Document 13047354

advertisement
ROAD SAFETY AUDIT
I-91 Interchange 19
­
Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
­
City of Northampton
­
January 2014
­
Prepared For:
MassDOT
Prepared By:
TranSystems
38 Chauncy Street
Boston, MA 02111
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Table of Contents
­
Background ................................................................................................................................ 1
Project Data............................................................................................................................... 1
Project Location and Description......................................................................................... 2
Safety Issue #1
Safety Issue #2
Safety Issue #3
Safety Issue #4
Safety Issue #5
Safety Issue #6
Safety Issue #7
Safety Issue #8
Safety Issue #9
High Speeds from Coolidge Bridge................................................................ 4
Signing ............................................................................................................ 5
Pedestrian/Bicycle Accommodations ............................................................. 6
Geometric Issues ........................................................................................... 7
Queue from left turn onto I-91 SB On-Ramp ............................................... 8
Solar Glare ..................................................................................................... 9
Access Management on Damon Road ........................................................... 9
Signal Orientation ........................................................................................ 10
Snow Storage ............................................................................................... 11
Recommendations ................................................................................................................. 11
List of Appendices
Appendix A.
Appendix B.
Appendix C.
Appendix D.
RSA Meeting Agenda
RSA Audit Team Contact List
Detailed Crash Data
Additional Information
List of Figures
Figure 1 - Locus Map.................................................................................................................................. 3
Figure 2 – Concept 13A (Preferred Concept) ........................................................................................ 13
List of Tables
Table 1.Participating Audit Team Members .............................................................................................. 2
Table 2.Potential Safety Enhancement Summary..................................................................................... 15
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Background
In 2004, the CT River Crossing Transportation Study was undertaken to investigate the crossings of the
Connecticut River and to determine if any additional crossings were required. The study recommended
construction of a full interchange at the Exit 19 Interchange. A subsequent study focusing on Interchange
19 included a detailed alternatives analysis and evaluation that reviewed a number of build and no build
options.
An extensive public participation program, including 11 Project Advisory Committee (PAC) meetings and
two Public Informational Meetings was conducted to guide the development of the study. At the end of
the study phase, a consensus was reached among the PAC and the public for a concept design to be
advanced through final design. The concept design includes:
• Modifying the Damon Road intersection to a roundabout
• Improvements to the I-91 SB on-ramp intersection to include an additional left turn lane with
receiving lanes on the ramp and extending the length of the left turn lanes.
• Improvements to the acceleration and deceleration lanes on the I-91 mainline.
The first step in advancing the project to final design is to conduct this Road Safety Audit to ensure that all
existing deficiencies are addressed in final design and to identify any short term improvements that could
be implemented prior to the construction of the final condition. The RSA study area is illustrated in
Figure 1.
Project Data
The RSA was conducted on Tuesday, December 3 from 1:00 p.m. to approximately 4:00 p.m. The audit
team (see Table 1) met at 1:00 p.m. in the District 2 office to discuss the existing crash data (attached as
Appendix C). The collision diagrams were reviewed, along with charts summarizing crashes by month, day
of the week, time of day, manner of collision, light condition, weather condition, surface condition
(wet/dry), and driver age. It was noted that most crashes occurred during the daytime (noon – 2:00 was
the highest period) on clear, dry days. The predominant month for crashes was October and the 21-29
year old age group was involved in the most crashes. The majority of crashes were of rear-end types.
Following the initial discussion, the RSA team re-convened in the field at the intersection. Field conditions
were observed from approximately 1:30 until 2:30. Weather was clear and cool; the pavement surface
was dry. Upon arriving at the site, it appeared that an accident or breakdown was just being cleared from
the end of the northbound off-ramp.
Page 1
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Table 1.
Participating Audit Team Members
­
Audit Team Member
Agency/Affiliation
Lenny Velichansky
Transystems
Laurie Scarborough
MassDOT, District 2
Corey O’Connor
MassDOT, Traffic Safety
Bao Lang
MassDOT, District 2
Chunxia Feng
MassDOT, District 2
Luke Hayes
MassDOT, District 2
Stephen Vanasse II
Northampton Fire
Alex Bublik
Northampton DPW
Ned Huntley
Northampton DPW
Wayne Feiden
Northampton Planning and Sustainability
Melissa Rowe
PVTA
Joe Cahill
Transystems
Michael Sarazan
Transystems
Rob Hicks
Transystems
Russ Sienkiewicz
Northampton Police
Khyati Parmar
PVPC
Project Location and Description
The project area is located just west of the Calvin Coolidge Memorial Bridge spanning the Connecticut
River and includes the intersection of Bridge Street and Damon Road/I-91 northbound off-ramp and the
intersection of Bridge Street and the I-91 southbound on-ramp. The project also includes the Exit 19
acceleration and deceleration lanes on the I-91 mainline.
Bridge Street (Route 9) is classified as a Principal Arterial and has two through travel lanes in each
direction through the project area. It serves as the primary route into downtown Northampton from the
University of Massachusetts in Amherst as well as other points east, such as the towns of Hadley, Amherst
and Belchertown. West of the intersection, Route 9 becomes a two lane road (one lane each direction).
Damon Road is classified as an urban minor arterial with one travel lane in each direction. The road is
widened at the intersection to include a right turn and two left turn lanes. The road serves as the primary
route to points north from the towns of Hadley and Amherst.
Interchange 19 is a half diamond interchange that works in conjunction with Interchange 20 to provide full
access to I-91. Interchange 19 provides access from I-91 northbound to Route 9 and from Route 9 to I-91
southbound. Vehicles from Route 9 wanting to access I-91 northbound would travel via Damon Road to
Interchange 20. Similarly, vehicles traveling on I-91 southbound with destinations on Route 9 would exit
at Interchange 20 and travel southbound on Damon Road.
Page 2
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
The intersection of Route 9 and the I-91 southbound on-ramp is partially signalized with the EB through
movement and the WB left turn lane to the ramp controlled by a signal. The westbound through traffic is
not controlled by the signal. Crash rate analysis from the years 2010 through 2012 of this intersection
indicates that the crash rate (0.18) is well below the statewide (0.80) and District 2 (0.82) averages.
The intersection of Route 9 and Damon Road/I-91 northbound off-ramp is fully signal controlled. There
are currently dedicated right turn only lanes from Route 9 WB onto Damon Road and from Damon Road
onto Route 9 westbound. There is also a right turn only lane from the off-ramp onto Route 9 eastbound.
Crash rate analysis from the years 2010 through 2012 for this intersection indicates that it is a high crash
location with a crash rate of 0.85. This is above the statewide average (0.80) and the District 2 average
(0.82). It is in the top 5% high crash location list in the Pioneer Valley Planning Commission and has an
equivalent property damage only (EPDO) of 52.
Figure 1 - Locus Map
Route 9 at SB On-Ramp
Route 9 at Damon Road/NB Off Ramp
Page 3
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Audit Observations and Potential Safety Enhancements
The RSA team identified, through discussion and observations, the following safety issues at the
Interchange 19 intersections:
1.
2.
3.
4.
5.
6.
7.
8.
9.
High speeds from Coolidge Bridge
Signing
Pedestrian/Bicycle Connectivity
Geometric Issues
Solar Glare
Trees/shrubs obstructing sight lines
Access Management on Damon Road
Signal Orientation
Snow storage
The following section describes the safety issues in greater detail and provides potential enhancements
that were discussed to address the concerns.
Safety Issue #1
High Speeds from Coolidge Bridge
Observations
Westbound approach from Bridge
Scenic view from Bridge
The predominant location for accidents in the interchange
area was on the westbound approach to the intersection
coming off of the Coolidge Bridge. These crashes were
overwhelmingly rear-end collisions, indicating that drivers
were likely traveling too fast for the roadway environment
or were otherwise inattentive/ distracted.
The
intersection represents a fairly significant change in the
driving environment as drivers travel from east to west
along Route 9. On the east side of the bridge, the town of
Hadley is much less developed and as such, traffic volumes
are lower than on the Northampton side. Route 9 is
generally more open on the Hadley side, leading to the
potential to increase speeds. The bridge itself is fairly
open with generous sight lines. One accident report cited
that the driver was looking at the scenery prior to the
accident. The views from the bridge as drivers cross the
river could lead to driver inattention.
Additionally, after passing the crest of the vertical curve on
the bridge, the approach roadway is on a 4% downgrade,
which naturally leads drivers to speed up; any driver
inattention coming over the bridge is exacerbated by the
fact that they will be speeding up if they don’t consciously
slow down. Sight distance to the signal is adequate;
however, queues typically extend onto the bridge. Sight
Page 4
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
distance could be an issue if the queue extends close to the crest of the vertical curve.
Enhancements
1.­ Advance Warning – Installing signs on the Hadley side of the bridge alerting drivers of the
intersection on the Northampton side of the bridge would make the drivers more aware that they
are entering a different driving environment.
2.­ Increased enforcement was discussed to lower speeds traveling over the bridge. The police chief
was no longer in attendance for the discussion, but the issue of jurisdiction was brought up, where
there are two different municipalities on either side of the bridge.
3.­ Pavement grooving was also discussed; however it was unclear if there would be sufficient room to
install the grooves between the bridge and the intersection, since installation of grooving on the
bridge itself should be avoided. There is about 300 ft of pavement from the end of bridge (last
bridge joint) to the Damon Rd intersection. In a safety evaluation done by the FHWA, the closest
grooves to the intersection were typically 300' to 500' away. Placing grooves inside the 300' most
likely wouldn't give drivers enough advanced warning. Also, typically the grooves were used at
stop controlled intersections and not signalized intersections.
http://www.fhwa.dot.gov/publications/research/safety/hsis/12047/index.cfm
4.­ Use a dynamic speed board to further alert drivers when they are speeding. The actual type of
speed board is to be determined after a review of the most effective types of boards. It may be
flashing “SLOW DOWN” or simply flashing lights when a vehicle approaches at a high speed. The
area would also have to be reviewed to ensure that there would be sufficient room to place the
speed board and that the speed board would be visible.
5.­ The long term enhancement of changing the intersection to a roundabout should reduce speeds
through the intersection. As part of the roundabout design, the use of a friction course asphalt
for the surface course could be investigate to further enhance safety.
Safety Issue #2
Observations
Signing
Several issues were observed related to the signing, including excessive signing, sign placement (some signs
were blocking others), and sign conditions – age and lack of retroreflectivity.
Of particular concern were the signs on Route 9
westbound coming off of the Coolidge Bridge.
Within the 400 feet between the Coolidge Bridge
abutment and the intersection there are currently 10
signs on the right side of the road. The signs include:
I-91 shield, I-91 directional guide sign, divided
highway graphic sign, lane designation sign, speed
limit sign, Begin right turn lane – yield to bikes, truck
route sign, hospital sign, second lane designation sign
and a second I-91 directional/guide sign. The first
Sign clutter on westbound approach
Page 5
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
signs that are encountered tend to block the sight line to the subsequent signs and could lead to additional
driver distraction while they are looking for direction. The first lane designation sign is especially difficult
to see.
An additional signing concern is the lack of advance signing for the lane drop on Route 9 westbound.
There is a graphical lane drop sign located immediately at the beginning of the lane drop, but nothing in
advance.
It was also noted that there is a sign post with no sign located in the southwest quadrant of Damon Road
and Route 9; it appears that the sign was hit and removed, but never replaced. Other signs are older and
do not appear to have the proper retroreflectivity.
Enhancements
1.­ Weed out less important signs - A short term improvement for the excessive signing could be to
weed out less important signs and potentially locate them elsewhere. One possibility would be to
investigate the location of the speed limit sign to reduce the speed on the bridge itself. According
to Speed Regulation #479, this speed limit sign should be located about 300 feet further east on
Route 9. It would also be allowable to move the sign an additional 200 feet east without
performing a speed study. This location of the speed limit sign would be closer to the crest of the
bridge and would stand out more as it would be away from the sign clutter. This would serve a
dual purpose of slowing vehicles down on the bridge and reducing some of the sign clutter just
over the bridge. Additionally, the I-91 shield sign is the first sign as drivers come over the bridge
and it blocks many of the other signs behind it. It may make sense to relocate this sign.
2.­ Investigate relocating lane assignment signs onto the mast arm such that they would be over the
lanes they are referring to. This would result in a better arrangement for the lane configuration
and would help to reduce the sign clutter on the side of the road.
3.­ Improve Sign Conditions - In the short term, an advance warning sign could be added for the lane
drop. Also, MassDOT could analyze the retroreflectivity and condition of the existing signs and
replace signs as needed.
4.­ Long Term Sign Improvements - The long term solution for the intersection includes changing the
Damon Road intersection into a roundabout. The signing will be completely redesigned for the
roundabout; the signing concerns will be taken into account as the design is developed. It was also
discussed at the RSA to include signs that would keep trucks out of downtown Northampton.
While this is not technically a safety issue, it could be investigated as part of the final design of the
proposed improvements.
Safety Issue #3
Observations
Pedestrian/Bicycle Accommodations
Current pedestrian and bicycle accommodations include a narrow sidewalk on the north side of Route 9
westbound and “Share the Road” signs to accommodate bicyclists. There can be heavy bicycle demand
during the winter, because the Norwottuck Trail is not plowed. During the RSA, the Norwottuck Trail
was closed due to maintenance and there were several cyclists observed traveling on Route 9.
Page 6
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
The sidewalk, which is only 3-4 feet wide, is further
impeded by trees and shrubs growing into it. This leads
to pedestrians walking closer to the roadway than they
normally would if the entire sidewalk width were
available. The nearest extent of sidewalk on the south
side of Route 9 extends no further east than Sheldon
Field. During the public process for the interchange
study, there was interest in extending the sidewalk
through the intersection area. This is not technically a
safety issue and it will be assessed during final design of
the intersections.
Narrow sidewalk impeded by vegetation
Enhancements
1.­ Tree/Shrub trimming - As a short term solution, the trees and shrubs could be trimmed back to
allow the entire existing sidewalk width to be used.
2.­ Future Accommodations – The long term solution includes modifying the Damon Road intersection
into a roundabout and making improvements to the southbound on-ramp intersection. A wider
sidewalk is proposed which would be relocated behind the bridge piers, separating the pedestrians
from traffic. Additionally, pedestrians would only need to cross one direction of traffic at a time in
a roundabout, and the vehicles will be traveling at a reduced speed compared to the existing
intersection.
Additionally, a shared use bypass path will be provided around the roundabout for pedestrians and
less experienced cyclists. Pavement markings and signs will be provided through the roundabout
for more experienced cyclists. A shared used path along Damon Road connecting Route 9 to the
Norwottuck Trail will be investigated as part of the design.
Safety Issue #4
Observations
Geometric Issues
For the most part, the roadway geometry was
adequate for the design speeds and the observed
speeds. The one geometric issue that was observed
was the right turn from Damon Road onto Route 9
westbound. The curve radius appeared to be too
sharp for larger trucks to maneuver through the
curve without encroaching into the middle lane of
Route 9 westbound and possibly into the median
island. One of the crashes analyzed indicated a
tractor trailer swinging wide to turn right hit a
passenger car in the right turn lane. The driver of
the tractor trailer was unaware that they had hit the
passenger car.
Sharp right turn from Damon Road onto Route 9 WB
Page 7
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Another geometric concern is the location of the lane drop on Route 9 westbound just west of the
southbound on-ramp to I-91. The concern is of drivers racing to pass each other prior to the lane drop.
This is particularly true for vehicles trying to pass PVTA buses prior to the one lane Route 9 leading into
downtown Northampton.
Enhancements
1.­ Intersection modifications (Roundabout) – The proposed intersection modification will be designed to
accommodate heavy vehicles through the roundabout. No viable short term enhancements were
identified.
2.­ Advance signing for lane drop – a short term solution for the lane drop situation could be for
MassDOT to add an advance warning sign to supplement the graphical sign at the lane drop itself.
3.­ Relocate lane drop – As part of the long term, final design for the intersections, the lane drop is
proposed to be shifted to the east in order for it to occur where vehicles are traveling slower by
providing less distance for vehicles to accelerate out of the roundabout.
4.­ Move bus stop – Move the existing bus stop on Route 9 to the west and/or provide a bus pullout
area to reduce potential conflicts near the lane drop.
Safety Issue #5
Observations
Queue from left turn onto I-91 SB On-Ramp
During the audit, it was observed that the queue from the left turn onto the I-91 SB on-ramp would
extend back to the Damon Road intersection. The queue generally cleared with each signal cycle,
however, it was discussed that during the peak hour, it does not always completely clear. One team
member stated that she observed that drivers often try to beat the queue by staying in the right lane until
they clear the Damon Road signal prior to entering the left turn lane. According to the team member,
this leads to conflicts trying to enter the left turn lane.
Enhancements
1.­ Pavement Markings/Signal Timings – For short term improvements, MassDOT could investigate the
signal timings to ensure they are optimized. Also, pavement markings could be added to reinforce
the left turn lane.
2.­ Add storage – As part of the long term intersection design, an additional left turn lane will be added
to Route 9 westbound. The left turn lane will also be extended to the east, providing increased
storage for the left turn lane. The on-ramp would be widened to provide two receiving lanes.
Page 8
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Safety Issue #6
Observations
Solar Glare
At approximately 2:00 p.m., the position of the sun
was aligned such that it was in the drivers’ eyes as
they crested the Coolidge Bridge traveling
westbound on Route 9. One of the accidents cited
the lack of visibility due to the sun glare. There are
currently no back plates on the signal heads to
increase the visibility.
Enhancements
1.� Install back plates – As a short term measure, back plates could be installed on the signal heads to
increase the visibility of the signals during times of solar glare.
2.� Long term design – Under the long term improvements, the intersection will become a roundabout.
The position of the sun will be considered during the design of the roundabout, although, it may
not be feasible to completely avoid solar glare issues, since Route 9 is aligned in an east-west
direction through the project area.
Safety Issue #7
Observations
Access Management on Damon Road
Three accidents occurred at the driveway located on
Damon Road approximately 200 feet north of the
intersection. Two of the crashes involved drivers trying
to pull into the driveway and the other involved a driver
trying to pull out of the driveway and enter Damon Road
traffic. The driveway closest to the intersections is
intended to be a right turn exit only driveway; however
this is only identified by two yellow pavement marking
arrows pointing roughly to the right. This driveway is
located at a point on Damon Road where there are three
lanes to cross in order to turn left. At least one of the
crashes was the result of a “courtesy crash” where a
driver in one lane allowed the vehicle out of the driveway,
which proceeded to crash with a vehicle in another lane.
The driveway to the Norwottuck Trail (Elwell Recreation
Area) parking lot is also located relatively close to the
intersection and is aligned at a curved area of Damon
Road. RSA Team members indicated that it is sometimes
difficult to make the left turn out of the Norwottuck Trail
parking lot onto Damon Road.
Aerial View – Damon Road
Page 9
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Driveway to Webster's Restaurant�
Entrance to Elwell Recreation Area
Enhancements
1.­ Physical restriction of left turns out of restaurant – As a short to mid-term measure, the driveway out
of Webster’s Restaurant could be reconfigured such that left turns would be physically precluded;
drivers wanting to turn left onto Damon Road would have to use the driveway located further to
the north.
2.­ Pavement Markings/signs – A short term measure for the Norwottuck Trail left turn could be to
install cross hatched pavement markings in front of the entrance in conjunction with “Do Not
Block Intersection” signs. Also, the desired traffic pattern for the restaurant could be reinforced
with regulatory signs prohibiting the left turns out of the driveway closest to the intersection.
3.­ Realign Driveway – A suggestion was made by a team member to investigate relocating the
Norwottuck Trail parking lot driveway further to the north, away from the intersection. The new
driveway would be approximately where the existing signalized trail crossing of Damon Road is
located. The feasibility of integrating the driveway with the signal could also be investigated.
Safety Issue #8
Observations
Signal Orientation
It was noted that most of the signal heads were not optimally oriented above the approach lanes. This
could cause some driver confusion when navigating through the intersection.
Enhancements
1.­ The only short term solution that was identified
­
was for MassDOT to look into whether the signal
­
heads could be realigned in their current location.
­
It was decided that it would not be worthwhile to
­
relocate the signal heads at this time because the
­
permanent solution would not include signals and
­
relocating the signal heads would require replacing
­
mast arms.
­
Damon Road Approach to Intersection
Page 10
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Safety Issue #9
Observations
Snow Storage
Team members discussed the storing of snow within the delta islands located within the interchange
ramps. During snowy winters the snow piles can become high, blocking visibility to the intersection.
Enhancements
The snow storage is primarily a MassDOT maintenance issue. A plan should be put into place to ensure
that adequate sight lines are maintained when storing plowed snow. This would be especially important
with the roundabout.
Recommendations
Based on the review of data, on-site field observations and group discussion, the RSA team identified the
following possible enhancements that could improve safety at the two subject intersections in the RSA
project area. Further study and design work will need to be conducted to determine the feasibility of
making some of the improvements.
Short-term enhancements include:
•
•
•
•
•
•
•
•
Install advance warning signs;
Improve signage -prioritize signs and eliminate unnecessary signs;
Trim back trees and shrubs along sidewalks;
Optimize signal timings;
Install back plates on signal heads;
Install cross-hatched pavement markings on Damon Road at Elwell Recreation Area driveway;
Realign signal heads as required;
Review snow storage plan as related to sight lines
Mid-term enhancements include:
•
•
•
•
Investigate installing pavement grooves prior to intersection;
Analyze retroreflectivity of signs and replace signs as needed;
Optimize signal timings;
Reconfigure driveway out of Webster’s Restaurant;
To enhance the safety of the intersection, the long-term enhancements are to:
• Incorporate proper signing into final design of intersections;
• Incorporate bicycle and pedestrian accommodations into final design of intersections;
• Incorporate proper lighting into the roundabout design to make drivers aware of the
geometry changes and pedestrian presence at night.
• Final design geometry will properly accommodate heavily vehicles.
• Relocate westbound lane drop to the east;
• Add an additional left turn lane on Route 9 westbound;
• Consider position of sun in laying out proposed design;
• Relocate driveway to Elwell Recreation Area;
Page 11
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
The preferred concept for the long term enhancements as selected by the PAC and the community is
shown in Figure 2. Table 2 summarizes these safety issues, possible enhancements, estimated safety
payoff, time frame, cost, and responsibility. Safety payoff estimates are based on engineering judgment and
are categorized as low, medium, and high. The time frame is categorized as short-term (<1 year), midterm (1 to 3 years), or long-term (typically >3 years). Long-term improvements are typically considered to
be substantial improvements with an expected time frame for implementation greater than 3 years. The
costs are categorized as low (<$10,000), medium ($10,001 to $50,000), or high (>$50,000).
Page 12
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Figure 2 – Concept 13A (Preferred Concept)
Page 13
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Page 14
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Table 2.
Potential Safety Enhancement Summary
­
Safety Issue
Safety
Payoff
Time
Frame
Cost
Responsible Party
Short Term
Low
MassDOT
High
Short Term
Low
Northampton/Hadley
High
Mid Term
Medium
MassDOT
Install trailer-mounted dynamic speed board
High
Short-Term
Low
Northampton/Hadley
Prioritize signs and eliminate or relocate less
important signs away from the busiest locations
for signs.
Low
Short Term
Low
MassDOT
Low
Mid Term
Low
MassDOT
Incorporate proper signing into the final design
Medium Long Term
of the intersection.
Low
MassDOT/Transystems
Trim back trees and shrubs to allow for full use
Medium
of sidewalk width.
Short Term
Low
MassDOT
Incorporate
bicycle
accommodations
into
intersections.
Long Term
High
MassDOT/Transystems
Potential Safety Enhancement
Install advance warning signs on the Hadley side
of the bridge to alert drivers of the intersection Medium
on the Northampton side of the bridge.
Increase speed enforcement
High Speeds from Coolidge
Investigate installing pavement grooves to alert
Bridge
drivers as they come off bridge. Initial review
indicates that pavement grooves would not be
feasible/effective due to the proximity of the
bridge.
Signing
Pedestrian/Bicycle
Connectivity
Analyze the retroreflectivity and condition of the
existing signs and replace signs as needed.
and
final
pedestrian
design
of
High
Page 15
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Safety Issue
Geometric Issues
Queue from left turn
onto I-91 SB On-Ramp
Solar Glare
Time
Frame
Cost
Responsible Party
Modification of Damon Road intersection to
Medium
roundabout.
Long Term
Medium
MassDOT
Add an advance warning sign to supplement the
graphical sign at the lane drop on Route 9
westbound.
Short Term
Low
MassDOT
Relocate the Route 9 westbound lane drop as part
Medium
of the final design of the intersections.
Long Term
Low
MassDOT/Transystems
Move bus stop west
Medium
Mid Term
Low
MassDOT
Investigate the signal timings to ensure they are
optimized. Also, pavement markings could be Medium
added to reinforce the left turn lane.
Short Term
Low
MassDOT
Add an additional left turn lane on Route 9
westbound.
The left turn lane will also be
extended to the east, providing increased storage
for the left turn lane. The on-ramp would be
widened to provide two receiving lanes.
Long Term
High
MassDOT/Transystems
Potential Safety Enhancement
Safety
Payoff
Low
High
Install back plates on the signal heads to increase
the visibility of the signals during times of solar Medium
glare.
Short Term Medium
The position of the sun will be considered during
the design of the roundabout, although, it may not
be feasible to completely avoid solar glare issues,
since Route 9 is aligned in an east-west direction
through the project area.
Long Term
Low
Low
MassDOT
MassDOT/Transystems
Page 16
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Safety Issue
Safety
Payoff
Time
Frame
Cost
Responsible Party
High
Mid-Term
Medium
Northampton
Install cross hatched pavement markings in front of
the entrance in conjunction with “Do Not Block Medium
Intersection” signs.
Short-Term
Low
Northampton
Investigate relocating the Norwottuck Trail parking
lot driveway further to the north, away from the Medium
intersection.
Long-Term
High
MassDOT
Look into whether the signal heads could be
realigned in their current location.
Low
Short-Term
Low
MassDOT
Develop plan to ensure that adequate sight lines are
maintained when storing plowed snow.
Low
Short-Term
Low
MassDOT
Potential Safety Enhancement
Reconfigure driveway out of Webster’s Restaurant
such that left turns would be physically precluded.
Access Management on
Damon Road
Signal Orientation
Safety Issue #9 Snow
Storage
Page 17
Road Safety Audit— I-91 Interchange 19 Bridge Street at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Page 18
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Appendix A. RSA Meeting Agenda
­
Page 19
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Page 20
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
I-91 Interchange 19
�
Northampton, MA
�
Road Safety Audit (RSA) Meeting
�
Tuesday, December 03, 2013
�
MassDOT District 2 Office
�
1:00 p.m.
�
Meeting Agenda
�
1:00 p.m.
Welcome and Introductions
1:10 p.m.
Review of Site Specific Material
1:30 p.m.
2:45 p.m.
3:30 p.m.
•
Crash and Traffic Analysis Memo – provided in advance
•
Existing Geometries and Conditions
Site Visit
•
Assemble as a group at the site for observation of conditions
•
As a group identify areas for improvement
Post Visit Discussion/Completion of RSA (at District 2 Office)
•
Discuss observations and finalize findings
•
Discuss potential improvements and finalize recommendations
Adjourn for the day
Next Steps: After the RSA meeting, Transystems will prepare a draft document and circulate it to
participants. Participants are asked to comment and respond to the draft document to assure it is
reflective of the RSA completed by the multidisciplinary team.
With comments submitted, a final document is produced; the final is expected to be available in January
2014.
Page 21
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Page 22
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Appendix B. RSA Audit Team Contact List
­
Page 23
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Page 24
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Participating Audit Team Members
Date: December 3, 2013­
Location: MassDOT District 2
811 North King St. Northampton, Mass.
Audit Team Members
Agency/Affiliation
Email Address
Phone Number
Name
Agency
Email
xxx-xxx-xxxx
Lenny Velichansky
Transystems
lavelichansky@transystems.com
857-453-5456
Laurie Scarborough
MassDOT, District 2
laurie.scarbrough@state.ma.us
413-582-0591
Corey O’Connor
MassDOT, Traffic Safety corey.oconnor@state.ma.us
857-368-9638
Bao Lang
MassDOT, District 2
Bao.lang@dot.state.ma.us
413-582-0547
Chunxia Feng
MassDOT, District 2
Chunxia.feng@state.ma.us
413-582-0555
Luke Hayes
MassDOT, District 2
Luke.hayes@dot.state.ma.us
Stephen Vanasse II
Northampton Fire
svanasse@northamptonma.gov
413-587-1100
Alex Bublik
Northampton DPW
abublik@northamptonma.gov
413-587-1570
Ned Huntley
Northampton DPW
nhuntley@northamptonma.gov
413-587-1570
Wayne Feiden
Northampton Planning
and Sustainability
wfeiden@northamptonma.gov
413-587-1265
Melissa Rowe
PVTA
mrowe@pvtransit.com
413-732-2161 x110
Joe Cahill
Transystems
jvcahill@transystems.com
857-453-5540
Michael Sarazan
Transystems
mjsarazan@transystems.com
857-453-5537
Rob Hicks
Transystems
rwhicks@transystems.com
857-453-5517
Russ Sienkiewicz
Northampton Police
rsienkiewicz@northamptonma.gov 413-587-1100
Khyati Parmar
PVPC
kparmar@pvpc.org
413-781-6095
Page 25
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Page 26
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Appendix C. Detailed Crash Data
­
Page 27
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Page 28
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
"!J~'\massDOT
Northampton, MA
Massadlusetls Department of Tr-portatlon
,
Bridge St (Rte 9) at 1-91 SB On Ramp
Highway Division
REGION: PVPC
TIME PERIOD ANALYZED:
COLLISION DIAGRAM
January 2010- December 2012
SOURCE OF CRASH REPORTS:
DATE PREPARED:
Northampton Police Department
Novermber 15, 2013
PREPARED BY: MJS
* NOT TO SCALE
SYMBOLS
TYPES OF CRASH
Head On
Rear End
- - • • Moving Vehicle
«( IJo Backing Vehicle
- - • • Non-Involved Vehicle
D
Fixed Object
----,v:=-:
~
SEVERITY
0
Angle
Injury
Turning Movement
0
Sideswipe
N
Fatal
Out of Control
Night Time Crash
Page 29
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
/Jl!J~gf?QI
Bridge
St~~~~:~~R~~~,I-~N~
Off Ramp
REGION: PVPC
TIME PERIOD ANALYZED:
COLLISION DIAGRAM
January 2010- December 2012
SOURCE OF CRASH REPORTS:
DATE PREPARED:
Northampton Police Department
Novermber 15, 2013
PREPARED BY: MJS
* NOT TO SCALE
Norwottuck Rail Trail
SYMBOLS
TYPES OF CRASH
--+IJl Moving Vehicle
(« IJl Backing Vehicle
Head On
Rear End
_____..,. Non-Involved Vehicle
D
Fixed Object
----,v:=-:
~
SEVERITY
0
Angle
Injury
Turning Movement
0
Sideswipe
N
Fatal
Out of Control
Night Time Crash
Page 30
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Damon Road at Bridge Street (SR 9) and 1-91 NB Off Ramp, Northampton, MA
CRASH MONTH
25% ~----------------------------------------------------------~
20%
20%
15% +---10% 10%
10% -t--=-:-:---1·
+--------------------------------------------
5% -+--.0%
..--1
+-~~~~~~~~~~~~~-L~~~~~~~~~~-r~~~~~
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sept
Oct
Nov
Dec
CRASH DAY OF WEEK
""n.
25%
20%
~w-
15%
-
-
10% 5%
0%
-
~~
5%
I I
--
--
---
--
Monday
-
15%
'V
-
-
r--
--
-
-
- --47-0,.{,--
f-·-~ r-f-
-
~0
-
·--
Tuesday Wednesday Thursday
Friday
Saturday
Sunday
CRASH TIME OF DAY
30% ~--------------~~----------------------------------------~
25%
20%
1 5% +--...·rm'r10%
5%
0%
+----------------
6am8am
Bam-
10am
10am- 12pm12pm
2pm
2pm4pm
4pm6pm
6pm8pm
8pm10pm
10pm- 12am12am
2am
2am4am
4am6am
CRASH MANNER OF COLLISION
60% ~--------~~----------------------------------------------,
50%
40%
30%
20% +-----Ttl'l'-10% .------::...__
0% +-----~
+-------+-------Single
Vehicle
Crash
Rear-End
Angle
Sideswipe, Sideswipe, Head on
same
opposite
direction direction
Rear to
Rear
Unknown
Page 31
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Crash Data Summary Tables and Charts
Damon Road at Bridge Street (SR 9) and 1-91 NB Off Ramp, Northampton, MA
CRASH LIGHT CONDITION
80%
60%
40%
20%
0%
~~
2%Daylight
Dawn
Dusk
oero--2%-
- o%
DarkDark Dark Lighted
Roadway Unknown
Roadway not lighted roadway
lighting
Other
Unknown
CRASH WEATHER CONDITION
60%
40%
20%
0%
0%
0%
0%
2%
Other
Unknown
0%
Cle ar
Cloudy
Rain
Snow
Sleet, Hail, Fog, Smog, Severe
Blowing
Freezing
Smoke Crosswinds sand, snow
Rain
CRASH ROAD SURFACE
80%
60%
VV/0
_
r--
,..,-,n
40% :---
~
-
20% :--0%
Dry
•v
n- ~
Wet
Snow
5"%
0%
0%
0%
0%
0%
Slush
Oth er
Unknown
r---1
Ice
Sand, mud, Water
dirt, oil, (standing,
gravel
moving)
CRASH DRIVER AGES
30%
25%
20%
15%
10%
5%
0%
%
15-20
21-29
30-39
40-49
50-59
60-69
70-79
80+
Page 32
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Crash Data Summary Table
Bridge Street (S.R. 9) at 1-91 SB On Ramp, Northampton, MA
Crash
Diagram
Ref#
Crash Date
Day
m/dtv
Time of
Directio Manner of
n
Da
Tvoe
V1:
1
2
9/5/2010
4/10/2011
Sun
Sun
6:11PM
12:49 AM
Collision
Tvoe
Light Condition
Tvoe
Weather
January 2010- December 2012
Road
DriVer Contributing Code
Condition Surface
Tvoe
Tvoe
#of
lniuries
Ages
s
t--t-- Rear-End Daylight
V1:
s
V1:
s
1---1--V2: s Rear-End
Clear
Dry
Followed too closely
0
51 43
V1:
7/29/2011
Fri
4
9/17/2011
Sat
5
10/2912011 Sat
9:29AM
Clear
Dry
Physical Impairment
0
21 35 21
V3 and V2 stopped at red tramc light waiting to make ten turn on to 1-91 S.
V1 approached V2 from the rear, did not stop, and collided with the rear of
V2. The collision caused V2 to collide with the rear ofV3. Operator ofV1
was arrested of OUI alcohol
Cloudy
Dry
Inattention
0
46 50
V1 was traveling east on Bridge St near the on ramp to 1-91 S when she
struck the rear ofV2, also traveling east. V1 didn't see V2 until the last
minute, striking the rear.
Daylight
Clear
Dry
Inattention
0
79 58
V1 was traveling eastbound on Bridge St. V2 was traveling westbound on
Bridge St and turned ten on Damon Road. V1 went through the red ligti and
struck V2 on the front right bumper.
Daylight
Cloudy
Dry
Disregarded traffic signs,
signals, road markings
0
41 18
V2 started to turn towards the on ramp. AI that time, V1 was northbound on
Bridge Stand did not slow for the red light. Seeing V1 approaching , V2
sped up to avoid a collision, V2 was struck by V1 in the right rear comer.
Dark- lighted
roadway
E
t--t-- Rear-End Daylight
V2:
E
V1:
E
11:06AM
1---1--- Angle
V2: s
1:30PM
1---1--- Angle
V2: s
V1:
V2 was traveling onto the 1-91 SB on ramp when a vehicle came onto the
ramp from Rte 9 EB causing V2 to brake heavily. V1 traveling behind V2
did not slow fast enough and struck V2 on the driver's side rear bumper
1---1--V3: s
3
Comments
D1 D2 D3
Tvoe
N
Summary based on Crash Reports obtained from the Northampton Police Department.
Page 33
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Crash Data Summary Table
Bridge Street (S R 9) at Damon Road and 1-91 NB Off Ramp, Northampton, MA
Crash
Crash Date Day
Dia17am
Ref#
m/dlv
Time of
Day
Tvoe
Direction
light
Concition
Tvoe
January 2010- December 2012
Weather Road
Driver Contributing Code
Condition Surfac
Tvoe
Tvoe
Tvoe
#of
ln"uries
Ages
Comments
D1 D2 D3 D4
~
-11- Mgle
V2: s
Daylight
Cloudy
Wet
Inattention
1
81
Sun 4:58PM
~
-4V2: s
Rear-End
Dayli!Jlt
Clear
Dry
Inattention
0
42 48
Fri
6:08PM
~~
~
~
V3. w
Rear-End
Dayli!Jlt
Clear
Dry
Inattention
2
20 21
5129/2010
Sat
6:25AM
Single Vehicle
Crash
Daylight
Unknown Dry
Inattention
0
70
V1 was driving on 1-91 NB and tried to exit too sharply. V1 drove over
the Exit 19 sign, drove into the median, struck the embankment, and
tried to re-enter the highway but struck the guardrail. His car then
rolled over and came to rest on its roof
6/24/2010
Thur 7:27AM
Dayli!Jlt
Clear
Dry
Disregarded traffic signs,
signals, road markings
1
56 42
V1 collided into the front driver side of V2.
V1 was exiting 1-91 and turning east onto Bridge Street. V2 was
proceeding through a green light and turning left onto Bridge Street.
V1 failed to yield the right of way and did not see V2 and struck V2 on
the passenger side of the vehicle.
1
118/2010
Fri
2
3/21/2010
3
4130/2010
4
5
3:35PM
N
V1:
~
Jf4- Mgle
V2: N
V1:
6
7/18/2010
Sun
7
8/24/2010
Tues 3:02PM
1:49AM
- V2:
8
9/7/2010
Tues 5:05PM
9
10/6/2010
Wed 1:02PM
10
10/2612010 Tues 6:50AM
11
10127/2010 Wed 8:13PM
12
10/2612010 Thur 1:06AM
13
1218/2010
14
12/1212010 Sun
15
Manner of
Collision
Tvoe
Wed 2:42PM
12/17/2010 Fri
1:43PM
E
E
~
V2. ~
w
Sideswipe, same
direction
Dark- lighted
Rain
roadway
Wet
Inattention
0
28 31
Rear-End
Dayli!Jlt
Dry
No improper driving
0
17 59
~
~ Rear-End
V2: w
V1: w
- - Mgle
V2: s
~ --'4
~
V3· --'4
Rear-End
V4: --'4
w
~
-4- Rear-End
V2: s
~ --'4 Rear-End
$V3: --'4
w
+
~+
s
~
V2.
Sideswipe, same
E direction
V2.
.As1gle
8:56PM
~ -¥.- Mgle
~
-4
V3: w
Cloudy
Two uninvolved vehicles stopped to allow V1 to enter driveway to
restaurant, V2, in RTL, did net stop
44
Light turned green, V1 drove into back of V2
21
V1 was directly behind V2 and was unable to stop and collided with
V2. The impact caused V2 to move forward and collide with V3.
Red light at bike crossing. V1 hit accelerator instead of brake.
V"L. operator stated he was stopped at the red light tor sometime when
V1 drove into the back of his vehicle.
V2 turning left: into Webster's Fish Hook driveway from northbound
Damon Road. V1 headed south on Damon Road. V1 tried to brake
and avoid accident with V2, but due to rainy conditions could not.
Daylight
Clear
Dry
Inattention
0
58 33
Daylight
Rain
Wet
Unknown
0
53 24
Dawn
Rain
Wet
Driving too fast for
conditions
0
V1 was traveling westbound and began to have a sneezing episode.
68 22 64 35 V1 struck V2, causing a chain reaction of rear-end collisions involving
V3andV4.
Darkunknown
Rain
Wet
Other improper action
0
45 23
V2 claims that V1 stopped short at red light
Dark- lighted
Rain
roadway
Wet
Inattention
0
23 17 28
Traffic queued fi'om stop light at on-ramp
V1 failed to use care while entering traffic
Dayli!Jlt
Clear
Dry
Inattention
0
57 82
Daylight
Rain
Wet
Inattention
0
81
59
Inattention
2
21
59 31
0
33 55
V1 claims to have had limited visibility due to sun glare
2
39 47
V1 claims to have not realized that the roads were
Dark- lighted
Clear
roadway
Dry
16
1/14/2011
Fri
2:32PM
~
-4V2: s
Rear-End
Dayli!Jlt
Clear
Dry
17
218/2011
Tues 7:08AM
~
V2: -4s
Rear-End
Daylight
Snow
Ice
V isibility
obstructed/Inattention
Driving too fast for
conditions
Disregarded traffic signs,
signals, road markings
V1 did not see V2. V2 was trying to pull into the left: turn lane on Bridge
St
V1 (EB on Bridge St) ran red light, hitting V2 and forcing it into V3
s ~ ppery
18
2/17/2011
Thur 8:20AM
~
~
V2: N
Rear-End
Dayli!Jlt
Clear
Dry
19
413/2011
Sun
~
--'4
V2: w
Rear-End
Daylight
Clear
Dry
No improper driving
0
19 44
20
7/18/2011
Mon 10:33AM
Dayli!Jlt
Clear
Dry
No improper driving
0
67 56
V1 's trailer (Tl) struck V2 while proceeding throu!Jl g'een li!Jlt
21
919/2011
Fri
12:10PM
Daylight
Clear
Dry
Distracted
0
55
V1 thinks he nodded off to sleep and had knocked down a large traffic
sion post and then smashed into a traffic lioht post.
22
10/1/2011
Sat
3:09PM
Daylight
Rain
Wet
Fallowed too closely
1
45 28
V2 was traveling southbound on the Calvin Coolidge Bridge and
stopped for traffic. V1 was also traveling southbound directly behind
V2 and cid not observe V2 stopped in traffic.
1:31PM
~
--'4
V2: w
Sideswipe, same
direction
Single Vehicle
N
Crash
V1:
V1:
-
V2:
-
s
s
Rear-End
0
28 40
V1 was stopped behind V2 when V1 's foot slipped off the brake and
she crashed into V2.
V1 looked away briefly and did not realize V2 had stopped at
intersection
Page 34
Road Safety Audit— I-91 Interchange 19 - Bridge Street (Route 9) at Damon Road/NB Off-Ramp/SB On-Ramp
Prepared by TranSystems
Crash Data Summary Table
Bridge Street (S.R. 9) at Damon Road and 1-91 NB Off Ramp, Northampton, MA
J anuary 2010 December 2012
<.;rash
Crash Date Day
Diagram
Ref#
m/dN
Time of
Dav
Tvoe
23
10/13/2011 Thur 12:50 PM
24
10/2212011 Sat
V1:
V1:
12:31 PM
-
V2:
V1:
25
10/2812011 Fri
2:24 /WI
Manner of
Collision
Tvoe
Direction
-
w
w
w
-
Weather Road
Condtion Surfac
Tvoe
Tvoe
Driver Contributing Code
#of
ln·uries
Ages
Comments
D1 D2 D3 04
Tvoe
V1 had a seizure while traveling down Bridge St, causing V1 to lose
control depart the road hit a sign and then hit a parked vehicle (V2).
Angle
Daylight
Cloudy
Dry
History
Heart/Epilepsy/Fainting
1
37
Rear-End
Dayfight
Cloudy
Dry
Followed too closely
0
21
Dark - lighted Hail,
Ice
roadway
Freezing
Rain
Swerving or avoiding due
to wind, slippery surface,
vehicle, object, nonmotorist in roadway, etc
0
18 45
Dark - lighted
Cloudy
roadway
Dry
Operating vehicle in erratic.
reckless, careless,
4
51
Rear-End
Dusk
Clear
Dry
Followed too closely
0
30 57
Single Vehicle
Crash
No improper driving
0
23
0
35 20
0
62 67
V1 turned right in left turn only lane
~eet,
w
-
V2:
light
Condition
Tvoe
Angle
E
43
V2 was stopping for stopped bridge traffic and was struck from behind
by V1. V1 stated she was looking at the scenery.
V1 was traveling westbound on the Coolidge Bridge. V2 was traveling
eastbound. V1 applied its brakes over the icy road causing V1 to spin
out. V1 turned 360 degees. The rear ofV1 struck the driver side of
V2.
28
11/17/2011 Thur 5:43PM
_g._ Angle
~
V2: E
27
11/17/2011 Thur 6:15PM
~
V2.
28
11/27/2011 Sun
Daylight
Clear
Dry
28
12129/2011 Thur 10:40 PM
-i4'
~ Rear-End
V2: w
Dusk
Clear
Dry
30
2!7/2012
~
V2:
Sideswipe, same
direction
Daytight
Clear
Dry
Rear-End
Daylight
Rain
Wet
Followed too closely
2
28 55
V1 and \12 were westbound on the Coolidge Bridge. V1 was behind
V2, attempted to stop but skidded into the back ofV2.
Angle
Daylight
Clear
Dry
Inattention
0
47
V1 was trave~ng eastbound on Rte. 9 went through a red light striking
V2 as it was making a left turn li'om Exit 19 on Rte. 9 WB.
Sideswipe, same
direction
Dark - lighted
Clear
roadway
Dry
Inattention
0
33 51
Rear-End
Daylight
Snow
Followed too closely
0
24
2:16PM
lues 4:23PM
V1:
31
3/3/2012
Sat
12:58 PM
32
3/22/2012
Thur 1:50PM
+
E
V1:
-V2:
V1:
-
V2:
N
+
-ww
E
-
V1:
33
34
3/24/2012
5/22/2012
Sat
10:40 PM
-V2:
Wed 12:53 PM
6/6/2012
Wed 5:19PM
37
6/12/2012
lues 12:36 PM
E
~
~
V2: w
V1: s
-
V2:
7/12/2012
E
~
~
V2. -.!!JE
5/2312012
Thur 11:22AM
s
V1:
N
V2:
E
- -
39
7/18/2012
Wed 1:36PM
~ -.!!J~
-b
V3: w
40
9/14/2012
Fri
-V2: - E
41
11/2812012 Men 5:52PM
V1:
12:12AM
V1:
59
N
~
~
V2. w
36
36
E
lues 8:56 /WI
35
1
Failure to keep in proper
lane or running off road
Disregarded trafnc signs,
signals, road markings
22
w
\12 turned left onto Bridge St. V1 was traveling on the 1-91 NB off
ramp. V1 subsequently hit \12 damaging V2's front passenger's side
quarter panel
81
Road surface was wet. V2 stopped for pedestrian at bike crossing
V1 was in wrong lane (right turn lane) and attempted to back up and
chanoe lanes.
Rear-End
Daylight
Clear
Dry
Visibility obstructed
0
42 54
Rear-End
Daylight
Rain
Wet
Inattention
0
24
Rear-End
Daytight
Cloudy
Dry
Inattention
0
23 18
V1 was stopped on Damon Rd attempting to make a right hand turn.
V1 thought V2 had proceeded forward, causing V1 to strike \/2.
Angle
Daylight
Clear
Wet
Unknown
2
41
V1 struck the side ofV2. There were no independent witnesses and
both parties stated they had the green light.
Sideswipe, same
direction
Daylight
Clear
Dry
Uperatlng vehicle 1n errat1c.
reckless, careless,
negligent, or aggressive
0
38 27 61
V1 1n len turn only lane attempted to pass unidentlhed 1 1 and v~
travel straight through intersection. V1 got sandwiched in between \12
and V3.
Angle
Dark - lighted
Clear
roadway
Dry
Inattention
0
61
V2 pulled up on right side ofV1 (TT). V1 's rear tires hit V2 while doing
RTOR. V1 was unaware of collision.
Dry
Inattention
1
60 22
E
-V2: -w
Rain
QUI. V1 went through red 6ght and drove into V2.
Uninvolved vehicle ran red light from Damon Rd causing V1 to stop
sudden tv.
V1 braked and pulled into left lane to avoid suddenly stopped vehicle
and ran off the riaht side of the hiahwav.
QUI. V1 travelingWB in EB lane then crossed over median, striking
two signs before striking V2.
Rear-End
Dark - lighted
roadway
Clear
54
69
31
V1 attempted to change lanes but struck \12 in the process.
When V1 exited 1-91, V1 did not realize that vehicles would be stopped
on the off ramp. The front end of V1 collided with the rear end of V2.
Summary based on Crash Reports obtained from the Northampton Police Department.
Page 35
Download