.. • COMMONWEALTH OF MASSACHUSETTS MASSACHUSETTS HIGHWAY DEPARTMENT BOARD OF CONTRACT APPEALS DATE: April 28, 2004, Item #1 CLAIM: B & E Construction Corporation, aggrieved by the Massachusetts Highway Department's denial of its cla;m for rental of a temporary bridge over the Nashua River on Route 119 on the GrotonIPepperellline while curative work took place on the permanent bridge under Contract No. 98442 appealed to Board of Contract Appeals. RECOMMENDATION: The claim of B & E Construction Corporation under Contract No. 98442 for the rental of a temporary bridge in the amount of$41,640.00 should be denied. FOR DEPARTMENT SECRETARY Item # __L ___________________________________________________---------------­ Date __Y~.J_LQ.L..... _......_..._......._.....___..._•......----_....... The Board accepted the recommendation to deny. Claim Denied. A TRUE COPY ·ATTEST X OtG (.Q".........l ..._~ SECRETfIIW,M;'\SS. HI GHW;'Y COMM . MA~S. HiGrl':VAY QFr-:~ .~n:i ENT ,~.!:~::.::?nw~;:!~~~2:::..::~~:::~ B&E Construction, Inc. (Contractor or B& E), aggrieved by the denial of its claim before the claims committee of the Massachusetts Highway Department (Department or MHD) for the cost of rental of a temporary bridge for $41,640.00 under MHD contract #98442 (Contract) appealed to the Board of Contract Appeals (Board) on February 9, 2001. I find that B&E’s appeal has no merit. B&E’s rental of a temporary bridge for 1.5 months was part and parcel of its contractually mandated expense to correct its own admittedly defective work. I therefore recommend the Board deny B&E’s appeal. STATEMENT OF THE CASE The Contractor’s appeal was heard June 12, 2001. A tape recording was made of the hearing. Present were Peter Milano Isaac Machado Cameron Smith Wayne Eng Chief Administrative Law Judge Deputy Chief Counsel MHD, District #3 President, B&E The following exhibits were admitted into evidence. Ex. #1 Ex. #2 Ex. #3 Ex. #4 MHD Contract # 98442; B&E Statement of Claim, 2/14/01, and 8 attachments; Memorandum of John Blundo, 2/20/01, to Judge Milano, with 3 attachments; and Memorandum of Thomas Waruzila, District #3 Highway Director, 3/5/01, to Judge Milano. Renewed hearings were scheduled for June 18, 2002, and then July 9, 2002. No renewed hearing was ever held. In July 2003 Chief Administrative Law Judge Peter Milano resigned. On March 1, 2004 the undersigned was appointed Chief Administrative Law Judge. On March 16, 2004 I conducted a conference on the record. Present were Mr. Wayne Eng, Mr. Isaac Machado, and Ms. Mary L. Bearse, Fiscal Management, MHD. I informed the parties that, in light of the resignation of Judge Milano, the appeal could either be reheard or decided on the existing record, if the parties so agreed. B&E and MHD stated they were content to have the appeal so decided. B&E and MHD argued their respective positions at the conference, but the administrative record was not reopened to take evidence. FINDINGS OF FACT Substantial evidence in the record, which consisted of tape recorded testimony and the four exhibits admitted by Judge Milano, supports the following findings of fact, which I recommend the Board adopt. 1. The Department awarded Contract # 98442 to the B&E Construction (Contractor or B&E) on July 22, 1998. The work was to reconstruct a bridge (by continuous steel stringer) over the Nashua River on the Groton/Pepperell line on Routes 111/119. B&E bid $1,996,747.22 for the work. 2. Item 993.3 of the Contract was for the rental of a temporary bridge needed to carry traffic over the Nashua River during the work. The bid documents required the Contractor to state a unit price per month for an estimated time of 15 months. B&E bid a unit price of $27,760/month for a total bid of $416,400.00 (15 X $27,760.00) on Item 993.3. The Department testified that 15 months was a “a conservative estimate intended to envelope [sic] reasonable temporary bridge use scenarios.” 2 3. The work under the Contract was to be in conformance with the Department’s Standard Specifications For Highways and Bridges (1988 ed.) (Standard Specifications) and the Supplemental Specifications (November 30, 1994) as amended by the Standard Special Provisions (February 19, 1998), and other standards set forth, including without limitation the Contract Plans and Special Provisions. 4. The Notice To Proceed was given on October 14,1998 with an original completion date of July 17, 1999. B&E made three requests for extension of time, all of which were duly granted by the Department. The time for completion was ultimately extended to December 15, 2000. 5. B&E entered into a contract with Acrow Corporation of America (Acrow) to supply the temporary bridge. The contract was not offered into evidence. 6. The Contract specifications called for a lightweight, steel reinforced concrete deck on the new bridge. B&E made a concrete pour in late June (or early July) on the new bridge deck after steel reinforcement rods (rebar) had been fitted. The specifications provided that the concrete should cover the rebar by a specified depth so that road salt would not contaminate the rebar and cause it to deteriorate. 7. MHD measured the thickness of the concrete overlay with a non-intrusive concrete depth-measuring device (Measuring Device). The Measuring Device readings of late June (or early July) showed that the concrete pour did not cover the rebar to the depth specified. 3 8. The Department ordered B&E to take corrective action. B&E disputed the need for corrective action, claiming that the Measuring Device was not accurate. The Department and B&E then conducted field testing. The results showed that the depth of the concrete overlay recorded by the Measuring Device correlated very closely to overlay depth measured by field testing. B&E conceded that corrective action was necessary. 9. B&E proposed a plan for corrective action to MHD on July 13, 2000, which called for B&E to chip away the original concrete overlay to expose the rebar. The rebar would then be cleaned, coated and covered by a new cement overlay. The Department approved B&E’s plan with minor modifications on July 17, 2000. 10. Three to four weeks elapsed from the time of the original concrete pour until the Department approved B&E’s plan for corrective action. 11. B&E began the corrective work in August 2000. It was completed by Labor Day. The temporary bridge was removed in early September 2000. 12. Six to eight weeks elapsed between the discovery of the defective work and B&E’s completion of the corrective work. 13. B&E paid Acrow for 14.4 months of bridge use. The Department paid B&E for 12.9 months of temporary bridge rental under Item 993.3. As a result of the need to correct the work, B&E paid Acrow additional rent for 1.5 months, which the Department refused to pay. B&E claims the Department must pay it $41,640.00, based on the unit price in Item 993.3 ($27,760 X 1.5). 4 14. The temporary bridge was removed in early September 2000 after B&E completed the remedial work. 15. Had B&E not been required to perform corrective work, B&E would not have paid Acrow the additional 1.5 month’s rent. DISCUSSION It is a familiar principle that public contractors must strictly comply with project plans and specifications. See Albre Marble & Tile Co. v. Goverman, 353 Mass. 546, 549 (1968). B&E admits by word and action that it failed to pour concrete over the rebar on the bridge deck to the depth specified. B&E does not claim that the Department or anyone else contributed to B&E’s failure to correctly perform the bridge deck work. The Contract expressly addresses the obligations of the contractor when its work fails to meet the governing specifications. Subsection 5.10 of the Standard Specifications entitled “Removal of Defective or Unauthorized Work” provides, in pertinent part, All defective work shall be removed, repaired or made good…. If the work or any part thereof shall be found defective at any time before the final acceptance of the whole work, the Contractor shall at his own expense make good such defect in a satisfactory manner. Subsection 5.10 governs the result here. The Department discovered the defect after the original concrete pour. It never accepted the work. B&E, once it had no choice but agree that the readings of the Department’s concrete Measuring Device were accurate, did not contest its responsibility to “remove” the non conforming cement cover, “repair” the work and “make good” its performance. B&E thus performed the corrective work that Subsection 5.10 required within eight weeks. Subsection 5.10 in broad, clear and unambiguous language provides that the Contractor “shall at his own expense make good such defect.” Where the wording of a 5 contract is found to be unambiguous, the contract must be enforced according to its terms. See BayBank Middlesex v. 1200 Beacon Properties, Inc., 760 F. Supp. 957, 963 (D. Mass. 1991). The phase “shall at his own expense make good such defect” plainly means that the financial onus to cure falls on the contractor alone. Part of B&E’s “own” expense to cure was its cost to rent a temporary bridge for 1.5 additional months. Under the Contract that cost is properly charged to B&E alone in the circumstances here. B&E makes three arguments contending that the Department, not B&E, must pay 1.5 months of extra rent under Item 993.3. None has merit. B&E first claims that, because Item 993.3 specifies a unit price/month for temporary bridge rental, the Contract imposes upon the Department a separate obligation to pay for bridge rental. As B&E puts it “The rental of the bridge is not related to the corrective action of the work. The state used the bridge for the 1.5 months in question.” But it is uncontradicted that the public used the temporary bridge only because use of the new bridge was delayed. Thus, the corrective action and the extended use of the temporary bridge are not separate but inextricably linked. B&E next claims that the Department must pay under Item 993.3 because the Contract estimate of 15 months was not exceeded. However, B&E erroneously supposes that the Department’s estimate of 15 months “guarantees” payment to B&E no matter the circumstances. Here had B&E’s work not been defective the temporary bridge would only have been used for 12.9 months. Item 993.3 is not a guarantee of payment for use for an estimated time of 15 months in all circumstances. Third, B&E argues that the Department should pay for the temporary bridge rental because it failed to notify B&E that it would refuse to pay B&E under Item 993.3 6 as B&E hoped. The Contract does not obligate the Department to notify B&E how it will rule on a claim B&E had yet to file.1 B&E had the obligation to present the Department with a plan to fix the work. The use of the temporary bridge was part of its plan and thus it is part of B&E’s “own expense.” FINDINGS I find that Subsection 5.10 requires B&E to bear the full expense necessary to correct its own defective work, of which increased bridge rental expense was an integral part. RECOMMENDATION The Board should adopt the findings of fact set forth above. I recommend that the Board deny B&E’s claim. Respectfully submitted, Stephen H. Clark Chief Administrative Law Judge 1 The Department did not defend this appeal on the grounds that B&E failed to timely file its claim for compensation. The Standard Specifications require, among other things, that “all claims … must be made in writing to the Engineer within one week after the beginning of any work or the sustaining of any damage ….” Section 7.16. B&E’s claim letter to the Department was dated October 20, 2000, which appears to be more than one month after B&E had fully performed the work to make good the defect. 7