Overview and Scrutiny Committee ...

advertisement
Overview and Scrutiny Committee
16 January 2012
Agenda Item No_17__
OVERVIEW AND SCRUTINY UPDATE
Summary:
This report updates the Committee on progress with
topics in its agreed work programme (attached at
Appendix G) and invites Members to identify any
arising items for future meetings. The Scrutiny
Committee’s working style and role is attached at
Appendix H.
Conclusions:
That progress is being made in some areas, others
need to be monitored and opportunities for scrutiny
should be discussed.
Recommendations:
That Members should consider any follow-up
actions required on these topics.
Cabinet Member(s):
Ward(s) affected
Mr T FitzPatrick
All
Contact Officer
telephone number
and email:
Emma Denny
01263 516010
emma.denny@north-norfolk.gov.uk
1.
Introduction
The Scrutiny Update report is a standing item on all Overview and Scrutiny
Committee agendas. The report updates Members on progress made with
topics on its agreed work programme and provides additional information
which Members may have requested at a previous meeting.
2.
Progress on topics since the last meeting
2.1
Ambulances
A response has been received from the Ambulance Service Trust to two
questions raised by the Chairman:
1) On Trust budget & Income what is the difference between the column A&E
SLA income and the column total income.
The difference between the two figures is because the trust operates more
than just the 999 service. For example, the Trust runs the out of hours GP
service in Norfolk and the new NHS 111 service in Norfolk as well as a range
of other services. The A&E income solely represents the funding for the 999
emergency service.
Overview and Scrutiny Committee
16 January 2012
2) On A19 performance which I would like confirmed stands for a response
time of 19 minutes our minutes show a response rate of 84.95% for 2010/11
whereas figures supplied show 80.60 for 2011 and 72.4 for 2012. What are
the correct figures and when they refer to a year is this actually a year from
Jan to Dec or is it a financial year ending on March 31st.
The figures supplied by email refer to calendar years and are correct.
Ambulance response times
A letter is attached at Appendix I from the Chair of the North Norfolk Clinical
Commissioning Group (NNCCG) outlining their concerns regarding
ambulance response times and stating their intentions to monitor the service
and improve provision. I will keep members updated with any progress on this
area.
2.2
Response to previous questions
At the September 2012 meeting, Councillor Claussen-Reynolds sought
clarification on whether the demand for the Learning for Everyone
programme outstripped resources. Jill Fisher has now provided a
response:
Demand does outstrip the resource available at times, and generally the
trainers are booked up 2-4 weeks in advance, but this is not even across the
year as there are obviously peaks during periods of significant redundancies
etc. The service aims to match resources to demand as far as possible given
that there are only 2 IAG workers available.
2.3
Recommendations from Task and Finish Group
A follow-up letter has been sent to the County Council seeking a response to
the initial request.
2.4
Mobile phone coverage
I will be responding to the County Council shortly regarding their request for
information on mobile phone coverage across our District. Please can
Members who wish to respond provide any information to me by Friday 18th
January.
3.
Changes to the Work Programme and Future Topics
At the December meeting Members requested an update on the Housing
Allocations Scheme and the Empty Homes Policy after 12 months. Nicola
Turner has requested that the report is made to committee 12 months after
implementation to ensure that she is able to give a comprehensive update.
Both items will be added to the work programme.