Livability & Mobility The Evaluation The Evolution of the MOEs 1. Approach taken to Casey’s MOEs a. All modes, livability objectives, new measures 2. WAG integral to the formation and evolution of the MOEs a. Principles (fatal flaw), Goals, Objectives and Measures 3. MOEs used throughout the process and to evaluate alternatives on their own merits a. MOEs shaped the alternatives (i.e., surface streets redesigned for all alternatives – rendering some MOEs obsolete) MOEs – The Distribution MOEs Mobility Livability Goals 3 3 Objectives 9 7 Measures 16 15 Applied to Existing Conditions and both Conceptual Alternatives The MOEs – Existing Conditions Mobility Goals Total Score = -10 1. Convoluted and Confusing Street network 2. Complicated connections for Bikes and Pedestrians 3. Limited visible connections to businesses, resources and neighborhoods 4. No coherent, systematic organization of access for modes and users The MOEs – Existing Conditions Livability Goals Total Score = -10 1. 2. 3. 4. 5. Haphazard integration of open space and historical resources Emerald Necklace Interrupted No “There” there for community connections or activities to center upon. Outward focused Obstructed visible connections to Boston’s historic open space resources Unclear order and use of space The MOEs – Bridge Conditions Mobility Goals Total Score = 3 1. 2. 3. 4. Better organized roadways, intersections, pedestrian and bike crossings and circulation North/south connections improved through intersection treatments Limited off-street bike improvements and connections (only east/west direction) MBTA bus operations not addressed – no change from today The MOEs – Bridge Conditions Livability Goals Total Score = 0 1. 2. 3. 4. Improved plantings and landscape treatments along the New Washington Street Corridor Barrier to open space historic resources modified for select areas Emerald Necklace not restored as southwest to northeast views obstructed Limited areas to create a focal point for activities The MOEs – At-Grade Conditions Mobility Goals Total Score = 7 1. 2. 3. 4. 5. Better organized roadways and intersections Less congestions and conflicts for vehicles, pedestrians and bikes Improved pedestrian and bike crossings and circulation both east/west and north/south Improved use of MBTA bus operations and staging areas (Upper Busway) Focal Areas created for simplified crossings and access to historic open space resources The MOEs – At-Grade Conditions Livability Goals Total Score = 13 1. 2. 3. 4. Better organized open space network creating opportunities for gateways and recognition of historic resources Emerald Necklace Restored View sheds restored – visual access to open space, neighborhood, business, and recreational resources Increased landscaping and areas for activities Traffic, Traffic, Traffic Traffic Design Goals •Improve Safety •Improve Pedestrian and Bicycle Accommodations •Enhance Transit Connections •Provide Acceptable Vehicular Traffic Operations Urban Design Goals •Place Making Opportunities •Landscaping •View Corridors Top 5 Areas of Concern Today Top 5 Areas of Concern Today Shea Circle • Too many entry/conflict points • Hostile to pedestrians and bikes • Above average crash rates Shea Circle • Treatment independent of the selected alternative • Number of entry points reduced • Additional Improvements are compatible with both alternatives DRAFT WORK IN PROGRESS BRIDGE ALTERNATIVE (STREET VIEW) Shea Circle • Treatment independent of the selected alternative • Number of entry points reduced • Additional Improvements are compatible with both alternatives DRAFT WORK IN PROGRESS BRIDGE ALTERNATIVE (STREET VIEW) AT-GRADE ALTERNATIVE Top 5 Areas of Concern Today South/Arborway/New Washington • Confusing intersection geometry • Closely spaced signals • Signal coordination difficulties South/Arborway/New Washington • Intersection geometry improved • Pedestrian accommodations improved DRAFT WORK IN PROGRESS BRIDGE ALTERNATIVE (STREET VIEW) South/Arborway/New Washington • Intersection geometry improved • Pedestrian accommodations improved • At-Grade provides additional enhancements: • Improvements along South/Washington Street • Relocated bus access DRAFT WORK IN PROGRESS BRIDGE AT-GRADE ALTERNATIVE ALTERNATIVE (STREET VIEW) Top 5 Areas of Concern Today New Washington-Mid Block • Closely spaced signals • Pedestrian signal complicates operation • Pick-up/drop-off congestion New Washington-Mid Block • Mid block pedestrian crossing relocated DRAFT WORK IN PROGRESS BRIDGE ALTERNATIVE (STREET VIEW) New Washington - Mid Block • Mid block pedestrian crossing relocated • At-Grade provides additional enhancements: • Relocated head house • Enhanced connection to Southwest Corridor DRAFT WORK IN PROGRESS AT-GRADE ALTERNATIVE BRIDGE ALTERNATIVE (STREET VIEW) Top 5 Areas of Concern Today Hyde Park/New Washington • Confusing intersection geometry • Missing pedestrian connections • No bicycle accommodations Hyde Park/New Washington • Intersection geometry improved • Pedestrian accommodations improved DRAFT WORK IN PROGRESS BRIDGE ALTERNATIVE (STREET VIEW) Hyde Park/New Washington • Intersection geometry improved • Pedestrian accommodations improved DRAFT WORK IN PROGRESS BRIDGE AT-GRADE ALTERNATIVE ALTERNATIVE (STREET VIEW) Top 5 Areas of Concern Today Asticou/Washington • Pick-up/drop-off and taxi activity • No bicycle accommodations • Busway/South St signal Asticou/Washington • No alteration with Bridge Alternative DRAFT WORK IN PROGRESS BRIDGE ALTERNATIVE (STREET VIEW) Asticou/Washington • At-Grade provides additional enhancements: • Improvements along Washington Street • Improved curb side loading areas • Relocated bus facility DRAFT WORK IN PROGRESS BRIDGE ALTERNATIVE (STREET VIEW) AT-GRADE ALTERNATIVE Overview of Existing Traffic Operations Existing Surface Roadways: •Confusing and Congested •Poor Pedestrian and Bicycle Accommodations •Limited Curbside Loading/Unloading •Closely Spaced Intersections Difficult to Manage •Significant Queuing through Adjacent Intersections •Multiple Conflict Points in Shea Circle Traffic Count Locations INTERSECTIONS TRAFFIC SIGNALS Defining the Peak Periods Casey Overpass and New Washington Street Combined Hourly Volumes (east-west) 3500 3000 2500 2000 1500 1000 500 0 12:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 AM AM AM AM AM AM AM AM AM AM AM AM PM PM PM PM PM PM PM PM PM PM PM PM 2035 Volume Projections CTPS regional model • Multi-modal model • Regional model • Calibrated based on current counts BRA local development parcels • 8 local development parcels • Traffic volumes and distribution per BTD standards 2035 Traffic Analysis • Based on Peak Hour for original alternatives (single-bridge and at-grade bow tie) – Worst Case • Not adjusted for: – – – – Median widths Non-peak design changes Bow-tie location adjustments Signalization refinements All modes are accommodated better in the future Comparison Today with Bridge and At-Grade Alternatives Similarities Differences • Overall Traffic Capacity • Roadway Geometry • North-South connections • Specific Travel Times • South/Washington Intersections are the critical link • Specific Turn Restrictions • Pedestrian and Bicycle Enhancements • Travel times for bus routes on New Washington St (16, 21, 31) are comparable • Traffic Volumes on Surface • South Street and Washington Corridor Improvements • MBTA Facility Enhancements How can traffic operations be similar? • North-south traffic volumes unchanged between alternatives • At-grade offers additional improvements to critical northsouth link on South Street • Removal of Bridge only adds east-west through traffic to surface streets (additional thru lanes provided at-grade) • All turning movements happen at grade regardless Urban Facilities Capacity Analysis Analysis includes: pedestrians, transit, bicycles and vehicles Focus is New Washington Street corridor Analysis Does not include amenities off-road or on other streets Minimal LOS differences between at-grade and bridge alternative CTPS Regional Traffic Model • Model runs for At-Grade and Bridge Alternatives • Initial results show no significant changes to: • Traffic Volumes • Vehicle Miles Traveled (VMT) • Vehicle Hours Traveled (VHT) • Air Quality/Emissions Screenline for Travel Patterns CTPS Key Findings • Both build scenarios allow the same magnitude of traffic to move through this area • Both build scenarios cater to the same markets • Both build scenarios result in similar travel times for trips Detailed LOS and Queue Analyses • Traffic Operations Improved for both alternatives over existing conditions (see Technical Memoranda) • Acceptable traffic operations provided for both alternatives • Queues managed within available storage area • Operations comparable for at-grade and bridge alternatives Travel Time Comparison • Travel times for existing based on current volumes and presented for comparison only • Travel times for alternatives based on 2035 volumes and in depth analysis • Travel times are for peak hours Peak Hour Travel Time Results • Both alternatives improve overall travel times within the project limits • Overall travel times for the alternatives are comparable • At-grade improves travel time for many moves, particularly north-south • At-grade increases travel time for affected left-turns and east-west regional traffic (30-90 seconds) • Regional delays offset local travel time increases East West Regional Travel • Regional travel times relatively unchanged for overall trip • Any in-bound delays at grade on New Washington are offset by existing delays at Murray Circle • In fact, the new design of New Washington may “meter” the travel times, providing more systematic processing of traffic Local Diversions (cut-through) • Concerns on cut through focused on east/west travel. • The At-Grade Alternative increases east/west travel by only 30 to 90 seconds. • The travel times along alternate routes (potential cut-through routes) are greater than the proposed at-grade network * Local Travel Time and Delay: Casey Overpass/New Washington * Inbound Local Travel Time and Delay: Neighborhood cut-through Future Traffic Conditions: Summary Improved over existing conditions and minimal difference between the alternatives for: • Pedestrian/Bike/Transit Operations • Overall Vehicle Capacity • No Added or Diverted Traffic • Overall Travel Times Remain Constant Traffic is not a differentiator between alternatives Traffic Simulations • Performed using VISSIM • Based on 2035 Peak Hour Traffic Volumes • Extensive effort involved • High degree of confidence in results • Preparation needed to start early in alternative development process Next Steps 1. Recommended Alternative 2. 25% Design Planning Study Meeting Schedule Meeting 1 Project Purpose, Goals and Existing Conditions Meeting 2 Issues & Opportunities, Evaluation Criteria, 2035 Traffic Projections, Framework for Design Elements Meeting 3 Development of Design Concepts, Refinement of Evaluation Criteria Meeting 4 Develop Draft Alternatives, Finalize Evaluation Criteria (MOEs) Meeting 5 Conceptual Alternatives, Applied MOEs and Traffic Analysis Meeting 6 Recommended Alternative and Next Steps Meeting Planning Study Schedule Public Meeting #6: Wednesday, December 14, 2011 English High School Questions? Comments!