Lane Departure Road Safety Audit for Route 2 in Shelburne, Massachusetts

advertisement

Lane Departure Road Safety Audit for

Route 2 in Shelburne, Massachusetts

Prepared by

Franklin Regional Council of Governments and

University of Massachusetts Traffic Safety Research Program

Massachusetts Highway Department

Prepared for

May 2008

Federal Highway Administration

1.0 Introduction to Road Safety Audits & Lane Departure Crashes in Massachusetts

The Federal Highway Administration defines a Road Safety Audit (RSA) as the formal safety examination of an existing or future road or intersection by an independent, multidisciplinary team .

The purpose of an RSA is to identify potential safety issues and possible opportunities for safety improvements considering all roadway users. Specific objectives of an RSA include, but are not limited to the following:

Minimize the risk and severity of road crashes that may be affected by the existing or future roadway at a specific location or nearby network;

Improve the awareness of safe design practices which are likely to result in safety benefits based upon potential safety concerns.

Although RSA’s have been employed in other countries for some time, they are being fully embraced across the United States as a low cost opportunity to make significant safety improvements at any number of stages ranging from project development and planning through existing operation.

Furthermore, RSA’s have proven to be effective on projects of all shapes and sizes. The RSA program here in the Commonwealth presents a unique and exciting opportunity for improvements in roadway safety.

The RSA program in Massachusetts is being implemented in accordance with the Commonwealth’s role as a Lead State in preventing run-off the road (lane departure) crashes and in conjunction with the

Strategic Highway Safety Plan (SHSP). Lane departure crashes are a notable problem area for

Massachusetts, especially for crashes with higher injury severities. Between 2002 and 2004, lane departure crashes accounted for nearly 20 percent of all crashes in Massachusetts and approximately one-quarter of crashes involving an incapacitating injury. Almost one-half of fatal crashes between

2002 and 2004 were lane departure crashes. As the crash severity increases, so to does the percent of crashes that are lane departures as shown in Figure 1.

Figure 1. Relationship Between Lane Departure Crashes and Injury Severity

In an effort to combat the lane departure problem, a strategy was developed for the SHSP to identify hot spot lane departure locations, perform road safety audits and implement low-cost comprehensive countermeasures. The enclosed following report summarizes the findings of a RSA focused on lane departure crashes (LD) along Route 2 in Shelburne, Massachusetts.

Page 2

2.0 Background Material for Route 2 in Shelburne

Shelburne, home to approximately 2,050 residents, is a Massachusetts municipality located in Franklin

County in the Northwestern part of the state. Route 2 through Shelburne is the gateway to the popular tourist attraction of the Village of Shelburne Falls, which boasts the natural attractions such as the glacial potholes and Salmon Falls and the famous Bridge of

Flowers, which draw large volumes of seasonal traffic along the corridor. This traffic can become particularly heavy during the fall season when foliage drives are popular. It is worth noting that Route 2 is a designated State and National Scenic

Byway, known as the Mohawk Trail Scenic Byway.

In addition to the high seasonal variation, the traffic volumes along Route 2 are fairly mixed with passenger cars, motorcycles, commercial motor vehicles, as well as bicycles.

Route 2 is a two-lane, bidirectional rural principal arterial

Figure 2 Route 2 in Shelburne roadway spanning approximately 7.5 miles through

Shelburne, and more globally, Route 2 is part of the National Highway System connecting Boston, MA to Buffalo, NY. The stretch of Route 2 under observation (located only in Shelburne) has lane widths of 12 ft. with 6-inch longitudinal pavement markings and 8-10 feet paved shoulders. The full length of

Route 2 through Shelburne was resurfaced in July 2007. Frequent horizontal and vertical curves make up this stretch of roadway.

A sample cross-section is pictured in Figure 2. Although the entire corridor through Shelburne was considered, a specific focus of this RSA was a 0.6 mile stretch approximately 1.25 miles west of the Greenfield town line, where 12 lane departure crashes occurred between 2003 and 2006.

The LD-RSA for Route 2 was held on July 11, 2007 at the Franklin Regional Council of Governments

Planning Department Conference Room .

In total, 12 team members participated in the road safety audit as listed in Table 1. As indicated in Table 1 representatives were present from Federal, State,

Regional and Local agencies and included a cross-section of engineering/planning, education, and enforcement expertise.

Table 1 Participating Audit Team Members

Audit Team Members

Bonnie Polin

Jennifer Inzana

Neil Boudreau

Alex Normandin

Richard Marquis

Laurie Scarbrough

Patrick Tierney

Tim White

Keith Wilson

One Hwang

Dennis Eugin

Michael Knodler

Agency/Affiliation

Massachusetts Highway Department – Safety Section

Massachusetts Highway Department – Safety Section

Massachusetts Highway Department – Traffic Engineering

Massachusetts Highway Department

Federal Highway Administration

Massachusetts Highway Department, District 2

Massachusetts Highway Department, District 1

Federal Highway Administration

Franklin Regional Council of Governments

Massachusetts Highway Department – Chief’s Office

Massachusetts State Police

University of Massachusetts - Amherst

Page 3

Given the length of the Route 2 through Shelburne and the relative unfamiliarity of many audit team members with the roadway, participants were asked to visit the site in advance of the meeting to familiarize themselves with the roadway attributes and characteristics. A copy of the meeting agenda and instructions as well as a packet of pertinent information was distributed to meeting invitees prior to the meeting (this information is included in the Appendix this report). Specifically, the additional information provided was pertinent to the LD-RSA safety initiative and included traffic volumes and speeds as well as a description of relevant crashes as summarized below:

Table 2 presents daily directional volumes collected as part of a 9-day volume study completed in August of 2004 by the Franklin Regional Council of Governments (FRCOG). As shown in

Table 2 the directional splits are approximately equally with an average weekday ADT of

14,112 vehicles and weekend ADT of 13,367 vehicles. The data were collected nearly one half mile east of the Shelburne Town line in Greenfield. A March 2006 volume study completed just west of the Shelburne/Greenfield town line by MassHighway reported an average weekday

ADT of 11,274 vehicles.

The posted speed along Route 2 in Shelburne is primarily 50 mph with a small stretch of roadway posted at 45 mph. The official speed regulations for Route 2 in Shelburne are summarized in Table 3.

Between 2003 and 2006 there were 40 reported crashes consistent with the lane departure initiative which were geolocated and presented in Figure 3. A more detailed summary of the 12 lane departure crashes in the specific 0.6 mile section under consideration are presented in

Figure 4. A complete summary of the 40 identified crashes over the 4-year period was provided to participants prior to the audit meeting. Please note that this does not reflect all crashes along

Route 2, but those deemed relevant to this lane departure initiative.

Table 2 Traffic Volumes for Route 2 – Collected August 2004

Eastbound Volumes

Daily AM PM

Date Volume

Wed. 8/11/04 7,005

Peak

586

Peak

511

Thur. 8/12/04 7,214

Fri. 8/13/04 7,530

Sat. 8/14/04 7,438

596

576

710

493

556

582

Sun. 8/15/04 6,226

Mon. 8/16/04 6,620

Tue. 8/17/04 6,975

Wed. 8/18/04 6,903

528

572

562

566

591

471

512

496

Westbound Volumes

Daily AM PM

Volume

6,922

7,105

8,168

7,902

5,168

6,304

6,857

6,893

Peak

384

354

474

633

362

359

430

418

Peak

671

725

773

713

487

680

683

669

Total Daily

Volumes

13,927

14,319

15,698

15,340

11,394

12,924

13,832

13,796

Thur. 8/19/04 7,086 564 490 7,207 412

Table 3 Summary of Speed Regulations for Route 2 in Shelburne

670 14,293

Westbound Eastbound

Beginning at the Greenfield line

7.14 miles at 50 mph

0.39 miles at 45 mph

Ending at the Buckland line

Beginning at the Buckland line

0.39 miles

7.14 miles

At 45 mph

At 50 mph

Ending at the Greenfield line

Page 4

Primary focus area of LD-RSA.

0.6 mile stretch of Route 2 with

12 crashes between 2003 and

2006 (see Figure 4)

Figure 3 4-Year Summary of Route 2 Lane Departure-Related Crashes.

Page 5

Figure 4 Summary of Details for Selected Crashes on Route 2 in Shelburne.

Page 6

3.0 Characterization of Major Traffic Safety Challenges

Following a brief introduction to the RSA process in general, the meeting participants were asked to summarize and characterize potential safety considerations along Route 2. The initial characterization of the major safety considerations focused on several key elements as follows:

Weather was discussed as a possible factor in a significant percentage of the considered crashes. The most common weather events involved vehicles sliding/losing control due to roadway conditions, and given the proximity of the adjacent travel lane or roadside resulted in a lane departure crash.

Another point of consideration at this stage of the RSA was access from adjoining roadways and driveways. Specifically noted were challenges with queued vehicles (e.g. not recognizing stopped vehicle) and the speed differential amongst vehicles.

Driver expectancy on this segment was listed as a possible concern and can be improved along this corridor. A fair portion of crashes occurred during adverse weather conditions or on a horizontal curve and advanced warning signs can be used to address both of these crash contributing factors. Also related to increasing driver expectancy was concern regarding animal crossings in the area.

Route 2 does not have any lighting. Poor lighting paired with signage that is difficult to interpret due to age or other reasons can create an unsafe environment for motorists. Solar panel lighting or other such lighting along this corridor can improve visibility, especially at night.

Other significant factors mentioned at the outset of the meeting that are discussed in further detail later in this report also included the following:

Passing opportunities (see Figure 5);

The presence of slower moving vehicles and absence of climbing lanes;

Driver expectancy at intersections;

Concern about increased traffic volume from future developments. For example, a condominium development project at Mount

Snow ski resort in Vermont may increase traffic volumes at and to the east of the Colrain-

Figure 5 Route 2 Passing Zones

Shelburne Road intersection as this is a route used by many to access this resort ; and

The presence of motorcycles and bicycles which frequent this stretch of roadway.

4.0 Summary of Short Term Recommendations for Route 2

The formal review of potential safety concerns along Route 2 was completed by the entire audit team.

Following identification of a potential safety issue the dialogue subsequently focused on possible countermeasures with some preliminary discussion regarding the feasibility of implementation

(timeframe and cost) as well as the potential payoff of safety benefits. Given the potential for an immediate impact there was an added focus on short term (less than 1 year) and low cost (less than

Page 7

$10,000) that could be done almost instantaneously resulting in a positive safety impact. Resulting recommendations for immediate actions along Route 2 include the following:

The placement of uniform chevron alignment signs at selected horizontal curves. Nearly all horizontal curves along Route 2 have advanced curve warning signs which show side street configurations (see Figure 6); however curve chevron signs and possibly roadside reflectors could be used at sharper horizontal curves. Specific locations would include the curve at Shelburne Summit Drive as well as Old Greenfield Road.

It is also recommended that advanced warning signs be installed in relevant areas such as: “Slippery When Wet”,

“Cross Road”, advance street name, or animal crossing signs

(near power line crossing). Please note that there is already

Moose Crossing signage (see Figure 7) in place along the

Figure 6 Advance Curve corridor.

Replace signage that is faded or worn with highly retroreflective signage. Please note that a majority of signage along this corridor is properly placed and in good condition, and this recommendation is intended to highlight the importance of this practice moving forward.

It is recommended that street signs with a 4 inch legend be replaced with more legible street signs (6 inch legend) and be

Figure 7 Moose Crossing made more visible.

Another recommendation for enhanced centerline visibility and delineation may be the addition of raised reflective pavement markers.

Continue maintenance of roadway: pavement surface, pavement markings, and edges to prevent edge line drop off.

It is recommended that existing passing zones be analyzed to verify they are of appropriate length and provide adequate sight distance. The general sense at the RSA is that they are currently adequate, but should be revisited. A longer-term possibility for consideration would include the addition of passing and/or climbing lanes.

Some general trimming and landscaping can help improve sight distance around horizontal curves, and driveways.

5.0 Summary of Additional Route 2 Countermeasures

Although an emphasis was placed upon short term and low cost improvements that could be carried out immediately, the focus of the team was not limited to solely those countermeasures. The following section details countermeasures discussed by the team, which are reflective of all costs and timeframes and includes both general (entire corridor) and specific safety opportunities. Please note that with respect to the timeframe there are some unknown variables that must be further explored. Several definitions exist for low, mid, and high cost as well as for short, mid and long term implementation timeframes. For purposes of this report, low cost improvements will be under $10,000, mid costs will be under $50,000, and high costs will be above $50,000. From a timeframe perspective short term will refer to less than 1 year while mid and long term will refer to countermeasures that will take 1 to 3, and greater than 3 years, respectively.

Page 8

Potential

Safety Issue Possible Countermeasures

Implementation

Timeframe

& Cost

Potential Safety

Payoff

Reflectorize existing guard rails along the entire corridor

Short Term &

Low Cost

Mid

Photos

Addition of curve ahead and chevron alignment warning signs and roadside reflectors at Old Greenfield

Road and Shelburne Summit Drive curves

Short Term &

Low/Mid Cost

Mid

Horizontal curvature

Maintain landscape and roadside to improve sight distance around curves

Short Term &

Low Cost

Low

Revisit crash data and consider additional guardrail along roadway at horizontal curves where there are crashes with fixed objects or embankments

Mid Term &

Mid Cost

Mid

Where loss of grip on horizontal curves has been found to be a contributing factor in crashes consider applying a high friction surface treatment such as TyreGrip.

Short/Mid Term

& Low/Mid Cost

Mid/High

Page 9

Potential

Safety Issue

Distracted or drowsy drivers

Possible Countermeasures

Implementation

Timeframe

& Cost

Consider rumble strips/stripes in non residential areas along roadway

Mid Term &

Mid Cost

Potential

Safety Payoff

Mid

Install raised centerline pavement markers to improve roadway delineation

Short Term &

Low/Mid Cost

Centerline and/or edge line crossover Consider installation of a median barrier between opposing traffic streams at locations with high frequency cross over the centerline crashes occur

Mid/Long Term

& High Cost

Late notification of approaching intersection

Install advanced warning signs indicating that there is an intersection ahead, and the cross street name(s). Ensure all street signs have 6 inch legend. A specific example is Colrain-Shelburne Road

Short Term &

Low/Mid Cost

Accommodating large program “Motorcycles are

Everywhere” administered by the tourist and motorcycle

Highway Safety Division populations

Participate in an educational

Provide notification of popular tourist attractions / intersections

Short Term &

Low Cost

Short Term

& Low Cost

Mid

High

Mid

Low

Mid

Photos

Page 10

Potential

Safety Issue Possible Countermeasures

Speed variance from cars entering/exiting the roadway and slow moving vehicles

Provide climbing lanes for slower vehicles and trucks if the percentage of trucks exceeds thresholds.

Add turn lanes at selected side street and driveways as volumes warrant

Implementation

Timeframe

& Cost

Long Term &

High Cost

Long Term &

High Cost

Potential

Safety Payoff

Mid/High

High

Minimizing the effects of lane departure; crossing the edge line

Maintain and fill roadside as needed to prevent edge drop-off

Provide road edge with guardrail

Install guardrail end treatments on all sections of guardrail

Short Term &

Low Cost

Mid Term &

Mid/High Cost

Short Term &

Mid Cost

Low

High

Mid/High

Dark stretches of

Roadway

Consider installation lighting along dark stretches of road. Solar power lighting may be a good option for this location

Long Term &

Mid/High Cost

Mid

Continued maintenance

The pavement condition, drainage, and coverage resulting from brush are in good condition. To assure safety this needs be maintained

Weather-related crashes along the

Route 2 corridor

Add warning signs alerting motorists of possible weather impacts.

Employ a VMS periodically during the winter months to remind motorists about weather issues.

Short Term &

Low Cost

Short Term &

Low Cost

Mid

Mid

WINTER

WEATHER

Photos

Page 11

6.0 Discussion

With respect to the safety improvement opportunities described in the previous section it is important to consider the following: 1) many treatments are both low cost and short term and 2) there is a complimentary nature of many of the safety strategies in that one improvement will aid with multiple safety issues. Please note that although this document provides a series of specific recommendations which warrant short-term implementation, it should be noted that the approach towards improved safety is dynamic in nature and warrants revisiting over time.

The designation of Route 2 as a State and National Scenic Byway (Mohawk Trail Scenic Byway) is an important consideration, as any of the changes implemented must be sensitive to this designation. The full Mohawk Trail Corridor Management Plan can be viewed online at http://frcog.org/pubs/index.php#trans

An additional topic discussed at the meeting was the potential impacts from future development which could add more traffic to the Route 2 corridor. As noted, Route 2 has a mixture of residential and commercial zoning along its length and the RSA team felt strongly that any future development should attempt to minimize where possible the number of curb cuts that access Route 2. Additionally, the safety impact of any new curb cut or roadway needs to be accounted for in the MassHighway permitting process.

Page 12

7.0 Appendix A: Distributed RSA Meeting Materials

Materials provided to RSA team members in advance of the meeting included the following:

1.

Meeting Invite

2.

RSA and Lane Departure Introduction

3.

Summary of Traffic Volumes

4.

LD-RSA Checklist

Please note that team members were also provided with the crash summaries prepared by FRCOG that were presented in Figure 3 and 4.

Page 13

Page 14

An Introduction to Road Safety Audits & Lane Departure Crashes in Mass.chusetts

The Federal Highway Administration defines a Road Safety Audit (RSA) as the formal safety examination of an existing or future road or intersection by an independent, multidisciplinary team .

The purpose of an RSA is to identify potential safety issues and possible opportunities for safety improvements considering all roadway users. Specific objectives of an RSA include, but are not limited to the following:

Minimize the risk and severity of road crashes that may be affected by the existing or future roadway at a specific location or nearby network;

Improve the awareness of safe design practices which are likely to result in safety benefits based upon potential safety concerns.

Although RSA’s have been employed in other countries for some time, they are being fully embraced across the United States as a low cost opportunity to make significant safety improvements at any number of stages ranging from project development and planning through existing operation.

Furthermore, RSA’s have proven to be effective on projects of all shapes and sizes. The RSA program here in the Commonwealth presents a unique and exciting opportunity for improvements in roadway safety.

The RSA program in Massachusetts is being implemented in accordance with the Commonwealth’s role as a Lead State in preventing run-off the road (lane departure) crashes and in conjunction with the

Strategic Highway Safety Plan (SHSP). Lane departure crashes are a notable problem area for

Massachusetts, especially for crashes with higher injury severities. Between 2002 and 2004, lane departure crashes accounted for nearly 20 percent of all crashes in Massachusetts and approximately one-quarter of crashes involving an incapacitating injury. Almost one-half of fatal crashes between

2002 and 2004 were lane departure crashes. As the crash severity increases, so does the percent of crashes that are lane departures as shown in the figure below.

In an effort to combat the lane departure problem, a strategy was developed for the SHSP to identify hot spot lane departure location, perform road safety audits and implement low-cost comprehensive countermeasures.

Page 15

Page 16

Page 17

GEOMETRIC DESIGN

Issue Comment

A. Speed – (Design Speed; Speed Limit & Zoning; Sight Distance; Overtaking

Are there speed-related issues along the corridor?

Please consider the following elements:

Horizontal and vertical alignment;

Posted and advisory speeds

Driver compliance with speed limits

Approximate sight distance

Safety passing opportunities

B. Road alignment and cross section

With respect to the roadway alignment and crosssection please consider the appropriateness of the following elements:

Functional class (Urban Principal Arterial)

Delineation of alignment;

Widths (lanes, shoulders, medians);

Sight distance for access points;

Cross-slopes

Curbs and gutters

Drainage features

C. Intersections

For intersections along the corridor please consider all potential safety issues. Some specific considerations should include the following:

Intersections fit alignment (i.e. curvature)

Traffic control devices’’ alert motorists as necessary

Sight distance and sight lines seem appropriate

Vehicles can safely slow/stop for turns

Conflict point management

Adequate spacing for various vehicle types

Capacity problems that result in safety problems

D. Auxiliary lanes

Do auxiliary lanes appear to be adequate?

Could the taper locations and alignments be causing safety deficiencies?

Are should widths at merges causing safety deficiencies?

Page 18

E. Clear zones and crash barriers

For the roadside the major considerations are clear zone issues and crash barriers. Consider the following:

Do there appear to be clear zones issues?

Are hazards located too close the road?

Are side slopes acceptable?

Are suitable crash barriers (i.e, guard rails, curbs, etc.) appropriate for minimizing crash severity?

Barrier features: end treatments, visibility, etc.

F. Bridges and culverts – (if necessary)

Are there specific issues related to bridges and culverts that may result in safety concerns?

G. Pavement – (Defects, Skid Resistance, and Flooding)

Is the pavement free of defects including excessive roughness or rutting, potholes, loose material, edge drop-offs, etc.) that could result in safety problems (for example, loss of steering control)?

Does the pavement appear to have adequate skid resistance, particularly on curves, step grades and approaches to intersections?

Is the pavement free of areas where flooding or sheet flow of water could contribute to safety problems?

In general, is the pavement quality sufficient for safe travel of heavy and oversized vehicles?

H. Lighting (Lighting and Glare)

It is important to consider to the impacts of lighting.

Some specifics include the following:

Is lighting required and, if so, has it been adequately provided?

Are there glare issues resulting from headlights during night time operations or from sunlight?

Page 19

TRAFFIC CONTROL DEVICES

Issue

I. Signs

Signage is a critical element in providing a safe roadway environment. Please consider the following:

Are all current signs visible (consider both night and day)? Are they conspicuous and clear? Are the correct signs used for each situation?

Does the retroreflectivity or illumination appear satisfactory?

Are there any concerns regarding sign supports?

J. Traffic signals

Although the focus of this RSA are lane departures, this does present an opportunity for us to consider any traffic signals. Specifically:

If present, do the traffic signals appear to be designed, installed, and operating correctly?

Is the controller located in a safe position?

(where it is unlikely to be hit, but maintenance access is safe)

Is there adequate sight distance to the ends of possible vehicle queues?

K. Marking and delineation

Is the line marking and delineation:

⎯ appropriate for the function of the road?

⎯ consistent along the route?

⎯ likely to be effective under all expected conditions? (day, night, wet, dry, fog, rising and setting sun, oncoming headlights, etc.)

Are centerlines, edgelines, and lane lines provided? If not, do drivers have adequate guidance?

Comment

Page 20

ROADWAY ACTIVITY

Issue

With respect to roadway activity please consider safety elements related to the following:

Pedestrians

Bicycles

Public transportation vehicles and riders

Emergency vehicles

Commercial vehicles

Slow moving vehicles

Comment

ENVIRONMENTAL CONSIDERATIONS

Issue

Weather & Animals

From an environmental perspective it is important to consider any potential impacts. Most notably is likely to be the impacts of weather or animals, including:

Possible effects of rain, fog, snow, ice, wind on design features.

Has snow fall accumulation been considered in the design (storage, sight distance around snowbanks, etc.)?

Are there any known animal travel/migration routes in surrounding areas which could affect design?

Comment

Page 21

Download