International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014 Case Study on Design and Construction of Tunnel M.S.Rahul Undergraduate Scholar, Hyderabad Abstract —A tunnel may be for foot or vehicular road traffic, for rail traffic, or for irrigation purposes. Some tunnels are aqueducts to supply water for consumption or for hydroelectric stations or sewers. Utility tunnels are used for routing steam, chilled water, and electrical power. The tunnel is relatively long and narrow; in general the length is more than twice the diameter The Dr. B.R. Ambedkar Pranahitha Chevella Sujala Sravanthi Lift Irrigation scheme’s objective is to irrigate 16.40 Lakh Acres of command area in the drought prone areas of Telangana region viz., Adilabad, Karimnagar, Medak, Nalgonda, Nizambad, Warangal and Ranga Reddy districts of Telangana state. The scheme envisages construction of barrage across Pranahitha River, a major tributary of Godavari River at Tummidihetti (V) in Koutla (M) of Adilabad district and 160 TMC of water from Pranahitha River is proposed to be diverted to Sripada Yellampally Project from where it is carried to command areas through lift irrigation schemes, gravity canals, tunnels, Modernization of tanks and reservoirs for irrigation total Ayacut of 16.40 Lakh Acres and providing drinking water facility to villages and also providing required water to industries. Keywords— Tunnel, Investigation, Excavation, Drilling, Portals, seepage control, Grouting, Measures Canal to existing Flood Flow canal to feed Mid Mannair Reservoir with the components such as Lined Gravity canal, CM & CD works, lifts, pressure mains and lined tunnels with all associate civil, Hydro Mechanical & Electro Mechanical works was entrusted to “MEIL-SEW-MAYTAS-BHEL (CONSORTIUM)”, II. Scope of Work The package starts from Kakatiya Canal @D-83 in Ragampet (V) to existing Flood Flow canal near Shanagar (V). a. Site investigation report(s). b. Brief review of Geological and Geotechnical investigation. c. Approach by Adit tunnel 8 m dia D-Shaped and 1.609 km in length with 1 in 12 slope d. Twin tunnel from the Kakatiya canal @D-83 in Ragampet (V) to surge pool at lakshmipuram (v) for about 4.133 km with 10.0 m dia and 7.5 m dia. e. Underground Surge pool 350 x 20 x 56 m D-shaped. f. Underground Pump house 205 x 25x64 Mts with a lift of about 109.10 Mts g. Delivery cistern h. The length of Gravity Canal is 4.060 Km from delivery cistern to Mothevagu reservoir. i. Foreshore of Mothevagu reservoir to Flood Flow Canal length of link canal is 1.900 Km I. Introduction The Dr.B.R.Ambedkar Pranahitha Chevella Sujala Sravanthi Lift Irrigation Scheme (Dr.BRAPCSSLIS) is being constructed having the 22 lifts. The project envisages irrigation of about 16,40,000 acres of uplands in the six districts and the total lift height from the river Pranahitha at RL+150.00m to Chevella reservoir at RL+635.00m, i.e., 493M These are carried out by III. multiple stages lifting and conveying through tunnels and gravity canals. The total length of system is divided into two parts, length of Gravity canal and length of the Tunnel. Length of the Gravity canal is 849 km (approx.) and Length of the Tunnel is 206 km (approx.). The total number of lifts is 22. The total power required for this lift is 3375 MW; estimated time for completion is 48 Months. The entire project is divided into several packages to facilitate execution of the work simultaneously. There are 28 packages under this project. In this study, analysis is done on Dr.B.R.Ambedkar PranahithaChevella Sujala Sravanthi package 8. The work of “Pranahitha Chevella Sujala Sravanthi lift irrigation scheme-link-II-package08” detailed investigation, designs and execution of lift irrigation scheme for drawl and lifting of 114.24 TMC of water from Ragampet (v), near Kakatiya canal, Choppadandi (M), Karimnagar District to Mothevagu Reservoir and carrying by a gravity ISSN: 2231-5381 Site Investigation http://www.ijettjournal.org Page 373 International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014 IV. Geological and Geotechnical Investigation Design and construction of tunnels in rock require thought processes and procedures that are in many ways different from other design and construction projects, because the principal construction material is the rock mass itself rather than an engineered material. Uncertainties persist in the properties of the rock materials and in the way the rock mass and the ground water will behave. All these uncertainties must be overcome by sound –flexible design and redundancies and safeguards during construction. The design of tunnels must involve selection or anticipation of method of construction. Geology plays a dominant role in many major decisions made in designing and construction of a t unn el. In tunnels, unlike other structures, the ground acts not only for the loading mechanism, but as t h e primary supporting medium as w e l l . When the excavation is made, the strength of the ground keeps the excavated hole open until the supports are i n s t a l l e d . Even after supports are in place, the ground pr ovi des a substantial percentage of the load-carrying capacity. Thus, for a tunnel, the rock or soil surrounding a tunnel is a construction material. Its engineering characteristics are as important as those of the concrete or steel used into the aspects of the work. A. Seismicity According to GSHAP the state of Telangana falls in a region with low 10 moderate seismic hazards. As per the 2002 Bureau of Indian Standards (BIS) map, this state also falls in zones II and III. Historically, parts of this have experienced seismic activity in the M 5.0-6.0 range. The Godavari river valley, adjustment to the site is within the NW-SE trending faults. These faults still show moderate seismicity occasionally. The Godavari graven area is in seismic zone II. In this zone an earthquake of magnitude of 6 or intensity VIII may be expected. The earthquake of magnitude 5.3 was measured at Bhadrachalam in 1969. As per IS-4880 (part-V), the tunnel lining is not designed foe seismic force unless the tunnel crosses an active fault. In which case, some flexibility is provided at that section to all for some movement in case of earthquake. However, at locations where studies in indicate that seismic forces will be significant they shall be catered for in the design. B. Field Work The site of package-8 is located in Karimnagar district of Telangana state. Six boreholes were drilled in the alignment of the proposed tunnel, varying depth of 100.0 m to 130.0 m. The subsurface investigation is carried out by boreholes and electroresistivity method (ERM) for suitability of the proposed site for the construction of tunnel. C. Electric Restivity Method (ERM) Resistivity surveys have been conducted along the alignment of tunnel for 4.133 KM of the package-8, to assess the sub –surface ISSN: 2231-5381 soil classification, which facilitate to design of various components of the tunnel, strata expected to encounter during the excavation etc. D. Vertical Electrical Sounding (VES) VES is conducted along the alignment axis at 100m intervals. The interpreted data of the VES gives various sub-surface layer thickness, its nature and depth to the massive rock. V.Tunnel Design The layout of tunnels depend on the grade, clearance required, alignment etc. wherever possible, from the standpoint of general alignment and cost, tunnel alignment should be straight to facilitate construction. Curved tunnels have been used on many railroad, water conveying tunnels, and highways, particularly in mountainous areas. As per the geological report made available, the entire stretch of tunnel from Km. 0.0 to Km. 4.133 passes through grey and pink granites rock strata. The total length of the tunnel is approximately 4133m due to length of tunnel (4.133 Km), and the entry exit of the tunnel cannot be approached without shafts or construction of Adit, it is necessary to establish a construction adit to provide two working faces in each tunnel to complete the work in the schedule period. A. Geometry of the Tunnel Methods and sequence of excavation affect the loads and displacements, which must be resisted by initial and permanent ground supports. The basic shape of an excavated opening must be selected for practicality of construction. IS 4880 part II 1976, lays down general guidance in regard to shape of the various sections generally use in tunnels. However, the said IS code has left the choice of particular shape on designer’s judgment based on prevailing conditions at site. The first step in the design of a tunnel is the determination of the cross section required for the trouble free operation. These selections of the tunnel cross-section influenced by: o The clearances specified in view of the vehicles and materials transported in the tunnel, o Geological conditions, o The method of driving the tunnel and the materials strength of tunneling. D-SHAPED tunnels are best suited in ‘conventional drilling and blasting method of construction point of view in good rock strata, as they have flater invert. In Pranahitha-Chevella lift irrigation scheme Package-8, tunnel is proposed with a 10.3m diameter D-Shaped Tunnel in right tube and 7.75m D-shaped tunnel in left tube. The hydraulic loss due to the D-shape tunnel is negligible in this case, compare with a circular tunnel of same cross sectional area, hence we can use D-shaped tunnel as mentioned above without losing any advantage of circular tunnel. http://www.ijettjournal.org Page 374 International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014 B. Shotcrete and Rock Bolt Initial As the tunnels generally passes through different types of rock formations, it is necessary to work out alternative cross sections if the tunnel depicting other acceptable types of support systems. The shotcrete in combination with rockbolt and wire mesh provide a good and fast solution for both initial and permanent rock supports. Being ductile it can absorb considerable deformation before failure VI. Construction The basic components of underground construction include the following: Excavation, by blasting or by mechanical means. Initial ground support. Final ground support. Other important components of construction include the following: Site preparation. Surveying. Portal preparation Ventilation of the underground works Drainage and water control Hazard prevention Controlling environment effects etc. D. Precision Survey The precision survey and setting out of the tunnel alignment shall consist of transferring the obligatory points like portal points, shaft/adit location, etc., from topographical maps/detailed design drawings to the actual site of construction. This is done either by “Direct Setting Out” or by “Triangulation”. In the mountainous regions it is extremely rare possibility that both the ends of the tunnel will be visible from each other and hence “Triangulation has to be invariably adopted for setting out the alignment. The levels of the various portals along the tunnel are fixed accurately by means of Total Station or using “Reciprocal Leveling”. E. Methods of Underground Excavation A. Sequence of Excavation For Tunnel The excavation and portal of the adit tunnel is established first. Main tunnel excavation for left tube and right tube is carried out through the adit tunnel from both face in each tunnel simultaneously by full face or heading and benching method depending upon the strata encountering and the machines using at site. The design team should specify or approve the proposed method of excavation. This tunnel is proposed to excavate using conventional drill and blast method B. General Procedure of Underground Excavation Tunnels can be driven through almost any material in nature, but the methods used and costs differ radically. Thus, the method used in tunneling in earth, soft sediments or crushed weathered rock depends chiefly on the bridge action period of the material above the roof of the tunnel and the position of water table, whereas the method used for tunneling through hard, intact rock requiring little or no supports depends upon the strength and condition of rock, because of great longitudinal extent of the work, many different kinds of conditions are encountered, which for maximum economy should be excavated and supported differently. C. Preliminary Works The preliminary works required commencing the excavation of a tunnel consists of the following: ISSN: 2231-5381 Precision Survey and setting out of the tunnel alignment. Open excavation for portal or excavation for shaft. Arrangement for collection of surface water and its drainage by gravity flow or pumping. Access roads to mucking areas. Erecting or winching and hauling equipment. Establishments of field workshop, compressors and air lines, pumps, water lines, ventilation fans and ducts, lighting, concreting arrangements, supports erection arrangements, etc. The underground excavation for tunnels shall be carried out in conformity with IS: 5878 Part II / Section-1 or other relevant reference mentioned as per the tender documents Tunneling soft strata shall conform to IS: 5878 part III other relevant references mentioned as per the tender documents. The actual operations for underground excavations may vary with the type and size of tunnel, method of excavation, type of geological formation encountered, equipment available, and the overall economics. Following are the methods commonly adopted for excavation of tunnel. 1. Full and Partial Face Advance Most tunnels are advanced using full-face excavation. The entire tunnel face is drilled and blasted in one round. Blast holes are usually drilled to a depth somewhat shorter than the dimension of the opening, and the blast “pulls” a round a little shorter than the length of the blast holes. The depth pulled by typical rounds is 2 to 4 m in depth. Partial face blasting is sometimes more practical or may be required by ground conditions or equipment limitations. 2. Full Face Attack In this method, the entire cross-section area of the tunnel to be excavated is attacked simultaneously. This method is generally recommended for small size tunnels in good rock conditions where major rock falls are not anticipated. http://www.ijettjournal.org Page 375 International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014 3. Top Heading And Benching This is the most common method, where the top part of the tunnel is blasted first, at full width, followed by blasting of the remaining bench. The bench can be excavated using horizontal holes or using vertical holes similar to quarry blasting. 4. Drift Method In driving large tunnel or tunnel in very poor strata it may be economical to drive a small tunnel called drift or a pilot tunnel prior to excavating the full face. Depending upon the nature of rock and other parameters, a drift may be excavated in the center, side, bottom or top. In this package 8, Top Heading and Benching method is adopted for underground tunnel excavation. The other methods used are: 1. 2. 3. Cut and cover methods Mechanized means such as Tunnel Boring Machines or Continuous miners Tunneling with aid of a protective shield. Drilling, Charging and Priming Patterns Blasting Design An important step in tunnels is Blasting. Blast design that will produce desired rock fragmentation results and low vibration levels. They specify explosive quantities and design borehole drill patterns including size, depth, and spacing. These factors vary based on the geology and location of the blast site. Different rock types require different kinds or amounts of explosives and different borehole spacing. Blasts are also designed to produce fragmentation, or rock size. Trial Blast As per the geological report, this tunnel passes through sound granite strata. Hence in this tunnel, it is proposed to execute adopting ‘conventional drilling and blasting method’ with drilling boomers. Since the size of the tunnel is more than 8m it is proposed to execute the tunnel by heading and benching due to the bigger size of the tunnel. If any fracture zone encountered during the execution of the project, it is proposed to execute the same by heading and benching with rock supports. F. Marking of Tunnel Profile The center of the tunnel and its level is marked on the face of the tunnel with the help of the precision survey instrument before each blast and from that center line point the designed shape of the tunnel is marked on the face. G. Setting up and Drilling Holes The blast patterns shall include the following: - Drilling patterns - Charging patterns - Priming Pattern ISSN: 2231-5381 Trial blasting will be performed at the beginning of the works in order to optimize blast design and drilling patterns. The purposed of this trial blasts is as follows: Estimation of blast design parameters suitable to the site Suitability evaluation of the approved blast design. Checking the blast vibration level. H. Loading Explosives and Blasting Explosives used in blasting are generally of emulsions type made of varying percentage of strength. Before loading is started, each hole is blown with high-pressure air jet or with water. A primer cartridge containing the detonator pointing towards the bottom of the hole and is tamped well into the bottom with the help of wooden or plastic pole. Finally, the remainder of the hole is filled with inert material (like damp mixture of sand and clay) and tightly clamped. The holes are then blasted from the safe distance. Adequate safety precautions are taken during drilling and blasting operations in conformity with IS: 4081 and other relevant guidelines. http://www.ijettjournal.org Page 376 International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014 or suitable attachment. Manual scaling may not be advisable or practical in safety point of view. L. Removal of the Muck I. De-Fuming or Removal of Foul Gases by Ventilation Ventilation is an important aspect, which has to be duly taken care of for efficient underground excavation of the tunnel. Adequate ventilation must be provided to make the working space safe for workers, by keeping the air fresh and breathable, free from harmful obnoxious gases and dust. Minimum requirements of purity of air, dust control and volume of air are in accordance with IS: 4756. The tunnel can be ventilated either by blowing air in or exhausting it out through a duct. In the blowing mode, fresh air enters from the surface through a vent pipe to a point near the face. This mode has advantage of constantly supplying fresh air to work space. In exhaust mode, the foul air is exhausted through the vent line. While this method creates a better environment along the tunnel, any heat, moisture, dust and smoke generated along the tunnel is delivered to the vicinity of the face. Dumper VII. Initial Ground Reinforcement (Rock Bolts) Initial ground reinforcement consists of; Un-tensioned rock dowels and occasionally, tensioned rock bolts. These are referred to as ground reinforcement, because their function is to help the rock mass support itself and mobilize the inherent strength of the rock as opposed to supporting the full load of the rock. It is much more economical to reinforce the rock mass than to support it. Rock bolt is the general term that includes rock dowels and cable tendons. Specifically, bolts are pre tensioned, while dowels are initially unstressed. The installation process is simple: drill the hole insert the requisite number of cartridges insert the steel bar with a spinning action and continue spinning for about 60 seconds to ensure complete mixing. Ventilation ducts. J. The material removed as a result of blasting is loaded into dumpers or mine cars, as the case may, and is taken out of the tunnel. In principle, tire or crawler mounted loaders/excavators and suitable dumpers are used for mucking operation. Removal of muck from underground excavations shall be in conformity with IS: 5878 Part – II/Section-2 and other tender provisions. The excavated materials (rock, soil etc.) from the tunnel shall be transported to the specified dumping area. A haul road of slope not greater than 1 in 10 shall be constructed for the hauling of excavated muck. Checking Misfires Immediately after the tunnel has been de-fumed and ventilated, the blasted face is checked carefully for any misfires. For this, an experienced and competent Forman enters the tunnel, removes the loose rock carefully from the face and makes sure that all cartridges have been fired. K. Scaling The Loose Material In these tunnels the rock bolts considered most appropriate are reinforcing steel bars, typically 25 mm diameter, 12 tons proven capacity. For 25 mm passive bolts, holes of 32 mm to 38 mm are required. The hole is filled from the bottom with cement capsules and the bolt is inserted as per the designs. Care must be taken to ensure that the hole is filled up to full depth. The bolts are threaded outside. When the grout is set, a washer plate is placed against the rock and secured in position with a nut. When shotcrete is used, the washer should be outside the main layer of shotcrete. After the checking of the misfire is over, the scaling operation will be carried out by use of excavators with hydraulic hammer ISSN: 2231-5381 http://www.ijettjournal.org Page 377 International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014 DRILLING FOR ROCK BOLTS SURFACE PREPARATION Good adhesion to the ground with the initial layer and good bond between successive layers are prerequisites of good shotcrete. This can best be accomplished with a high-pressure combination air-water jet applied with a long jet pipe nozzle held relatively close to the surface. ROCK BOLTS VIII. Seepage control A. Dry-Mix Aggregate Preparation The process of Tunneling is always disrupted with the presence of Ground water table in its path and also the local seepage of water. This is taken care by the use of Shotcrete and drilling Ground water drainage holes IX. Shotcrete When dry-mix aggregate storage is on-site, protection from the elements is necessary. Stock piling by size groups should prevent sub size segregation. For best result, an aggregate dampness of 3% to 6% should be maintained. Less will absorb too much mix water; more will result in too high water cement ratio. Shotcrete today plays a vital role in most of the tunnel and shaft construction in rock because of its versatility, adaptability and economy. Desirable characteristics of shotcrete include its ability to be applied immediately to freshly excavated rock surfaces and to complex shapes such as shaft and tunnel intersections, enlargements, crossovers and bifurcations and the ability to have applied thickness and mix formulation varied to suit variations in ground behavior. B. The Mix The mix design shall be as per the IS standards. The mixing of materials shall be done using a suitable capacity batching plant. Inclusion of steel fibers will require little or no change from the plain shotcrete mix. The principle effect will be increased. Over all, the mix design should keep water cement ratio and the cement factor as low as possible and the coarse aggregate fraction as large as practicable. Shotcrete is not just “pneumatically applied concrete”. Although the basic materials (cement, aggregate, water) are the same and meet the same Indian Standards, additives (e.g.: accelerators, micro silica and steel fibers) change its character to make shotcrete unique and usable in quite a different fashion than concrete. In this package 8, Wet mix procedure has been adopted. The wet mix process consists of mixing measured quantities of aggregates, cement, and water and introducing the resulting mix into a vessel for discharge pneumatically or mechanically through a hose to final delivery from a nozzle. It has the advantage of rigidly controlling the water/cement ratio of the product. Existing equipment can handle maximum aggregate size of 3/4 inches. C. Nozzle The best shotcrete “on the wall” is produced when the nozzle is kept within 3 to 5 feet of the surface being shot and perpendicular to the surface or within 15 degrees of the same. Deviation from this will result in less compaction and more rebound. Considering the particles in shotcrete stream is travelling at 170 to 340 mph. In package 8, a remotely controlled nozzle at the end of a long bottom has been adopted. D. Curing Curing of the shotcrete shall be taken up by spraying water jet on the surface. X. Backfill Concrete On tunnel supports and tunnel lining respectively, the job of the tunnel support or tunnel lining does not end with the installations of a support system (steel ribs, rock bolts, shotcrete) ISSN: 2231-5381 http://www.ijettjournal.org Page 378 International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014 and provision of lining. It is necessary to backfill the space between the support system and the excavated surface, for arresting the displacements and movement of the strata around an excavated and supported system and the excavated surface. The back filling is done by means of placing tightly packed M20 concrete behind the supports. XI. Grouting In order to ensure complete of concrete lining and the rock behind it, contact grouting with cement grout will be done after the lining concrete has matured for at least twenty-one days (21). Grouting in tunnels is of two types: XII. Tunnel Lining The lining of the tunnel will be taken up when the excavation of the tunnel, has been completed. Keeping in view that three faces are available for concreting it is proposed to use three conveniently designed shutters for lining of the tunnel to complete the lining as per the Construction Schedule. In the sections, where excavations of benching of tunnel are completed, shall be concreted with the help of specially designed shutters for overt and sidewall. The shutters will be 10.5 to 12.5 meter long, which will enable the concrete lining of whole overt section of 10 to 12 meter length in one go. These shutters give an average lining progress of 150 meter/month/shutter. A. Back fill or contact grouting B. Pressure grouting or consolidation grouting A. Contact Grouting The main purpose of contact grouting is that it fills up all voids and cavities between the concrete lining and the rock. Contact grouting also known as low pressure grouting or back fill grouting. Back fill grouting shall be done at a pressure not exceeding 5 kg/cm2 and shall be considered as a part of concreting. The normal varies from 2 kg/cm2 to 5kg/cm2. It shall be done throughout the length of the concrete lining not earlier than 21 days after placement after the concrete in the lining has cooled off. B. Pressure Grouting or Consolidation Grouting In the conventional drilling and blasting method of tunnel excavation and blasting method of tunnel excavation, the rock around the cavity gets shattered to a certain depth depending upon the depth of blast holes and type of rock. The aim of consolidation grouting is to consolidate the shattered rock by filling up the joints and discontinuities in the rock, which got opened out during blasting operations. As a result of pressure grouting, the rock quality gets improved thus increasing the resistance of the rock to carry internal water passage. The consolidation grouting is done after back fill grouting is completed in a length of at least 60 m ahead of the point of grouting. Pressure grouting shall be done all around the cavity and for a uniform radial distance equal to least 0.75 times the finished diameter of tunnel from the finished concrete face. The normal range of pressure grouting shall be 7 to 10 kg/cm 2. Process of Grouting Drilling holes Cleaning and washing holes Testing holes ISSN: 2231-5381 Grouting holes Testing of grouted zone for efficancy of grouting Tunnel Lining A concrete pump of 30 cum capacity or equivalent shall accomplish the Placements of concrete behind the shutter. The concrete shall be produced by suitable capacity concrete batch plant installed at the entrance and adit of the tunnel. XIII. Ground Water Drainage Holes As per IS: 4880 (Part V)-1972 drainage holes may often provide in other than water conveying tunnels to relieve external pressure, if any, caused by seepage along the outside of the tunnel lining. It is recommended that drainage holes may be spaced at 3m centers, at intermediate locations between the grout rings. At successive sections, one vertical hole may be drilled near the crown alternating with two drilled holes, one in each side wall. Drainage holes extend to a minimum of 15cm beyond the back of the lining or grouted zone. Since this is a water-conveying tunnel and the ground water table is below the tunnel bed level, it is proposed not to provide any water drainage hole XIV. Safety Measures Safety is of utmost importance during the construction of tunnels. Provision of Helmets, Masks and Work wear is mandatory for the work force http://www.ijettjournal.org Page 379 International Journal of Engineering Trends and Technology (IJETT) – Volume 13 Number 8 – Jul 2014 REFERENCES Code Books o IS 4880:1972 Part I General design Part II Geometric design Part III Hydraulic design Part IV Structural design of concrete lining in rock Part V soils Structural design of concrete lining in soft strata and o XV. Conclusion The tunnel carries water from Pranahitha-Chevella Tank through tunnels. This enables us to lift water from lower region to higher region through hydraulic pumps and drop the water in gravity canals from which the water is distributed to the irrigated lands. Our project is Study of the construction of tunnels that are a subpart of the PCLIS, which is package-8 situated at Laxmipur, RamaduguMandal. The use of tunnel irrigation reduces the need of LAND ACQISTION, which usually takes up most of the allotted budget to the project. The tunnels also have a low Operation and Maintenance of them. It is both effective and economical with use of Tunnel system. Part I The project has Twin D-shaped tunnels of diameter more than 10.0m; in such case a pilot tunnel is excavated first followed by slashing on both the sides of the pilot tunnel. Part V A. Concrete Lining is provided depending upon the rock class encountered during the excavation, in the following way: Part II IS 5878:1971 Precision survey and setting out Underground excavation in rock Section I: Drilling and blasting. Section II: Ventilation, lighting, mucking and dewatering. Section III: Tunneling method for steeply inclined tunnels, shafts and underground powerhouses. Part III Underground excavation in soft strata Part IV Tunnel supports Concrete lining Introduction to Tunnel Construction By David Chapman, Nicole Metje, Alfred Stärk Design of Reinforced Concrete Structures By S.Ramamrutham. Class I- No rock supports are required, but as per agreement provisions 500mm M20 plain cement concrete lining is provided. Class II- No support is required except spot bolt at some points and also as per agreement 500mm M20 plain cement concrete lining is provided. Class III- Initial rock support shall take the entire load and there is no need of final concrete lining. As per agreement 500mm M20 plain cement concrete lining is provided. Class IV- Initial ground support shall be provided with 50mm thick shotcrete immediately after excavation with steel supports, lagging, backfill concrete and grouting. Class V- Initial ground support shall be provided with 100mm thick shotcrete immediately after excavation with steel supports, lagging, backfill concrete and grouting. ISSN: 2231-5381 http://www.ijettjournal.org Page 380