Study Advisory Group Meeting #4 December 11, 2014 – 4:00PM Buzzards Bay Coalition, New Bedford Agenda • • • • • Introductions Study Purpose & Process Short & Medium-Term Alternatives Long-Term (Bridge) Alternatives What’s Next? – Alternatives Analysis (Evaluation Criteria) – Project Schedule Introductions • MassDOT – Ethan Britland – Project Manager • HDR Study Team – – – – – – John Weston – HDR Team Project Manager Stefanie McQueen – HDR Team Deputy Project Manager Luigi Casinelli – HDR Team Traffic Lead Reddy Edulakanti – HDR Team Traffic Engineer Pete Davis – HDR Team Lead Bridge Designer Jill Barrett (FHI) – Public Involvement Study Purpose • Evaluate multi-modal transportation & associated land use issues • Develop potential solutions • Recommend improvements along the Route 6 Corridor Study Process MassDOT 5-Step Planning Process Project Status Update • Work Completed to Date: Draft Goals & Objectives Evaluation Criteria Public Involvement Plan Existing Conditions Issues & Constraints Analysis Preliminary Short & Medium-Term Alternatives Conceptual Long-Term Alternatives • Next Steps: – Refine Alternatives (Short, Medium & Long-Term) – Evaluate Alternatives (using Evaluation Criteria & Public Input) – Make Final Recommendations for Improvements Short/Medium-Term Alternatives • Corridor Traffic Improvements • Bicycle/Pedestrian Improvements • Variable Message/ITS Signs – Sign Systems – Detour Routes Corridor Traffic Improvements Existing Conditions – 2014 LOS Corridor Traffic Improvements Future Conditions – 2035 No Build Corridor Traffic Improvements Future Conditions – 2035 with Improvements Corridor Traffic Improvements Proposed Improvements Corridor Traffic Improvements Corridor Travel Times & LOS Bicycle/Pedestrian Improvements Existing Conditions/Issues Bicycle/Pedestrian Improvements Existing (April 2015) Bridge Cross Sections Middle Bridge (Swing Span) Cross Section Typical Cross Section Bicycle/Pedestrian Improvements Proposed Bridge Bike Lane Addition Cross Section New Middle Bridge Cross Section Bicycle/Pedestrian Improvements Proposed Lane Adjustment/Bike Lane Addition Bicycle/Pedestrian Improvements Proposed Lane Adjustment Cross Sections Bicycle/Pedestrian Improvements Alternative Lane Adjustment/Bike Lane Addition Bicycle/Pedestrian Improvements New Bedford Bicycle/Pedestrian Improvements Bicycle/Pedestrian Improvements Route 6/MacArthur Drive Pedestrian Ramp Options Variable Message/ITS Signs Existing & Proposed ITS Signs Variable Message/ITS Signs Existing and Proposed Detour Routes Variable Message/ITS Signs Go-Time/Real Time Traffic Management (RTTM) System Left: Graphic User Interface for Travel Time Display Top Right: Portable Variable Message Sign (VMS) Bottom Right: Static Time Travel Board Long-Term (Bridge) Alternatives • Vertical-Lift Bridge • Double-Leaf Bascule Bridge (Standard) • Single-Leaf Bascule Bridge (Dutch or Rolling) Vertical-Lift Bridge James River Bridge, Virginia (U.S. 17) Double-Leaf Bascule Bridge (Standard) Berkley Bridge, Norfolk, VA (I-264) Single-Leaf Bascule Bridge (Dutch) Mystic River Bascule Bridge, Mystic, CT Existing Bridge • Key Considerations – Maintenance of roadway traffic – Maintenance of marine traffic – Impacts to local businesses – Aesthetics – Construction requirements – Costs Vertical Lift Bridge - Overview • Navigational channel width – up to 280 ft. – Horizontal clearance is sufficient for anticipated vessels (Hurricane Barrier is 150 ft.) Pont Jacques Chaban-Delmas, France • Air draft – maximum 120 ft. – Vertical clearance is sufficient for typical vessels – Limits ability for specialized cargo vessels, such as those carrying wind turbine components New Memorial Bridge, Portsmouth, NH Vertical Lift Bridge – Plan/Profile Existing Bridge Vertical Lift Bridge Vertical Lift Bridge – Plan Vertical Lift Bridge – Construction • Staging: 3 lane vehicular traffic during construction • Both navigational channels open during construction • Construction Duration – 33 months – – – – – Mobilization (Months 1-6) Construction (Months 6-33) Fabrication (Months 5-24) Roadway Closures – one time, 2 weeks (Month 28) Navigational Closures – 1 long weekend (Month 28) Vertical Lift Bridge – Costs/Opening • Estimated Cost - $90 to 120 million • Open/Close Time – Existing Bridge – 7.5 minutes – Vertical Lift – 7.5 minutes • Partial Open/Close for Typical Fishing Vessel – may save 30-60 seconds. Double-Leaf Bascule Bridge - Overview • Bridge counter-weight located below roadway surface • Navigational channel width – 150 ft. – Horizontal clearance is sufficient for anticipated vessels (Hurricane Barrier is 150 ft.) • Air draft – unlimited – No limits to vertical clearance for vessels Double-Leaf Bascule Bridge - Plan/Profile Existing Bridge Double-Leaf Bascule Bridge Double-Leaf Bascule Bridge - Plan Double-Leaf Bascule Bridge - Construction • Staging: vehicular traffic closed for most of construction • West channel closed during construction • Construction Duration – 37 months – – – – – Mobilization (Months 1-6) Construction (Months 4-37) Fabrication (Months 5-26) Roadway Closures – 24 months (Month 10-34) Navigational Closures – 3 long weekends (Months 10, 32 & 33) Double-Leaf Bascule Bridge - Costs/Opening • Estimated Cost - $85 to 100 million • Opening/Close Time – Existing Bridge – 7.5 minutes – Double-Leaf Bascule Bridge – 7.5 minutes • Limited opportunity for partial opening (partially opened bridge represents a navigational hazard) Single-Leaf Bascule Bridge - Overview • Bridge counter-weight located above roadway surface • Navigational channel width – 150 ft. – Horizontal clearance is sufficient for anticipated vessels (Hurricane Barrier is 150 ft.) • Air draft – unlimited – No limits to vertical clearance for vessels Single-Leaf Bascule Bridge - Plan/Profile Existing Bridge Single-Leaf Bascule Bridge (Rolling) Single-Leaf Bascule Bridge - Plan Single-Leaf Bascule Bridge - Construction • Staging: 2 lane vehicular traffic during construction • At least one channel open during construction (new channel open in Month 22) • Construction Duration – 26 months – – – – – Mobilization (Months 1-6) Construction (Months 6-26) Fabrication (Months 5-17) Roadway Closures – three months (Months 18-20) Navigational Closures – 1 long weekend (Month 21) and West Channel closed for two months (Months 19-20) Single-Leaf Bascule Bridge - Costs/Opening • Estimated Cost - $50 to 70 million • Opening/Close Time – Existing Bridge – 7.5 minutes – Double-Leaf Bascule Bridge – 7.5 minutes • Limited opportunity for partial opening (partially opened bridge represents a navigational hazard) What’s Next? • Refine Alternatives (Short, Medium, & Long-Term) • Alternatives Analysis – Evaluation Criteria will be used to assess the Alternatives • Economic Development Opportunities • Bridge Operations • Transportation Impacts • Safety • Environment • Community • Alternative Feasibility Example Criteria: • Number of businesses impacted • Construction Duration • Vertical & horizontal clearance (feet) • Estimated number of bridge openings • Average delay times • Impact to natural resources • Capital & maintenance costs Project Schedule New Bedford-Fairhaven Bridge Corridor Study Schedule Project Schedule 2014 TASK 1. Project Scoping (Study Area, Goals and Objectives) 2. Existing Conditions & Issue Evaluation 3. Alternatives Development 4. Alternatives Analysis 5. Recommendations 6. Final Report Public and Stakeholder Participation Public Informational Meeting = Study Advisory Group (SAG) = Jan Feb Mar Apr May Jun Jul 2015 Aug Sept Oct Nov Dec Jan Feb Mar Questions? Comments and feedback can be emailed to jbarrett@fhiplan.com