Project Mobility: Route 3 Express Toll Lanes Study

advertisement
Project Mobility:
Route 3 Express Toll Lanes Study
Introductory Briefing to the South Shore Coalition
March 26, 2015
Massachusetts Department of Transportation
Highway Division
Agenda
1.
2.
3.
4.
5.
6.
2
Introductions
Purpose of the meeting
Overview of Public-Private Partnership (P3)
opportunity
Overview of toll lane study
Discuss opportunity for project in Long Range
Transportation Plan
Q & A and Discussion
Goals for South Shore Coalition Briefing
Provide overview of the P3 concept, origins
and benefits
• Introduce the Route 3 Express Toll Lane study
• Describe study process, next steps and
interest in Long Range Transportation Plan
• Answer questions
•
3
Why Express Toll Lanes on Rte. 3?
Address identified safety
problems
• Restore the breakdown
lane to its intended use
• Improve mobility for
autos and buses
• Reduce congestion
•
4
Public-Private Partnerships (P3): Overview
Legislature authorized P3 in 2009 Transportation
Reform
• A private concessionaire leases asset for 30-50
years, implements the project and returns the
facility in a state of good repair
• The financing mix can vary:
•
•
•
•
•
•
5
state payments;
private equity;
private loans; and
federal TIFIA loans
Toll revenues cover financing & maintenance costs
P3 Advantages
Opportunity to share or transfer risk
• Ability to pursue projects in times of limited
federal and state funding
• As in Design-Build projects, increased
opportunities for private-sector innovation and
improved project delivery
•
What is Project Mobility?
•
Project Mobility is a study to explore Express Toll
Lanes on Route 3 South
•
Proposed project runs from the Norwell-Marshfield
line, north of Exit 12, to Exit 18/19 at the Braintree
Split and beyond Exit 6 on I-93/Route128 in Quincy,
about 17 miles
•
Toll lanes would be in median with restored shoulder
•
Two toll-lane options are being studied:
•
•
•
7
two-lane reversible facility (reverses a.m. & p.m.)
single, permanent dedicated lane in each direction
Toll lane free for buses
Project Mobility Objectives
8
Key Issue is Safety:
Peak Period Breakdown Lane Use
More crashes and higher crash rate on Rte. 3
segments with active breakdown lane
• Data suggest peak-period breakdown lane use
influences crash rates
 Rte. 3 SB: 17% more crashes
•

Rte. 3 NB: 37% more crashes
• Project would restore shoulder for emergency use only
9
Key Issue is Safety:
High-Crash Locations Throughout Corridor
Rte. 3 interchanges are on State list of the highest
crash locations in Greater Boston region*
• Burgin Pkwy/Washington Street, Exit 18/19
• Union Street, Exit 17
• Main Street, Rte. 18, Exit 16
• Derby Street, Exit 15
• Hingham Street, Rte. 228, Exit 14
• Washington Street, Rte. 53, Exit 13
* MassDOT Highway Safety Improvement Program-identified crash clusters, 2011–2013 for the area between Merrimack Valley & Northern
Middlesex; Central Mass., and Old Colony.
10
Project Mobility Project Area
11
Existing Conditions, South Section
Exit 12 (Rte. 139) to Exit 14 (Rte. 228)
12
Existing Conditions, Middle Section
Exit 14 (Rte. 228) to Exit 16 (Rte. 18)
13
Existing Conditions, North Section
Exit 16 (Rte. 18) to Exit 18/19
14
Option 1: Two-lane Reversible
Shoulder
North Section
Shoulder
Shoulder
South Section
Express Toll Lane
Shoulder
General Purpose Lane
Shoulder
Option 2: Single Express Toll Lane in Each Direction
Shoulder
Shoulder
North Section
Shoulder
Shoulder
Express Toll Lane
Shoulder
General Purpose Lane
South / Middle Section
Transportation & Mobility
Express toll lanes give drivers flexibility to
choose toll lane or existing lanes
• Research finds that few drivers choose to
use toll lanes all the time
• Detailed traffic and revenue
studies will determine appropriate tolls
• Travel time savings must be
significant to attract users and
reduce congestion in free lanes
•
17
Operational Issues
Goal is to use pricing to manage toll lane volumes
to maintain a minimum continuous speed of about
45 mph
• Goal is to improve travel speeds in general
purpose lanes by attracting drivers to the toll lanes
• All Electronic Tolling (AET) will prevent delays
associated with toll plazas
• Toll pricing structure has not been
established
•
18
Environmental Issues
•
•
•
•
•
•
19
Corridor has sensitive resources: wetlands,
water supplies, protected habitat
Majority of widening is within existing right-ofway and median
Unavoidable impacts to wetlands
Improvements to wildlife passages
Stormwater management benefits
Potential for noise barriers
South Section Environmental
20
Middle Section Environmental
21
North Section Environmental
22
Consistency with MPO Goals
Safety
Improves high-crash cluster locations identified
by MassDOT
• Adds capacity to help reduce peak-period
congestion and resulting rear-end collisions
• Restores breakdown lane for its intended
emergency-only use which may help reduce
crashes
•
23
•
Manages congestion using active lane
management and congestion pricing
•
Improves mobility for bus passengers with freeflow express lanes
•
Improves mobility for pedestrians and cyclists
with new accommodations on bridges
•
Reduces congestion on arterials
by improving travel time on Rte. 3
24
Cape Cod Times/Steve Heaslip
Consistency with MPO Goals
Capacity Management/Mobility
Consistency with MPO Goals
System Preservation
Helps achieve state of good repair
• Rehabs or replaces 27 bridges
• New pavement on existing lanes
• New ITS elements
•
•
25
•
Permanent Variable Message Signs
•
Fiber optic cable
Modernizes roadway drainage
Consistency with MPO Goals
Economic Vitality
Modernizes and expands Route
3 to improve access to existing
employment centers and homes
• Reduces auto and bus riders’
travel time
• Helps address perception of
South Shore as hampered by
mobility issues
•
26
Cost and Schedule
27
•
Estimated construction duration: 4 years
•
Estimated construction cost: $600 m–$800 m
•
P3 procurement will induce private investment
•
Project must be in new Long-Range Transportation
Plan to initiate federal environmental process
Study Status
28
•
MassDOT has initiated a study of engineering,
traffic, financial and environmental issues
•
Federal and state environmental processes to
begin later in 2015
•
Public and agency outreach is beginning
Questions & Discussion
Comments or questions?
Route3ExpressLanes@dot.state.ma.us
29