To: Secretary Daniel A. Grabauskas, EOT Through: Commissioner John Cogliano, MHD eJJf- From: Stephen H. Clark, Administrative Law JUdge)lt ~ Date: January 20, 2005 Re: Report and Recommendation fJ ~r < r I am pleased to submit for your consideration and approval the attached report and recommendation. HNTB, a consultant that designed the Brightman Street Bridge in Fall River undcr MHD contract #92607, appealed on October 4,1999 seeking $717,460.00 in funds "to cover labor escalation costs." The appeal should be dismissed because it is moot. Subsequent tu its appeal HNTB and the Department at various times between 2000 and 2004 modified the Contract. Among such modifications were increases to the Contract of approximately $292,000.00. Such increases to the Contract supersede HNTB's appeal. Because the subject matter of the appeal was addressed in subsequen t contract modifications, approved by both HNTB and the Department, the appeal has been rendered moot and should be dismissed. Massachusetts Highway Department· Ten Park Plaza, Boston, MA 02116-3973 · (617) 973-7800 INTRODUCTION HNTB, a consultant responsible for the design of the Brightman Street Bridge in Fall River-Somerset under MHD contract #92607 (Contract), appealed to this office on October 4, 1999 seeking $717,460.00 “for additional funds [to be added to the existing contract] to cover the escalation in labor costs.” HNTB appealed after the Department decided in 1999 that it would not make a cost escalation adjustment to the Contract. Subsequently, between 2000 and 2004, the Department and HNTB agreed to several Contract modifications, including requests for extra costs. Accordingly, this appeal is moot and should be dismissed. BACKGROUND At the time it appealed HNTB had since 1992 been under Contract to design a replacement for the Brightman Street Bridge in Fall River. The Contract permitted (but did not require) the parties to renegotiate the contract fee if there was an approved extension of time for more than one year beyond the “specified time period” of performance. In 1998, the year before this appeal, the Department and HNTB had agreed to a $500,000 cost escalation adjustment and a contract increase of $200,000 for added work after the Contract term had been extended. When HNTB appealed the maximum contingent obligation under the Contract was $6,385,000.00. Statement of Claim, Ex. 10. HNTB styled this appeal as a “ non-adversarial claim” to obtain additional funds “to accommodate cost escalation due to [project] extensions.” On January 13, 2000, Judge Milano held a conference with representatives of both the Department and HNTB.1 1 The undersigned replaced Judge Milano on March 1, 2004 and makes this report and recommendation to the Commissioner of the Department pursuant to St. 2004, c. 196, s. 5. Thereafter, on January 25, 2000, HNTB requested the Department to make a transfer of funds and certain internal budget reallocations within the Contract totaling $185,986.00. The Department agreed to both requests, which the Board of Commissioners (Board) approved on April 19, 2000. Between 2000 and 2004 the Department approved further increases in the total contingent cost of the Contract. By August 19, 2004 the total value of the work done had risen to $6,677,067.90. The Contract is active in fiscal year 2005. The Department’s most recent payment (for $16,102.22) was approved on September 29, 2004. Neither HNTB nor the Department took any action at the office of the Administrative Law Judge following the conference of January 13, 2000. DISCUSSION HNTB’s appeal was not from a final decision of the Department. Rather, its appeal was apparently made in the context of on-going negotiations. Those negotiations were partially successful since the Board approved the reallocation of existing Contract funds on April 19, 2000. Thereafter, between 2000 and 2004, HNTB and the Department reached additional agreements by which the Contract amount of $6,385,000.00 (at the time of the appeal) increased by approximately $292,000.00 to $6,677,067.90 (by August 19, 2004). CONCLUSION AND RECOMMENDATION There is no doubt that HNTB’s 1999 appeal is no longer the subject of any present controversy. If HNTB filed a justiciable appeal in this office in 1999, a proposition subject to considerable doubt, that appeal is now moot. The subject matter of 2 HNTB’s 1999 appeal has been entirely overtaken by events, as the Department’s subsequent reallocations and additions to the Contract show. I conclude that the appeal is moot and that for that reason should be dismissed. Respectfully submitted, Stephen H. Clark Administrative Law Judge 3