Study Advisory Group Meeting #6 June 24, 2015 – 4:00PM New Bedford Public Library, New Bedford Introductions • MassDOT – Ethan Britland – Project Manager • HDR Study Team – John Weston – HDR Team Project Manager – Stefanie McQueen – Planning – Jill Barrett (FHI) – Public Involvement Agenda • • • • Introductions Study Purpose & Process Short & Medium-Term Recommendations Long-Term (Bridge) Alternatives – Previously Reviewed Alternatives – New Alternatives – Alternatives Analysis/Evaluation Criteria • Long-Term Recommendation • Study Completion Schedule • Next Phases Study Purpose • Evaluate multi-modal transportation & associated land use issues • Develop potential solutions • Recommend improvements along the Route 6 Corridor Study Process MassDOT 5-Step Planning Process Why Study the Bridge? Key Issues/Constraints 1. Bridge Reliability/ Structural Soundness 2. Bridge Navigational Width 3. Bridge Vertical Clearance 4. Frequency/Duration of Openings 5. Environmental Considerations 6. Bicycle/Pedestrian Conditions Short/Medium-Term Recommendations • Corridor Traffic Improvements • Bicycle/Pedestrian Improvements • Variable Message/ITS Signs – Sign Systems – Detour Routes Corridor Traffic Improvements Future Conditions – 2035 with Improvements Bicycle/Pedestrian Improvements New Bedford Bicycle/Pedestrian Improvements Variable Message/ITS Signs Existing & Proposed ITS Signs Long-Term (Bridge) Alternatives Previously Reviewed: Primary Concern: Alternative 1 Vertical-Lift Bridge (110-135 ft.) Height Constraint Alternative 2 Double-Leaf Bascule Bridge Construction Duration Alternative 2W Wide Double-Leaf Bascule Bridge Alternative 3 Construction Duration Single-Leaf Rolling Bascule Bridge Long-term Reliability Alternative 3W Double-Leaf Rolling Bascule Bridge Long-term Reliability No Build Repair Existing Swing Bridge Navigational Constraint New Alternatives Considered: Alternative 1T Taller Vertical-Lift Bridge (150 ft.) Alternative 3D Double-Leaf Dutch-Style Bascule Bridge Alt 1T – Taller Vertical Lift Bridge • • • • Two towers – 200 ft. high Navigational channel width – up to 270 ft. Air draft – 150 ft. Construction Duration – 33 months – Roadway Closures – one time, 2 weeks (Month 28) – Navigational Closures – 1 long weekend (Month 28) • Estimated Capital Cost - $100-130 million Alt 3D – Double-Leaf Dutch-Style Bascule Bridge • Counter-weight located above roadway surface; bridge deck lifted using a pivot point (heel trunnion) • Navigational channel width – 200 ft. • Air draft – unlimited • Construction Duration – 26 months – Roadway Closures – three months (Months 18-20) – Navigational Closures – 1 long weekend (Month 21); West Channel closed for two months (Months 19-20) • Estimated Capital Cost - $100-125 million Alternatives Analysis/Evaluation Criteria • Evaluation Criteria: – – – – – – – Bridge Operations (i.e., vertical clearance, number of openings) Transportation Impacts (i.e., vehicle delay, connectivity) Safety (i.e., emergency vehicle access, navigation safety) Economic Development (i.e., shipper cost savings) Environment (i.e., coastal or wetland resource impacts) Community (i.e., open space or cultural resource impacts) Alternative Feasibility (i.e., costs, construction duration) • Rating System: Alternative Comparison Matrix Alternative 1: Vertical Lift Bridge (Rating) Alternative 1T: Vertical Lift Bridge (Rating) Alternative 2: Double-Leaf Bascule Bridge (Rating) Alternative 2W: Double-Leaf Bascule Bridge (Rating) 110-135 feet ○ 150 feet ○ Unlimited ● Unlimited ● 270 feet ● 270 feet ● 150 feet ◒ 220 feet ● Greatly Improved ● Greatly Improved ● Moderately Improved ◒ Greatly Improved ● Visual impacts Some Impact ○ Some Impact ○ No Impact ● No Impact ● Long-Term Reliability Risk Medium Risk ◒ Medium Risk ◒ Medium Risk ◒ Medium Risk ◒ $90-$120 Million ○ $100-$130 Million ○ $85-$100 Million ◒ $130-$160 Million ○ Annual operating and maintenance costs $490,000 ◒ $490,000 ◒ $490,000 ◒ $490,000 ◒ Construction duration 33 months ○ 33 months ○ 37 months ○ 37 months ○ 2 wk road closure ● 2 wk road closure ● 24 mth road closure ○ 24 mth road closure ○ Significant access impacts ○ Significant access impacts ○ Significant access impacts ○ Significant access impacts ○ Evaluation Criteria Feet of vertical clearance (vessel height) Feet of horizontal clearance (vessel width) Impact to safe navigation Capital costs Construction phase impacts to vehicular traffic Construction phase indirect impacts to abutting businesses Red Cell = primary difference among alternatives Yellow Cell = secondary difference among alternatives Alternative Comparison Matrix (cont.) No-Build: Repair Existing Swing Bridge Alternative 3: Single-Leaf Rolling Bascule Bridge (Rating) Alternative 3W: DoubleLeaf Rolling Bascule Bridge (Rating) Alternative 3D: DoubleLeaf Dutch-Style Bascule Bridge (Rating) Unlimited ● Unlimited ● Unlimited ● Unlimited ● 95 feet ○ 150 feet ◒ 220 feet ● 200 feet ● Impact to safe navigation N/A Moderately Improved ◒ Greatly Improved ● Greatly Improved ● Visual impacts N/A Limited Impact ◒ Limited Impact ◒ Limited Impact ◒ Medium Risk ◒ High Risk ○ High Risk ○ TBD Capital costs $45 Million ● $50-$70 Million ● $90-$110 Million ◒ $100-$125 Million ◒ Annual operating and maintenance costs $400,000 ● $400,000 ● $490,000 ◒ $490,000 ◒ Construction duration 18 months ● 26 months ◒ 26 months ◒ 26 months ◒ 2 wk road closure ● 3 mth road closure ◒ 3 mth road closure ◒ 3 mth road closure ◒ Minor-Moderate access Impacts ● Moderate access impacts ◒ Moderate access impacts ◒ Moderate access impacts ◒ Evaluation Criteria Feet of vertical clearance (vessel height) Feet of horizontal clearance (vessel width) Long-Term Reliability Risk Construction phase impacts to vehicular traffic Construction phase indirect impacts to abutting businesses Red Cell = primary difference among alternatives Yellow Cell = secondary difference among alternatives Long-Term Alternative Recommendation • Advance two bridge-type alternatives forward into Preliminary Design: – Taller Vertical Lift Bridge (150 ft.) – Double-Leaf Dutch-Style Bascule Bridge • Preliminary Design would include: – Bridge Type Study – after collecting site specific details (site survey, geotechnical data, force and load criteria) assess design feasibility of each bridge type and respective costs. – US Coast Guard Navigation Evaluation – determine the ability of the proposed bridge to meet current and future navigational needs with regards to horizontal and vertical clearances. Study Completion Schedule End of July Release Draft Corridor Study Report for Public Comment August 30-day Public Review Period September Issue Final Corridor Study Report Next Phases (Long-Term Recommendation) MassDOT Highway Division Project Development & Design Guide Process Project Phase Step 1 – Identify Problem/Need/Opportunity* Step 2 – Planning* Duration 1-3 months 3-24+ months Step 3 – Project Initiation 1-4 months Step 4 – Design, Environmental & Right-of-Way 48+ months Step 5 – Programming (Funding) 3-12+ months Step 6 – Procurement 6-12 months Step 7 – Construction 3-60+ months * Completed as part of this study Next Phases (Short/Medium-Term Recommendations) • Several ongoing projects are nearing completion: – Bridge roadway construction - Fall 2015 – “Octopus Intersection” pedestrian improvements - Fall 2015 • MassDOT ITS project to replace existing signs is underway • Signal timing improvements can be addressed once roadway construction is complete and traffic normalizes • Other pedestrian/bicycle improvements could be completed as part of Whale’s Tooth Station project, long-term bridge improvement project, or separately once bridge construction is complete Questions? Study information can be found on the study website: http://www.massdot.state.ma.us/newbedfordstudy Comments and feedback can be emailed to: jbarrett@fhiplan.com