New Jersey Department of Transportation ROUTE 295 RANCOCAS-MOUNT HOLLY ROAD TO ROUTE 130 M.P. 44.8 to 56.8 Burlington County 7 Municipalities PAVEMENT REPAIR & RUBBLIZATION Richard Jaffe, P.E. Executive Manager, Bureau of Civil Engineering Schedule: Activity Date Start Design October 2008 Advertise September 2009 Receive Bids November 2009 Start Construction January 2010 RT. 130, MP 56.8 Rancocas Mt. Holly Road , MP 44.8 Project Design Team • NJDOT - In House Design Roadway Structures Pavement Management Other NJDOT SME’s • Taylor Wiseman & Taylor Topographical Survey Traffic Control & Staging • RBA Drainage Permits Environmental Permits • Jacobs Engineering - IT • Baker Pavement Analysis Risk Management Existing Conditions: Roadway • Three Lanes in Each Direction. Bridges • 21 Bridges Within Project Limits Interchanges • Route 130 • Rising Sun Road • 12’ Lanes • 12 Overhead Bridges • 12’ Outside Shoulder • 9 Underpasses • 3’ Inside Shoulder • 32 Culvert Crossings • Florence-Columbus Road • Burlington- Mt. Holly Road • 54’ Var. Grass Median • Rancocas- Mt. Holly Road Background Info: • Segment of Route I-295 constructed between 1972 & 1974 • Has reached terminal serviceability – 36 Years • Deteriorating Pavement due to Alkali Silica Reaction (ASR) • Rough Ride Major Proposed Improvements: • Rubblize concrete pavement. 8” bituminous overlay. • Reconstruct bituminous shoulders (1′ widening) • Improve vertical clearance under 3 bridges • Add ITS facilities. • Update Guide Rail, Clear Zone, Acceleration Lanes. Traffic Staging and Construction: • Lane Closure Alternatives – Continuous, Weekend, Night-time • User Delay – Duration, Daily Impact, Cost • Constructibility – Quality, Safety, Cost • Public Outreach – Internet, On-Site, Community Capacities & Traffic Demand Route 295 (MP 52.05) Northbound (December 2008 Traffic Counts) Capacities & Traffic Demand 7000 2000 3 Lane Normal Capacity 3 Lane Workzone Capacity 2 Lane Workzone Capacity 1 Lane Workzone Capacity Weekday Demand 1000 Weekend Demand Traffic Volume 6000 5000 4000 3000 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 24 Hour Day Stage 1A & 1B: January-June 2010 Shoulder and drainage work Stages 2 and 4 (59 days each): June-August 2010 & 2011 Incentive/Disincentive = $100,000 per day Bonus Maximum = $6 million Traffic Staging Highlights: • Reconstruct Shoulders for Traffic • Emergency Pullovers every ½ Mile • Movable Barrier for Quick Deployment • Roaming Detours for Interchange Work Lane Rentals: Contractor may rent lanes during some peak hours: I- 295 NB 4-7 PM M-F Stages 1, 3, 5 I-295 SB 6-9AM M-F Stages 1, 3, 5 Cost: $1,000 per hour Purpose: Allows contractor greater flexibility for construction. Doesn’t close lanes unnecessarily. Lessons for Accelerated Schedule: • • • • No Turning Back Bring Together Team Make Decision Move On Innovative or Unusual Features: • One sided highway closures to maximize speed and quality of construction • Roaming detours to facilitate accelerated interchange and mainline reconstruction • Lane rentals to allow contractor to weigh construction efficiencies versus costs Risks: • Accelerated Construction Schedule • Public Reaction to Lane Closures RT. 130, MP 56.8 Rancocas Mt. Holly Road , MP 44.8 Questions? Richard Jaffe Mahesh Patel