BDC12S-08 Page 1 of 2 New Jersey Department of Transportation 1035 Parkway Avenue, PO Box 600, Trenton, New Jersey 08625-0600 Baseline Document Change Announcement ANNOUNCEMENT: BDC12S-08 DATE: December 17, 2012 SUBJECT: Chain-link fence - Revision to Subsection 509.04 of the 2007 Standard Specifications for Road and Bridge Construction REFERENCE: Miscellaneous changes to the Standard Roadway Construction-Traffic Control-Bridge Construction Detail 2007 BDC12D-01 dated December 18, 2012 Subsection 509.04 of the 2007 Standard Specifications for Road and Bridge Construction has been revised to conform the Department Items with the AASHTO M181 Types of Chain-Link Fences. The following revisions have been incorporated into the Standard Input SI2007 as of December 17, 2012. SECTION 509 – BRIDGE RAILING AND FENCE 509.04 MEASUREMENT AND PAYMENT THE ENTIRE SUBSECTION IS CHANGED TO: The Department will measure and make payment for Items as follows: Item BRIDGE RAILING (___RAIL, ALUMINUM) BRIDGE RAILING (___RAIL, STEEL) CHAIN-LINK FENCE, TYPE I, ZINC-COATED STEEL, BRIDGE, __'__" HIGH CHAIN-LINK FENCE, TYPE II, ALUMINUM-COATED STEEL, BRIDGE, __'__" HIGH CHAIN-LINK FENCE, TYPE III, ALUMINUM ALLOY, BRIDGE, __'__" HIGH CHAIN-LINK FENCE, TYPE IV, PVC-COATED STEEL, BRIDGE, __'__" HIGH CHAIN-LINK FENCE, TYPE I, ZINC-COATED STEEL, BRIDGE, __'__" HIGH, CURVED TOP CHAIN-LINK FENCE, TYPE II, ALUMINUM-COATED STEEL, BRIDGE, __'__" HIGH, CURVED TOP CHAIN-LINK FENCE, TYPE III, ALUMINUM ALLOY, BRIDGE, __'__" HIGH, CURVED TOP CHAIN-LINK FENCE, TYPE IV, PVC-COATED STEEL, BRIDGE, __'__" HIGH, CURVED TOP Pay Unit LINEAR FOOT LINEAR FOOT LINEAR FOOT LINEAR FOOT LINEAR FOOT LINEAR FOOT LINEAR FOOT LINEAR FOOT LINEAR FOOT LINEAR FOOT BDC12S-08 Page 2 of 2 Implementation Code R (ROUTINE) Changes must be implemented in all applicable Department projects scheduled for Final Design Submission at least one month after the date of the BDC announcement. This will allow designers to make necessary plan, specifications, and estimate/proposal changes without requiring the need for an addenda or postponement of advertisement or receipt of bids. Recommended By: Approved By: Original Signed by Original Signed by Richard Jaffe Acting Director, Capital Program Support Richard T. Hammer Assistant Commissioner, Capital Program Management RJ: KS: HP BDC12S-08.doc