Appendix 16 Appeal Decisions Inquiry opened on 6 March 2012 Site visits made on 26 March, 17 April and 15 June 2012 by Paul Griffiths BSc(Hons) BArch IHBC an Inspector appointed by the Secretary of State for Communities and Local Government Decision date: 29 June 2012 Appeal A: APP/K0235/A/11/2160077 Chelveston Renewable Energy Park, Chelveston Airfield, Chelveston • • • • The appeal is made under section 78 of the Town and Country Planning Act 1990 against a refusal to grant planning permission. The appeal is made by Chelveston Renewable Energy Ltd against the decision of Bedford Borough Council. The application Ref.10/00484/MAF, dated 24 February 2010, was refused by notice dated 29 March 2011. The development proposed was described as ‘construction and use of 4 (four) wind turbines each 125m in height to blade tip and one anemometer mast 80m high, including construction of access tracks, turbine bases, laying of underground cables and visitor car park’. Appeal B: APP/G2815/A/11/2160078 Chelveston Renewable Energy Park, Chelveston Airfield, Chelveston • • • • The appeal is made under section 78 of the Town and Country Planning Act 1990 against a refusal to grant planning permission. The appeal is made by Chelveston Renewable Energy Ltd against the decision of East Northants District Council. The application Ref.EN/10/00415/FUL, dated 24 February 2010, was refused by notice dated 7 March 2011. The development proposed was described as ‘construction and use of 5 (five) wind turbines each 125m in height to blade tip and one anemometer mast 80m high, including construction of access tracks, turbine bases, laying of underground cables and visitor car park’. Preliminary Matters 1. The Inquiry sat between 6 - 9 and 12 - 16 March and again on 21 March 2012. Submissions on the National Planning Policy Framework1 were dealt with in writing, as were those on the UU2, and closing statements from all the main parties, in accordance with a timetable set out and agreed on 21 March 2012. The Inquiry was closed in writing on 15 May 2012. 2. The proposals are EIA development for the purposes of the Town and Country Planning (Environmental Impact Assessment) (England and Wales) Regulations 1999 (as amended). The originating applications were accompanied by an ES3 that was subsequently expanded upon through an addendum issued in July 2010, and another in October 2010. 1 2 3 Referred to hereafter as the Framework Unilateral Undertaking Environmental Statement www.planningportal.gov.uk/planninginspectorate 16.1 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 3. Some concerns were raised about aspects of the ES, and especially the way it approaches impacts on heritage assets. However, there has been no sustained suggestion that the ES, as amended, does not meet the needs of the relevant Regulations. On my analysis, the ES, as amended, meets those needs and, along with all the other material presented to the Inquiry, I have taken it into account in determining the appeals. While there are two schemes, the ES, as amended, deals with them as one proposal. While the proposals are divisible, I have dealt with the appeals in much the same way 4. I carried out accompanied site visits on 26 March 2012 in accordance with an agreed itinerary. These were completed on 17 April 2012 when I visited the appeal site itself and the industrial unit the appellant proposes to use for fabrication purposes. Later that day, I carried out some unaccompanied site visits, as set out in the same itinerary. I had intended to complete these on the following day but had to abort because of inclement weather. These visits were completed on 15 June 2012. During those unaccompanied visits, I also took the opportunity to take in the large number of designated heritage assets identified in the ES, the subsequent addenda, and the evidence. 5. In its decision notice, Bedford Borough Council amended the description of development to read ‘construction and use of 4 (four) wind turbines, each 125m high to blade tip, and one anemometer mast (80m high) including construction of access tracks, turbine bases and laying of underground cables’. As reflected in the SoCG4, that is a more accurate description of what is proposed and I have dealt with Appeal A on that basis. The description of development used by East Northamptonshire District Council in its decision notice refers to nine wind turbines, five of which are located within the district. I find the reference to those wind turbines located in the adjoining borough unnecessary and for the purposes of Appeal B have reverted to the description of development from the originating application, with minor revisions in the interests of consistency. There is also the issue around the anemometer mast to be dealt with. I return to that below. Decisions Appeal A 6. The appeal is allowed and planning permission is granted for construction and use of 4 (four) wind turbines, each 125m high to blade tip, and one anemometer mast (80m high) including construction of access tracks, turbine bases and laying of underground cables at Chelveston Renewable Energy Park, Chelveston Airfield, Chelveston in accordance with the terms of the application, Ref.10/00484/MAF, dated 24 February 2010, subject to the conditions set out in Annex A to these decisions. Appeal B 7. The appeal is allowed and planning permission is granted for construction and use of 5 (five) wind turbines, each 125m in height to blade tip, including construction of access tracks, turbine bases, laying of underground cables and visitor car park at Chelveston Renewable Energy Park, Chelveston Airfield, Chelveston in accordance with the terms of the application, Ref.EN/10/00415/FUL, dated 24 February 2010, subject to the conditions set out in Annex B to these decisions. 4 Statement of Common Ground agreed between the appellant and the Councils www.planningportal.gov.uk/planninginspectorate 2 16.2 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 Application for Costs 8. An application for costs was made by PRESERVE against the appellant. This application is the subject of a separate Decision. Main Issue 9. This is whether any benefits of the proposals are sufficient to outweigh any harm they would cause to (1) the character and appearance of the surrounding landscape, including any cumulative impact; (2) the setting of heritage assets; (3) the living conditions of nearby residents through visual impact, noise, shadow flicker, or anything else; and (4) other matters raised. Reasons Benefits 10. According to the figures put forward by the appellant, each wind turbine would have an electricity generating capacity of up to 2.5 MW. This means that the wind farm as proposed, with 9 wind turbines, would have a generating capacity of up to 22.5 MW. The appellant predicts that the wind farm will generate around 59,000 MWh per year, enough to supply the needs of about 12,500 households, and create savings of approximately 25,000 tonnes of carbon dioxide per year. 11. These calculations drew some criticism because, it is said, they are based on an optimistic capacity factor of 30% and fail to take account of reductions in output efficiency due to the alignment and proximity of the proposed wind turbines. However, according to the appellant, the figures put forward are based on raw wind data gathered at the site between 2006 and 2008 and take full account of the layout proposed. On that basis, I see no good reason to suspect that the figures presented by the appellant are unduly optimistic. 12. The Localism Act has received royal assent, and the Government has made clear its intention to revoke them but at the time of writing, Regional Spatial Strategies remain part of the development plan. The scheme at issue under Appeal A comes within the region covered by the RSS for the East of England5 and the scheme at issue under Appeal B by the RSS for the East Midlands6. 13. Policy ENG2 of the RSS for the East of England sets out that the development of new facilities for renewable power generation should be supported, with the aim that by 2010, 10%, and by 2020, 17% of the region’s energy should come from renewable sources. Paragraph 9.6 of the RSS for the East of England translates this to an installed renewable energy capacity, onshore, of 820 MW by 2010, and 1620 MW by 2020. 14. Based on the DECC7 figures presented to the Inquiry by the Councils and the appellant, as of 20 March 2012, the East of England Region had 1160 MW of renewable energy technologies in operation, 581 MW awaiting or under construction, and 181 MW as planning applications under consideration. While I heard that the 2010 target in the RSS for the East of England was not met, it appears that there is sufficient capacity in operation, and permitted, or under consideration, to comfortably surpass the 2020 target. 5 6 7 East of England Plan: The Revision to the Regional Spatial Strategy for the East of England of May 2008 The East Midlands Regional Plan Department of Energy and Climate Change www.planningportal.gov.uk/planninginspectorate 3 16.3 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 15. However, there is a complication. A significant proportion of the renewable energy capacity in operation (750 MW) comes from the Tilbury B biomass power station. There have been recent problems with a serious fire, but notwithstanding that, the plant will only run until its scheduled closure under the LCPD8, or the end of 2015, or the remainder of its permitted 20,000 hours of operation under the LCPD have been used. 16. Whichever, the Council accepted that Tilbury B will not contribute anything in 2020. Clearly, the loss of such a significant contributor means that there must be significant doubt about whether the 2020 target of 1620 MW will be met. 17. In terms of Appeal B, RSS for the East Midlands Policy 40 says that in establishing criteria for onshore wind energy, amongst other things, the contribution to national and international environmental objectives on climate change and the regional renewables target, should be given particular consideration. 18. Policy 40 refers to Appendix 5 to the RSS for the East Midlands that sets regional targets for the production of renewable energy. The 2010 target for onshore wind was 122 MW, rising to 175 MW in 2020. Again using the DECC figures presented to the Inquiry, as of 20 March 2012, the East Midlands Region has 135 MW of onshore wind in operation, 180 MW awaiting or under construction, and 229 MW under consideration through planning applications. On that basis, it seems that the 2020 regional target for onshore wind will be comfortably exceeded. 19. However, proper analysis cannot focus on onshore wind alone. The 2010 regional target for all renewable energy technologies was 324 MW, rising to 3671 MW in 2020. The Council accepted that the 2010 target was not met. As of 20 March 2012, the agreed DECC figures show a total for all renewable energy technologies in the East Midlands Region of 221 MW in operation, 574 MW awaiting or under construction, and 247 MW as planning permissions being considered. Even allowing for the time between now and 2020, the 2020 target looks a long way off at the current rate of provision. 20. On top of that, the RSS for the East Midlands envisages that 3253 MW of the 2020 target will be secured through micro-generation wind and photo-voltaics. That does seem optimistic at best. It seems that very little progress has been made with micro-generation in the region and that is unlikely to change quickly. It is obvious that more established commercial renewable technologies, including onshore wind, will have to make up the significant shortfall if the 2020 target for all renewable energy technologies is to be meaningfully approached, let alone met. 21. In that overall context, the proposals would make a relatively small, given the scale of the 2020 targets, but tangible contribution to renewable energy generation required by RSS for the East of England Policy ENG2 and RSS for the East Midlands Policy 40. However, despite the current status of Regional Spatial Strategies as part of the development plan, given Government intentions towards them, and the concern expressed in the Framework about ‘targets’ and an ‘unaccountable regional apparatus’, it seems more pertinent to consider the national picture. This is most clearly expressed in the Roadmap9. 8 9 Large Combustion Plant Directive The UK Renewable Energy Roadmap www.planningportal.gov.uk/planninginspectorate 4 16.4 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 22. My attention was drawn to paragraph 2.20 of the Roadmap. This notes that the pipeline for new plant across the UK is currently healthy, with around 22 GW of potential new capacity in planning, consented, or under construction. When taken together with existing capacity and accounting for historic consenting rates, 29 GW could be in operation in 2020. In terms of onshore wind, the relevant Minister has confirmed that 5 GW has been built, permission exists for 6 GW and permission is being sought for 7 GW, against an overall ambition of 13 GW. Viewed in that light, the national situation in relation to onshore wind appears healthy too. 23. However, paragraph 2.21 of the Roadmap adopts a more cautionary tone because, as it says, we cannot be certain that all the projects in the pipeline will be consented or commissioned or that they will progress quickly enough to contribute when needed. That is why EN-110 states that there is an urgent need for new large scale renewable energy projects to come forward to ensure that we meet the 2020 target and wider decarbonisation ambitions. 24. Those targets and ambitions are set out earlier in the Roadmap. Paragraph 1.1 sets out that the Coalition Government has made clear its commitment to increase the amount of renewable energy deployed in the UK to make the nation more energy secure, to protect consumers from fluctuations in the price of fossil fuels, to help drive investment in new jobs and businesses in the renewable energy sector, as well as keeping us on track to meet our carbon reduction objectives for the coming decades. Paragraph 1.2 notes that the goal is to ensure that 15% of all of our energy demand is met from renewable sources by 2020 in the most cost effective way, with ambition equally strong across all areas of the UK. Paragraph 1.3 looks beyond 2020 and cites advice from the CCC11 that there is scope for the penetration of renewable energy to reach 30-45% of all energy consumed in the UK by 2030. 25. Reflecting all that, paragraph 93 of the Framework says that planning plays a key role in helping shape places to secure radical reductions in greenhouse gas emissions, minimising vulnerability, providing resilience to the impacts of climate change, and supporting the delivery of renewable energy. This, we are told, is central to the economic, social and environmental dimensions of sustainable development. Paragraph 97 suggests that to help increase the use and supply of renewable and low carbon energy, local planning authorities12 should recognise the responsibility on all communities to contribute to energy generation from renewable or low carbon sources. Moreover, paragraph 98 notes that in determining planning applications, applicants should not be required to demonstrate the overall need for renewable or low carbon energy and recognises that even small-scale projects provide a valuable contribution to cutting greenhouse gas emissions. 26. Against that background, the national pipeline to 2020, in terms of renewable technologies overall and onshore wind specifically, may be healthy, but that health depends, to a large extent, on proposals already in the planning process, like those before me, coming to fruition, in time. It is also clear that Government ambitions go well beyond 2020 and if those ambitions are to be realised, the pipeline will need new projects to continue coming forward in order to sustain supply. 10 11 12 Overarching National Policy Statement for Energy Committee on Climate Change I take that to include the Secretary of State and/or those acting on his or her behalf throughout the document www.planningportal.gov.uk/planninginspectorate 5 16.5 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 27. The Framework does not repeat the key principle, set out in PPS2213, that the wider environmental and economic benefits of all proposals for renewable energy projects, whatever their scale, are material considerations that should be given significant weight in determining whether proposals should be granted planning permission. But, supporting the transition to a low carbon future in a changing climate is one of the key principles of the Framework. That, coupled with what the Government has said in the Roadmap and EN-1 makes it clear that the benefits of these proposals in terms of the generation of energy from a renewable source, securing reductions in greenhouse gas emissions, adding to energy security, and providing resilience to the impacts of climate change, must carry significant weight in the overall planning balance. 28. Another element of the proposals prayed in aid by the appellant centres on the potential to create local employment opportunities, not just for operation and maintenance but also during the design and construction phases. The appellant intends to use a local firm to construct as much as possible of the development proposed locally and that all of the civil engineering works and site infrastructure will be managed with ‘in-house’ labour. To achieve that, additional, suitably-skilled, labour will need to be recruited. It is also the aim of the appellant to build the wind turbine towers locally (either at an industrial unit in Higham Ferrers or at their Wymington base) bringing further direct employment opportunities and the potential to exploit wider demand, in the context of the relative lack of UK manufacturing capacity for turbine towers. 29. The Councils and PRESERVE suggest that little or no weight should be attached to this aspect of the scheme given that there are no formal means of securing it. That there are no means of ensuring that the potential to generate economic activity and employment in the manner identified by the appellant comes to fruition is correct. However, there is no good reason to suspect insincerity on the part of the appellant. Moreover, as paragraph 18 of the Framework confirms, the Government is committed to securing economic growth in order to create jobs and prosperity and paragraph 19 says that significant weight should be placed on the need to support economic growth through the planning system. Paragraph 1.1 of the Roadmap is also supportive. None of these documents suggest that weight can only be attached to the economic benefits of development proposals if there is a formal delivery mechanism to ensure those benefits are secured. Against that background, the potential of the proposals to generate economic growth and create jobs must attract significant weight in their favour. 30. As set out, these benefits of the proposals attract significant weight in their favour. Whether these benefits are sufficient to outweigh any harmful consequences identified is the crux of the cases. Landscape Impact 31. As a precursor to an assessment of the impact of the proposals on the character and appearance of the surrounding landscape, it is necessary to note one of the core principles of the Framework; that the intrinsic character and beauty of the countryside should be recognised. Paragraph 109 of the Framework states that the planning system should contribute to and enhance, the natural and local environment by, amongst other things, protecting and enhancing valued landscapes. 13 Planning Policy Statement 22: Renewable Energy (now cancelled) www.planningportal.gov.uk/planninginspectorate 6 16.6 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 32. In terms of the approach of the development plan to the landscape, the context is different for the two separate appeals. In terms of Appeal A, Bedford Local Plan14 Policy BE30 sets out a range of considerations to be taken into account in decision-making including, of relevance, the visual impact of proposals and their contextual relationship, the contribution it makes to the landscape qualities of the area and, where appropriate, the extent to which local distinctiveness is reinforced or created. 33. BCSRIP15 Policy CP2 seeks to ensure that the character and quality of local landscapes are preserved and, where appropriate, enhanced. Broadly, this approach is repeated in BCSRIP Policies CP21, CP 23 and CP24. 34. In terms of Appeal B, RSS for the East Midlands Policies 26 and 31 suggest that the Region’s landscapes should be protected and enhanced. Criterion (o) of Policy 13 of the NNCSS16 requires proposals to conserve and enhance landscape character. 35. Government advice in EN-1 is that landscape and visual assessment should include reference to any landscape character assessment and associated studies as a means of evaluating landscape impacts. The appeal site and its more immediate surroundings lie within NCA17 91: Yardley-Whittlewood Ridge. 36. In simple terms, this NCA is defined as a broad plateau, elevated above adjacent vales. The NCA 91 analysis points to the elevation of the plateau making it suitable for airfields and, as set out in the SoCG, the appeal site is part of what was an airfield, originally operated by the RAF, but later the USAAF. The analysis also notes that from the plateau top the land slopes away gently with long views over surrounding vales giving a feeling of being elevated, of openness, and expansiveness. 37. The boundary between Bedford Borough and East Northamptonshire District subdivides the appeal site. As such, the appeal site and its surroundings fall within two separate LCAs18: Riseley Clay Farmland LCA (Bedford) and the Chelveston and Caldecott Claylands LCA (East Northamptonshire). It is agreed that despite the different classifications, the landscape characteristics of these LCAs share similarities. 38. Bearing that out, the former is described as a rural, peaceful area with a remote feel. Disused airfields are noted as a feature of the higher plateaux where the absence of field boundaries emphasises an ‘empty’ character. Rural villages with their Churches, and subtle tributary valleys and streams are recognised as elements of high sensitivity along with sections of open elevated ground at the crest of the subtle valleys and open, gently rolling landform. Wider views of Church towers are highlighted as being particularly sensitive. 39. The latter is described as an expansive, flat or gently undulating landscape where plateaux are divided by broad shallow valleys. It is highlighted that wide views give the landscape an expansive and sometimes exposed character. It is also noted that Church spires often provide important focal points and punctuation marks in the landscape. 14 15 16 17 18 Bedford Local Plan Bedford Borough Council Core Strategy and Rural Issues Plan DPD North Northamptonshire Core Spatial Strategy National Character Area Landscape Character Areas www.planningportal.gov.uk/planninginspectorate 7 16.7 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 40. It is clear from the evidence and what I saw at my site visits that these wider descriptions of relatively large areas are a little limited in that they fail to take account of smaller areas within them that might exhibit different characteristics and sensitivities. Nevertheless, an analysis of landscape impact must begin with the appeal site itself, which is criss-crossed by a variety of PRoWs19. 41. The appeal site has the kind of exposed, open character typical of the LCAs. There is little in the way of field boundaries and much of it is used for grazing livestock. Remnants of the former use are still evident as are buildings and structures associated with other activities on the site, notably the biofuel and biomass plants and Heras fencing. There are wide views out from the site over the surrounding countryside. 42. Notwithstanding all that, the sheer scale of nine turbines proposed, at a height of around 125 metres, and the ancillary infrastructure, would dominate the site itself, the PRoWs that pass through, and views out from, it. If as policy nationally, regionally and locally dictates, the countryside is to be recognised for its intrinsic character and beauty, and protected or enhanced, the imposition of structures of such scale and height, along with their ancillary infrastructure, can have nothing but a harmful impact on the character and appearance of the landscape of the site itself, and areas immediately surrounding it. 43. However, the open, exposed nature of the site, the wide scope of views beyond, and the evident remnants of former uses, would ameliorate that harmful impact to a large degree. The relatively wide spacing between the wind turbines would also act as a dilutor of impact. The synergy between the wind turbines and the other renewable energy-based activities relatively close-by would give a functional logic to their location. 44. As acknowledged at the Inquiry, the Heras fencing that has been erected to delineate the PRoWs that cross the site is utilitarian and unattractive in appearance. I heard much complaint about it but there is no suggestion that it is unauthorised in planning terms. The appellant is prepared to accept a condition, if planning permissions are granted, to replace the fencing with something that would perform the same function, but appear easier on the eye. While this would do little or nothing to lessen the effect of the wind turbine array on the landscape, it would lead to some localised visual improvement and therefore offers some benefit, as part of the scheme overall. 45. The scale of the wind turbines proposed and their consequent landscape impact would tend to reduce with separation distance but it is abundantly clear from the various photo-montages presented to the Inquiry and my site visits that, located on a plateau, the array would appear prominent on the skyline from all around the site, including PRoWs like the Three Shires and Nene Ways. 46. Notwithstanding that the existing wind turbines at Burton Wold are visible from various areas around the appeal site, the wind turbines proposed would appear incongruous in their landscape setting. As previously indicated, if the intention of policy is to ensure the landscape is protected or enhanced for its intrinsic character and beauty, then they must have a harmful impact on the wider landscape. The nub of the analysis of landscape impact is the extent of harm that would be caused. 19 Public Rights of Way www.planningportal.gov.uk/planninginspectorate 8 16.8 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 47. There was some discussion about the virtues, or otherwise, of locating wind turbines on the skyline. To my mind, there are distinct advantages to such a position in a landscape with an exposed and expansive character like that under consideration here. A careful choice of coloured finish can give the wind turbines a recessive quality, when seen against the sky, in some weather conditions. More importantly, leaving aside landscape and other impacts, welldesigned wind turbines can exhibit a sculptural quality, accentuated by their movement. That quality is best appreciated when the simple background of the sky is reflected in the simplicity of the landscape. The exposed skyline location would not prevent the wind turbines proposed from appearing as incongruous, large-scale, man-made impositions on the landscape, but it would have some functional logic, and serve to reduce the resulting harmful impact. 48. Concerns raised about landscape impact by the Councils and PRESERVE concentrated on a series of interrelated aspects. The first is the Til Valley. This lies within the Riseley Clay Farmland LCA but clearly exhibits rather different characteristics to the generality of the LCA. I agree that it, and the settlements that lie along the course of the River Til, are of higher sensitivity. In views of the valley from the south-east and east in particular, the wind turbine array will appear as a prominent, incongruous feature on the skyline. They would appear significantly higher than the depth of the valley and rise in a rather dominant way above it. However, they would not be seen in these views as part of the valley, but as elements located in a separate part of the landscape, with different characteristics. This would tend to reduce the harmful impact on the particular landscape of the valley, and the settlements within it. 49. There would be more distant views of the wind turbine array across the Nene Valley. Again the array would be prominent in these views and an incongruous element. However, these views would also take in large commercial buildings and former gravel pits, amongst other things, so in that overall context, the harmful impact of the proposals in these views would be limited. 50. The prominence of Churches as wayfaring landmarks is highlighted in the LCAs and is clearly an important characteristic of the surrounding landscape, as borne out by the Northamptonshire ‘Squires and Spires’ adage. Part of the analysis of the proposals on this characteristic goes to the significance of the Churches themselves, in cultural heritage terms, that I deal with below. However, the punctuation provided by Church towers and spires is clearly an important aspect of landscape character. 51. The wind turbines proposed would be much higher than the towers and spires of the Churches. Notwithstanding that, those Church towers and spires would still remain present in the landscape. Anyone travelling through the landscape would not be prevented from using them as wayfaring landmarks by the presence of the wind turbines proposed. Neither would the punctuation provided by the Church towers and spires be lost. 52. In terms of cumulative impact, the position changed during the Inquiry with the dismissal of the Bicton appeal20 and details of the high court challenge to the Nun Wood decision21. As set out, the wind farm at Burton Wold is visible from areas around the appeal site. However, it is too far away to cause a cumulative impact, with the proposals before me, of any great import. 20 21 APP/H0520/A/11/2146394 APP/Y0435/A/10/2140401, APP/K0235/A/11/2149434 and APP/H2835/A/11/2149437 www.planningportal.gov.uk/planninginspectorate 9 16.9 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 53. The CPRE made points about cumulative impact when walking along the Three Shires Way from the serial experience of wind farms at Petsoe End, Podington22, Nun Wood and the proposals at issue in these appeals. I visited the suggested viewpoint near Oakley as suggested. 54. The wind farm at Petsoe End is operational. A decision on the redetermination of the appeal relating to the Podington wind farm, following a successful high court challenge, is awaited. Nun Wood is currently subject to a high court challenge. In that context, it is not clear whether the entirety of the cumulative impact envisaged by the CPRE will ever manifest itself. In any event, from what I saw, there would be sufficient separation between them to prevent any significant cumulative impact on the landscape. 55. In more general terms, footnote 17 on page 22 of the Framework sets out that in assessing the likely impacts of potential wind energy development in determining planning applications for such development the approach set out in EN-323, read in conjunction with EN-1, should be followed. 56. The proposal is intended to endure for a period of 25 years and is reversible. Paragraph 2.7.17 of EN-3 states that that the time-limited nature of wind farms is likely to be an important consideration in assessing impacts of onshore wind farms (albeit larger ones) on the landscape. As set out, there would be some harm to the landscape and 25 years is a long time in human terms, if not in terms of how landscapes evolve. However, harm is a product of impact and duration, and the fact that the harm caused by the proposals would be transient must lessen its impact, overall. 57. The appellant has also expressed a willingness to remove the existing Boxer Mast if planning permission is granted for the proposals. This lattice structure, a remnant of former uses of the site, and approximately 70 metres high, is widely visible and as a significant man-made imposition, detracts from the surrounding landscape. Its removal, which could be secured by condition, would be a benefit of the proposals. 58. To summarise, the proposal would have a harmful impact on the landscape whether viewed close-up or from further away. However, as set out, that harmful impact would be mitigated, though not extinguished, by a series of factors. Nevertheless, any harmful impact on the landscape renders the proposal contrary to BLP Policy BE30, BCSRIP Policies CP2, CP21, CP23 and CP 24, RSS for the East Midlands Policies 26 and 31 and criterion (o) of Policy 13 of the NNCSS. The Impact on Designated Heritage Assets 59. The proposals would have no direct impact on the fabric of any designated heritage asset but issues have been raised about their impact on the settings of a large number. 60. The Framework defines the setting of a heritage asset as the surroundings in which a heritage asset is experienced. Its extent is not fixed and may change as the asset and its surroundings evolve. Elements of a setting may make a positive or negative contribution to the significance of an asset, may affect the ability to appreciate that significance, or may be neutral. 22 23 APP/K0235/A/09/2108506 National Policy Statement for Renewable Energy Infrastructure www.planningportal.gov.uk/planninginspectorate 10 16.10 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 61. EH24 guidance in ‘The Setting of Heritage Assets’ says, in paragraph 2.2, that setting embraces all of the surroundings (land, sea, structures, features and skyline) from which an asset can be experienced or that can be experienced from or within the asset. Setting does not have a fixed boundary and cannot be definitively and permanently described as a spatially bounded area or as lying within a set distance of a heritage asset. Of particular relevance, the guidance notes that the construction of a distant but high building may extend what might previously have been understood to comprise setting. 62. As the ES bears out, the nature of this definition, and its amplification, means that the setting of a significant number of designated heritage assets would be affected by the proposals. Notwithstanding that, the Councils and PRESERVE limited their analyses in a manner proportionate to the significance of the assets concerned, and the degree to which the proposals would affect their significance and the ability to appreciate it. This follows advice in paragraph 122 of the still extant PPS5 Practice Guide25 reflected by EH in Section 4.2 of ‘The Setting of Heritage Assets’. The evidence of the appellant to the Inquiry (which differs in approach to that of the ES) takes a similar tack. Having spent no little time taking in the designated heritage assets identified in the ES, and the evidence, I concur with the approach adopted by the parties at the Inquiry and have concentrated my analysis in much the same way. 63. An assessment of the impact of the proposal on the setting of these designated heritage assets must be made against the background of a series of statutory and policy documents. First, Section 66(1) of the Planning (Listed Buildings and Conservation Areas) Act 1990 sets out that in considering whether to grant planning permission for development which affects a listed building, or its setting, the decision-maker shall have special regard to the desirability of preserving the building, or its setting, or any features of special architectural or historic interest which it possesses. 64. In terms of the setting of those designated heritage assets affected by Appeal A, RSS for the East of England Policy ENV6 states that local planning authorities and other agencies should identify, protect, conserve, and where appropriate, enhance the historic environment of the region, including conservation areas and listed buildings, and their settings. BLP26 Policy BE21 states that the Borough Council will seek to preserve and enhance the setting of listed buildings by appropriate control over the design of new development in their vicinity and over the use of adjacent land. BCSRIP27 Policies CP21 and CP23 also seek to preserve/protect and, where appropriate, enhance, amongst other things, SAMs28, listed buildings and their settings 65. In terms of the setting of those designated heritage assets affected by Appeal B, RSS for the East Midlands Policy 26 seeks to ensure the protection, appropriate management and enhancement of the Region’s cultural heritage through the application of a series of principles. Of relevance, the Region’s internationally and nationally designated historic assets should receive the highest level of protection; and damage to historic assets or their settings should be avoided wherever and as far as possible, recognising that such assets are usually irreplaceable. 24 25 26 27 28 English Heritage PPS5 Planning for the Historic Environment: Historic Environment Planning Practice Guide Bedford Local Plan Bedford Borough Council Core Strategy and Rural Issues Plan DPD Scheduled Ancient Monuments www.planningportal.gov.uk/planninginspectorate 11 16.11 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 66. RSS for the East Midlands Policy 27 sets regional priorities for the historic environment. In particular, it calls for the historic environment to be understood, conserved and enhanced, in recognition of its own intrinsic value, and its contribution to the Region’s quality of life. Criterion (o) of Policy 13 of the NNCSS29 requires proposals to conserve and enhance designated built environment assets, and their settings. NNCSS Policy 5 also seeks to protect and enhance historic assets. 67. The Framework deals with determining planning applications that affect heritage assets in paragraphs 128 to 135. Paragraph 129 requires local planning authorities to identify and assess the particular significance of any heritage asset that may be affected by a proposal (including by development affecting the setting of a heritage asset). 68. Paragraph 132 sets out that when considering the impact of a proposed development on the significance of a designated heritage asset, great weight should be given to the asset’s conservation. The more important the asset, the greater the weight should be. It goes on to note that significance can be harmed or lost through alteration or destruction of the heritage asset or development within its setting; substantial harm to or loss of a Grade II listed building should be exceptional; and substantial harm to or loss of designated heritage assets of the highest significance, notably SAMs, and Grade I and II* listed buildings should be wholly exceptional. 69. Paragraph 133 goes on to note, of relevance, that where a proposed development would lead to substantial harm to or total loss of significance of a designated heritage asset, consent30 should be refused unless it can be demonstrated that the substantial harm or loss is necessary to achieve substantial public benefits that outweigh the harm or loss. Paragraph 134 says that where a proposed development will lead to less than substantial harm to the significance of a designated heritage asset, this harm should be weighed against the public benefits of the proposal. 70. Before assessing impacts on the setting of individual designated heritage assets in the context of statute, the policy background, and the Framework, it is necessary to address the concept of significance. This is defined in the Framework as the value of a heritage asset to this and future generations because of its heritage interest. That interest may be archaeological, architectural, artistic or historic. As an addition to the previous definition in PPS531, we are now told that significance derives not only from a heritage asset’s physical presence, but also from its setting. 71. On top of that, there is a need to make some sort of assessment of how the concept of substantial and less than substantial harm can be calibrated. The Framework is silent on the matter, as was PPS5 before it. If one looks to the PPS5 Practice Guide for clarification, substantial harm, demolition or destruction are dealt with under the same heading in paragraphs 91 to 95. There is no specific guidance or example of where on a notional sliding scale of harm, harm to a designated heritage asset might become substantial. The Council’s witness maintained that substantial harm sits half-way between no harm and total loss. 29 30 31 North Northamptonshire Core Spatial Strategy I take that term to be interchangeable with permission Planning Policy Statement 5: Planning for the Historic Environment (now cancelled) www.planningportal.gov.uk/planninginspectorate 12 16.12 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 72. However, a fair reading of paragraphs 91-95 suggests that the author(s) must have considered substantial harm to be something approaching demolition or destruction; otherwise there would little sense in dealing with them under the same heading. On that basis, I adopt the position taken by the appellant’s witness; that substantial harm lies further along that sliding scale, approaching demolition or destruction. As set out, no part of the fabric of any of the designated heritage assets identified would be affected by the proposals. As a consequence, a good deal of their archaeological, architectural, artistic and historic interest would remain intact despite any effect on their settings. 73. The Councils and PRESERVE criticised the approach taken by the Inspector in a recent decision32 to the impact of the proposals on the setting of the designated heritage assets affected therein. Obviously, I am aware of the circumstances surrounding it. I have dealt with the proposals before me here on the basis of the evidence presented. However, I would observe that the definition of setting is based around an individual’s experience of heritage assets. As the definition refers, appreciation is a fundamental part of that experience. In this context, appreciation can be better informed by understanding. 74. Similarly, the definition of significance revolves around the value we (as people) place on heritage assets. As the thoughtful contribution to the Inquiry made by Mrs Butter bore out, it is people’s attachment of value to certain buildings and artefacts that gives them significance in cultural heritage terms. But it is also fair to observe that people can, through the same thought process, understand that some buildings or structures do not carry the same sort of significance. In that context, it is not unreasonable to highlight the obvious differences between heritage assets and wind turbines and question why the presence of the latter necessarily prevents, or makes more difficult, an understanding, or appreciation, of the former. 75. It is with all that in mind that I turn to consider the impact of the proposals on the settings of the individual designated heritage assets referred to. Having regard to the evidence of the parties, and what I observed at my site visits, the designated heritage assets, and the impact of the proposals upon them, in terms of the nature and degree of that impact, can be grouped together. 76. The first group is made up of the surrounding churches, buildings, and archaeological remains that share a broadly similar relationship with the surrounding landscape and something of a landmark quality. Nearest to the site of the proposals, the Church of St Mary the Virgin at Yelden dates predominantly from the 14th Century and is a Grade I listed building. It has a visual, and, it seems, historical relationship, with the remains of the nearby Motte and Bailey Castle (a SAM). 77. A little further away, the Church of St John the Baptist, Caldecott dates from the 13th Century and is a Grade II* listed building. The Church of St Mary, Shelton is a Grade I listed building. A little further away again, the Church of St Peter, Newton Bromswold dates from the mid 13th to mid 14th Century and is a Grade I listed building. The Church of All Saints, Hargrave dates from the late 12th Century and is a Grade II* listed building. Further away again, the Church of St Margaret, Covington is a Grade II* listed building, the Church of All Saints, Upper Dean is a Grade I listed building, as is the Church of St Mary 32 APP/G2815/A/11/2156757 www.planningportal.gov.uk/planninginspectorate 13 16.13 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 Magdalene, in Melchbourne. To the north-west of Upper Dean is a windmill, listed Grade II. Near the Church of St Mary Magdalene lies Melchbourne House, a Grade II* listed building that lies within a designed parkland. More distant still, the Church of St Mary, Higham Ferrers, is a Grade I listed building, as are the Churches of St Lawrence, Stanwick and St Peter, Raunds. 78. All these listed buildings, and the SAM, are of national importance in terms of their archaeological, architectural, artistic and historic values, clearly. On top of that, though the degree varies because of their particular characteristics, their status as landmarks, in their settings, is an important contributor to their significance. Notwithstanding the existing presence of the Boxer Mast, and that the wind farm at Burton Wold is visible from various locations in the area, the relative lack of visual competition feeds their dominant or landmark status. In that context, the removal of the Boxer Mast, as proposed by the appellant, if the appeals are allowed, would represent a benefit. 79. It is fair to say that the effect of the proposals on the setting, and thereby the significance, of the Church of St Mary the Virgin at Yelden, and the remains of the Motte and Bailey Castle nearby, formed the primary focus of the cases advanced by the Councils and PRESERVE on this issue. There are two aspects to the effect of the proposals on the settings of these two designated heritage assets. In the context of the village itself, the Church is a relatively large building, with a tower and a (short) spire. Raised up on a plinth, it dominates the buildings around it, and is easily visible from all around the village, acting as a focal point. This position at the head of the village hierarchy is an important element of the significance of the Church and one way in which its setting contributes to that significance. 80. There would be points within, and on the borders of the village, where the wind turbine array would be seen in juxtaposition with the Church. However, notwithstanding the height of the wind turbines, the degree of separation would mean that the Church would remain the dominant foreground element in these views. It would be readily apparent to the observer that the wind turbines were not part of the settlement. In that way, the position of the Church as the focal point of the village, with primacy in the village hierarchy, would not be undermined. The wind turbines would be a distracting presence in some views towards the Church but not to the extent that the ability of an observer to appreciate its significance, and the contribution its position in the village hierarchy makes to that significance, would become unduly difficult. 81. The raised mound of the Castle, and the other earthworks around it, are prominent (though secondary to the Church), particularly around the southeasterly parts of the village. Most views towards the Castle mound, and the associated earthworks, from within the village, would not take in the wind turbines proposed. There would be views of the wind turbines behind the Castle mound (and indeed the Church) from points within the SAM but, because of the degree of separation, along with the tower and spire of the Church, the Castle mound and the earthworks around it would dominate the foreground. 82. The wind turbines proposed would not be perceived as part of the settlement but as elements well beyond it. Again the wind turbines would be a distraction but their presence would not prevent the significance of the SAM, or the contribution its village setting, or the relationship with the Church, makes to that significance, from being readily appreciated. www.planningportal.gov.uk/planninginspectorate 14 16.14 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 83. From points further afield, the Church and, to a lesser extent, the Castle mound are seen as the principal, defining elements of the village and the visual relationship between the two is readily discernible. However, the Church, the SAM, and the village around them are located in the valley of the River Til and, as a consequence, set down in the landscape. From many points outside the village, the Church tower and spire break the skyline to a limited extent or from some points not at all. The Castle mound would be less prominent still. In this way, while prominent in the landscape in views towards them, the presence of the Church and the Castle mound as dominant elements in the village is a more important contributor to their significance than their presence in the landscape, overall. 84. Nevertheless, there are many places in the cone of view from south-west to south-east of the Church, from the Three Shires Way, the footpath that approaches and crosses the SAM, on the approach from Newton Bromswold, and on the Swineshead Road, in particular, where the proposed wind turbine array would be visible on the skyline, in juxtaposition with, and sometimes behind, the Church and, in some instances, the Castle mound. 85. Given the height of the proposed wind turbines, they would appear much taller than the Church, and the Castle mound, and supplant them as the dominant element in these views. The movement of the blades would attract additional attention. However, there would be a relatively significant degree of separation, and because the wind turbines would be seen on the skyline, well beyond the built form of the village, they would not be perceived as part of it. As a consequence, while the presence of the wind turbines would act as a significant distraction to the observer, and appear more prominent than the Church and the Castle mound as elements in the landscape, they would not supplant the more important positions of the Church and Castle mound as dominant elements in the village. On that basis, while some harm would be caused to the settings of the Church and the Castle mound, and thereby their significance, the degree of harm would be less than substantial. 86. The Church of St Peter, Newton Bromswold lies further to the south-west of the site of the proposals than the designated heritage assets in Yelden. Situated on a ridge, and with a slender tower topped by an octagonal spire, it dominates the village and acts as a prominent landmark in its wider surroundings. As with the Church of St Mary in Yelden, both the area immediately around the Church and the surrounding landscape contribute to its significance. 87. The wind turbines proposed would be visible from the churchyard and from areas around the village. However, notwithstanding the height of the wind turbines, their number and disposition, and kinetic characteristics, because of the degree of separation, the Church of St Peter would remain the dominant focus in these views. The wind turbines would not be seen as parts of the village. In that way, the Church would retain its primacy, locally. 88. In some wider views of the Church, the wind turbines would be seen in conjunction with it. From areas to the south of the Church, the wind turbines would act as a backdrop to the Church, and its spire. Given their size and movement they would compete with the spire for attention. However, the Church and its spire would be much closer to the observer and remain the dominant element in the foreground. The distraction caused by the wind turbines would not be so great that the prominent landmark status of the Church and its spire would be undermined to any great degree. www.planningportal.gov.uk/planninginspectorate 15 16.15 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 89. As a consequence, while the proposals would cause some harm to the setting of the Church of St Peter, and thereby its significance, that harm would be less than substantial. 90. The Churches of St Mary, Higham Ferrers, St Lawrence, Stanwick and St Peter, Raunds are all characterised by tall spires and are located on the eastern valley side of the River Nene. The proposed wind turbine array would be located between 3 and 4 kilometres to the east or south-east of these Churches on higher ground. There are places where the wind turbine array would be visible behind the spires in views across the valley of the Nene. 91. However, despite the height of the wind turbines proposed, the degree of separation would allow the spires to remain the more dominant elements in the foreground of these views, with the wind turbines seen well beyond them. The obvious landmark quality of the Churches would not be undermined to any great degree. As a consequence, the degree of harm caused to the setting of these Churches, and thereby their significance, would be less than substantial. 92. Both the Church of St John the Baptist, Caldecott and the Church of St Mary, Shelton lie within 2 kilometres of the proposed wind turbines. Both Churches lack spires and are located in churchyards that are enclosed by mature trees. As a consequence, they have little presence as landmarks in the wider landscape and, of their settings, it is the area immediately around them that contributes most to their significance. 93. About 2.5 kilometres from the appeal site, the Church of All Saints, Hargrave has a relatively short spire but again it is largely screened by trees so rarely appears as a prominent feature in the landscape. Again, of its setting, it is the area close to this Church that contributes most to its significance. 94. There would be places around the fringes of these villages where the Churches would be seen in juxtaposition with the proposed wind turbines. In these views, the proposed wind turbines would distract the eye, especially when moving and detract from what prominence these Churches have in the landscape. However, from those parts of the settings, immediately around the Churches, that contribute most to their significance, the wind turbines would be screened to a significant degree by the trees. 95. On that basis, while some harm would be caused to the settings of these Churches, and thereby their significance, that harm would be minimal, and certainly less than substantial. 96. At a distance of between 3 and 4 kilometres from the proposals lie the Churches of St Margaret, Covington, All Saints, Upper Dean, and St Mary Magdalene, in Melchbourne. All these are buildings of relatively modest scale and height that are best appreciated close-up, as dominant features in the villages they serve. They do not have any great landmark qualities. 97. The wind turbines may well be visible from areas immediately around the Churches but because of the separation distances involved, the Churches would remain the principal elements in these views and their position as dominant features in the settlements around them would not be undermined to any great degree. As such, the harm that would be caused to their settings, and thereby their significance, would be marginal, and less than substantial. www.planningportal.gov.uk/planninginspectorate 16 16.16 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 98. Also in the village of Melchbourne is Melchbourne House, a former country house (now apartments) that lies within a designed parkland, itself set within the wider landscape. Neither the Councils nor PRESERVE raised concerns about it but the appellant assessed the impact of the proposals upon its setting. My site visit bore out the need to have regard to that impact. As the appellant sets out, it is possible to discern two designed views that form part of the setting of the house. Both contribute to the significance of the listed building. The first is the open view from the front of the building over the parkland to the southeast. The wind turbines proposed would not impinge upon that view. 99. The second is the view of the house itself on the approach through the parkland on the main drive from Riseley. The wind turbines proposed will appear behind the house in some views from the drive. Given their scale and movement, they would act as a distraction but given the degree of separation, and the size and proximity of Melchbourne House in those views, its dominant position in the foreground would not be supplanted. As such, while there would be a harmful impact on the setting of Melchbourne House as a result of the distracting effect of the wind turbines, and thereby its significance, the degree of harm would be less than substantial. 100. To the north-west of the village of Upper Dean is a windmill, listed Grade II. It is relatively tall and, sitting on a ridge, it is a distinctive feature in the landscape, in views of it from the east in particular. Given the functional reasons underpinning its situation on raised ground, the wider landscape is an important contributor to its setting, and thereby its significance. 101. The wind turbines proposed would appear behind it in these views but because they would be some way distant, despite their size and movement, they would not replace the windmill as the primary focus in views towards it. They would not prevent an appreciation of why the windmill was located in a position to catch the wind. Indeed, there would be some synergy between the comparison of older and more modern ways of harnessing energy from the wind. This would tend to ameliorate the distracting effect of the wind turbines proposed. On that basis, the degree of harm to the setting of the windmill would be marginal, and clearly less than substantial. 102. The next class of designated heritage asset is made up of listed buildings that have a rather different relationship with their surroundings. The Cottage, Chelveston is a house that dates from the early 18th Century. It is a Grade II listed building. Duchy Farmhouse, Caldecott dates from 1633, according to a date-stone, and is a Grade II listed building. Manor Farmhouse, Caldecott dates from early to mid 18th Century and is a Grade II listed building. The associated Barn dates from a similar time and is also a Grade II listed building. Poplar Farmhouse, Caldecott appears to date from the late 17th Century and is a Grade II listed building. It has farm buildings associated with it. Wildacre, Hargrave is a house that dates from the late 17th to the early 18th Centuries and is listed Grade II. Finally, Hillstone Cottage, Hargrave dates from the mid 18th Century and is listed Grade II. 103. Obviously, these listed buildings are of national importance in terms of their archaeological, architectural, artistic and historic values. However, they have an intimate relationship with the settlements they form part of, and from what I saw, derive little of their significance from the wider surroundings beyond those settlements. The proposed wind turbine array would be visible from and in conjunction with all these listed buildings. However, given the degrees of www.planningportal.gov.uk/planninginspectorate 17 16.17 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 separation involved, and the fact that the array would clearly be perceived as a feature well beyond the settlements, their presence would in no instance be dominant or overwhelming. 104. As a consequence, while the visible presence of the array might appear somewhat distracting, it would not undermine the ability to appreciate the significance of the designated heritage assets concerned, or the contribution setting makes to that significance, to any great extent. In that light, while the distracting presence of the wind turbine array would have a harmful impact on their settings, the degree of that harm would be less than substantial. 105. My attention was also drawn to the Covington and Upper Dean Conservation Areas. As conservation areas, these are of national importance in terms of their archaeological, architectural, artistic and historic values. The way in which they sit in the surrounding landscape (their settings) is a facet of it, but the major extent of their significance is the intrinsic value of the areas themselves, and the buildings within them. While the wind turbines proposed would be visible, in views towards them, from various points within, and, more particularly, at the western edges of the conservation areas, they would be between 3 and 4 kilometres away. With that degree of separation, their visual presence would be no more than a largely peripheral diversion. Visibility would not make it difficult to appreciate the significance of the conservation areas concerned, or the limited contribution setting makes to that significance. As such, the degree of harm caused would be marginal, and certainly much less than substantial. 106. Turning to general considerations, as previously set out in relation to landscape impact, paragraph 2.7.17 of EN-3 outlines that the time-limited nature of a wind farm is likely to be an important consideration in assessing impacts of onshore wind farms (albeit larger ones) on the setting of heritage assets. This is also acknowledged by EH in ‘Wind Energy and the Historic Environment’. 107. The proposals are intended to endure for 25 years. It has been suggested that the appellant might seek to renew any planning permissions or that the wind turbines might be replaced within the periods of permission sought. However, it is highly likely that either course would mean further planning applications that would need to be judged, on their merits, at the appropriate time. As far as the proposals at issue are concerned, once the 25 year period has elapsed, the wind turbines and ancillary infrastructure would be removed, and the harmful impact on the settings of the designated heritage assets would be gone. 108. It is correct to acknowledge that 25 years is a long time in relation to the human lifespan, but in terms of the age of the designated heritage assets affected and, more importantly, the period that they can reasonably be expected to endure, it is a relatively insignificant period. The degree of harm that would be caused to the setting of the designated heritage assets identified is a function not only of the impact of the proposals, but also of the time that impact would persist. The degree of harm caused by proposals designed to endure for twenty five years must be less than if the same proposals were intended to endure for longer than twenty-five years. 109. The Councils raised issues about the manner in which Inspectors approach questions about the temporal nature of wind farms and reversibility, contrasting the approach in two recent decisions33. However, Government 33 APP/G2815/A/11/2156757 and APP/H0520/A/11/2146394 www.planningportal.gov.uk/planninginspectorate 18 16.18 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 advice in EN-3 is quite clear, and EH acknowledges these factors to be material considerations too. In that context, I take the view that the approach I have set out above and indeed previously, is correct. 110. To summarise, for the reasons set out, the proposals would cause harm to the settings, and thereby the significance, of a range of designated heritage assets. The degree of harm would vary, but in no case would it reach the level of substantial. The overall degree of harm would be reduced by the transient nature of the proposals and their reversibility. Nevertheless, that there would be some harm means that the proposals would not accord with RSS for the East of England Policy ENV6, BLP Policy BE21, BCSRIP Policies CP21 and CP23, RSS for the East Midlands Policies 26 and 27, and Policy 5 and criterion (o) of Policy 13 of the NNCSS. Notwithstanding that, the balancing exercise implicit in Section 66 of the Planning (Listed Buildings and Conservation Areas) Act 1990, explicit in the Framework, and set out in Section 38(6) of the 2004 Act34 means that this harm has to be balanced against other considerations. I return to that exercise below. The Living Conditions of Local Residents 111. As for those dwellings affected that lie in Bedford Borough, criterion i) of BLP Policy BE30 says the visual impact of development and its relationship with its context is something which will be taken into account when development proposals are considered. 112. In terms of those within East Northamptonshire District, RSS for the East Midlands Policy 40 tells that when assessing onshore wind energy schemes, consideration should be given to, amongst other things, the number and size of the wind turbines and their visual impact. On top of that, one of the core principles of the Framework is to always seek a good standard of amenity for existing occupiers of land and buildings. 113. Reference was made to the approach of another Inspector who set out that when turbines are present in such number, size and proximity that they represent an unpleasantly overwhelming and unavoidable presence in main views from a house or garden, there is every likelihood that the property concerned would come to be regarded as an unattractive and thus unsatisfactory (but not necessarily uninhabitable) place to live. He went on to assert that it is not in the public interest to create such living conditions where they did not exist before35. This approach offers a helpful, general guide. 114. I was also referred to a number of other appeal decisions36 where Inspectors have found visual impact to be a significant issue. I find these more difficult to apply, in general terms, given that the relationship between a wind turbine array as proposed and dwellings, the topography, screening, and so on will be different in each case. For that reason, I do not believe that separation distances that might have been found unacceptable elsewhere, are automatically unacceptable in the cases before me. 115. Manor Farm, Silcombe House, and Top Cottage are sited in relatively close proximity to each other, to the south-east of the proposed turbine array. I visited the group in the course of my site visits. 34 35 36 The Planning and Compulsory Purchase Act 2004 What has been termed the ‘Lavender Test’ For example APP/A3010/A/06/2107850 (Retford) www.planningportal.gov.uk/planninginspectorate 19 16.19 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 116. Most or all of the turbine array would be visible from some points within the interior of Manor Farm and its gardens with the closest turbine (BB4) about 485 metres away and others about 565 metres (BB5), 740 metres (BB3) and 900 metres (BB6). The remainder of the array would be set behind the closest turbines but still visible. At a height of about 125 metres, given the degree of separation, the wind turbines, especially the closest ones, would have a significant visual impact in views towards them. I noted from my site visit that the house is sunk down into the ground which would tend to accentuate the height of the proposed wind turbines. It is also correct to note that the movement of the wind turbines would accentuate their visual impact. 117. Notwithstanding that, the array would not appear dominant or overbearing. The view to the north-west is not the primary outlook from Manor Farm and there are lots of open views from Manor Farm and its grounds that would not take in the wind turbines or, like the views in a south-westerly direction (the direction in which the main frontage of the dwelling faces), in which they would appear peripheral. As a consequence, the visual impact of the turbine array would not have any significant deleterious impact on the living conditions of the occupiers. Manor Farm would not become an unattractive or unsatisfactory place to live. 118. It is also correct to note that those views directly towards the array from Manor Farm would be filtered through existing boundary planting. In relation to that boundary planting, the appellant, in the completed UU, has suggested that the planting can be maintained and, where necessary, supplemented, during the life of the planning permission. However, that is conditional upon my finding that such an obligation is justified by or in accordance with the provisions of Regulation 122 of the CIL37 Regulations and the Framework. 119. The CIL Regulations do not apply to wind turbine development38 but the Framework, in paragraph 204, states that planning obligations need to be, amongst other things, necessary to make the development acceptable in planning terms. The planting maintenance and supplementation put forward in the UU would help to screen the proposals but given that views in that direction are not primary views, these measures are not necessary to make the development acceptable in planning terms. 120. Silcombe House lies to the east of Manor Farm. Again, parts, or the whole, of the turbine array would be visible from some rooms within the dwelling and from its garden with the closest turbine (BB4) around 560 metres away, another (BB5) about 600 metres distant, and others upwards of 800 metres away. As with Manor Farm, in views towards them, the wind turbines would have a significant visual impact, heightened by the movement of the turbine blades. 121. Again though, the visual impact would not dominate or overpower the outlook from the dwelling, overall. The principal open views from the house and its garden are to the south and south-east; views in which the wind turbines would at worst be peripheral. Views towards the wind turbines from within and without the dwelling would have Manor Farm or the farm buildings to the north as partial screening elements in the foreground. 37 Community Infrastructure Levy As confirmed by paragraph 38 of the Department for Communities and Local Government publication CIL: An Overview 38 www.planningportal.gov.uk/planninginspectorate 20 16.20 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 122. As a consequence, the visual impact of the turbine array would not have any significant detrimental effect on the living conditions of the occupiers. Silcombe House would not become an unattractive or unsatisfactory place to live as a result of the proposals. 123. Top Cottage lies to the north-east of Manor Farm and is set about 3 metres higher. It lies about 590 metres from the closest wind turbine (BB5) with another 615 metres distant (BB4) and the remainder between 850 and 1440 metres away. With that degree of separation, the wind turbines, the closest ones when moving especially, would have a significant visual impact in views towards them, but this would be tempered by seeing them above and in the context of the farm buildings that lie to the west of the dwelling. The primary, open views from Top Cottage are to the east and south; views in which the wind turbines proposed would have little presence. 124. Taking those points together, the visual impact of the wind turbines would not have any significant detrimental effect on the living conditions of the occupiers of Top Cottage. It would not become an unattractive or unsatisfactory place to live as a consequence. 125. There is a complex of around 52 dwellings, known as Chelston Rise, to the south-west of the proposed array that I visited during my site visits. According to the Council, the closest wind turbine (EN2) would be about 740 metres away from the nearest dwelling, the next two (BB3 and EN8) in the order of 1200 metres away, with the remainder of the array beyond that. The proposals include two anemometer masts (of which only one is required), one (ENMM) would be 570 metres away and the other (BBMM) 910 metres away. Chelston Rise sits about 3 metres lower than the ground level where the closest wind turbine would be located. 126. My visits to Chelston Rise demonstrated that the Boxer Mast, a lattice structure about 70 metres high, sited about 350 metres39 from the nearest dwelling, has a significant presence in views from the complex in a north-easterly direction, despite the screening effect of vegetation on the boundary. If the proposals were built out as presented, the wind turbines and the anemometer masts would obviously heighten the visual impact that the Boxer Mast already has on Chelston Rise. However, the analysis is not as simple as that. The appellant has made it clear that in the event Appeals A and B are allowed, only one anemometer mast would be required. To that end, the one closest to Chelston Rise (ENMM) could be deleted from the proposals by condition. Similarly, the appellant is prepared to accept a condition requiring the removal of the existing Boxer Mast in the event that planning permission is granted for the proposals. 127. If the proposals proceeded on that basis, residents of Chelston Rise would see an array of wind turbines with the closest (EN2) about 740 metres away, the next two (BB3 and EN8) about 1200 metres away and the remainder of the array at greater distances beyond that. The remaining anemometer mast (BBMM) would be 910 metres away. I recognise that the wind turbines and the anemometer mast would be taller than the Boxer Mast, though further away, and, in the case of the wind turbines, contain moving elements. In views towards the array, the visual impact would be significant, and screening from vegetation, even as it grows over the life of the proposals, would offer little in the way of relief. 39 The SoCG refers www.planningportal.gov.uk/planninginspectorate 21 16.21 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 128. Again though, while significant, given the degree of separation, and the relatively narrow field of view that the array would fill, the visual impact of the proposals would not be dominant or overwhelming whether viewed from within dwellings with facing windows, or from gardens, or from open areas within the overall complex. The living conditions of occupiers at Chelston Rise would not be significantly undermined; the dwellings would not become unattractive or unsatisfactory places to live as a consequence of the proposals; and neither would Chelston Rise as a settlement. 129. The appellant also offered to remove the closest turbine (EN2) from the scheme under consideration through Appeal B by condition should I find the impact on residents at Chelston Rise by reason of it in conjunction with other elements unacceptable. Given my conclusions above, that is not necessary. 130. Concern was raised by other residents about the visual impact of the proposals, notably those who live on the fringes of Yelden, facing the site of the proposed wind turbines. I visited some of these properties during my site visits. At the sort of separation distances involved, what will happen is that certain views from within these properties, and their gardens, will change as a result of the proposals. It is a long-established planning principle that the right to a view from a property is not inviolable. There would be no dominant or overpowering visual impact as a result of the proposals and no significant diminution in the living conditions of the residents affected as a result. A similar situation would arise at Lodge Farm, to the north-east of the proposals, in these terms. 131. Having regard to Government guidance in ETSU-R-9740, the Councils and the appellant have agreed in the SoCG that subject to suitably worded conditions, the living conditions of local residents would be sufficiently protected from noise. There are differences, however, around day and night-time noise limits; I refer to those below in dealing with the suggested conditions. 132. Some concern was also raised about the noise monitoring location that informed the day-time and night-time limits for Lodge Farm in the draft conditions. It is unfortunate that noise monitoring could not have been carried out within the residential curtilage of Lodge Farm. Nevertheless, I inspected the alternative noise monitoring location used during the course of my site visits, and am content that it offers a reasonable comparator. 133. The occupier of Lodge Farm raised concern about the potential for shadow flicker. Given the relative orientation of the wind turbine array and Lodge Farm, and the degree of separation, it might be a possibility. However, the Councils are content that this can be dealt with through a condition that sets out a protocol for how this phenomenon could be dealt with, if a complaint about it is made to the relevant Council. There is nothing unusual about that approach and I agree that it offers sufficient security to the occupiers of Lodge Farm, and indeed the occupiers of any other dwelling that might be affected in this way. 134. Taking all these points together, the visual impact of the proposals would have no significant harmful impact on the living conditions of local residents. Subject to suitably worded conditions, there would be no difficulties in terms of noise or shadow flicker. On that basis, there would be no departure from criterion i) of BLP Policy BE30, or Policy 40 of the RSS for the East Midlands, or the Framework, as a result of the proposals. 40 ETSU-R-97: The Assessment and Rating of Noise from Wind Farms www.planningportal.gov.uk/planninginspectorate 22 16.22 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 Other Matters 135. There are a number of PRoWs that cross the site. The BHS41, and others, expressed concern about the proximity of the turbines proposed to bridleways and the potential for shadows cast by the moving wind turbine blades on those routes, to cause difficulties, and indeed dangers, for horses and their riders. The Companion Guide to PPS2242 that remains extant, notes in paragraph 56 that the BHS has suggested a 200 metre exclusion zone around bridle paths to avoid wind turbines frightening horses and goes on to note that while desirable, this is not a statutory requirement. Notwithstanding that, I heard that since the Companion Guide to PPS22 was published, the BHS has modified its stance to the extent that it now suggests a separation distance of three times the height of the wind turbines which, in this case, would equate to about 425 metres. 136. Amongst other factors, the layout of the turbine array proposed has been informed by the location of bridleways. None of the wind turbines would sit within 200 metres of a bridleway. As such, the layout corresponds with what the Companion Guide to PPS22 considers desirable. Some of the wind turbines would sit well within the separation distance the BHS now favours. I recognise that the BHS may have modified its guidance in response to the increased height of more modern wind turbines but unless and until the Government modifies its own guidance, a failure to meet current BHS stance is not a matter to which I attach any significant weight. 137. The wind turbines would be visible to any approaching rider and their mount from some distance away on the approaches so the potential for a horse to be surprised by their sudden appearance is very limited. Nevertheless, it is clear from the ES that the wind turbines could cast shadows on the bridleways for much of the day in Winter. In Spring, Summer and Autumn, the incidence would be less but there would be potential for shadows in the early evening, which I am told is a popular time for riders. Horses can be temperamental creatures and I have no good reason to doubt that some might be frightened by moving shadows cast by the wind turbines, putting themselves, their rider, and others in danger. However, this potential difficulty needs to be approached in a proportionate fashion. Whether shadows would be cast on the bridleways depends not only on the time of year, and time of day, but also, on particular weather conditions. In that context, while the potential for shadows would act as something of a constraint on the use of the bridleways by riders and their horses that is insufficient, on its own, to warrant dismissing the appeals. 138. In the completed UU, the appellant has offered to provide a permissive bridleway along the south-east boundary of the site which would allow riders to follow an alternative route, unaffected by shadows from the wind turbines. However, paragraph 204 of the Framework states that planning obligations should only be sought where they are necessary to make the development acceptable in planning terms; directly related to the development; and fairly related in scale and kind to the development. Given my conclusions on this particular issue, it is clear that the provision of the permissive bridleway would not meet those tests. While it would be a welcome benefit to riders I am sure, it is not something that is necessary to make the development acceptable in planning terms. 41 42 British Horse Society Planning for Renewable Energy: A Companion Guide to PPS22 www.planningportal.gov.uk/planninginspectorate 23 16.23 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 139. There are also a series of footpaths that criss-cross the site. Neither the wind turbines proposed nor the anemometer masts would be within topple over distance of the footpaths and this arrangement would comply with the advice set out in paragraph 57 of the Companion Guide to PPS22. The impact of the proposals on the experience of riders and walkers using the PRoW across the appeal site is something that is tied into the landscape impact of the proposals, and dealt with previously. 140. Concerns were also raised about the potential for tension between the proposals and the biomass renewable energy plant that has been approved for the site in terms of air quality. The Councils raise no such concern and my reading of their material, notably the ‘Temple’ Report, and the submission of Mr Butter, strongly supports that as the correct view to take. 141. I also heard criticism of what are seen as over-generous Government subsidies for on-shore wind farms. These, it is said, relegate cost and efficiency to a secondary role and encourage schemes that might otherwise not have come forward. That may or may not be the case but the manner in which Government uses subsidies to encourage the development of on-shore wind farms (or indeed, anything else) is a matter for them. It is not something that an Inspector can take account of in dealing with site-specific proposals. 142. The SoCG outlines a series of other issues which the Councils accept as noncontentious, subject to conditions, and I have heard nothing convincing to suggest that I ought to reach a contrary view. These include ecology, archaeology, highway, aviation and general safety, and direct impacts on PRoWs. I refer to some of these in dealing with conditions below. 143. As set out, the completed UU, submitted by the appellant, deals with several matters. The additional landscaping and permissive bridleway have been dealt with previously. However, it also makes provision for a Community Fund Contribution to be made to local Parish Councils through what is termed a Community Fund Delivery Vehicle. 144. The financial contributions involved could be expended by the Parish Councils in line with the Community Fund Objectives set out in the UU. The appellant maintains that this approach accords with the community benefit protocol proposed by Renewable UK and endorsed by Government. That may be the case but paragraph 204 of the Framework states that planning obligations should only be sought where they are necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind to the development. 145. The Community Fund Contribution is not necessary to make the proposals acceptable in planning terms and it is not clear to me how it is directly related to the development, or fairly and reasonably related in scale and kind to it. The funding would be welcome, I am sure, but it is not something to which I can attach weight to as a benefit of the proposals. The Balancing Exercise 146. I am acutely aware of the degree of local opposition to the proposals through the many written and oral submissions made to the Inquiry and the positions adopted by the Councils and PRESERVE. I considered very carefully too, the helpful contribution made by the local Member of Parliament. www.planningportal.gov.uk/planninginspectorate 24 16.24 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 147. However, all that opposition is not determinative, in itself, and must be viewed in the overall policy context. Like the Roadmap, paragraph 97 of the Framework notes the responsibility on all communities to contribute to energy generation from renewable sources. Against that background, I turn to the balancing exercise. 148. There is no specific provision for a balancing exercise in the development plan regime for Appeal B. However BLP Policy BE7 which relates to Appeal A sets out that in assessing proposals for renewable energy schemes, the Borough Council will have particular regard to the following issues: i) the immediate and wider impact of the proposed development on the landscape; ii) the need to protect features and areas of natural, cultural, historical and archaeological interest; iii) the measures that would be taken, both during and after construction, to minimise the impact of the development on the landscape, local land use and residential amenity; iv) the local and wider benefits that the proposal may bring; v) certain renewable energy resources can only be harnessed where the resource occurs; and vi) any requirements for future restoration of the site. 149. This policy encapsulates the requirement to balance often conflicting factors, as set out in Section 38(6) of the 2004 Act, and also referred to in the Framework, specifically in relation to the impact on designated heritage assets. 150. In making that assessment, the proposals would provide significant benefits in terms of the generation of energy from a renewable source, securing reductions in greenhouse gas emissions, adding to energy security, and providing resilience to the impacts of climate change. Allied to that is the potential of the proposals to generate economic growth and create jobs. 151. On the other hand, the proposals would cause harm to the landscape, though that would be ameliorated by a series of factors. The proposals would also cause harm to the settings, and thereby the significance, of a range of designated heritage assets. In all cases that harm would be less than substantial but, obviously, Section 66 of the Planning (Listed Buildings and Conservation Areas) Act 1990 requires the decision-maker to have special regard to the desirability of preserving those settings. There would also be a limited degree of harm caused in terms of the use of bridleways. 152. In terms of the development plan, the proposals would comply with RSS for the East of England Policy ENG2 and RSS for the East Midlands Policy 40. However, the failure to comply with BLP Policy BE30, BCSRIP Policies CP2, CP21, CP23 and CP 24, RSS for the East Midlands Policies 26 and 31 and criterion (o) of Policy 13 of the NNCSS in landscape impact terms and RSS for the East of England Policy ENV6, BLP Policy BE21, BCSRIP Policies CP21 and CP23, RSS for the East Midlands Policies 26 and 27, and Policy 5 and criterion (o) of Policy 13 of the NNCSS, in terms of the impact on the setting of designated heritage assets, means that the proposals, overall, fail to accord with the requirements of the development plan 153. Nevertheless, paragraph 98 of the Framework tells us that planning applications for schemes like those at issue should be approved (unless, of course, material considerations indicate otherwise) if impacts are (or can be made) acceptable. I take that as an acknowledgement that a degree of harm can be accommodated if the benefits outweigh that harm. www.planningportal.gov.uk/planninginspectorate 25 16.25 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 154. That is borne out by the acknowledgement in EN-3 that modern onshore wind turbines used in commercial wind farms are large structures and there will always be significant landscape and visual effects from their construction and operation for a number of kilometres around a site. 155. On my analysis, the significant benefits provided by the proposals are material considerations that clearly outweigh the limited harm caused to bridleway users and the failure to accord with the development plan in terms of the less than substantial harm that would be caused to the landscape, and the settings of designated heritage assets. As a result, I conclude that planning permission should be granted for the proposals, subject to conditions. Conditions 156. I have considered the suggested conditions discussed and, in the most part, agreed, between the appellant and the Councils in the light of advice in Circular 11/9543. In general terms I have made minor changes to ensure conditions tally with the standard forms in the Circular and in the interests of precision. Many of the suggested conditions apply to both appeals but a few do not. I have identified the reasons behind that. 157. Commencement conditions are required, obviously, but there is a difference between the parties in that the Councils believe the standard 3 years to be sufficient while the appellant favours 5 years. Given the number of matters that need to be agreed through conditions, pre-commencement, and difficulties that may arise with procurement, I regard 5 years as a reasonable period. 158. In order to facilitate any subsequent application for a minor material amendment, conditions are necessary to set out the approved plans. I have not included those drawings that show elements that are ‘typical’. Details of these elements are covered under other conditions. Given my findings in relation to the effect of the proposals on the living conditions of residents at Chelston Rise, Appeal B also needs a condition to clarify that despite being shown on the plans, the anemometer mast (ENMM) shall not be constructed. The description of development for Appeal B needs to be amended to reflect that too. 159. The proposals are presented on the basis that they will endure for 25 years. Conditions are required to secure that and to deal with subsequent decommissioning and site restoration. It is also necessary to apply conditions to deal with the situation should any of the wind turbines fail to operate for a continuous period of six months. 160. Clearly, the construction process and the delivery of components to the site would be a complex exercise. It is reasonable therefore to require the submission of a Construction Traffic Management Plan and a Construction Method Statement for the approval of the Councils. It is necessary to restrict the hours when construction work and deliveries can take place. Given the degree of separation between the site and dwellings, the wider range of times put forward by the appellant seem reasonable. This ought to ensure the construction work takes less time, overall. A number of highway related conditions have been suggested but these are unnecessary given the requirement to submit a Construction Traffic Management Plan. 43 Circular 11/95: The Use of Conditions in Planning Permissions www.planningportal.gov.uk/planninginspectorate 26 16.26 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 161. As indicated, the overall design of the wind turbines and the anemometer mast are important factors. To that end conditions are required to secure details of design, finishes and so forth. It is also necessary to control signage. 162. I recognise that the appellant may wish to have some signage on the wind turbines to reflect the previous use of the site as an airfield in the interests of the many veterans who visit. However, the use of a phrase like ‘unless otherwise agreed in writing by the local planning authority’ is not an acceptable way around controls and it is best that any signage subsequently proposed is dealt with through the appropriate channels. 163. Given the nature of the applications, it is reasonable to specify maximum heights for the wind turbine blades and hubs. To prevent visual tension, it is important to specify that the wind turbine blades rotate in the same direction. 164. It is necessary to control lighting on the wind turbines and anemometer mast (save for those that might be required for air safety) and to ensure that all cabling is laid underground. Archaeology needs to be covered by conditions. 165. A series of conditions are necessary to deal with ecological matters in accordance with the mitigation requirements of Natural England and the ES. Linked to that, and also a reflection of the ES, conditions are necessary to secure landscaping. I see no reason in the latter conditions to specify additional planting adjacent to rights-of-way crossing the site given that this is a requirement of the planning permission relating to the biomass plant. 166. A condition has been put forward to deal with fencing adjacent to the rights of way crossing the site. This is necessary because, as I have set out in assessing impacts on the landscape and rights of way, better boundary treatment(s) would represent a visual improvement over the existing Heras fencing. Points were made about the clearance of this fencing from the rights of way but rather than specifying a clearance it is best to allow this to be addressed, if necessary, through the overall submission of a scheme. 167. As is generally the case in these matters, conditions are necessary to specify the way in which the wind turbines and/or the anemometer mast can be microsited. A distance of 25 metres in any direction seems reasonable. Typically, again, conditions are required to address what should happen in the event of complaints about shadow flicker and interference with televisions. In terms of the latter, I regard 18 months as a reasonable period for complaints to surface. 168. Conditions are required to address air safety and surface water drainage. Given previous uses of the site, it is also necessary to deal with the potential for, and possible repercussions from, contamination. 169. The removal of the Boxer Mast is an important facet of the finding that the visual impact of the proposals would have no significant detrimental effect on local residents. There is also benefit in landscape terms and in respect of the setting of heritage assets. That removal needs to be secured by condition, therefore. The suggested condition would require removal before the First Export Date. That is not acceptable because it might mean residents would suffer the visual impact of the wind turbines, the anemometer mast, and the Boxer mast for a significant period. I have therefore modified the suggested condition to require demolition before any of the wind turbines are erected. www.planningportal.gov.uk/planninginspectorate 27 16.27 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 170. A series of conditions have been suggested to deal with noise. That designed to address noise in general terms is agreed between the Councils and the appellant save for the noise limits, set out in the tables, at nearby receptors. The Councils, having regard to what they term the very quiet background noise levels (and the reference to them in ETSU-R-97) suggest that the tables are populated with noise limits 5dB below the ETSU derived limits. Background noise levels might be very low in some locations but the forecasts submitted show that the candidate turbines proposed would operate, in most conditions, with significant headroom below the ETSU derived limits. 171. In that context, I see no reasonable justification to apply a reduction across the board or depart from the orthodox ETSU approach. I have therefore used the alternative tables put forward by the appellants and I am satisfied that the noise limits therein provide a reasonable balance between the protection of local residents’ living conditions and the need for the wind farm to operate with a degree of freedom. 172. One of the other noise conditions suggested seeks to require the appellant to submit details of the wind turbine to ensure that it will meet the same criteria as those measured during monitoring and prediction models. I find that unnecessarily restrictive. It is for the appellant to select the type of wind turbine to be used and I cannot believe that they would be so reckless or foolish to select a wind turbine model that would not operate within the noise limits set out. In that context, the suggested condition is unnecessary. 173. Conditions have also been suggested to set out what the wind farm operator must do to remedy any breach of the noise limits. Those are not necessary either because the appellant is obliged to ensure the wind turbines operate within the noise limits in any event. If there is a breach then the Councils have enforcement powers available to ensure compliance and it is in the interests of the appellant to ensure that the breaches do not occur. Notwithstanding the lack of objection from the appellant to them, conditions along the lines suggested are in no way necessary. 174. Amongst other conditions suggested, I have set out my approach to the economic benefits that might arise if elements of the wind turbines are built locally. In that context, it is not necessary to control that by condition. Final Conclusion 175. For the reasons given above I conclude that the appeals should be allowed. Paul Griffiths INSPECTOR www.planningportal.gov.uk/planninginspectorate 28 16.28 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 APPEARANCES FOR THE LOCAL PLANNING AUTHORITIES: Robert Jameson LLB Solicitor, Jameson and Hill Instructed by Bedford Borough and East Northamptonshire District Councils He called Jane Jarvis Cooper Partnership Ltd BSc(Hons) DipLD MA CMLI Roy M Lewis Grover Lewis Associates BA(Hons) MA (Arch Cons) MRTPI IHBC Peter White Team Leader, Planning Appeals & Enforcement, BA(Hons) MA DipTP Bedford Borough Council MRTPI Abigail Morgan Director, SustainEnable Ltd DipUP MSc ABEng MRTPI Bryn Hudson BSc(Hons) Env Health DipSIOA, Environmental Health Officer, took part in the discussion on noise conditions on 21/03/12 FOR PRESERVE: Tina Douglass of Counsel She called Michelle Bolger BA(Eng) BA(LArch) DipLA CMLI Tanya Welton Joelle Soul Jinny Casey Peter Laughton Craig L Jones BA MSc MRTPI Instructed by Craig Jones of Treharne-Jones Associates Ltd Liz Lake Associates Resident of Chelston Rise Resident of Yelden Resident of Yelden Resident of Yelden Treharne-Jones Associates Ltd FOR THE APPELLANT: Tom Hill QC He called David Henson AMIMechE Sarah ReynoldsKettlewell BSc(Hons) DipLD MA CMLI Andrew R McKenzie BSc PhD FIOA Stephen Carter BSc PhD MIfA FSAScot Karl Cradick MSc MRTPI Instructed by Savills Chelveston Renewable Energy Ltd The Landscape Partnership Hayes McKenzie Partnership Ltd Headland Archaeology (UK) Ltd Savills www.planningportal.gov.uk/planninginspectorate 29 16.29 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 INTERESTED PERSONS: Alistair Burt Cllr Adrian Dale Dr John Casey Peter Scott Mark Weston Keith Wyld Cllr Andrew Phillips Cllr Kate Gelder Sue Butter Peter Mommersteeg MP for North-East Bedfordshire Chairman of Chelvston-cum-Caldecott Parish Council Local Resident Campaign for the Protection of Rural England British Horse Society Local Resident Dean & Shelton Parish Council Melchbourne & Yelden Parish Council Resident of Upper Dean Resident of Caldecott DOCUMENTS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Statement of Common Ground Rebuttal Proof and Appendices by Sarah Reynolds-Kettlewell Additional Appeal Decisions (PRESERVE) Addendum and Update by Peter White (Councils) Council’s Letters of Notification Details about Architech Animation Studios (PRESERVE) Extract from revised SPG: London Views Management Framework (PRESERVE) Note from Architech addressing various matters (PRESERVE) Agreed Glossary of Terms for Landscape and Visual Impact Assessment Comparative Timeline for Chelveston Wind Farm Project and disposal of Houses at Chelston Rise (Appellant) Plan of Chelston Rise (PRESERVE) Copy of Appeal Decision: APP/N2535/A/04/1166685 (PRESERVE) Copy of Al Morrow’s E-Mail of 22 December 2011 (PRESERVE) Statement of Alistair Burt MP Statement of Cllr Adrian Dale Statement of Dr John Casey Submissions of Peter Scott (CPRE) Submissions of Mark Weston (BHS) Statement of Keith Wyld Statement of Cllr Andrew Phillips Statement of Cllr Kate Gelder Material relating to relationship between the Anaerobic Digester and the Wind Farm, including the ‘Temple’ Report (Councils) Letter from David Butter CEng FRAeS BSc(Eng) MPhil DECC National Renewable Energy Statistics as of 9 March 2012 (Councils) Appeal Decision: APP/H0520/A/11/2146394 (PRESERVE) Timeline to accompany e-mail correspondence regarding VVMs, CD list and cultural heritage evidence (PRESERVE) Appeal Decision: APP/G2815/A/11/2156757 (Councils) Bundle of material relating to noise monitoring locations (Appellant) Noise Conditions (working draft as of 13/03/12) Errata of Karl Cradick Background Note on Regional Renewable Energy Target Attainment (Appellant) Replacement Appendix 11, Page 1 to Michelle Bolger’s Evidence (PRESERVE) www.planningportal.gov.uk/planninginspectorate 30 16.30 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 Layout and Photomontages relating to APP/A3010/A/06/2017850 (Appellant) Material relating to the Tilbury B Biomass `Power Station (Appellant) Historic Maps (Sue Butter) E-mail trail relating to DECC Restats Grounds of High Court Challenge to Nun Wood Copy of East of England Plan Policy ENG2: Renewable Energy Targets Submissions of Peter Mommersteeg Response to Peter Mommersteeg’s submissions from David Henson Further comments from Peter Mommersteeg Material relating to National Landscape Character Areas 88, 89/94 and 91 Objection from Anglian Water and associated material DECC National Renewable Energy Statistics as of 20/03/12 (Councils) DECC National Renewable Energy Statistics (Appellant) Extract from Hansard 08/03/12 Details of Aveillant Draft Unilateral Undertaking Suggested Conditions (as discussed 21/03/12) Site Visit Itineraries Letter of 20/03/12 from Mark Weston BHS about permissive bridleway Bundle of representations about the Framework Bundle of material about the UU UU (final, completed version) Costs application, associated material and response Opening and Closing Statements APPEAL A PLANS: APP/K0235/A/11/2160077 A B C D E F G H I J K CREL1052-A-BBC: Site Location Plan CREL1014-P-BBC: Revised Wind Turbine Layout and Site Location Plan CREL1014-P: Revised Wind Turbine Layout and Site Location Plan CREL1008-B: Typical Wind Turbine Details CREL1009-B: Typical Anemometer Mast Plan and Elevations CREL1049-A: Typical Access Track and Cable Trench Cross Section CREL1050-A: Typical Anemometer Mast Compound Layout CREL1051-D: Typical Wind Turbine Compound Layout CREL1056-0: Typical Turbine Foundation Details CREL1057-O: Visitor Car Park, Access Tracks and Viewing Area CREL1061-0: Extract from Oaks Survey 25.04.06 Showing Boxer Mast APPEAL B PLANS: APP/G2815/A/11/2160078 A B C D E F G H I J K CREL1052-A-ENDC: Site Location Plan CREL1014-P-ENDC: Revised Wind Turbine Layout and Site Location Plan CREL1014-P: Revised Wind Turbine Layout and Site Location Plan CREL1008-B: Typical Wind Turbine Details CREL1009-B: Typical Anemometer Mast Plan and Elevations CREL1049-A: Typical Access Track and Cable Trench Cross Section CREL1050-A: Typical Anemometer Mast Compound Layout CREL1051-D: Typical Wind Turbine Compound Layout CREL1056-0: Typical Turbine Foundation Details CREL1057-O: Visitor Car Park, Access Tracks and Viewing Area CREL1061-0: Extract from Oaks Survey 25.04.06 Showing Boxer Mast www.planningportal.gov.uk/planninginspectorate 31 16.31 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 Annex A: APP/K0235/A/11/2160077 1) The development hereby permitted shall begin not later than five years from the date of this decision. 2) The development hereby permitted shall be carried out in accordance with the following approved plans: CREL1052-A-BBC: Site Location Plan; CREL1014-P-BBC: Revised Wind Turbine Layout and Site Location Plan; CREL1014-P: Revised Wind Turbine Layout and Site Location Plan; CREL1057-O: Visitor Car park, Access Tracks and Viewing Area; and CREL1061-0: Extract from Oaks Survey 25 04 06 showing Boxer Mast. 3) The permission hereby granted shall be limited to a period of 25 years from the date when electricity is first exported from any of the wind turbines to the electricity grid (the ‘First Export Date’). Written notification of the First Export Date shall be given to the local planning authority no later than 14 days after the event. 4) Not later than 12 months before the expiry of this permission, a decommissioning and site restoration scheme shall be submitted to and approved in writing by the local planning authority. The scheme shall make provision for the removal of the wind turbines, the associated above ground equipment, and foundations to a depth of at least one metre below ground and include details of the management and timing of works, a traffic management plan to address likely traffic impact issues during the decommissioning period, noise controls during decommissioning, an environmental management plan to include details of measures to be taken during the decommissioning period to protect wildlife and habitats, identification of access routes, location of material lay-down areas, restoration measures and a programme of implementation. Decommissioning and site restoration shall be completed in accordance with the approved details within 24 months of the expiry of this permission. 5) If any of the wind turbines hereby permitted fails to operate for a continuous period of six months, a scheme for the repair or removal of the relevant turbine(s) shall be submitted to the local planning authority for its written approval, within three months of the end of that six month period. The scheme shall include, as relevant, a programme of remedial works where repair is required; or a method statement and timetable for the dismantling and removal of the relevant wind turbine and associated above ground works and foundations to a depth of at least one metre below ground and subsequent site restoration. The scheme shall be implemented in accordance with the approved details. 6) No development shall take place until a Construction Traffic Management Plan (CTMP) has been submitted to and approved in writing by the local planning authority. The CTMP shall include details of the routing of construction traffic; its scheduling and timing; the management of junctions with and crossings of, the public highway and other public rights of way; escorts for abnormal loads; temporary warning signs; temporary removal and replacement of highway infrastructure/street furniture; reinstatement of any signs, verges or other items displaced by construction traffic; and banksmen. The CTMP, including any improvements or works to accommodate construction traffic where required shall be implemented in accordance with the approved details. www.planningportal.gov.uk/planninginspectorate 32 16.32 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 7) No development shall take place until a Construction Method Statement (CMS) has been submitted to and approved in writing by the local planning authority. Development shall be carried out in accordance with the approved CMS. The CMS shall address the following matters: i) Details of the phasing of all construction works; ii) Details of the construction and surface treatment of all hard surfaces and tracks; iii) Details of the proposed storage of materials and soils and the disposal of surplus materials; iv) Dust management; v) Details of wheel-washing facilities and their operation; vi) Details of the temporary site compound for storage of materials and machinery (including areas designated for car parking); vii) Construction details of the site access and the creation and maintenance of associated visibility splays; viii) Cleaning of site entrances, site tracks and the adjacent public highway and the sheeting of all HGVs taking spoil or construction materials to or from the site to prevent spillage or the deposit of any materials on the public highway; ix) Pollution control, protection of the water environment, bunding of fuel storage areas, surface water drainage, sewage disposal, and discharge of foul drainage; x) Proposals for post-construction restoration/reinstatement of the temporary working areas, track shoulders and crane pads; xi) Details of emergency procedures and pollution response plans; xii) A site environmental management plan to include details of measures to be taken during the construction period to protect wildlife and habitats; xiii) Site illumination during the construction period; and xiv) Details of the routing of underground cables. 8) Construction work shall only take place between the hours of 07:00 to 19:00 on Monday to Friday inclusive and 07:00-13:00 on Saturdays with no such work on a Sunday or Public Holiday. Outside these hours, works at the site shall be limited to dust suppression. Emergency works may be carried out at any time provided that the operator retrospectively notifies the local planning authority in writing of the emergency and works undertaken within 48 hours. 9) The delivery of any construction materials or equipment for the construction of the development, other than wind turbine blades, nacelles and towers, shall be restricted to the hours of 07:00 to 19:00 on Monday to Friday inclusive and 07:00 to 13:00 on Saturdays. There shall be no such deliveries on a Sunday or Public Holiday unless otherwise agreed in writing by the local planning authority having been given a minimum of two working days notice of the proposed delivery. 10) The overall height of the wind turbines shall not exceed 125 metres measured to the tip of the blades when the blade tip is at its highest point and the hub height 80 metres, when measured from original ground level immediately adjacent to the turbine base. www.planningportal.gov.uk/planninginspectorate 33 16.33 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 11) No development shall take place until details of the design, dimensions, finish and colour of the wind turbines and any external transformer units and of the anemometer mast have been submitted to and approved in writing by the local planning authority. No name, sign, symbol or logo shall be displayed on any external surface of the wind turbines, any external transformer units or the anemometer mast other than those required to meet statutory health and safety requirements. The development shall be carried out in accordance with the approved details and retained as such thereafter. 12) All wind turbine blades shall rotate in the same direction. 13) Other than where required for the purposes of air safety, neither the wind turbines nor the anemometer mast shall be illuminated and there shall be no permanent external illumination relating to the proposal other than any required during the construction period, maintenance operations, or emergency lighting. 14) All cabling between the wind turbines and between the wind turbines and the sub-station shall be laid underground. 15) No development shall take place until a written Archaeological Scheme of Investigation has been submitted to and approved in writing by the local planning authority. The scheme shall include: i) a programme and methodology of site investigation and recording; ii) a programme for post-investigation assessment; iii) details of the provision to be made for analysis of the site investigation and recording; iv) details of the provision to be made for publication and dissemination of the analysis and records of the site investigation; v) details of the provision to be made for archive deposition of the analysis and records of the site investigation; and vi) nomination of a competent person(s) or organisation to undertake the works set out in the written scheme of investigation. The Archaeological Scheme of Investigation shall be carried out in accordance with the approved details. 16) No development shall take place until details of checking surveys for protected species or the nests of any breeding birds on the site have been submitted to, and approved in writing by, the local planning authority. The surveys shall be carried out by a suitability qualified ecologist, in accordance with the approved details, in the last suitable season prior to the commencement of site preparation and construction work. No development shall take place until the results of the surveys, along with details of, and a programme for, any mitigation works required as a consequence, have been submitted to and approved in writing by the local planning authority. Any mitigation works required shall be completed in accordance with the approved details. 17) No development shall take place until a Landscape/Habitat Management Scheme has been submitted to and approved in writing by the local planning authority. The scheme shall include a programme and details of new tree and hedgerow planting, the enhancement of existing hedgerows, the establishment of conservation headlands, and replacement planting for trees and hedgerow plants that become diseased or are destroyed or die within five years of the date of planting. The scheme shall be implemented in accordance with the approved details. www.planningportal.gov.uk/planninginspectorate 34 16.34 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 18) No development shall take place until an Ecological Enhancement/Mitigation Scheme, including a programme of implementation, has been submitted to and approved in writing by the local planning authority. This scheme shall accord with the outline commitments in the ES and include areas of more species rich grassland; native woodland and hedgerow planting; pond enhancements; and terrestrial habitat for newts. The Ecological Enhancement/Mitigation Scheme shall be carried out in accordance with the approved details. 19) No development shall take place until a scheme for post-construction monitoring of any impact of the proposals on birds and bats, specifying the survey methodology; frequency of visits; and duration, has been submitted to and approved in writing by the local planning authority. The scheme shall be implemented in accordance with the approved details. 20) No development shall take place until a scheme of landscape works, based around that referred to in the ES, has been submitted to and approved in writing by the local planning authority. The scheme shall include: i) planting proposals including location, species, number, density and size; ii) the relationship of new planting to buildings, roads, footpaths, drains and the location of all services; iii) areas of grass turfing or seeding and other surface materials; iv) depth of topsoil to be provided where necessary; v) an implementation programme; and vi) details of long-term management and maintenance for the new planting. The scheme shall be implemented in accordance with the approved details. 21) No development shall take place until a scheme for the replacement of the Heras fencing adjacent to the rights of way within the former airfield site with an alternative form of security fencing, and an implementation programme, has been submitted to and approved in writing by the local planning authority. The scheme shall be carried out in accordance with the approved details and retained as such thereafter. 22) Notwithstanding condition no.2, the wind turbines and anemometer mast may be micro-sited within 25 metres of the grid references set out in the ES Addendum of July 2010. A plan showing the position of the turbines, anemometer mast and tracks established on the site shall be submitted to the local planning authority within one month of the First Export Date. 23) Prior to the First Export Date a scheme setting out a protocol for the assessment of shadow flicker in the event of any complaint being received from the owner or occupier of a dwelling which lawfully exists or had planning permission at the date of this grant of planning permission, including the remedial measures to be taken, shall be submitted to and approved in writing by the local planning authority. Operation of the wind turbines shall accord with the approved protocol. 24) Prior to the First Export Date a scheme providing for a baseline survey and the investigation and alleviation of any electro-magnetic interference to television caused by the operation of the wind turbines shall be submitted to and approved in writing by the local planning authority. The scheme shall provide for the investigation by a qualified independent television engineer of any complaint of interference with television reception at a lawfully occupied dwelling which lawfully exists or had planning permission at the date of this permission, where such complaint www.planningportal.gov.uk/planninginspectorate 35 16.35 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 is notified to the developer by the local planning authority within 18 months of the First Export Date. Where impairment is determined by the qualified television engineer to be attributable to the wind turbines approved herein, mitigation works shall be carried out in accordance with the approved scheme. 25) The developer shall provide one month’s prior written notice to the local planning authority of the anticipated date of erection of the first wind turbine and prior to that erection, details of the height above ground level of the highest structure in the development; and the position of each wind turbine in terms of latitude and longitude. 26) No development shall take place until an air safety lighting scheme for the wind turbines and the anemometer mast, along with documentary evidence that the scheme meets the requirements of the CAA, NATS and MoD, and an implementation programme, has been submitted to and approved in writing by the local planning authority. The scheme shall be implemented in accordance with the approved details. 27) No development shall take place until a surface water drainage scheme, and a programme for its implementation, has been submitted to and approved in writing by the local planning authority. Development shall be carried out in accordance with the approved details. 28) No development shall take place until a scheme making provision for the protection of the site from contamination has been submitted to and approved in writing by the local planning authority. The scheme shall be implemented before the First Export Date and retained thereafter. No other development shall take place until: i) A desk-top study has been carried out which includes the identification of previous uses on the site and potential contaminants that might be encountered and a diagrammatical representation (Conceptual Model) for the site of all potential contaminant sources, pathways and receptors; ii) A site investigation has been designed for the site using the information from the desk-top study that enables a) a risk assessment to be undertaken relating to human health, ground and surface waters, and other ecosystems; b) refinement of the Conceptual Model; and c) the development of a Method Statement detailing the remediation requirements; iii) The site investigation has been undertaken in accordance with the approved details and a risk assessment undertaken; iv) A Method Statement detailing the remediation requirements, including measures to minimise the impact on human health, ground and surface waters, and other ecosystems, using the information obtained from the site investigation has been submitted to and approved in writing by the local planning authority. Remediation shall be carried out in accordance with the approved details. 29) If, during the course of the development, contamination not previously identified, is found to be present at the site, then no further development shall be carried out until the developer has submitted an addendum to the Method Statement to the local planning authority and gained their written approval of it. The addendum to the Method Statement must www.planningportal.gov.uk/planninginspectorate 36 16.36 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 detail how the previously unsuspected contamination will be dealt with. Development shall then continue in accordance with the approved details. 30) Upon completion of the remediation detailed in the Method Statement, a report shall be submitted to the local planning authority that provides verification that the required works relating to contamination have been carried out in accordance with the approved Method Statement(s). Postremediation sampling and monitoring results shall be included in the report to demonstrate that the required remediation has been fully implemented. Proposals for future monitoring and reporting shall also be detailed in the report. 31) The Boxer Mast shall be demolished before any of the wind turbines approved herein are erected. 32) The rating level of noise emissions from the combined effects of the wind turbines (including the application of any tonal penalty) at any residential property, when determined in accordance with the attached Guidance Notes, shall not exceed the values for the relevant integer wind speed set out in Tables 1 and 2 attached to these conditions and: (A) No wind turbine shall generate electricity to the grid until the local planning authority has approved in writing a scheme submitted by the wind farm operator which details the measurement of noise emissions from the wind turbines at the operator’s expense, to demonstrate compliance with this condition. This noise measurement study shall commence within one month of all the turbines becoming fully operational and continue for a sufficient period to obtain measured noise levels corresponding to wind directions from the site to the measurement locations over a range of operational wind speeds from cut-in to rated power. The measurement locations shall comprise no more than five of those listed below and shall be agreed with the local planning authority prior to any measurements being carried out. Hargrave Lodge Hargrave Village Lodge Farm Silcombe House Manor Farm Yelden Village USAAF Housing Caldecott Chelveston The results of the noise measurement study shall be provided to the local planning authority in order to discharge and demonstrate compliance with this condition. (B) Prior to the First Export Date, the wind farm operator shall submit to the local planning authority for written approval a list of proposed independent consultants who may undertake compliance measurements in accordance with this condition. Amendments to the list of approved consultants shall be made only with the prior written approval of the local planning authority. www.planningportal.gov.uk/planninginspectorate 37 16.37 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 (C) Within 21 days from receipt of a written request of the local planning authority, following a complaint to it alleging noise disturbance at a residential property, the wind farm operator shall, at its expense, employ an independent consultant approved by the local planning authority to assess the level of noise emissions from the wind farm at the complainant’s property in accordance with the procedures described in the attached Guidance Notes. The written request from the local planning authority shall set out the conditions described in Guidance Note 2(b) and shall include a statement as to whether, in the opinion of the local planning authority, the noise giving rise to the complaint contains or is likely to contain a tonal component or noise exacerbated by amplitude modulation as defined in Guidance Note 5. The wind farm operator shall provide the information relevant to the complaint logged in accordance with paragraph (F) to the local planning authority in the format set out in Guidance Note 1(e) within 28 days of receipt in writing of the local planning authority’s request. (D) Where there is more than one property at a location specified in the Tables attached to this condition, the noise limits set for that location shall apply to all residential properties at that location. Where a residential property to which a complaint is related is not identified by name or location in the Tables attached to these conditions, the wind farm operator shall submit to the local planning authority for written approval proposed noise limits selected from those listed in the Tables to be adopted at the complainant’s residential property for compliance checking purposes. The proposed noise limits are to be those limits selected from the Tables specified for a listed location which the independent consultant considers as being likely to experience the most similar background noise environment to that experienced at the complainant’s residential property. The submission of the proposed noise limits to the local planning authority shall include a written justification of the choice of the representative background noise environment provided by the independent consultant. The rating level of noise emissions resulting from the combined effects of the wind turbines when determined in accordance with the attached Guidance Notes shall not exceed the noise limits approved in writing by the local planning authority for the complainant’s residential property. (E) Prior to the submission of the independent consultant’s assessment of the rating level of noise emissions, the wind farm operator shall submit to the local planning authority for written approval the range of meteorological and operational conditions to determine the assessment of rating level of noise emissions. The proposed range of conditions (which shall include the range of wind speeds, wind directions, power generation and times of day) shall be those which prevailed during times when the complainant alleges there was disturbance due to noise, having regard to the written request of the local planning authority under paragraph C). The assessment of the rating level of noise emissions shall be undertaken in accordance with the assessment protocol approved in writing by the local planning authority. www.planningportal.gov.uk/planninginspectorate 38 16.38 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 (F) The wind farm operator shall provide to the local planning authority the independent consultant’s assessment of the rating level of noise emissions undertaken in accordance with the Guidance Notes within 2 months of the date of the written request of the local planning authority made under paragraph (C) of this condition unless the time limit is extended in writing by the local planning authority. The assessment shall include all data collected for the purposes of undertaking the compliance measurements, such data to be provided in the format set out in Guidance Note 1(e) of the Guidance Notes and shall, if required, include an assessment of the level of amplitude modulation in line with the best available guidance existing at the time of the complaint to be agreed with the local planning authority. The instrumentation used to undertake the measurements shall be calibrated in accordance with Guidance Note 1(a) and certificates of calibration shall be submitted to the local planning authority with the independent consultant’s assessment of the rating level of noise emissions. (G) Where a further assessment of the rating level of noise emissions from the wind farm is required pursuant to Guidance Note 4(c) of the attached Guidance Notes, the wind farm operator shall submit a copy of the further assessment within 21 days of submission of the independent consultant’s assessment pursuant to paragraph (F) above unless the time limit for the submission of the further assessment has been extended in writing by the local planning authority. (H) The wind farm operator shall continuously log nacelle wind speed, nacelle orientation, power generation and nacelle wind direction for each turbine and shall continuously log wind speed, wind direction and wind direction data recorded at the permanent anemometer monitoring mast (if erected) in accordance with this permission, all in accordance with Guidance Note 1(d) of the attached Guidance Notes. The data from each wind turbine, and the data from the permanent anemometer mast, shall be retained for a the duration of this permission. The wind farm operator shall provide this information in the format set out in Guidance Note 1(e) of the attached Guidance Notes to the local planning authority on its request within 14 days of receipt in writing of such a request. Note: For the purposes of this condition (A-H), a ‘residential property’ is a building within Use Class C3 or C4 of the Use Classes Order which lawfully exists or had planning permission at the date of this consent. www.planningportal.gov.uk/planninginspectorate 39 16.39 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 Table 1: Between 07:00 and 23:00 - Noise level dB LA90, 10-minute Location Hargrave Lodge Farm Hargrave Village Lodge Farm Silcombe House Manor Farm Yelden Village USAF Housing Caldecott Chelveston Standardised wind speed at 10 metres height (m/s) within the site averaged over 10-minute periods 1 2 3 4 5 6 7 8 9 10 11 12 LA90 Decibel Levels 37 35 35 35 36 35 38 36 40 37 35 35 35 36 35 38 36 40 37 35 35 35 37 35 38 36 40 37 36 35 36 38 35 38 36 40 38 37 35 39 41 36 39 37 41 41 40 39 42 43 38 41 39 43 43 44 44 46 46 41 44 42 45 46 46 48 49 49 44 46 45 47 48 48 50 51 51 46 48 46 47 50 48 50 51 53 47 49 46 47 51 48 50 51 53 47 49 46 47 51 48 50 51 53 47 49 46 47 Table 2: Between 23:00 and 07:00 - Noise level dB LA90, 10-minute Location Hargrave Lodge Farm Hargrave Village Lodge Farm Silcombe House Manor Farm Yelden Village USAF Housing Caldecott Chelveston Standardised wind speed at 10 metres height (m/s) within the site averaged over 10-minute periods 1 2 3 4 5 6 7 8 9 10 11 12 LA90 Decibel Levels 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 45 45 43 43 43 43 44 43 43 49 49 43 45 43 43 48 46 48 52 52 46 49 45 45 51 50 51 54 56 49 52 47 47 Note to Tables 1 & 2: The standardised wind speed at 10 metres height within the site refers to wind speed at 10 metres height derived from those measured at hub height, calculated in accordance with the method given in the Guidance Notes. www.planningportal.gov.uk/planninginspectorate 40 16.40 52 53 54 54 58 51 54 47 47 52 53 54 54 58 51 54 47 47 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 Annex B: APP/G2815/A/11/2160078 1) The development hereby permitted shall begin not later than five years from the date of this decision. 2) The development hereby permitted shall be carried out in accordance with the following approved plans: CREL1052-A-ENDC: Site Location Plan; CREL1014-P-ENDC: Revised Wind Turbine Layout and Site Location Plan; CREL1014-P: Revised Wind Turbine Layout and Site Location Plan; CREL1057-O: Visitor Car park, Access Tracks and Viewing Area; and CREL1061-0: Extract from Oaks Survey 25 04 06 showing Boxer Mast. 3) The permission hereby granted shall be limited to a period of 25 years from the date when electricity is first exported from any of the wind turbines to the electricity grid (the ‘First Export Date’). Written notification of the First Export Date shall be given to the local planning authority no later than 14 days after the event. 4) Not later than 12 months before the expiry of this permission, a decommissioning and site restoration scheme shall be submitted to and approved in writing by the local planning authority. The scheme shall make provision for the removal of the wind turbines, the associated above ground equipment, and foundations to a depth of at least one metre below ground and include details of the management and timing of works, a traffic management plan to address likely traffic impact issues during the decommissioning period, noise controls during decommissioning, an environmental management plan to include details of measures to be taken during the decommissioning period to protect wildlife and habitats, identification of access routes, location of material lay-down areas, restoration measures and a programme of implementation. Decommissioning and site restoration shall be completed in accordance with the approved details within 24 months of the expiry of this permission. 5) If any of the wind turbines hereby permitted fails to operate for a continuous period of six months, a scheme for the repair or removal of the relevant turbine(s) shall be submitted to the local planning authority for its written approval, within three months of the end of that six month period. The scheme shall include, as relevant, a programme of remedial works where repair is required; or a method statement and timetable for the dismantling and removal of the relevant wind turbine and associated above ground works and foundations to a depth of at least one metre below ground and subsequent site restoration. The scheme shall be implemented in accordance with the approved details. 6) No development shall take place until a Construction Traffic Management Plan (CTMP) has been submitted to and approved in writing by the local planning authority. The CTMP shall include details of the routing of construction traffic; its scheduling and timing; the management of junctions with and crossings of, the public highway and other public rights of way; escorts for abnormal loads; temporary warning signs; temporary removal and replacement of highway infrastructure/street furniture; reinstatement of any signs, verges or other items displaced by construction traffic; and banksmen. The CTMP, including any improvements or works to accommodate construction traffic where required shall be implemented in accordance with the approved details. www.planningportal.gov.uk/planninginspectorate 41 16.41 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 7) No development shall take place until a Construction Method Statement (CMS) has been submitted to and approved in writing by the local planning authority. Development shall be carried out in accordance with the approved CMS. The CMS shall address the following matters: i) Details of the phasing of all construction works; ii) Details of the construction and surface treatment of all hard surfaces and tracks; iii) Details of the proposed storage of materials and soils and the disposal of surplus materials; iv) Dust management; v) Details of wheel-washing facilities and their operation; vi) Details of the temporary site compound for storage of materials and machinery (including areas designated for car parking); vii) Construction details of the site access and the creation and maintenance of associated visibility splays; viii) Cleaning of site entrances, site tracks and the adjacent public highway and the sheeting of all HGVs taking spoil or construction materials to or from the site to prevent spillage or the deposit of any materials on the public highway; ix) Pollution control, protection of the water environment, bunding of fuel storage areas, surface water drainage, sewage disposal, and discharge of foul drainage; x) Proposals for post-construction restoration/reinstatement of the temporary working areas, track shoulders and crane pads; xi) Details of emergency procedures and pollution response plans; xii) A site environmental management plan to include details of measures to be taken during the construction period to protect wildlife and habitats; xiii) Site illumination during the construction period; and xiv) Details of the routing of underground cables. 8) Construction work shall only take place between the hours of 07:00 to 19:00 on Monday to Friday inclusive and 07:00-13:00 on Saturdays with no such work on a Sunday or Public Holiday. Outside these hours, works at the site shall be limited to dust suppression. Emergency works may be carried out at any time provided that the operator retrospectively notifies the local planning authority in writing of the emergency and works undertaken within 48 hours. 9) The delivery of any construction materials or equipment for the construction of the development, other than wind turbine blades, nacelles and towers, shall be restricted to the hours of 07:00 to 19:00 on Monday to Friday inclusive and 07:00 to 13:00 on Saturdays. There shall be no such deliveries on a Sunday or Public Holiday unless otherwise agreed in writing by the local planning authority having been given a minimum of two working days notice of the proposed delivery. 10) The overall height of the wind turbines shall not exceed 125 metres measured to the tip of the blades when the blade tip is at its highest point and the hub height 80 metres, when measured from original ground level immediately adjacent to the turbine base. www.planningportal.gov.uk/planninginspectorate 42 16.42 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 11) No development shall take place until details of the design, dimensions, finish and colour of the wind turbines and any external transformer units and of the anemometer mast have been submitted to and approved in writing by the local planning authority. No name, sign, symbol or logo shall be displayed on any external surface of the wind turbines, any external transformer units or the anemometer mast other than those required to meet statutory health and safety requirements. The development shall be carried out in accordance with the approved details and retained as such thereafter. 12) All wind turbine blades shall rotate in the same direction. 13) Other than where required for the purposes of air safety, neither the wind turbines nor the anemometer mast shall be illuminated and there shall be no permanent external illumination relating to the proposal other than any required during the construction period, maintenance operations, or emergency lighting. 14) All cabling between the wind turbines and between the wind turbines and the sub-station shall be laid underground. 15) No development shall take place until a written Archaeological Scheme of Investigation has been submitted to and approved in writing by the local planning authority. The scheme shall include: i) a programme and methodology of site investigation and recording; ii) a programme for post-investigation assessment; iii) details of the provision to be made for analysis of the site investigation and recording; iv) details of the provision to be made for publication and dissemination of the analysis and records of the site investigation; v) details of the provision to be made for archive deposition of the analysis and records of the site investigation; and vi) nomination of a competent person(s) or organisation to undertake the works set out in the written scheme of investigation. The Archaeological Scheme of Investigation shall be carried out in accordance with the approved details. 16) No development shall take place until details of checking surveys for protected species or the nests of any breeding birds on the site have been submitted to, and approved in writing by, the local planning authority. The surveys shall be carried out by a suitability qualified ecologist, in accordance with the approved details, in the last suitable season prior to the commencement of site preparation and construction work. No development shall take place until the results of the surveys, along with details of, and a programme for, any mitigation works required as a consequence, have been submitted to and approved in writing by the local planning authority. Any mitigation works required shall be completed in accordance with the approved details. 17) No development shall take place until a Landscape and Habitat Management Scheme has been submitted to and approved in writing by the local planning authority. The scheme shall include a programme and details of new tree and hedgerow planting, the enhancement of existing hedgerows, the establishment of conservation headlands, and replacement planting for trees and hedgerow plants that become diseased or are destroyed or die within five years of the date of planting. The scheme shall be implemented in accordance with the approved details. www.planningportal.gov.uk/planninginspectorate 43 16.43 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 18) No development shall take place until an Ecological Enhancement/Mitigation Scheme, including a programme of implementation, has been submitted to and approved in writing by the local planning authority. This scheme shall accord with the outline commitments in the ES and include areas of more species rich grassland; native woodland and hedgerow planting; pond enhancements; and terrestrial habitat for newts. The Ecological Enhancement/Mitigation Scheme shall be carried out in accordance with the approved details. 19) No development shall take place until a scheme for post-construction monitoring of any impact of the proposals on birds and bats, specifying the survey methodology; frequency of visits; and duration, has been submitted to and approved in writing by the local planning authority. The scheme shall be implemented in accordance with the approved details. 20) No development shall take place until a scheme of landscape works, based around that referred to in the ES, has been submitted to and approved in writing by the local planning authority. The scheme shall include: i) planting proposals including location, species, number, density and size; ii) the relationship of new planting to buildings, roads, footpaths, drains and the location of all services; iii) areas of grass turfing or seeding and other surface materials; iv) depth of topsoil to be provided where necessary; v) an implementation programme; and vi) details of long-term management and maintenance for the new planting. The scheme shall be implemented in accordance with the approved details. 21) No development shall take place until a scheme for the replacement of the Heras fencing adjacent to the rights of way within the former airfield site with an alternative form of security fencing, and an implementation programme, has been submitted to and approved in writing by the local planning authority. The scheme shall be carried out in accordance with the approved details and retained as such thereafter. 22) Notwithstanding condition no.2, the wind turbines and anemometer mast may be micro-sited within 25 metres of the grid references set out in the ES Addendum of July 2010. A plan showing the position of the turbines, anemometer mast and tracks established on the site shall be submitted to the local planning authority within one month of the First Export Date. 23) Prior to the First Export Date a scheme setting out a protocol for the assessment of shadow flicker in the event of any complaint being received from the owner or occupier of a dwelling which lawfully exists or had planning permission at the date of this grant of planning permission, including the remedial measures to be taken, shall be submitted to and approved in writing by the local planning authority. Operation of the wind turbines shall accord with the approved protocol. 24) Prior to the First Export Date a scheme providing for a baseline survey and the investigation and alleviation of any electro-magnetic interference to television caused by the operation of the wind turbines shall be submitted to and approved in writing by the local planning authority. The scheme shall provide for the investigation by a qualified independent television engineer of any complaint of interference with television reception at a lawfully occupied dwelling which lawfully exists or had planning permission at the date of this permission, where such complaint www.planningportal.gov.uk/planninginspectorate 44 16.44 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 is notified to the developer by the local planning authority within 18 months of the First Export Date. Where impairment is determined by the qualified television engineer to be attributable to the wind turbines approved herein, mitigation works shall be carried out in accordance with the approved scheme. 25) The developer shall provide one month’s prior written notice to the local planning authority of the anticipated date of erection of the first wind turbine and prior to that erection, details of the height above ground level of the highest structure in the development; and the position of each wind turbine in terms of latitude and longitude. 26) No development shall take place until an air safety lighting scheme for the wind turbines and the anemometer mast, along with documentary evidence that the scheme meets the requirements of the CAA, NATS and MoD, and an implementation programme, has been submitted to and approved in writing by the local planning authority. The scheme shall be implemented in accordance with the approved details. 27) No development shall take place until a surface water drainage scheme, and a programme for its implementation, has been submitted to and approved in writing by the local planning authority. Development shall be carried out in accordance with the approved details. 28) No development shall take place until a scheme making provision for the protection of the site from contamination has been submitted to and approved in writing by the local planning authority. The scheme shall be implemented before the First Export Date and retained thereafter. No other development shall take place until: i) A desk-top study has been carried out which includes the identification of previous uses on the site and potential contaminants that might be encountered and a diagrammatical representation (Conceptual Model) for the site of all potential contaminant sources, pathways and receptors; ii) A site investigation has been designed for the site using the information from the desk-top study that enables a) a risk assessment to be undertaken relating to human health, ground and surface waters, and other ecosystems; b) refinement of the Conceptual Model; and c) the development of a Method Statement detailing the remediation requirements; iii) The site investigation has been undertaken in accordance with the approved details and a risk assessment undertaken; iv) A Method Statement detailing the remediation requirements, including measures to minimise the impact on human health, ground and surface waters, and other ecosystems, using the information obtained from the site investigation has been submitted to and approved in writing by the local planning authority. Remediation shall be carried out in accordance with the approved details. 29) If, during the course of the development, contamination not previously identified, is found to be present at the site, then no further development shall be carried out until the developer has submitted an addendum to the Method Statement to the local planning authority and gained their written approval of it. The addendum to the Method Statement must detail how the previously unsuspected contamination will be dealt with. www.planningportal.gov.uk/planninginspectorate 45 16.45 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 Development shall then continue in accordance with the approved details. 30) Upon completion of the remediation detailed in the Method Statement, a report shall be submitted to the local planning authority that provides verification that the required works relating to contamination have been carried out in accordance with the approved Method Statement(s). Postremediation sampling and monitoring results shall be included in the report to demonstrate that the required remediation has been fully implemented. Proposals for future monitoring and reporting shall also be detailed in the report. 31) The Boxer Mast shall be demolished before any of the wind turbines approved herein are erected. 32) Notwithstanding condition no.2, the anemometer mast (ENMM) shown on the approved plans referred to above shall not be erected. 33) The rating level of noise emissions from the combined effects of the wind turbines (including the application of any tonal penalty) at any residential property, when determined in accordance with the attached Guidance Notes, shall not exceed the values for the relevant integer wind speed set out in Tables 1 and 2 attached to these conditions and: (A) No wind turbine shall generate electricity to the grid until the local planning authority has approved in writing a scheme submitted by the wind farm operator which details the measurement of noise emissions from the wind turbines at the operator’s expense, to demonstrate compliance with this condition. This noise measurement study shall commence within one month of all the turbines becoming fully operational and continue for a sufficient period to obtain measured noise levels corresponding to wind directions from the site to the measurement locations over a range of operational wind speeds from cut-in to rated power. The measurement locations shall comprise no more than five of those listed below and shall be agreed with the local planning authority prior to any measurements being carried out. Hargrave Lodge Hargrave Village Lodge Farm Silcombe House Manor Farm Yelden Village USAAF Housing Caldecott Chelveston The results of the noise measurement study shall be provided to the local planning authority in order to discharge and demonstrate compliance with this condition. (B) Prior to the First Export Date, the wind farm operator shall submit to the local planning authority for written approval a list of proposed independent consultants who may undertake compliance measurements in accordance with this condition. Amendments to www.planningportal.gov.uk/planninginspectorate 46 16.46 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 the list of approved consultants shall be made only with the prior written approval of the local planning authority. (C) Within 21 days from receipt of a written request of the local planning authority, following a complaint to it alleging noise disturbance at a residential property, the wind farm operator shall, at its expense, employ an independent consultant approved by the local planning authority to assess the level of noise emissions from the wind farm at the complainant’s property in accordance with the procedures described in the attached Guidance Notes. The written request from the local planning authority shall set out the conditions described in Guidance Note 2(b) and shall include a statement as to whether, in the opinion of the local planning authority, the noise giving rise to the complaint contains or is likely to contain a tonal component or noise exacerbated by amplitude modulation as defined in Guidance Note 5. The wind farm operator shall provide the information relevant to the complaint logged in accordance with paragraph (F) to the local planning authority in the format set out in Guidance Note 1(e) within 28 days of receipt in writing of the local planning authority’s request. (D) Where there is more than one property at a location specified in the Tables attached to this condition, the noise limits set for that location shall apply to all residential properties at that location. Where a residential property to which a complaint is related is not identified by name or location in the Tables attached to these conditions, the wind farm operator shall submit to the local planning authority for written approval proposed noise limits selected from those listed in the Tables to be adopted at the complainant’s residential property for compliance checking purposes. The proposed noise limits are to be those limits selected from the Tables specified for a listed location which the independent consultant considers as being likely to experience the most similar background noise environment to that experienced at the complainant’s residential property. The submission of the proposed noise limits to the local planning authority shall include a written justification of the choice of the representative background noise environment provided by the independent consultant. The rating level of noise emissions resulting from the combined effects of the wind turbines when determined in accordance with the attached Guidance Notes shall not exceed the noise limits approved in writing by the local planning authority for the complainant’s residential property. (E) Prior to the submission of the independent consultant’s assessment of the rating level of noise emissions, the wind farm operator shall submit to the local planning authority for written approval the range of meteorological and operational conditions to determine the assessment of rating level of noise emissions. The proposed range of conditions (which shall include the range of wind speeds, wind directions, power generation and times of day) shall be those which prevailed during times when the complainant alleges there was disturbance due to noise, having regard to the written request of the local planning authority under paragraph C). The assessment of the rating level of noise emissions shall be undertaken in www.planningportal.gov.uk/planninginspectorate 47 16.47 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 accordance with the assessment protocol approved in writing by the local planning authority. (F) The wind farm operator shall provide to the local planning authority the independent consultant’s assessment of the rating level of noise emissions undertaken in accordance with the Guidance Notes within 2 months of the date of the written request of the local planning authority made under paragraph (C) of this condition unless the time limit is extended in writing by the local planning authority. The assessment shall include all data collected for the purposes of undertaking the compliance measurements, such data to be provided in the format set out in Guidance Note 1(e) of the Guidance Notes and shall, if required, include an assessment of the level of amplitude modulation in line with the best available guidance existing at the time of the complaint to be agreed with the local planning authority. The instrumentation used to undertake the measurements shall be calibrated in accordance with Guidance Note 1(a) and certificates of calibration shall be submitted to the local planning authority with the independent consultant’s assessment of the rating level of noise emissions. (G) Where a further assessment of the rating level of noise emissions from the wind farm is required pursuant to Guidance Note 4(c) of the attached Guidance Notes, the wind farm operator shall submit a copy of the further assessment within 21 days of submission of the independent consultant’s assessment pursuant to paragraph (F) above unless the time limit for the submission of the further assessment has been extended in writing by the local planning authority. (H) The wind farm operator shall continuously log nacelle wind speed, nacelle orientation, power generation and nacelle wind direction for each turbine and shall continuously log wind speed, wind direction and wind direction data recorded at the permanent anemometer monitoring mast (if erected) in accordance with this permission, all in accordance with Guidance Note 1(d) of the attached Guidance Notes. The data from each wind turbine, and the data from the permanent anemometer mast, shall be retained for the duration of this permission. The wind farm operator shall provide this information in the format set out in Guidance Note 1(e) of the attached Guidance Notes to the local planning authority on its request within 14 days of receipt in writing of such a request. Note: For the purposes of this condition (A-H), a ‘residential property’ is a building within Use Class C3 or C4 of the Use Classes Order which lawfully exists or had planning permission at the date of this consent. www.planningportal.gov.uk/planninginspectorate 48 16.48 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 Table 1: Between 07:00 and 23:00 - Noise level dB LA90, 10-minute Location Hargrave Lodge Farm Hargrave Village Lodge Farm Silcombe House Manor Farm Yelden Village USAF Housing Caldecott Chelveston Standardised wind speed at 10 metres height (m/s) within the site averaged over 10-minute periods 1 2 3 4 5 6 7 8 9 10 11 12 LA90 Decibel Levels 37 35 35 35 36 35 38 36 40 37 35 35 35 36 35 38 36 40 37 35 35 35 37 35 38 36 40 37 36 35 36 38 35 38 36 40 38 37 35 39 41 36 39 37 41 41 40 39 42 43 38 41 39 43 43 44 44 46 46 41 44 42 45 46 46 48 49 49 44 46 45 47 48 48 50 51 51 46 48 46 47 50 48 50 51 53 47 49 46 47 51 48 50 51 53 47 49 46 47 51 48 50 51 53 47 49 46 47 Table 2: Between 23:00 and 07:00 - Noise level dB LA90, 10-minute Location Hargrave Lodge Farm Hargrave Village Lodge Farm Silcombe House Manor Farm Yelden Village USAF Housing Caldecott Chelveston Standardised wind speed at 10 metres height (m/s) within the site averaged over 10-minute periods 1 2 3 4 5 6 7 8 9 10 11 12 LA90 Decibel Levels 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 45 45 43 43 43 43 44 43 43 49 49 43 45 43 43 48 46 48 52 52 46 49 45 45 51 50 51 54 56 49 52 47 47 Note to Tables 1 & 2: The standardised wind speed at 10 metres height within the site refers to wind speed at 10 metres height derived from those measured at hub height, calculated in accordance with the method given in the Guidance Notes. www.planningportal.gov.uk/planninginspectorate 49 16.49 52 53 54 54 58 51 54 47 47 52 53 54 54 58 51 54 47 47 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 Guidance Notes for Condition 32 (Appeal A) and 33 (Appeal B) These notes are to be read with and form part of the noise conditions. They further explain the conditions and specify the methods to be employed in the assessment of complaints about noise emissions from the wind farm. The rating level at each integer wind speed is the arithmetic sum of the wind farm noise level as determined from the best-fit curve described in Note 2 of these Guidance Notes and any tonal penalty applied in accordance with Note 3 with any necessary correction for residual background noise levels in accordance with Note 4. Reference to ETSU-R-97 refers to the publication entitled ‘The Assessment and Rating of Noise from Wind Farms’ (1997) published by the Energy Technology Support unit (ETSU) for the Department of Trade and Industry (DTI). Note 1 (a) Values of the LA90,10-minute noise statistic should be measured at the complainant’s property, using a sound level meter of EN 60651/BS EN 60804 Type 1, or BS EN 61672 Class 1 quality (or the equivalent UK adopted standard in force at the time of the measurements) set to measure using the fast time weighted response as specified in BS EN 60651/BS EN 60804 or BS EN 61672-1 (or the equivalent UK adopted standard in force at the time of the measurements). This should be calibrated in accordance with the procedure specified in BS 4142: 1997 (or the equivalent UK adopted standard in force at the time of the measurements). Measurements shall be undertaken in such a manner to enable a tonal penalty to be applied in accordance with Guidance Note 3. (b) The microphone shall be mounted at 1.2 - 1.5 metres above ground level, fitted with a two-layer windshield or suitable equivalent approved in writing by the local planning authority, and placed outside the complainant’s residential property and be not more than 35 metres from it. Measurements should be made in ‘free field’ conditions. To achieve this, the microphone shall be placed at least 3.5 metres away from the building facade or any reflecting surface except the ground at the approved measurement location. In the event that the consent of the complainant for access to his or her property to undertake compliance measurements is withheld, the wind farm operator shall submit for the written approval of the local planning authority details of the proposed alternative representative measurement location prior to the commencement of measurements and the measurements shall be undertaken at the approved alternative representative measurement location. (c) The LA90,10-minute measurements should be synchronised with measurements of the 10-minute arithmetic mean wind speed and wind direction data and with operational data logged in accordance with Guidance Note 1(d) and rain data logged in accordance with Note 1(f). (d) To enable compliance with the conditions to be evaluated, the wind farm operator shall continuously log arithmetic mean nacelle wind speed (duly corrected for the presence of the rotating blades) arithmetic mean nacelle orientation, nacelle wind direction and arithmetic mean power generated during each successive 10-minute periods for each wind turbine on the site. The wind farm operator shall continuously log arithmetic mean wind speed in metres per second and arithmetic mean wind direction in degrees www.planningportal.gov.uk/planninginspectorate 50 16.50 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 from north, at the permanent meteorological mast (if erected), such measurements to be taken at the hub height of the wind turbines in each successive 10-minute periods. The hub height wind speeds recorded from the nacelle anemometers or as calculated from the power output of each turbine, or at the permanent meteorological mast, shall be supplemented by standardised ten metre height wind speed data calculated for each 10-minute period from those measured at hub height assuming a reference roughness length of 0.05 metres and using the equation given on page 120 of ETSU-R-97. All 10-minute periods shall commence on the hour and in 10-minute increments thereafter synchronised with Greenwich Mean Time and adjusted to British Summer Time where necessary. Standardised 10 metre height wind speed data shall be correlated with the noise measurements determined as valid in accordance with Note 2(b), such correlation to be undertaken in the manner described in Note 2(c). The records shall be kept for the duration of the planning permission. (e) Data provided to the local planning authority in accordance with paragraphs (F) (G) and (H) of Condition 32/33 shall be provided in comma separated values in electronic format. (f) A data logging rain gauge shall be installed within 3 m of any sound level meter installed in the course of the independent consultant undertaking an assessment of the level of noise emissions. The gauge shall record over successive 10-minute periods synchronised with the periods of data recorded in accordance with Note 1(d). Note 2 (a) The noise measurements should be made so as to provide not less than 20 valid data points as defined in Note 2. (b) Valid data points are those measured during the conditions specified by the Local Planning Authority set out in paragraph (C) of Condition 32/33 but excluding any periods of rainfall measured in accordance with Note 1(f). (c) Values of the LA90,10-minute noise measurements and corresponding values of the 10-minute standardised ten metre height wind speed for those data points considered valid in accordance with Note 2(b) shall be plotted on an XY chart with noise level on the Y-axis and wind speed on the X-axis. A least squares, ‘best fit’ curve of an order deemed appropriate by the independent consultant (but which may not be higher than a fourth order) shall be fitted to the data points to define the wind farm noise level at each integer speed. Note 3 (a) Where, in the opinion of the local planning authority as advised to the wind farm operator in its written request under paragraph (C) of Condition 32/33, noise emissions at the location or locations where compliance measurements are being undertaken contain or are likely to contain a tonal component, a tonal penalty shall be calculated and applied using the following rating procedure. (b) For each 10-minute interval for which LA90,10-minute data have been determined as valid in accordance with Note 2, a tonal assessment shall be performed on noise emissions during 2-minutes of each 10-minute www.planningportal.gov.uk/planninginspectorate 51 16.51 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 period. The 2-minute periods should be spaced at 10-minute intervals provided that uninterrupted uncorrupted data are available (‘the standard procedure’). Where uncorrupted data are not available, the first available uninterrupted clean 2-minute period out of the affected overall 10-minute period shall be selected. Any such deviations from the standard procedure shall be reported. (c) For each of the 2-minute samples the tone level above audibility shall be calculated by comparison with the audibility criterion given in Section 2.1 on pages 104 -109 of ETSU-R-97. (d) The tone level above audibility shall be plotted against wind speed for each of the 2-minute samples. Samples for which the tones were below the audibility criterion or no tone was identified, a value of zero audibility shall be substituted. (e) A least squares ‘best fit’ linear regression shall then be performed to establish the average tone level above audibility for each integer wind speed derived from the value of the ‘best fit’ line fitted to values. If there is no apparent trend with wind speed then a simple arithmetic mean shall be used. (f) The tonal penalty is derived from the margin above audibility of the tone according to the figure below derived from the average tone level above audibility for each integer wind speed. Note 4 (a) If a tonal penalty is to be applied in accordance with Note 3 the rating level of the turbine noise at each wind speed is the arithmetic sum of the measured noise level as determined from the best fit curve described in Note 2 and the penalty for tonal noise as derived in accordance with Note 3 at each integer wind speed within the range set out in paragraph (C) of Condition 32/33. (b) If no tonal penalty is to be applied then the rating level of the turbine noise at each wind speed is equal to the measured noise level as determined from the best fit curve described in Note 2. (c) If the rating level at any integer wind speed lies at or below the values set out in the Tables attached to the conditions or at or below the noise limits approved by the local planning authority for a complainant’s residential property in accordance with paragraph (D) of Condition 32/33 then no further action is necessary. In the event that the rating level is above the limit(s) set out in the Tables attached to the noise conditions or the noise limits for a complainant’s residential property approved in accordance with paragraph (D) of the Condition 32/33, the independent consultant shall undertake a further assessment of the rating level to correct for www.planningportal.gov.uk/planninginspectorate 52 16.52 Appeal Decisions APP/K0235/A/11/2160077 & APP/G2815/A/11/2160078 background noise so that the rating level relates to wind turbine noise emission only. (d) The wind farm operator shall ensure that all the wind turbines in the development are turned off for such period as the independent consultant requires to undertake the further assessment. The further assessment shall be undertaken in accordance with the following steps: i. Repeating the steps in Note 2, with the wind farm switched off, and determining the background noise (L3) at each integer wind speed within the range set out in paragraph (C) of Condition 32/33. ii. The wind farm noise (L1) at this speed shall then be calculated as follows where L2 is the measured level with turbines running but without the addition of any tonal penalty: [ L1 = 10 log 10 L2 /10 − 10 L3 /10 ] iii. The rating level shall be re-calculated by adding the tonal penalty (if any is applied in accordance with Note 3) to the derived wind farm noise L1 at that integer wind speed. If the rating level after adjustment for background noise contribution and adjustment for tonal penalty (if required in accordance with note (iii) above) at any integer wind speed lies at or below the values set out in the Tables attached to the conditions or at or below the noise limits approved by the local planning authority for a complainant’s residential property in accordance with paragraph (D) of Condition 32/33 then no further action is necessary. If the rating level at any integer wind speed exceeds the values set out in the Tables attached to the conditions or the noise limits approved by the local planning authority for a complainant’s residential property in accordance with paragraph (D) of Condition 32/33 then the development fails to comply with the conditions. Note 5 (a) Amplitude modulation is the modulation of the level of broadband noise emitted by a turbine at blade passing frequency. www.planningportal.gov.uk/planninginspectorate 53 16.53