Agenda Item No_____17______ CROMER OFFICE IMPROVEMENTS Summary: Conclusions: This paper brings together the business case for office improvements which will improve customer service and at the same time provide a financial saving for the Council. The three areas of work detailed, if approved, will allow efficiencies to be realised through better use of staff and buildings resource. In addition, they will support the change agenda required to deliver the Council’s Corporate Plan and will significantly improve customer interaction with the Council. Recommendations: 1. To delegate authority to officers, in conjunction with the Portfolio Members for Resources and Customer Services, to procure the necessary building works, along with any professional input required in respect of the customer services improvement works. 2. That £31,500 is allocated from the Restructuring and Invest to Save earmarked reserve to fund the removal of the Annexe and associated works 3. To authorise officers to obtain the necessary quotes and/or tenders to ensure the safe removal of the annexe building and the reinstatement of the facilities currently contained therein. Reasons for Recommendations: To ensure that the works are carried out by an appropriate contractor procured within the framework provided by the Council’s Financial Standing Orders Cabinet Member(s) Cllr Rhodri Oliver (Corporate Assets) Cllr Tom Fitzpatrick (Customer Services) Contact Officer, telephone number and email: Nick Baker 01263 516221 nick.baker@north-norfolk.gov.uk 1. Introduction The Cromer office building is now over 20 years old and has had little work carried out in terms of its layout during that time except for occasional desk moves for individual teams. At the present time, there is a need to ensure that every measure is taken to maximise efficiencies and realise savings and income. Changes to the office environment will allow such measures to be achieved whilst at the same time improving the service and office environment for Members, officers and customers alike. The three areas of work identified in the report together, will enable improved working by bringing together the newly created service teams and creating staff efficiencies by improvements in the way we deal with customer contacts. 2. Redesign of the Front Office Reception 2.1 Background Contact for Council services come in a number of ways – via the website www.northnorfolk.org, telephone, email, face to face in the Council offices at Cromer and Fareham, post and also the visits we make to customers’ homes and / or work premises. Approximately 51,000 transactions, i.e. circa 200 per day, take place within the Cromer “Front offices” every year. This includes dealing visitors for pre-booked appointments and deliveries. The Cromer reception area was last reviewed in 1999 and since then there have been a number of changes made and issues identified to include: • The creation of a customer services team who aim to resolve enquiries for a range of services at first point of contact • The closure of the dedicated cash office • Introduction of charging for pre-application advice in planning • Commitment to fully utilising space within the building • Health and safety concerns regarding this area • On-going changes around electronic communication Now is the time to respond to these and create an environment that is not only fit for purpose today but has the flexibility to complement and enable changes within the organisation, as required, to meet business needs in the future. The Council has recognised the significance of the website and there is a development programme underway to improve the transactional capabilities of the website. However, even if we are successful in encouraging our customers to make more use of the website, there will always be instances where the type of enquiry and/or level of reassurance the customer needs is better met through face-to-face contact. 2.2 Rationale for Change The Council’s Corporate Plan 2012-2015, commits to making “the Council more efficient so that we can both deliver our priorities and offer value for money for local taxpayers”. We therefore need to create in the front office, a customer service environment that supports specific organisational priorities and allows us to work in the most cost effective and efficient way. Over time, four separate, service based reception areas have evolved around; Revenues and Benefits, Planning and Environmental Services, Housing and Corporate Reception. The Housing team has a specific role and it has been recognised that positive improvements have recently been made in this area. Staff covering the other three areas are all part of the Customer Services Team and, to a significant degree, are multi-skilled and able to resolve most enquiries. However, because the team is dispersed across the office and thinly spread, it makes it difficult to retain service knowledge, fully utilise resources and provide resilience. In addition, the telephony team are currently located away from the face-to-face team, making it more challenging to react to peaks in customer demand in either area. Officers are considering the needs of three distinct but differing stakeholder groups, namely: Customers, Officers and Members. The Customer Services Team has an historical record of general customer comments. Additionally, a survey is being undertaken to gauge customers’ views of the reception area. Teams who have a front office need within the Council, have already been asked regarding their views on future changes and will continue to be involved throughout the various stages of the project. A Member survey is also being undertaken at the time of writing. All of these the findings will be fed into the design brief. Some of the customer transactions that take place at the main counters can be of a personal nature and we have received a number of comments from customers to say that they have felt uncomfortable and embarrassed as their conversation can be heard by people either in the queue or sitting alongside. Any redesign needs to take account of this and provide private areas where such transactions can take place. Also, the rooms used for some customer transactions, historically Planning, are too small and officers have to move between the private room and a back/front office workstation. In addition, the rooms are not equipped with the technology needed to provide good service to some customers. The latter issue is set to increase as more and more Planning applications and associated documents are in electronic format and it is necessary to consider how best to deal with both initial applications potentially needing to be scanned and for Planning Agents who often need access to electronic methods of display etc. Feedback received from both Members and officers indicates that our current provision for meeting rooms is inadequate. The lack of rooms means that the staff canteen is frequently used and although suitable for some meetings, it is not the most appropriate place for meetings such as staff appraisals and supplier presentations etc. The redesign of the reception area will enable a series of meeting spaces to be created. These will be able to be used for customer transactions as well as officer meetings. As the level of customers using face-to-face access decreases over time, the area will be utilised more by officers. This will allow for space elsewhere in the building to be freed up. Aside from the provision within Housing, there is currently no area which allows for self-service via the website and this needs to be addressed if we are to maximise the benefits offered by technology in the future. The Corporate Health and Safety team have carried out an assessment of the reception area and the current arrangements present a significant risk to the organisation. Although there has been some interim action taken, the redesign will address the long term requirements. 2.3. Project Objectives 2.3.1 The key objectives for this project are: • To provide a customer services environment which is more focussed on the customers’ needs • The creation of one Customer Services team in one central location to reinforce the new ways of working • Create efficiency by bringing together the four separate reception areas • Better utilisation of staff time enabling savings to be made • Creation of better areas for private, sensitive and/or complex customer and officer discussions to take place • Full utilisation of the current reception and associated areas to free up space elsewhere in the building • Address the current health and safety issues within this area 2.3.2 Other objectives include: • Promote self-service take up • Create an environment that demonstrates a ‘one Council’ approach • Create an environment which is flexible enough to cope with future organisational needs and priorities of customer service 2.4. Options Appraisal 2.4.1 Do nothing Advantages • No disruption for the organisation or our customers • No capital outlay Disadvantages • No revenue saving through staff efficiencies • No resolution to health and safety issues, putting the Council at significant risk • Remain challenging to react to changes in customer demand as the Customer Services team (all access channels) would not be situated together • Unable to bring dispersed reception areas together making it difficult for staff to retain service knowledge, be fully utilised and provide resilience • Unable to fully utilise the area, wasting valuable floor space • Unable to provide a comfortable and confidential environment for some customer enquiries. • Unable to create appropriate meeting rooms which are equipped to offer resources for appropriate discussions and customer resolution • Remains difficult to promote self-service making it more challenging to educate and encourage customers to transact with us in this (electronic) way • The environment will continue to contribute to low staff morale and sickness levels ultimately affecting the service to for customers • The environment will continue to confuse the customer 2.4.2 Cost Implications • No capital expenditure • 2.5 Likely compensation pay-outs as a result of non-compliant work stations/areas General Improvement 2.5.1 Essentially this would involve the removal of existing counters to be replaced by individual desks Advantages • Resolution of health and safety Issues • Minimal disruption for the organisation and customers • Some small improvements in terms of privacy Disadvantages • No revenue saving as unable to reduce staff numbers • Remain challenging to react to changes in customer demand as the Customer Services team (all access channels) would not be situated together • Unable to bring disperse reception areas together remaining difficult for staff to retain service knowledge, be fully utilised and provide resilience • Unable to fully utilise the area to best effect • Unable to provide a suitable environment for some customer enquiries continuing to make officers and customers uncomfortable • Unable to create additional meeting rooms which will mean that in some cases unsuitable environments will continue to be used • Remains difficult to promote self serve making it more challenging to educate and encourage customers to transact with us in this (electronic) way • The environment will continue to contribute to low staff morale and sickness levels ultimately affecting the service to or customers • The environment will continue to confuse the customer 2.5.2 Likely Cost It is anticipated that the cost would be in the region of £20,000 and would include the following works: 2.6 • Removal of existing counter arrangements • Replacements desks/work stations • Re provision of services (IT, electrics etc) Complete redesign of the Reception Area and associated space 2.6.1 Advantages • Improved service to the customer • Revenue savings resulting from a reduction in staff • Resolution to health and safety issues mitigating any risk to the Council • Customer Services team (various access channels) will be brought together enabling a better reaction to a change in customer demand • Make it easier for Customer Service Advisors to develop skills across all areas, retain knowledge, be fully utilised and provide resilience as disperse reception areas will be brought together • Improved service to the customer • Area will be fully utilised providing better value for money • A suitable environment for all customer enquiries will be provided making it a more pleasant experience for everyone • Additional meeting space will be created with the potential to free up space elsewhere in the building and provide more suitable environments • Potential to generate income from office space made available • The environment for customers to self-service will be enhanced making it easier to educate and encourage customers to transact with us in this (electronic) way • Increase in staff morale resulting in enhanced level of service to or customers • The layout will reduce any confusion for the customer Disadvantages • Significant disruption for the organisation and customer when works are taking place 2.6.2 Likely Cost • 2.7 The full cost is unknown at this stage as tenders have not yet been sought. However, there is a budget within the current capital programme for customer service improvements which is not yet fully allocated. It is anticipated that the available funding within the budget will be sufficient to cover the associated costs for the redesign. Recommended Option The first two options do not allow the organisation to make best use of its staff and offices and the outstanding issues will not be addressed. The option that best meets the organisations objectives, highlighted in this business case, is to redesign the whole reception area, change the look and feel of the environment and create one coherent team. 2.8 Benefits and Realisation In view of the stated organisational objectives a redesign of the Cromer reception will significantly assist the organisation in achieving an increase in customer satisfaction by ensuring that our customers experience is consistent and professional. It will also allow the organisation to work in a more cost effective and efficient way. 2.9 Immediate cashable savings Significant benefit realisation will be through a reduction in staff, through more efficient and effective working methods. Due to the flexibility created through a number of temporary contracts, this will be achieved within three months of any refurbishment. It is anticipated that this cashable saving will be in the region of £33,000 per year. 2.10 Future cashable and efficiency savings Further benefits will be realised over time and will mainly be related to the Customer Services team working more efficiently and effectively, better use by the whole organisation of the reception area, along with a reduction in the number of customer contacts. The latter point will arise partly as a result of the improved website, the project for which overlaps with the proposed customer services change. These further benefits will lead to service quality improvements as well as cashable savings. 2.11 Planned Improvements • Three separate reception areas being brought together – With the meet and greet facility and the service areas being in close proximity, customers are far more likely to obtain resolution at the first point of contact and a lot of Customer Services time will be saved by the reduction in double handling. This will in turn increase capacity and further reduce waiting times for customers. This will also ensure that staff numbers are kept to a minimum providing the potential for staff savings in the future. Staff will find it easier to retain service knowledge, be fully utilised and provide resilience and Team Leaders will be spending less time conducting refresher training and amending rotas etc. • Create appropriate areas for private, sensitive and complex customer transactions and officer discussions to take place – This will provide a more comfortable experience for both customers and officers and will help ensure more effective resolution of the issues and improve the level of service. The areas will be fully equipped with the necessary technology to enable a more efficient and effective way of working. • Utilisation of the reception area including the redundant cash office to create additional meeting rooms and office space This will create space elsewhere in the building ultimately allowing the newly created service teams to come together and the potential to generate income from the space that will become available elsewhere in the building. This includes the move of Electoral Services, part of the wider office moves project, from the Annex into the main office, allowing the removal of the Annexe and subsequent savings. 2.12 • Creation of new work stations for staff - This will address the current Health and Safety issues and will also provide a better working environment for the staff, which should both improve staff morale and lead to better customer service. • Creation of a generic self-serve area - This will assist in the education of our customers and encourage them to contact us through the website (the most cost effective access channel) supporting the desired channel shift and providing the capacity for further staff savings. • Ensuring that the solution is a flexible one - This will provide the organisation with the ability to change the way we deal with front office contact as demand changes e.g. the likely need to scan of a wider range of documents. Scope The area included in the scope has an impact to a certain degree on the whole organisation but it specifically includes the front office requirements of the following services: Environmental Health, Planning, Housing, Revenues and Benefits. Identified constraints to the project include: • • • • 2.13 The existing structure of the building The area identified within the scope Staff resource Available budget Resource Requirements Staffing resource for this project will largely be found in existing staff resource with the exception of some temporary project management support. There will be specific staff resource implications for: • • • • Finance – throughout the project but specifically with tendering and procurement Property Services – throughout the project providing project assurance, developing the specification, evaluating tenders and liaising with the contractors and/or suppliers IT – liaising with contractors and/or suppliers and providing the necessary infrastructure Customer Services – throughout the project but specifically with contribution to the specification and internal and external communications • 2.14 Environmental Services, Planning and Revenues and Benefits staff implications for contribution to the specification Project Organisation, Programme and Timetable A project team has been established as follows and will report to the Customer Service Improvement Programme Board: Project Sponsor Project Manager IT Client Users Asset Management Finance Additional client users Nick Baker Trevor Nelson Terry Rayner Estelle Packham(Customer Services) Duncan Ellis (Head of Assets and Leisure) To be advised Steve Hems (Environmental Services) Lisa Grice (Housing) Lorraine Gray (Planning) Liz Codling (Revenues and Benefits) Tony Turner (Property Services) Zoe Bloomfield (Customer Services) Ben Rowe (Customer Services) The proposed implementation timetable is outlined below: Task Scope Project Outline Project Proposal Identify Project Board Obtain Project Management Resource Prepare Business Case Complete specification for Design phase Agree Business Case with CLT Cabinet approval of Business Case Identify Interior Design Service providers Evaluate potential provider submissions Appoint Interior Design Service provider Complete and Agree Interior Design Complete Tender for Build Phase Identify potential suppliers for Build phase Issue tender documents for Build phase Tenders returned Tenders evaluation Detailed Implementation Plan Build phase (timing to be determined) Programmed Date March 2012 April 2012 April 2012 August 2012 August - September 2012 September – October 2012 1 October 2012 3 December 2012 November/December 2012 December/January 2012/13 January 2013 February 2013 February 2013 February 2013 March 2013 April 2013 April/May 2013 May/June 2013 July/August 2013 2.15 Risks At present the Council is at financial, legal and reputational risk because of significant health and safety issues relating to a majority of the work stations within the main reception area at Cromer. A detailed analysis of the risks associated with the reception refurbishment will be included within the implementation plan but in summary they include: 3 • Reputational Risk due to disruption to staff and customers • Failure to deliver an effective solution within the budget constraints • Staff resource issues • Implementation delays • Failure to realise benefits Removal of the Annexe Building 3.1 Background The annexe building was initially assembled and rented during 2005/2006 to accommodate Victory Housing Trust. After Victory’s move to North Walsham in 2009, the Annexe was purchased and used predominantly for disaster recovery and training, with Electoral Services moving into the unit during 2010. The showers were constructed in 2010 to support the Council’s health agenda. As part of the office move proposals the Electoral Services function will be moving back into the main building and therefore the majority of the space previously required within the annexe will no longer be needed. The annexe itself is in a poor state of repair with the front section (entrance, auditor office, kitchen and toilets) being considered life expired. The rear section has an estimated remaining life of 10 years, although maintenance and repair costs could increase significantly. 3.2 Costs There are a number of revenue costs associated with the annexe, the most substantial of which relates to non-domestic rates (NNDR) charges of nearly £10,200 per annum. There are also general costs associated with repairs and maintenance and servicing of alarms, air conditioning and sewer pumps which total nearly £3,700. Furthermore there are cleaning and electricity costs which are estimated at £7,500, which means the total annual revenue cost for the building is around £21,400. Year 0 2012/13 £ Costs: Revenue: Removal of existing structure Relocation of showers Re-instatement of car parking Year 1 2013/14 £ Year 2 2014/15 £ Year 3 2015/16 £ Year 4 2016/17 £ Year 5 2017/18 £ Total 14,000 7,500 10,000 31,500 0 0 0 0 0 31,500 0 0 0 (10,191) (3,700) (7,500) (10,191) (3,700) (7,500) (10,191) (3,700) (7,500) (10,191) (3,700) (7,500) (10,191) (3,700) (7,500) 0 (21,391) (21,391) (21,391) (21,391) (21,391) (106,955) 31,500 (21,391) (21,391) (21,391) (21,391) (21,391) (75,455) Income/savings NNDR saving R&M/alarm/servicing savings Electricity/cleansing savings Total Revenue Costs/(Savings) 3.3 Proposals It is proposed that the annexe be demolished, the services capped and the car park re-instated. The cost of these works is estimated to be in the region of £31,500, but this would in turn lead to anticipated ongoing annual revenue savings of £21,400 as highlighted above. The total saving over the next 5 years is forecast to be just over £75,000 as can be seen from the table above. The Electoral Services team is moving back into the main office as part of the office moves. It is recommended that the IT training room be relocated to meeting room 2 and, as part of the Council’s disaster recovery plans, an emergency room has already been established in Fakenham in conjunction with Kings Lynn and West Norfolk Borough Council. The existing showers in the Annexe are well used by members of staff who cycle to work and/or exercise at lunchtimes and this supports the Council’s Staff Welfare and Health and Wellbeing agenda. The showers could be relocated within the main office adjacent to the toilets in part of the area currently occupied by Building Control. This location is recommended as it would make the plumbing straightforward as the services are already all in place for the toilets, the cost has been estimated by the Property Manager to be £7,500 and this is included within the £31,500 mentioned above. 3.4 Summary It is therefore recommended that the Annexe is disposed of to realise the £75,000 estimated 5 years saving. The reinstatement of the car park will provide additional car parking capacity which will help with any future tenants that the Council may be able to attract to use the main office building. The relocation of the showers will also support the Council’s health and staff welfare agenda. The IT training room is being relocated to meeting room 2, with the Disaster Recovery suite already relocated to Fakenham. 4 Office Moves It is planned to undertake significant internal office moves over the coming months. Primarily, this is to respond to the changes to service groupings following the Senior Management restructure and the need to relocate staff in these new teams together to enable efficient and effective working. In addition, even with staff moving into the main office from the Annexe, we know that enough space for around 30 desks could be made available for rent to other public sector organisations. At this stage, officers are approaching potential users, although none have been confirmed at this stage. Clearly, if this could be achieved, subsequent income would offset the overhead costs of the building. We also intend to use the moves as an opportunity to rationalise office furniture and other resources such as printers which will provide further, albeit relatively small, savings. We recognise that any office move can cause disruption and clearly, we would wish to minimise this as far as possible and maintain service levels for customers. Managers have had initial discussions with the Properties team who are overseeing the process and further detailed consultation will take place as the teams move together. Due to the need for the Corporate IT Team to provide additional support for the Revenues and Benefits Shared Service project, most of the required office moves have been put back for some weeks, as IT infrastructure support is also needed for these moves. It is anticipated that the majority of the office moves will therefore take place early in 2013. In terms of cost, there will inevitably be some expenditure required to facilitate the office moves although this will be minor. There will also be some potential costs involved if the Property Services team are required to complete office moves and cannot respond to maintenance issues. It is anticipated however, that these can be kept within existing budgets. 5 Financial Implications and Risk 5.1 The costs of the Front Office Reception refurbishment are unknown at this stage as tenders have not been sought and clearly, it would be unwise to specify a price before seeking tenders. However, significant Capital Reserve exists within the Customer Service Improvement budget and it is anticipated that the cost will fall well within this amount. 5.2 The £31,500 to remove the Annexe represents quite clearly, an “Invest to Save” project and will be funded from the Restructuring and "Invest to Save" earmarked reserve. The risks associated with procurement of works and their delivery on time will be managed by the appointment of appropriate professional support. 5.3 The reputational risks around changes to the customer services area will be managed by ensuring that alternative front office provision is maintained throughout the period of any works. The risk identified around cost overruns against budget will be managed by letting appropriate contracts for work and ensuring that best value is achieved throughout the procurement process. 6 Sustainability 6.1 There are no major sustainability issues arising directly from the report. However, the removal of the Annexe will significantly improve energy consumption levels at the Cromer office site. 6.2 Furthermore, the refurbishment of the reception area and the office moves will enable improved use of printers and other IT equipment. 7 Equality and Diversity The refurbishment of the Front Reception area will provide better access to services to all sections of the community. 8 Section 17 Crime and Disorder considerations There are no anticipated impacts on Crime and Disorder arising from this report. 9 Conclusion The three areas of work detailed above, if approved, will allow efficiencies to be realised through better staff and buildings resource use. In addition, they will support the change agenda required to deliver the Council’s Corporate Plan and will significantly improve customer interaction with the Council.