“Salt and Pepper” Tower Reinstallation Process Explained August 2015 Update After careful historical and engineering review, the Massachusetts Department of Transportation (MassDOT) developed a plan to dismantle, clean, restore, and reset the granite blocks of the iconic “Salt and Pepper” towers of the Longfellow Bridge. Over the past century, the towers have settled, requiring the dismantling and re-setting. The plan will safely maintain the blocks’ integrity during the process. Each 58-foot tower has 515 pieces of granite, which vary in size and can weigh as much as three tons. The restoration process began in March 2014 with the dismantling of the upstream towers, followed by the downstream towers in July 2015. The process involved dismantling the Removal of the Granite Top of towers, demolishing the interior concrete lining, and creating a the Pier 5 Tower – May 2014 new support structure to hold up the new, level concrete slab on which the towers will be reinstalled. With the completion of the preparatory work and new concrete road decks placed to provide access to this part of the bridge, the rebuild of the towers can begin. Before the granite can be reinstalled, epoxy coated reinforcing steel is formed into a cage that will become part of the new concrete liner walls (see photo at left). This will define the interior of the tower. Reinforcing Steel Cage Cambridge (Pier 6) Tower – August 2015 The restored granite blocks will then be loaded onto a barge at the storage location and floated to the jobsite. Several sets of blocks for both upstream pier towers will be brought to the bridge at one time. A separate barge will carry a crane for lifting the blocks into place. It will also provide an area to mix sand, cement, lime, and miscellaneous materials, so that mortar can be made close to the work area. After many measurements are taken and locations for the blocks are confirmed, the first row is lifted from the barge to the pier deck using Lewis Pins (see photo at right). They will be set in a mortar bed with shims to ensure they are the proper height. This first step is critical to ensure the proper alignment and placement of all the blocks above. Granite Blocks with Lewis Pins – July 2015 Page 1 of 2 There are 17 blocks in the first row and 19 in the second. Each row has a different number of pieces – as many as 22 or as few as eight. When the location has been confirmed, the Lewis Pins are removed and the block is in its final location. Any excess mortar is removed before it sets, so that it does not adhere to the exterior face of the granite. During the restoration of the granite, a hole was drilled in the back of each block for a dowel to be installed to meet seismic requirements. After the piece is set in its final placement, the dowel is installed in the hole. Records on the setting sequence will be kept by the masons doing the installation. For this first part of the reinstallation, the masons will install three rows of blocks at the Cambridge (Pier 6) upstream tower. While the masons are working at Pier 6, the iron workers will build the Before and after images of the granite door posts of the reinforcing steel cage at the Boston Pier 6 tower. (Pier 5) upstream tower. Once the masons complete the three rows at the Pier 6 tower, they will then repeat the process on the Pier 5 tower. Meanwhile, back at Pier 6, wood will be installed on the interior side of the rebar cage of the newly installed granite to help form the liner wall when the concrete is poured. A pump truck will deliver the concrete to the bridge and will pour the concrete to a predetermined height below the top of the granite. The concrete will tie together the granite with the newly installed dowels and the steel to make a reinforced wall that can withstand seismic shifts. The masons, iron workers, carpenters, and laborers will continue to go back and forth between the two piers to maintain progress. This also allows the mortar and concrete time to cure before starting the row above. The process is repeated 14 times to install 34 rows of blocks at each tower, two or three rows at a time. The granite is always higher than the concrete, because it acts as the outside wall of the concrete form. Completion of the upstream tower rebuild is anticipated for the end of 2015, but is weather dependent. The downstream towers will be rebuilt in a later phase of the project. If you have any questions or would like to know more, please contact the project team at longfellowbridge@state.ma.us or 617-519-9892. Page 2 of 2