TO: Lina Swan, Director of Fiscal Operations FROM: Stephen H. Clark, Administrative Law Judge DATE: May 4, 2005 RE: Request for Direct Payment Claimant: Contractor: Contract # City/Town: Amount: J. M. Cook Co., Inc. (Cook) Roads Corporation (Roads) Contract #30157 Franklin (Pond Street Reconstruction) $2,925.00 1. I have reviewed the direct payment demand (Demand) by Cook dated April 26, 2005 and received by the Department on April 29, 2005. For the reasons set forth below, I find the Demand as filed does not comply with the requirements of G.L. c.30, s.39F (Section 39F) and must be rejected without prejudice. 2. Section 38F requires that the Demand be “sent by certified mail” to the general contractor at the time it is mailed to the awarding authority. Although the Demand recites that it was sent certified mail to the Department, no statement or proof of certified mailing to Roads appears. Because no statement or proof that the mailing requirement appears—as for example, by reciting the number on the postal mailing receipt—Cook failed to meet the mailing requirement of Section 39F. 2. Section 39F requires that a “demand shall be by sworn statement.” That requirement of Section 39F is typically met by a statement such as “The undersigned swears under the pains and penalties of perjury that the statements made in this direct payment demand are true, complete and correct.” Cook’s Demand is not sworn. This fatal defect alone requires rejection of the Demand. 3. Section 30F requires that the Demand contain “a statement of the status of completion of the subcontract work.” Cook states that “[a]ll of the items of Work relative to Cook Invoice #2280 were completed in the late spring and early summer of 2000….” Because that statement is not under oath it cannot be considered. However, as it is likely that Cook will refile a demand, I point out that Section 39F appears to require that a subcontractor’s statement of completeness should be made with respect to the subcontract work as a whole, not work billed under a single invoice. See Section 39F(1)(d). 4. Section 39F requires that a “demand shall contain a detailed breakdown of the balance due under the subcontract.” Cook’s Demand fails to meet this statutory requirement as well. Cook’s Demand contains no “detailed breakdown” at all—it merely attaches various documents to a letter and apparently seeks to have the Department read the attachments assess their significance. Section 39F, on the other hand, plainly requires that a subcontractor demand contain detailed breakdown of the balance due under the subcontract. This Cook must do if it refiles its Demand under Section 39F.1 5. Cook’s Demand is rejected without prejudice; it may refile a new Demand at another time. 6. Accordingly, take no further action on this Demand. cc: J. M. Cook Co., Inc. 252 Milford Street Upton, MA 01568 The Roads Corporation 241 Treble Cove Road North Billerica, MA 01852 Deputy Chief Engineer, Construction District Highway Director, District 3 1 In the event Cook files a renewed demand at a later date that demand should contain a “detailed breakdown of the balance due under the subcontract” that clearly sets forth the original value of the subcontract, all additions to the subcontract through Department approved amendments, all pending but unapproved amendments, all payments made by the general contractor for work done, any retainage held, all credits, back charges and all other information needed to demonstrate what Department approved work was done but remains unpaid.