Construction Update – August 2014 The Massachusetts Department of Transportation’s (MassDOT) Longfellow Bridge Rehabilitation Project began in July 2013 when the Boston-bound side of the bridge was closed to all modes of travel for demolition. One lane of traffic carries vehicles into Boston using the former Cambridge-bound, downstream side; a bike lane in each direction is provided on the roadway; and pedestrians continue to use the sidewalk. Cambridge-bound traffic is being detoured using a signed route from Charles Circle to Land Boulevard using Leverett Circle and Monsignor O’Brien Highway/Route 28 (Charles River Dam Road). Construction hours are generally 7 AM to 3:30 PM, with nighttime work scheduled as needed. On a few weekends each year, the MBTA Red Line trains are replaced by buses between Kendall Square/MIT Station and Park Street Station. The contractor has requested one weekend in October 2014. The date will be announced when approved by the MBTA. Project details and detour maps can be found on the website at www.mass.gov/massdot/longfellowbridge. Email advisories are distributed announcing detours, lane closures and major construction milestones, so be sure to sign up on the website. View toward Cambridge Summary of Progress: Rehabilitation, demolition and reconstruction activities are taking place at various locations along the Boston-bound side of the bridge. Activities include removing concrete sidewalk and deck slabs; removing granite stairways and walls; installing new steel elements; and blasting, priming and painting steel that will remain in place. Deck removal and replacement with the gantry crane is progressing from Cambridge toward Boston. Removal of the iconic “salt and pepper” towers on the upstream side of the bridge in Boston and Cambridge was completed in June. The contractor is now reinforcing the piers in preparation for replacing the towers in late 2014/early 2015. The realigned Mugar Way off-ramp from Storrow Drive eastbound to Charles Circle has been Realigned Mugar Way off-ramp from Storrow Drive eastbound Page 1 of 3 opened to traffic, making way for additional project activities in that location. The following is a summary of work completed to date, a description of ongoing construction and a look at upcoming activities that will take place over the next few months. All work reported is for demolition and rehabilitation of the Boston-bound (upstream) side of the bridge. Bridge spans are numbered beginning with spans 13 and 12 at Memorial Drive in Cambridge progressing across the Charles River to Span 1 over Storrow Drive eastbound in Boston. Pier 10 is located in the Charles River in Cambridge and Pier 1 is located in Boston between Storrow Drive east and westbound. Work Completed Since April 2014: • • • • • • • • • • • • • Steel girders installed on upstream side of Span 12 over Memorial Drive westbound Seismic reinforcement completed within Piers 10, 9, 8 and 7 Pier 5 tower removed (Boston side) Granite parapet and stairs removed at Boston abutment stairway and wing wall Drilled shafts installed at Pier 6 in Cambridge and Pier 5 in Boston for tower foundation support Arch girders blasted and primed for start of steel repairs at all spans except 5, 2 and 1 Concrete sidewalks to Pier 5 removed (work progresses from Cambridge toward Boston) Pier 6 reinforced steel base slab Gantry crane supports and rails extended to Pier 5 (from Cambridge side) Concrete deck slabs removed up to Pier 6 (from Cambridge side) Steel framing and columns removed from Spans 11, 10, 9 and 8 Steel repairs completed in Span 11 Traffic shifted onto realigned Mugar Way off-ramp Concrete placed for Span 12 deck and sidewalk on upstream side over Memorial Drive westbound Ongoing Work: • • • • Formwork and rebar for Span 12 deck Spans 5, 3 and 2 arch girder containment setup, blast and prime for repairs (Boston side) Seismic reinforcement at interior of Piers 6 through 1 Steel repairs in Span 10 Cast iron handrail and fascia restoration Page 2 of 3 Upcoming Work: • • • • • Continue concrete deck demolition and steel column removal from Span 6 toward the Boston abutment Extension of gantry crane supports to Pier 1 Steel erection and concrete deck placement at Span 11 (over eastbound Memorial Drive) and Span 10 (over Charles River) Steel girder repairs at Spans 9 and 8 Deck placement on Pier 6 For more information about the project, visit the website at www.mass.gov/massdot/longfellowbridge. For questions or to report issues related to construction, please call the project hotline at 617-519-9892 or email longfellowbridge@state.ma.us. Page 3 of 3