Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area

advertisement
Disposal of disused
offshore concrete gravity
platforms in the OSPAR
Maritime Area
Report No. 338
February 2003
P
ublications
Global experience
e International Association of Oil & Gas Producers has access to a wealth of technical
knowledge and experience with its members operating around the world in many different terrains. We collate and distil this valuable knowledge for the industry to use as
guidelines for good practice by individual members.
Consistent high quality database and guidelines
Our overall aim is to ensure a consistent approach to training, management and best
practice throughout the world.
e oil and gas exploration and production industry recognises the need to develop consistent databases and records in certain fields. e OGP’s members are encouraged to use
the guidelines as a starting point for their operations or to supplement their own policies
and regulations which may apply locally.
Internationally recognised source of industry information
Many of our guidelines have been recognised and used by international authorities and
safety and environmental bodies. Requests come from governments and non-government organisations around the world as well as from non-member companies.
Disclaimer
Whilst every eff ort has been made to ensure the accuracy of the information contained in this
publication, neither the OGP nor any of its members past present or future warrants its accuracy
or will, regardless of its or their negligence, assume liability for any foreseeable or unforeseeable
use made thereof, which liability is hereby excluded. Consequently, such use is at the recipient’s
own risk on the basis that any use by the recipient constitutes agreement to the terms of this disclaimer. e recipient is obliged to inform any subsequent recipient of such terms.
Copyright OGP
All rights are reserved. Material may not be copied, reproduced, republished, downloaded, stored in
any retrieval system, posted, broadcast or transmitted in any form in any way or by any means except
for your own personal non-commercial home use. Any other use requires the prior written permission
of the OGP.
ese Terms and Conditions shall be governed by and construed in accordance with the laws of England
and Wales. Disputes arising here from shall be exclusively subject to the jurisdiction of the courts of
England and Wales.
Disposal of disused offshore
concrete gravity platforms in the
OSPAR Maritime Area
Report No: 
February 
Contributers
Erik Hjelde
TotalFinaElf Exploration Norge AS
Bob Hemmings
Shell Exploration
Egil Olsen
ExxonMobil International
Ove Tobias Gudmestad
Statoil ASA
Kjell orvald Sørensen
Norsk Hydro asa
Michael Hall
ConocoPhillips
Chairman
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
Summary
e objective of this document is to present the experienced gained by the industry in the
period – in a “state-of-art” review of the technical challenges and other assessment
issues considered in order to identify the best disposal option for disused offshore concrete
gravity substructures within the OSPAR Maritime Area.
OSPAR Decision / provides the regulatory framework for decommissioning all offshore structures. In respect of gravity based concrete structures the Decision states that
“e dumping, and the leaving wholly or partly in place, of disused offshore installations
within the maritime area is prohibited”, but adds that “…if the competent authority of the
Contracting Party concerned is satisfied that an assessment …shows that there are significant
reasons why an alternative disposal…is preferable to reuse or recycling or final disposal on
land, it may issue a permit for…a concrete installation...to be dumped or left wholly or partly
in place…”. e part of the concrete platform where such alternative disposal options may
be assessed would be the concrete substructure; ie the load bearing structure supporting the
topside facilities. No derogation possibility exists for the topside facilities.
ere are altogether  concrete platforms located within the maritime area of the OSPAR
Convention, in Norwegian (), British (), Dutch () and Danish () sectors of the North
Sea.
Between the adoption of Decision OSPAR / and July , decommissioning of  concrete platforms has been considered. Related studies have been carried out and completed
and they represent most of the knowledge gained by the industry since .
e two North Sea operators who have presented decommissioning proposals on behalf of
the their co-ventures, have considered the following main disposal options for four disused
offshore concrete platforms:
• Removal for onshore disposal
• Removal for deep water disposal
• Partial removal (cut down the structure down to -m to respect the IMO Guidelines)
• Leave in place
is report highlights the main findings on the four key elements in the comparative assessment of each disposal option:
• Technical feasibility
• Safety for personnel
• Environmental impact
• Cost
is review identifies several uncertainties associated with the removal of both first and
second-generation concrete gravity structures such that a case-by-case evaluation will be
required to assess the specific circumstances for each installation. e first generation of
offshore concrete gravity platforms installed in the s were not designed or constructed
for future removal operations. Although provisions for removal were incorporated into the
design of later, second-generation concrete platforms, these may not be fully effective because
the obstacles to and hazards associated with removal were not appreciated.
An important development over the period of this review has been the introduction of a
comprehensive programme of consultation involving a wide range of stakeholders, experts
and other users of the sea to view the question of decommissioning from as many angles as
possible. is consultation and engagement process has been pivotal in arriving at balanced
conclusions in respect of the major decommissioning activity that has taken place between
 and .
©  OGP

International Association of Oil & Gas Producers
e need for monitoring of concrete substructures left in place is highlighted. Concrete
structures left in the marine environment will degrade slowly and may be expected to remain
standing for  to  years. Shorter-term contamination of the marine environment due
to residual oil in storage chambers and pipe-work is not expected to be significant.
Future liability is addressed where the responsibility remains with present owners unless otherwise agreed with the regulators. It is particularly the long-term liability that is of concern
for both the industry and the authorities.

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
Table of contents
1
Introduction................................................................................................................................................................ 4
2
Description of concrete gravity platforms ......................................................................................................... 5
. Design.................................................................................................................................................. 
. Construction........................................................................................................................................
. Installation...........................................................................................................................................
3 Population of concrete gravity platforms............................................................................................................ 8
. Concrete gravity platforms in the OSPAR Maritime Area.................................................................... 
. Concrete gravity platforms outside the OSPAR Maritime Area............................................................
4 International regulatory requirements for decommissioning ...................................................................... 10
5
Decommissioning alternatives ..............................................................................................................................11
. Removal .............................................................................................................................................. 
. Removal for deep water disposal .........................................................................................................
. Partial removal ....................................................................................................................................
. Leave in place......................................................................................................................................
6 Safety.......................................................................................................................................................................... 20
7
Environmental impact ............................................................................................................................................ 22
. Re-float for onshore disposal .............................................................................................................. 
. Deepwater disposal ............................................................................................................................ 
. Cutting to - metres.......................................................................................................................... 
. Leave in place..................................................................................................................................... 
. Long-term fate of concrete structures ................................................................................................. 
8 Monitoring ................................................................................................................................................................ 24
9
Liability....................................................................................................................................................................... 25
10 Cost............................................................................................................................................................................ 26
11 Decommissioning experience and future plans ............................................................................................... 27
. Recent work on disposal of concrete platforms ................................................................................... 
. Future decommissioning plans........................................................................................................... 
12 Public consultation.................................................................................................................................................. 29
13 Conclusions .............................................................................................................................................................. 30
Appendix 1– Concrete gravity platforms within the OSPAR Maritime Area......................................... 31
Appendix 2– Concrete gravity platforms outside the OSPAR Maritime Area ...................................... 33
Reference List .......................................................................................................................................................... 34
©  OGP

International Association of Oil & Gas Producers

Introduction
In , the International Association of Oil and Gas Producers - OGP, (then the Oil Industry
International Exploration and Production Forum - E & P Forum) published a report (E&P
Forum report number ) on decommissioning offshore gravity-based concrete structures,
from the perspective of the international regulatory regime in force at that time. At its
Ministerial level conference in  Contracting Parties to the OSPAR Convention agreed
a new and binding Decision (Decision (/) on disposal of disused offshore installations.
At the heart of this Decision was the recognition that re-use, recycling or final disposal
on land will generally be the preferred option for decommissioning offshore installations.
Nonetheless, recognising the particular problems associated with the decommissioning large
concrete structures, the decision also set out conditions whereby these structures might be
left in place (wholly or partially) or dumped at sea, including a detailed consultation mechanism that would engage all contracting parties. e final decision on decommissioning
would still reside with the national competent authority.
e objective of this document is to update the earlier  report, taking into account
knowledge and experience gained by the industry in the period  to  and in the light
of the new regulatory conditions for the North East Atlantic, focusing in particular on the
issues and risks associated with the decommissioning options considered.

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
 Description of
concrete gravity platforms
2.1
Design
A concrete gravity platform is one that is placed on the seabed and by its own weight is capable of withstanding the environmental forces it may be exposed to during its lifetime. Most
of the platforms are additionally stabilised by skirts that penetrate into the seabed.
ese platforms are huge in size and weight. Some of them are among the most impressive
structures ever built. e weights of the concrete substructures range from , tonnes to
,, tonnes, and support topsides weighing from between , to , tonnes.
Some of the concrete substructures have oil storage ranging from , to ,, barrels (approximately , to , tonnes) (see Appendix  and  for further details).
Main purpose of most concrete gravity platforms was to provide storage facilities for oil at the
offshore location at a time when no, or few export pipelines were available for transport of oil
from the oil fields to shore. e aim was to provide sufficient storage capacity in the platform
base storage cells to enable continued production from the field. e stored oil would then
typically be pumped from the platform storage cells via an offloading system to shuttle tankers. Concrete structures were also designed to provide sufficient support for topsides loads of
more than  tonnes
e requirement for new fixed concrete structures with offshore storage capabilities has gradually decreased with the development of offshore pipeline infrastructure and the introduction of new technology including sub sea engineering, flexible risers and based on Floating
Production Storage and Offloading installations (FPSOs).
One advantage of the concrete gravity based structures compared with conventional piled
steel jacket structures, was that they could be floated/towed out to the installation site and
installed with the topsides already in place. e installation could thus to a great extent be
completed onshore/inshore before tow-out to the field, thereby minimising offshore hook-up
and commissioning work.
Since the s, several concrete platform designs have been developed. Most of the designs
have in common a base caisson (normally for storage of oil) and shafts penetrating the water
surface to give support for the topside structures. e shafts normally contain utility systems
for offloading, draw down and ballast operations, or they serve as drilling shafts.
e most common concrete designs are:
• Condeep (with one, two, three or four columns) – see Figure .
• ANDOC (with four columns) – see Figure .
• Sea Tank (with two or four columns) – see Figure .
• C G Doris – see Figure .
• Ove Arup – see Figure .
e first concrete gravity platform to be installed in the North Sea was a C G Doris platform,
the Ekofisk Tank, in Norwegian waters in June . During summer , three other concrete platforms were installed, two Condeeps and another C G Doris platform; all placed in
the UK sector of the North Sea.
After these first successful installations of concrete gravity platforms, a number of different
designs was developed. e last concrete platform was installed in .
©  OGP

International Association of Oil & Gas Producers
Figure 2.1: A typical Condeep design
Figure 2.4
2.2
Figure 2.2: A typical ANDOC design (Anglo
Dutch Offshore Concrete)
A typical concrete gravity platform
designed by Doris Engineering
Figure 2.5
Figure 2.3 A typical Sea Tank Design
platform where the base is of
concrete with storage capacity on
which a steel jack-up rig is fixed
Construction
e lower part of the concrete gravity structure including the skirts, is built in a dry dock. When the lower
part of the caisson or storage tanks had been fabricated
and has reached a certain height, the concrete substructure is floated out of the dry dock and moored at an
inshore deep-water site where the pouring of concrete
continues. As the construction advances the structure
is more or less continuously ballasted down to maintain a workable height for slip-forming activities. e
outfitting of the shafts then takes place before the deck
structure is installed.
e topsides on some concrete substructures are installed inshore, in components, by a
heavy lift vessel before being towed offshore. On others, the deck structure and modules
are installed as a complete unit onto the concrete substructure in sheltered inshore waters.
e concrete substructure is ballasted with water so that only about  metres of the columns
protrude above water. Barges then position the complete topsides over the concrete columns.
e concrete substructure is then de-ballasted and gradually the weight of the topsides is
transferred onto the concrete substructure.

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
A number of incidents has shown the deep ballasting operation to be very critical as extreme
water pressure is applied to the concrete substructure. One concrete substructure collapsed
during such an operation in . e implosion that followed as it sank caused the concrete
substructure to be completely broken up. Other structures have shown severe cracking without reaching a catastrophic stage. Such uncertainties in question be an important issue when
addressing the technical challenges of potential re-floating during decommissioning. ese
factors are discussed later in Section ..
A distinct benefit of installing the complete topsides with modules on the concrete substructure in sheltered waters is that most of the hook-up and commissioning work is performed
before towing the complete platform to its final location offshore. is has meant that the
platform could be operational very shortly after it was safely installed.
2.3
Installation
Concrete gravity platforms installed prior to
 were equipped with a simplified installation
system consisting of a combined water depletion and grout system. is system was used for
drainage of water under the platform and in the
skirt compartments during platform installation. Following platform installation, the system
was used for placing grout under the platform,
thereby securing full contact between the platform underside and the seabed.
Water and grout return lines were also installed. ese were used for draining out the displaced water, while injecting grout under the platform and enabled the installation team to
check that the grout had been distributed evenly under the platform. e grout thus ensured
that the contact pressure was equally distributed over the foundation area. ere is, however,
uncertainty as to whether the grout would stick to the underside of the platform during a
removal attempt, or whether it would fall off when the platform lifts off from the seabed. A
sudden loss of the grout may have an adverse effect on the stability of the platform (see also
Section ..).
From , platforms installed in the North Sea (so-called second generation installations) were equipped with a more sophisticated installation system involving separate water
removal system for use in the installation phase. is system was not filled with grout during
the grouting operation but was sealed off. It was intended that this system could be used to
inject water under the platform in a controlled way during a possible re-float operation, in
order to assist in loosening the platform from the seabed.
©  OGP

International Association of Oil & Gas Producers

3.1
Population of concrete gravity
platforms
Concrete gravity platforms in the OSPAR Maritime Area
e OSPAR region covers the whole of
the North East Atlantic area including the
North Sea. All together there are  concrete platforms in this maritime area (see
Appendix  for details).
��
����� ����������
��
������ ����������
�
ere are  concrete gravity base plat- �
forms in Norwegian waters in water
depths from  to  metres. e earliest, �
the Ekofisk Tank, was installed in .
e largest concrete platform ever built is �
the “Troll Gas” platform installed in .
e UK sector has  concrete platforms, �
��
������ ����������� �������
the majority of which were installed in
Figure 3.1: Number of concrete platforms in
the OSPAR Maritime Area
the s. e last concrete structure to
be installed was the “Harding” platform
in  (concrete base only). Two concrete platforms are located offshore the Netherlands
and one offshore Denmark. e “Arne South” platform in the Danish Sector was installed
in  and is the last concrete platform to be installed in the OSPAR Maritime Area. Of
the  concrete platforms in the North Sea,  have facilities for oil storage within the base
of the structure.
Figures ., . and . show respectively, the type (in terms of first or second generation),
location of the concrete gravity platforms within the OSPAR Maritime area as well as the
number in different water depths. e notation “second generation” indicates that removal
was addressed as a design condition during design and construction.
Figure 3.3 Number of Concrete Platforms per depth interval in the OSPAR Maritime Area

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
DRAUGEN
�������
STATFJORD
���������
C
�
A �
�
DUNLIN �
A
������
C
B
�
GULLFAKS
B ��������
A�
�
D
�
CORMORANT�A
���������
C
�
BRENT �B
�����
NINIAN �������
CENTRAL
������
Norway
������
TROLL-A
�����
��
OSEBERG-A
�������
��
FRIGG-TP1
�����
� ���
FRIGG-CDP1
�����
� ����
FRIGG-TCP2
�����
� ����
BERYL�A
�����
HARDING
�������
MCP-01
���
� ��
SLEIPNER-A
��������
��
EKOFISK���
2/4-T
�������
��
SOUTH����
ARNE�A
�����
�������
Denmark
F3-FB-1P
�����
� ��
UK
��
RAVENSPURN�����
NORTH
����������
��CP
Germany
�������
HALFWEG
�������
Netherlands
�����������
Figure 3.2 Locations of Concrete Platforms in the OSPAR Maritime Area
3.2
Concrete gravity platforms outside the OSPAR Maritime Area
Concrete has also been used for platform construction in other parts of the world, albeit to a
lesser extent than the North Sea: notably in Australia, where three structures were installed
in the mid-s; the recently installed Malampaya concrete structure in the Philippines; the
massive Hibernia platform offshore Canada, and two small structures in the shallow waters
of the Baltic. ese latter two platforms at Schwedeneck See are currently being decommissioned, and removal is expected in the near future.
Details of the platforms are provided in Appendix .
©  OGP

International Association of Oil & Gas Producers

International regulatory requirements
for decommissioning
Decommissioning procedures for disused offshore installations are generally set out in
national legislation, with accompanying guideline and practice documents. Internationally,
there are a number of agreements relating to aspects decommissioning, principally addressing partial removal and disposal at sea.
e IMO Guidelines and Standards for the removal of Offshore Installations adopted by
IMO Contracting States in , set out conditions for removal of installations with the aim
of protecting navigation and the safety of other legitimate users of the sea. In essence the
guidelines suggest that where complete removal is not possible, partial removal should leave
an unobstructed water column of  metres.
e London Convention  (formerly known as the London Dumping Convention) is an
agreement that regulates dumping material at sea (including offshore installations). e 
Protocol to the London Convention  categorises offshore installations as platforms or
other man-made structures at sea, and although the Protocol is not in force, the Contracting
Parties to the  Convention have adopted Guidelines for assessing disposal options.
In addition to being signatories to the London Convention, States littoral to the North
East Atlantic are also signatories to the OSPAR Convention. Annex  to the agreement
contains the provision relating to the prevention and elimination of pollution from offshore
installations. Although this Annex sets out general conditions, subsequent measures agreed
by Contracting Parties have tightened the regime as regards disposal at sea. In particular,
Decision / contains a virtual prohibition of disposal for all installations with a limited and
small number of exceptions including large concrete structures. Any proposal for disposal
at sea (including leaving in place is subject to an extensive international consultation exercise, but with the final decision resting with the national competent authority (taking into
account the views of other Contracting States).

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area

Decommissioning alternatives
In the specific case of the OSPAR region, while the regulation allows for disposal at sea as a
decommissioning option, the option only relates to the concrete substructure. Topsides need
to be removed to land unless there are exceptional or unforeseen circumstances or where the
topside support structure is an integral part of the sub-structure. is is frequently the case
for concrete gravity structures.
Any recommendation to dispose of a concrete substructure at sea needs to be supported by
a detailed comparative assessment of the disposal options. e following sections set out the
main issues that need to be considered in determining the best disposal option for a concrete
substructure.
5.1
Removal
As explained in Section ., the first generation of offshore concrete gravity platforms
installed in the seventies were not designed or constructed for a future removal operation.
Later concrete platforms were designed with removal in mind, but the extent of the challenges and possible obstacles and hazards that might occur may not always have been fully
appreciated in the original design. Hence, the uncertainties identified in the first generation
concrete platforms may also be valid for the second-generation concrete substructures.
5.1.1
Removal method
For large concrete gravity platforms, the most likely removal method will, in essence, be to
reverse the method of installation. However, there are a number of issues that the installation
operation did not need to consider but that would require consideration upon removal.
All concrete platforms located in the North Sea today have been installed by controlling the
level of water ballast within the concrete substructure. When on location, a careful increase
of the water level allowed safe and accurate positioning of the platform. An adjustment of
the relative water levels in the cells of the caisson allowed an on-bottom correction to achieve
a true vertical position of the platform. On most of the structures significant amounts of
cement grout were injected under the base slab of the platforms to ensure a uniform distribution of loads on to the seabed.
In principle, a reverse installation could also minimise the offshore work by allowing removal
of all the topside facilities to shore. ese can then be removed in a sheltered location where
the weather conditions allow a more efficient execution of work.
However, studies have shown that weight increases during the operating phase may require
a significant amount of the topside loads to be removed before engaging in a re-float operation. is is because limited buoyancy may be available to lift the structure from the seabed.
A weight uncertainty also arises due sand produced from the reservoir trapped in the storage
cells, the possible adherence of under-base grout and soil, marine growth and the absorption
of water in the cement matrix. e exact weight of the topsides may also add to the uncertainties as considerable amount of equipment have been added during an operational life
often more than  years. To secure an adequate weight tolerance for the re-float operation, a
number of offshore lifts may thus be required prior to removal in order to reduce the overall
weight.
All piping penetrations through the concrete hull below water level have to be closed to
ensure a watertight structure. Any excessive leaks will jeopardise the platform’s ability to
remain afloat in all phases until it is safely located in a dry dock for final deconstruction. is
period could last for up to three years after initial removal.
Essential equipment required during the re-float phase will be the water ballast systems
and pipe connections inside the concrete substructures. Originally, these systems ensured a
©  OGP

International Association of Oil & Gas Producers
gradual filling of water ballast to ensure a controlled touchdown on the seabed. On the first
generation of platforms, these ballast systems where typically only designed as installation
aids and not maintained or grouted up after the structure was in place.
On some structures it will be necessary to inject water under the base slab to mobilise additional upward force to be able to pull the base skirts out of the subsoil. is water injection
has to be carefully monitored in parallel with the water de-ballasting during the re-float
operations.
For safety reasons it is preferred that the re-float operations are performed with no personnel
on the platform.
e towing route to shore will have to be carefully evaluated to ensure sufficient draught
during the towing operation. Some structures may have such deep draughts that the inshore
sheltered areas that they can enter may be limited.
5.1.2
Technical uncertainties
Each of the platform designs described in Section  has its own features depending on the
service for which they were intended. e feasibility of a removal operation will depend on
clarification of a number of uncertainties that will exist, even if the concrete platform was
initially designed with future removal in mind.
Studies recently undertaken have identified the following main common uncertainties and
difficulties related to the removal of concrete gravity base structures. ese are:
• Sealing and testing of penetrations
• Structural integrity in re-float phase
• Under-base grout
• Sudden uncontrolled release
• Under base injection
• Mechanical systems
Sealing and testing of penetrations
Sealing of penetrations and cracks in the concrete substructures are seen as major concerns.
e problems include limited or no access to penetrations and cracks, inability to test a sealed
penetration, difficulties in detecting and sealing cracks etc. Conductor penetrations in drill
shafts may be particularly difficult to address. Although cracks may have been sealed during
the operational phase of the installation, these may re-open and cause leaks during re-floatation and towing operation as the loads change.
Structural integrity in re-float phase
During the re-float operations the concrete platform may need to be de-ballasted to a greater
extent than during the installation. Additional uplift forces to overcome friction and suction in the seabed may be required. It may also be difficult to empty one cell or buoyancy
compartment during de-ballasting. is will require additional de-ballasting in the remaining compartments to compensate for the non-emptied cell(s). is, in turn, may give high
differential pressures in the compartments, that may lead to total collapse if the structural
strength is exceeded.
A preventive measure would be to introduce compressed air into the cells. is would assist
in maintaining the overall structural integrity and mitigate the stresses in certain structural
elements. However, this must be carefully evaluated as it may introduce a risk of overstressing vital structural parts. An excessive “pop-up” to a level where the air pressure exceeds the

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
ambient water pressure could introduce severe structural consequences, as well as being a
hazard to personnel and vessels involved in the re-float operation.
An excessive differential loading between the cells may cause collapse of internal walls on
some types of structures. is concern is also applicable if the platform experiences excessive
tilt during the re-float phase.
As each individual concrete structure has its own characteristics, a thorough structural
analysis checking all applicable load cases will be required to eliminate these uncertainties.
e current applicability of the codes used in the original design and any experience gained,
have to be duly considered. Over the last  years, the design codes have introduced more
stringent structural strength requirements. All structural analysis for removal operations
should therefore be based on conservative assumptions reflecting any deterioration and any
uncertainties that affect the design. e safety factor should not be lower than specified in
current design codes for construction, installations and operations.
is structural check will also be necessary for second-generation concrete platforms having
re-float as a load condition in the original design. Allowance must be made for designs that
did not fully recognise the challenges and possible obstacles that might occur during a refloat operations; often taking place over  years after installation.
Under base grout
On some platforms, grout was injected under the slab to ensure a uniform soil pressure
after installation. Also, during completion of the production wells, grout was injected and
is expected to have been spread underneath and become attached to the slab. Prior to a refloatation there is no method available to assess the amount of grout under the base slab, or
whether or not the grout will remain attached to the base.
If a re-floatation is carried out and a large amount of grout is attached to the underside,
inshore deconstruction is not advisable, since there is no method to remove the grouting from
the underside within an acceptable risk. Both mechanical equipment and explosives have
been evaluated for use in detaching the grout. However, it should be noted that use of such
methods might cause a sudden release of a large amount of grout and cause instability of the
substructure causing it to sink.
Sudden uncontrolled release
After release from the seabed, the concrete platform could have unbalanced buoyancy that
could cause an uncontrolled release from the seabed. Uncertainties in platform weight and
centre of gravity, soil resistance, under base grout lost before, during or after re-float, and
possible soil suction may contribute to unbalanced buoyancy. Some platforms have an accumulation of drill cuttings inside the concrete shafts. Deposits of produced sand in the storage
compartments also add to the uncertainty in knowing the exact weight of the structure. is
could lead to an unpredicted instability and pitching of the structure after being released
from the seabed.
Under base injection
Injection of water under the base slab will require certain strength in the upper soil layers
under the platform. Exceeding this threshold will result in failure of the soil, causing channelling or “piping” thus allowing water to escape preventing a pressure build-up under the
base. Placing gravel around the base of the substructure could in some instances reduce the
risk for developing channelling in the soil.
©  OGP

International Association of Oil & Gas Producers
Mechanical systems
e de-ballasting operations as well as any under base water injection will require mechanical systems that are proven to be fully reliable in all functions and operations. e original
systems are very likely to have deteriorated after many years in seawater unless they have
been properly maintained and tested during the in-service life of the platform. Demanding
requirements on the durability and reliability of the system were not fully accounted for
during the design, as they would stay idle for decades prior to use, without the opportunity
to test the system. e original carbon steel piping may, therefore, have to be changed before
the system can be used. Part of the piping embedded in concrete may have to be flushed
and smaller diameter, flexible or expanding piping inserted into the old and deteriorated
pipelines. Prior to the operations, any parts used for removal must be thoroughly inspected,
tested and commissioned. However, it may often be difficult to inspect or even impossible to
replace these systems.
e only alternative is then to install an external ballast piping system linking each buoyancy
compartment together that would be located outside the concrete substructure. is will
involve additional risks with extensive use of divers. A new buoyancy system would require
penetrations to be made in the storage tanks that would introduce potential new points of
leakage.
An external system would also be exposed to dropped objects and impact from collision with
support vessels. Such operations have not been executed before and could add a considerable
cost to the project. Methods and procedures need to be developed and tested inshore before a
conclusion can be drawn on their feasibility. It is also questionable if such solutions will give
the required reliability needed to launch a re-float operation within the acceptance criteria.
Case-by-case evaluation
Finally, it is important to note that each platform will have its own and unique problems (for
example weight increases, stability, cracks, structural strength, high probability of leakage
etc), and that each platform therefore should be considered on a “case by case” basis. Only indepth studies for each installation can conclude whether its re-floatation is possible or not.
Appropriate risk analysis is a tool that can be used to establish the risk level compared to the
acceptance criteria set for similar offshore operations.
5.1.3
Towing
A towing operation to a sheltered inshore location needs to be considered before a full
removal is considered acceptable.
e major differences between an installation tow and a removal tow are related to the risk
of:
• Grout attached to the underside of the base slab can fall of and hit a live pipeline;
• Grout falling resulting in instability of the platform and causing it to sink;
• Major leakage may occur in sealed penetrations and cracks, causing the platform to sink
during an offshore or an inshore phase of the towing route (it could hit an offshore live
pipeline, block the entrance to a harbour etc).
Towing points on the concrete platform also need to be thoroughly inspected and tested and,
if necessary, replaced before a re-floatation and towing operation is attempted.

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
5.1.4
Inshore/onshore deconstruction
e inshore and onshore deconstruction phase for a typical concrete substructure is estimated to take two to four years. erefore, the concrete substructure needs to be kept floating for at least two to three years. e concerns for the inshore deconstruction phase are
basically the same as for the re-floatation/ towing operation, however, there are differences,
as described below.
Detachment of grout from the underside of the base slab while the floating substructure is
being cut into small pieces represents an unsafe working site for personnel. Sudden loss of
grout is likely to cause instability of the substructure resulting in a tilt, and in a worst case
scenario, the sinking of the substructure.
If uncontrollable leaks arise due to failure of previously sealed penetrations, in-service deterioration of the piping system and structure, or unpredictable loss of grout and soil from the
underside of the base slab, it could have catastrophic consequences resulting in loss of life.
If the structure sinks at an inshore location the environmental consequences may be more
severe than if it occurs at an offshore location. e increased consequences include the
assumption that more fuel will be required onboard the structure to keep the temporary
buoyancy system and other temporary systems running required for the deconstruction
work, and that the distance from the installation to shore will be only a few hundred metres.
On the other hand, it is assumed that any inshore releases can be managed more effectively
by use of pumps etc.
Concrete substructures that have been used for oil storage would be require cleaning to
remove any free oil that could be released prior to its onshore disposal and possibly before any
re-float operation is carried out. Of particular concern are the storage cells of the platforms
where no access is possible except via a piping system. Concrete is a semi permeable material
and it should be assumed that oil has penetrated into the pores of the concrete walls. e
extent of oil contamination of the concrete walls inside the storage cells is, however, considered to be relative small as the concrete material is normally very dense. Furthermore, a
layer of wax is likely to be deposited on the concrete walls, limiting the oil penetration into
the wall. It may be very difficult to remove the oil contained in the concrete pores by water
flushing, steam cleaning or other cleaning methods. us the reuse potential of this concrete
material may be limited to for example for use as road hardcore or landfill.
5.1.5
Reuse at another location
If a concrete platform can be safely removed from its present location within the acceptance
criteria set, a reuse at another location would then be evaluated. However, a number of criteria have to be fulfilled at its new location such as: satisfactory soil condition, water depth,
environmental conditions, fulfilling current design codes and level of safety.
Reuse of the concrete substructure as, for example bridge foundation or quay support, could
be a practical solution compared to an expensive deconstruction work. Each platform would
have to be assessed for the particular re-use opportunities that may present themselves.
©  OGP

International Association of Oil & Gas Producers
5.2 Removal for deep water disposal
5.2.1 Removal method
e activities in this alternative are essentially the same as those discussed in Section .
“Removal”. e main difference is that for this alternative the complete topsides (including the main support frame) would need to be removed before the re-float of the concrete
substructure takes place. Alternatively, the topsides could be removed when the structure
is afloat at an inshore sheltered area, and then the concrete substructure could be towed to
an approved deep-water site for disposal. As much of the internal and external steelwork as
practicable is likely to be removed for reuse or recycling onshore.
Following the re-float operation, the concrete substructure will be towed to an approved
deep-water location. By taking water out of the cells and then submerging the substructure
by pumping water into the columns an “implosion” could occur, which would effectively
demolish the concrete. For some concrete substructures this method would not be possible
due to the design features. In those cases it is likely that the complete substructure would hit
the seabed and be severely deformed and disintegrate.
5.2.2 Technical uncertainties
e technical uncertainties in the re-float stage are essentially those valid for the removal and
onshore disposal alternative described in Section ...
5.2.3 Towing operation
e risks associated with the towing operation are the similar to those for towing to an
inshore location. However, the towing route to a deepwater location for disposal may be
substantially longer than for removal to land and the weather conditions encountered might
be more severe. us the length of good weather periods may be critical.
5.3 Partial removal
Partial removal of a concrete substructure represents a removal of parts of the substructure to
such an extent that it fulfils the Guidelines given by the International Maritime Organization
(IMO), namely to leave a free water column of  metres above the remaining structure for
safety of navigation (see also Section ).
5.3.1 Removal method
Mechanical Means
is option presupposes that all the topsides and the external/internal steel works are
removed and taken to shore for recycling or deconstruction before the deconstruction of the
concrete part commences. Offshore deconstruction alternative entails cutting the concrete
substructure into pieces at the offshore location. e concrete pieces are likely to be left next
to the remaining substructure. Alternatively they may be lifted on to a vessel and transported
to shore for recycling or deconstruction.
e internal steel outfitting in the shafts would be removed in reverse installation order to
the greatest extent possible. However, it may not be possible to remove some of the outfitting
before the concrete structure has been deconstructed down to the level of the actual outfitting. e only controlled method of cutting reinforced concrete is by using cutting tools such
as diamond wire or saws controlled by divers. Use of explosives has been evaluated, but studies concluded that it could not be the preferred option as it is not possible to guarantee that
present methods will successfully cut the heavily reinforced, pre-stressed structure at the first

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
attempt. e environmental consequences (noise and possible disturbance of fish and marine
mammals) may also be reasons for not using explosives.
Mechanical cutting the concrete shafts could either be done from inside a dry shaft or from
the outside. An external cofferdam would be required if making the cuts from the inside to
prevent ingress of water. Personnel would be required to operate the cutting machinery inside
the shaft.
For the concrete substructures of column and caisson types, the shafts can be cut to obtain
the required depth. However, if the top of the caisson reaches into the >-metre zone, parts
of the caisson would have to be removed. is would represent extensive additional underwater work.
For concrete substructures with no shafts, the preferred cutting method would be to cut the
substructure down to - metres, piece by piece, either lifting away each piece or toppling
them outwards. e actual cutting operations would require extensive underwater works that
ideally should be performed by remotely operated means. However, extensive use of divers in
various operations would almost certainly be required.
Initiating structural collapse
is option pre-supposes the use of explosives to initiate structural collapse of the concrete
structure. e explosives may be placed on the outer surface and/or the inner surface of the
structure.
e platform is expected to remain as a “pulverised” heap of concrete and reinforcement on
the seabed, and may represent a hazard for bottom trawls. To make the site over-trawlable,
the remains of the structure may be re-distributed on the seabed and/or rock may be dumped
to cover the remnant structure. Rock dumping may also reduce minor leaching of hydrocarbons to the water column (from residuals attached to the structure and any accumulated
drill cuttings).
All possible precautions would have to be taken to limit the effect that the explosives would
have on fish and other sea mammals present in the area. e time of the year selected for the
operation, the type of explosives and the position of the explosives on the structure etc, will
be important to limit the effect on the marine environment. However, despite all precautions taken, it is inevitable that some fish would be killed within a few hundred metres of
the explosion.
5.3.2 Technical uncertainties
e various methods proposed for cutting the concrete substructures down to - metres are
considered to be theoretically feasible although there are a number of critical operations that
would need to be proven. No experience exists today of cutting such heavily reinforced prestressed concrete structural members under water. e traditional tools used on land such as
diamond wire or saw have not been exposed to underwater conditions such as the North Sea.
Studies have revealed that prior to launching any offshore works, extensive development and
testing of equipment will be required to prove its practical feasibility and efficiency.
Diamond wire tool
e most likely cutting technique is a diamond wire tool. Different contractors have
advanced this as a feasible method. However, the tool will need to be fabricated and tested
before a clear conclusion can be drawn on the capability of such a tool to cut reinforced concrete under compression.
In the past there have been difficulties with the diamond wire tool, especially if the material
to be cut is a “composite” material and under compression. Most of the load-bearing sections
©  OGP

International Association of Oil & Gas Producers
in any concrete substructure, including the concrete shafts, consist of high strength concrete
with an inner and outer dense layer of steel reinforcement and pre-stressing tendons in steel
ducts. e pre-stressing tendons ensure that the concrete section remains in compression at
extreme wave loads to avoid cracking in the concrete.
e pre-stressing tendons were installed in purpose-built ducts in the shafts, tensioned and
bonded to the structure by injection of grout in the annulus between the tendons and the
duct walls. If the bonding between the cable and the grout is not properly performed, an
enormous amount of energy could be released when the pre-stressing tendons are cut. e
effect on the concrete of such a release of energy is not fully understood.
Another problem, which has been experienced in the past, is controlling the tension in the
diamond wire. Any over-tensioning will cause the diamond wire to break. Excess transverse feed velocity of the wire or the presence of vibrations in the tool/ wire could result in
over-tensioning the wire. If the wire breaks during the final cuts, the wire has to be cut and
abandoned, since the gap created by the wire will close due to shear leg effects or effect of the
tension wires. us, a new cut has to start above or below the previous cut.
Weaknesses have also been revealed in some of the diamond wire types making them unsuitable for cutting steel material.
Diamond saw tool
A diamond cutting saw is more likely to be used when access is restricted to only one face of
the concrete section to be cut. Studies have shown that the diameter of a diamond saw could
reach . metres to be able to cut structural elements with thickness  to  cm.
is cutting tool would require heavy support to be fixed to the concrete surface to guide the
cutting tool in a controlled manner. Jamming of the diamond saw is also very likely for the
same reason as described for the diamond wire tools.
Explosives
e ability of explosives to cut thick (up to one metre) concrete walls effectively underwater
with substantial amounts of pre-stressing and reinforcing steel is not well proven and involves
many uncertainties. e firing of explosive charges to topple the structures is a “point of no
return” and is likely to result in an unplanned situation from which it may be impossible or
extremely difficult and dangerous to recover.
Explosives may, however, be used to make the final cut to enable the toppling or bending of
a cut section outwards to reach the - metre requirement.
Structural stability
For the non-shaft concrete substructures, the cutting operation of structural members will
weaken the structural integrity gradually. By removing structural members the ability to
withstand wave forces will be reduced. If it is not possible to complete the work in one
summer season, it is very likely that the winter storms will deteriorate the structural strength
further; to such an extent that it will be hazardous to send divers back to resume the work
the following summer. e storage tanks will also be problematic to deconstruct, since there
are no practical methods to divide the structure into smaller parts underwater.
e other concern with this disposal option is the stability of the section for the period after
the final cuts are made until a heavy lift vessel lifts off the section.
e cuts have to be planned and performed in such a way, as to maintain the stability of the
section as long as possible. us, three or four sections of the circumference of the legs have
to remain intact until a sufficient weather window is forecasted. Holes therefore have to be

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
pre-drilled into the concrete walls by divers or remote operated vehicle (ROV) to be able to
insert the diamond wire cutting tool and perform the cuts of the sections.
As mentioned above, the critical period will be when making the final cuts. If the cutting tool
fails during these final cuts the cut section may be lost if the weather worsens.
5.4
Leave in place
e leave-in-place alternative presupposes that the topsides are removed and taken to shore
for disposal and if considered a hazard, external steelwork would also be removed to shore.
5.4.1
Work to be done
e modules and support frames, forming the topsides, would be removed first. Before
removing the deck, the accessible steelwork inside the platform would be removed as far as
practicable.
On some concrete substructures the support frame consists of concrete beams, often forming
part of the main structure. In such cases it is likely that these structural parts would remain
with the concrete substructure.
Flushing and cleaning of any oil storage tanks would be performed to reduce the content
of hydrocarbon and other residuals to a minimum. e internal walls in the storage tanks
would not be exposed to the sea outside, but would remain protected inside the storage
tanks for natural degradation to take place as the concrete structure slowly deteriorates.
Environmental impact assessments are required to demonstrate that any impacts arising are
within acceptable limits.
e necessary navigation aids would be installed on the substructure in accordance with
applicable national and international requirements. e navigation system would be designed
in an easily maintained package with back-up systems (for example by means of a helicopter
but not dependent on a helicopter deck). A programme for maintaining a reliable navigation
system would be designed, agreed with the competent authorities and introduced.
Debris around the concrete substructure would be recovered, where practicable and brought
to shore.
5.4.2 Technical uncertainties
Removal of topsides would include known technical operations, but could still be very challenging requiring detailed planning and control to prevent major unforeseen events.
e hydrocarbon and other residues left in the storage cells of the concrete substructures
present an additional challenge. e design allows the cells to be flushed through a complex pipe work system, but on some platforms, this system provides the only access into the
cells. Rigorous inspection and conventional cleaning methods by scraping or through use
of solvents are either not feasible or environmentally unattractive. Both alternative access
and cleaning techniques would need to be developed or a thorough assessment performed
to demonstrate the acceptability of any potential impacts to the environment by the gradual
release and natural degradation process as the structure slowly deteriorates. See also Section
.
©  OGP

International Association of Oil & Gas Producers

Safety
Health and safety of the workforce is crucial in any decommissioning work of offshore installations. e level of safety should be the same as during installation and operations and work
should be carried out in accordance with the principle that the risk for the workforce should
be as low as is reasonably practicable.
ere is very little experience of managing hazards and risks associated with offshore (and
onshore) decommissioning of gravity concrete structures. In each of the three large-scale
removal operations of steel structures conducted in the North Sea, there has been a fatality.
ese incidents all occurred when the structures were being dismantled in shore or on land.
Nonetheless it is clear that the risks to personnel both in the conduct established operations
and arising from the substantial technical and environmental uncertainties (for example cutting, use of divers, lifting, towing) are significant and must be a major factor in defining the
best ‘disposal’ alternative for an individual installation.
To place the importance of safety in a ‘Regulatory Context’, the UK Health and Safety
Executive indicates that the risk of fatality for an individual shall not be greater than ×-
per year ( in ) and shall be as low as reasonable practicable. In practice a personnel
risk level considerably lower than this will be sought for in all decommissioning activities in
accordance with the principle that risks shall be as low as reasonably practicable.
Refloat for onshore disposal
ere is no experience to date in relation to removal and onshore disposal of concrete platforms. Evaluations made in the planning of the Ekofisk  Disposal [] and the Frigg Field
Cessation Plan show that there is a significant risk to personnel in removing the concrete
substructures, even though personnel may not be on the structure during the re-float.
If a serious problem developed during the refloat or towing, it would be necessary to undertake remedial works to remove the substructure in a damaged condition. e predicted
fatalities in that situation could be considerably higher than predicted for a straightforward
refloat operation.
Additional risks are introduced if the complete topsides are removed offshore prior to the
refloat operation. is risk may be less if the topsides are lifted off in an inshore sheltered
area. However, that reduced risk would be offset by an increased risk of having personnel
dismantle the concrete substructure whilst floating and dependent on the continued integrity
of the ballasting systems for the extended deconstruction period and the handling of material
to shore.

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
Deepwater disposal
During the tow out to the deep-water location it is assumed that no personnel would be
onboard the platform. Preparations for sinking the concrete substructure are likely to be
made with people located on a nearby vessel. However, it may be necessary to put people on
board in the event of a failure of the mechanical systems initiating the sinking process. A
deep-water disposal of a concrete substructure would eliminate high risk to personnel during
inshore and onshore deconstruction phases.
Cutting down to -55 metres
Studies have shown that cutting the concrete shafts is likely to involve high risk to personnel. Even though much of the underwater work can be done by remotely operated vehicles
(ROV), extensive use of divers must be assumed. Diver interventions are likely to be required
to reduce the down time. Mechanical failures may require the work to be stopped and the
equipment brought up to the supporting vessel for repair.
If any unplanned events take place requiring additional works to meet the --metre requirement, the risk to personnel would obviously increase.
Leave in place
e topside removal phase will present certain risks where limited experience is available. e
installation of the deck structure with modules was often done by means of a “deck-mating”
with limited offshore lifts. Offshore removal cannot be achieved by reversing this process.
Removal of exterior steelwork will also expose personnel to risk although remote techniques
will be preferred. e impact of cleaning and inspection will need to be addressed as techniques are developed. Ongoing monitoring and maintenance of navigation aids will also
need consideration.
©  OGP

International Association of Oil & Gas Producers

Environmetal impact
Concrete and steel are not intrinsically polluting. With the exception of residual hydrocarbons leaking to the environment, the impacts of decommissioning large concrete gravity
structures both at the site of oil and gas production and inshore at dismantling locations will
largely relate to physical disturbance, and interference with amenities and other users of the
sea.
7.1
Re-float for onshore disposal
e environmental impact of the removal with onshore disposal will be most dominant
during the inshore and onshore deconstruction. e onshore deconstruction of the huge concrete substructure will cause aesthetic impacts such as visual effects, noise, smell and dust.
Noise is considered the most dominant factor. e sources of noise could be:
• Chipping of concrete with a hydraulic chisel hammer
• Crushing of concrete in a crushing mill
• Drilling and blasting concrete
• Noise from cranes and diesel engines
During the rather long period the concrete substructures may have to remain afloat during
deconstruction (two to three years), there will be a risk that the substructure could sink at
its inshore location. ere is a high probability of not being able to re-float the substructure
subsequently.
Environmental studies have shown that unlike steel structures, the significant energy consumption (and consequent discharges of CO2 required to bring ashore and the recover of
the steel embedded within offshore concrete substructures, generally exceeds the energy
consumption and discharges required to replace that steel using iron ore.
7.2
Deepwater disposal
Disposal of the concrete substructures in deep water may cause minor environmental impact
due to leakage of oil from temporary tanks used for pumps necessary to control the buoyancy
of the structure during re-float, towing and sinking operations.
If the concrete substructure has been used for oil storage, residual sludge and other deposits
inside the storage tanks may have some local environmental impact at the disposal site. Even
though extensive flushing/ cleaning of the storage tanks will have been performed prior to
the re-float operation and tow to the deep water site, residual sludge and other deposits with
a high wax content will remain inside the tanks.
During the sinking process, it is likely that the platform will be more or less pulverised or
severely deformed due to overpressure and impact when it hits the sea bottom. e surfaces of
the inner storage tanks will immediately be exposed to seawater. However, since the residuals
are assumed to be relatively immobile (due to high wax content) and will be contained in
pores in the inner walls of the storage tanks, a very slow leaching of hydrocarbons from the
surfaces to the seawater is anticipated.
A seabed inspection and environmental survey will normally be performed prior to leaving
the deep-water site.
Deep-water disposal will eliminate major environmental impacts onshore during the deconstruction phase.

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
7.3
Cutting to -55 metres
is alternative may expose the oil storage tanks to the open sea if their distance below the
sea surface is less than  metres. Otherwise, the environmental impact would be the same as
described below for the leave-in-place option.
7.4
Leave in place
Long-term impact on the marine environment from any contents of the concrete substructure left in place for natural decay should be included in the environmental impact assessment. In those cases where concentrations exceed agreed thresholds, preparation for disposal
should include measures to remove them or to reduce the quantities of these contaminants
to an acceptable level.
Flushing and cleaning of concrete substructures used for the storage of crude oil may be
required to reduce the content of hydrocarbon and other contaminants to an acceptable level.
Residual quantities of oil will remain adhered to the internal walls of the concrete storage
tanks and will not be exposed to the sea until the structure eventually breaks up.
Leaving a concrete substructure in place may limit the fishing activity in the vicinity of
the substructure. If debris in the area around the substructure is recovered, the chances of
snagging fishing gear should be considerably reduced. Removal of external steelwork on the
substructure will reduce debris littering the nearby seabed in future.
7.5
Long-term fate of concrete structures
Ultimately all the components and contents of a concrete substructure dumped at sea, partially removed or left in place will corrode, decay, disintegrate and collapse onto the seabed.
Studies on long-term stability [] have considered the long-term effects of seawater and pressure on concrete and concrete strength. Other aspects considered have been the mechanisms
associated with corrosion of reinforcement and bacterial attack in compartments where
hydrocarbons are stored. e overall conclusion of these studies is that concrete is a very
durable material where changes are measured in hundreds of years.
Initially concrete cover in the splash zone (the sea surface open to the action of wave erosion)
is likely to break away from the reinforcement after  years, but the remaining strength will
support the legs for several hundred years more until leg collapse is assumed to occur after
 to  years. e base cells could remain largely intact unless breached by falling debris
over  years and taking considerably longer to substantially disintegrate.
Once surface navigation aids can no longer be maintained, other electronic or physical
means of marking the remains would need to be considered.
©  OGP

International Association of Oil & Gas Producers

Monitoring
Concrete substructures left in place will be equipped with navigation systems that fulfil both
national requirements as well as the International Maritime Organization requirements to
secure safe navigation for users of the sea. e navigation aids will be designed to ensure a
high level of reliability. ey will incorporate back-up systems should be serviced at regular
intervals.
To assist fishermen, some operators may introduce the position of the concrete substructure
into the “Fish SAFE” programme, presently in operation in the UK.
Regular surveillance would be carried out to check that the navigation aids are operational.
It is envisaged that the navigation aids will be designed in such a way as to allow them to be
changed out from a helicopter, thus obviating the need to man the platform for this purpose.
e responsibility for the maintenance of the navigation aids remains with the owners, unless
otherwise agreed with the authorities.
During the regular surveillance of the navigation aids it would be appropriate to make a
visual inspection of the general condition of the concrete substructure visible above the
water surface. Any unexpected deterioration should be evaluated to check if it represents any
hazard to the users of the sea.
For structures dumped at sea, occasional monitoring may be required to confirm the location
and condition of the structure on the seabed.

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area

Liability
e owners of installations at the time of decommissioning will normally continue to be the
owners of any residues, unless otherwise agreed with the authorities. e owners (in most
cases the licensees to a production licence) will be jointly and severally liable for damage
caused wilfully or inadvertently in connection with a disused facility left in place.
Any claims for compensation by third parties arising from damage caused by any remains
will be a matter for the owners and the affected parties and will be governed by the general
law.
Given the long term over which concrete structures are likely to persist in the marine environment after decommissioning, there are unresolved considerations concerning liability
that require resolution.
©  OGP

International Association of Oil & Gas Producers

Cost
e cost of bringing a concrete substructure to shore for reuse represents a considerable proportion of the total cost of decommissioning. is needs to be considered in an economic
evaluation considering the benefit to society of reusing the substructures, for example as
bridge foundations. Significant economic risks would arise during a re-float operation due to
the uncertainties involved. is is particularly the case for the first generation concrete installations that were not designed for removal, but could be valid also for the second generation
platforms as the challenges of full removal were not properly understood during the design.
e cost of cleaning up the seabed after structural failure of the installation, during re-float
or towing is likely to be extremely high.
More than half of the cost of a decommissioning event may be expended before obtaining
sufficient confidence that a successful re-float can be performed within the set acceptance
criteria. is will also be reflected in the cost for deepwater disposal, even when the cost of
deconstruction inshore is not incurred.
ere will also be cost associated with installation and maintenance of navigational aids if a
structure is left in place.
e cost associated with leaving a concrete substructure in place will be related to cleaning
of the facilities of hydrocarbons if the substructure has been used for oil storage. External
steelwork attached to the concrete structure is likely to be removed.
e cost estimates presented for the Ekofisk Tank and the three concrete substructures on
the Frigg Field predict significant cost levels for removal and onshore deconstruction of concrete substructures. ey vary from about  MNOK or m to  MNOK or m
(assuming an exchange rate of . NOK per ) depending on the type of installation in
question. e cost of removing the topside facilities including the support frame, either offshore or inshore is an additional cost.

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area

Decommissioning experience and
future plans
11.1 Recent work on disposal of concrete platforms
A number of studies has been undertaken place since  when OSPAR Decision / was
introduced. Extensive studies have investigated the feasibility of removing concrete gravity
based substructures. e Cessation Plans for the Ekofisk I (operated by Phillips Petroleum
Company Norway in Stavanger) and the Frigg Field (operated by TotalFinaElf Exploration
Norge AS, in Stavanger), where there are respectively one and four concrete substructures,
have both been subject to detailed assessments in accordance to the framework given in
Annex  of OSPAR Decision /.
Further information about these two cessation plans with comprehensive reference
lists of performed studies can be found on the following web sites:
• Ekofisk  Cessation:
http://www.phillips66.no/cessation
������
• Frigg Field Cessation: http://www.totalfinaelf.no/cessation
ese concrete substructures represent typical offshore concrete
gravity platforms in operation in the North Sea today. e
results of these in-depth studies have identified key
problem areas related to each of the above-mentioned
platforms, and have provided valuable input to this
report.
�����
�������
��
e two fields are located as follows
On the Norwegian Continental Shelf
Ekofisk Tank GBS, located on the Ekofisk Field [3],[4]
Frigg/TCP2, located on Frigg Field [5]
On the UK Continental Shelf
Frigg/CDP1, located on Frigg Field [5]
Frigg/TC1, located on Frigg Field [5]
As a result of their studies, the two operators of the four disused concrete platforms have
on behalf of the owners submitted a recommendation to the competent national authorities to leave the substructures in place. Norway has performed the consultation process
requested by OSPAR regarding leaving in place the Ekofisk Tank GBS with its protective
barrier. OSPAR Contracting Parties did not raise any significant objection. e Norwegian
Storting (Parliament) has given the final approval for leaving in place the Ekofisk Tank with
its Protective Barrier. e three concrete substructures on the Frigg Field are at present under
consideration by the Norwegian and UK authorities.
©  OGP

International Association of Oil & Gas Producers
Another important source of knowledge has been obtained through a number generic studies. e most recent include:
In Norway
Summary report for Phase I and II: “Removal of Offshore Concrete Structures”, rev. , dated
.., Dr. tech. Olav Olsen, Oslo [].
In UK
Joint Industry Project: UKCS Decommissioning Study”, report No. -ER, dated 
January , W.S. Atkins, Aberdeen [].
e Dr Tech. Olav Olsen study looks at re-floatation and onshore deconstruction of specific
concrete installations. e WS Atkins study looks at different disposal options such as leave
in-place, partial removal etc., including safety, environmental and technical issues related to
the different options.
11.2 Future decommissioning plans
It is difficult to predict the exact time when an offshore installation will be decommissioned.
e main uncertainties are often the reservoir behaviour towards the end of production, as
well as the oil and gas price. An alternative use for the platform could also prolong its operational lifetime. At the time of preparation of this report, it expect that the major phase of
decommissioning will take place between  and , but some structures are designed
for operation until at least  (see Appendix ).

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area

Public consultation
e decommissioning of offshore oil and gas platforms, including gravity based concrete
structures, is controlled by a regulatory process set out by the relevant national Governments
having offshore activities in the OSPAR Maritime Area. For example the requirements for
public consultations in Norway and UK have subtle differences but many of the key principles are common (see references [], [] and []).
Part of this regulatory process includes the statutory consultation of various parties for
their views on the recommended disposal option. It has also become industry practice to go
beyond what is required by regulation. A much broader range of interested parties is invited
to comment at an early stage when disposal options are being developed. e stakeholders’
views are sought on issues raised and on how the assessment is conducted.
e industry has seen the importance of an open, transparent and inclusive decision-making
process since the Brent Spar incident in . All recent large-scale platform decommissioning now follow the pattern where technical options are developed in parallel with a dialogue
and consultation process with a wide group of stakeholders.
During the process of establishing a recommended disposal option for both the Ekofisk Tank
and the Frigg concrete platforms, an extensive communication strategy towards the various
stakeholder groups was adopted. e principle was to invite the stakeholder participation at
an early stage of the process.
After having identified the stakeholders with an interest in the decommissioning process,
they were asked to comment on development of scope of work and raise any issues or concerns they would wish to see addressed. A number of additional studies were initiated as
a result of constructive proposals received, which are now part of the respective Cessation
Plans presented to the Authorities.
Up to two or three years may pass before a recommendation for disposal can be presented
and the stakeholders should be kept engaged and informed throughout this phase. A variety
of tools to communicate and involve interested parties may be used including meetings, letters, websites, telephone calls, information bulletins, interactive events and presentations.
Offshore trips may be organised to allow the stakeholders to obtain an impression magnitude
of the structures and the challenges in decommissioning an offshore installation.
e commitment to keep in close contact with the Stakeholder groups does
not stop when a Cessation Plan has been
submitted to the authorities. e intentions should be to keep the stakeholders
informed about the progress until the
approved decommissioning programme
is completed.
Figure . illustrates that practice for
public consultation adopted for the first
four decommissioned concrete installations in the OSPAR Maritime Area.
������� ������������
�� ��� ��������
�������� �����
������������ �� �����
�� ��� ��� ���
���������� ��������
���� ������������
�������� ��
�������� ������
When a recommended disposal option
has emerged, further contact with the
stakeholders should be made explaining
the reason behind the recommendation.
������������ ��
�����������
�������� ������
�� �� � �� � �����
����������� �� ���
���������������
����
Figure 12.1: Principles adopted for recent Public Consultation of
Concrete Gravity Platforms in the North Sea
©  OGP

International Association of Oil & Gas Producers

Conclusions
In the period  to , detailed consideration has been given to the decommissioning
of large concrete gravity based platforms in the North Sea. ese considerations have drawn
extensively upon the numerous studies as well as evaluations undertaken as part of the decommissioning projects for the Ekofisk  and the Frigg Field. ese studies have indicated:
• Each concrete gravity platform is unique and, as such, decommissioning of concrete
gravity platforms needs to be considered strictly on a case-by-case basis. Individual
concrete substructures have their own particular history and design features, and will
require specific studies to investigate the issues and risks associated with the different
decommissioning alternatives.
• e first generation of offshore concrete gravity platforms installed in the s were not
designed or constructed for future removal operations. Although provisions for removal
were included in the design of later concrete platforms, it appears that these may not be
fully effective because the obstacles and hazards were not fully recognised. Hence, the
uncertainties identified in first generation concrete platforms may also be applicable to
the second-generation platforms.
• Uncertainties associated with decommissioning include: structural integrity of the
concrete installation when it is released from the seabed; weight and buoyancy of the
re-floated structures; safety and issues associated with-long term liability.
• Effective consultation mechanisms have been developed to engage stakeholders and
other users of the sea in considering the options for decommissioning.
• A comprehensive environmental impact assessment (EIA), undertaken by independent parties, is a vital element when considering the implications of different disposal
alternatives. e environmental impact assessment should include consideration of the
long-term impact on the marine environment from any contaminants that may be left
in the substructure. It is important to allow the stakeholders to review and comment
upon both the proposed scope of work for the EIA and the subsequent outcome from
the assessment.
• Concrete structures left in place in the marine environment are extremely durable, will
degrade very slowly and may be expected to remain standing for  to  years.
• Contamination of the marine environment in the vicinity of the decommissioned installation is not expected to be significant, especially given strict controls on cleaning during
decommissioning.
• Costs of decommissioning will be significant irrespective of the ultimate outcome of the
consideration of a full range of options. For example, the cost of removal and onshore
deconstruction of a concrete platform is estimated to be in the range  MNOK/
m to  MNOK/m, depending on the type of platform (excluding the cost
of removal and disposal of the platform topsides). More than half this cost may be
expended before obtaining sufficient confidence that an operation to re-float the substructure would be successful.

©  OGP
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
Appendix 
Concrete Gravity Platforms within the
OSPAR Maritime Area
Concrete gravity based structures in the Norwegian Continental Shelf
Field
Type
Platform
function
Operator
Water
depth
(m)
Instal.
date
Topsides
weight
(Te)
Substructure
weight (Te)
incl. ballast
Oil
storage
(bbl)
Designed
ror
removal
Planned
decom
date
Ekofisk Tank+
Protective
barrier
Doris
Oil Storage
Phillips
Norway
70
1973
33,400
273 700
896 900
1,000,000
no
1999
Frigg TCP2
Condeep
Production
TotalFinaElf
(Norway)
103
1977
22,900
229,200
no
no
2004
Statfjord A
Condeep
Production/
Drilling/Quarter
Statoil
145
1977
41,300
254,000
1,200,000
no
2010
Gullfaks A
Condeep
Production/
Drilling/Quarter
Statoil
134
1986
47,500
651,000
1,195,000
yes
2016
Gullfaks B
Condeep
Drilling/Quarter
Statoil
142
1987
27,000
583,500
no
yes
2016
Gullfaks C
Condeep
Production/
Drilling/Quarter
Statoil
217
1989
52,000
784,000
2,000,000
yes
2016
Draugen
Condeep
Production/
Drilling/Quarter
Shell
(Norway)
250
1993
28,000
208,000
1,400,000
yes
2016
Oseberg A
Condeep
Production/
Quarter
Norsk
Hydro
109
1988
37,000
320,000
no
yes
2020
Statfjord B
Condeep
Production/
Drilling/Quarter
Statoil
145
1981
42,200
434,000
1,900,000
yes
2010
Statfjord C
Condeep
Production/
Drilling/Quarter
Statoil
145
1984
48,100
358,000
1,900,000
yes
2014
Sleipner A
Condeep
Production/
Drilling/Quarter
Statoil
83
1992
37,000
788,000
no
yes
2035
Troll Gas
Condeep
Production/
Drilling/Quarter
Statoil
330
1995
25,000
661,500
no
yes
2046
Designed
for
Removal
Planned
decom
date
Concrete gravity based structures in the UK Continental Shelf
Field
Type
Platform
Function
Operator
Water
Depth
(m)
Instal.
date
Topsides
Weight
(Te)
Substructure
Weight (Te)
incl. Ballast
Oil
Storage
(bbl)
Frigg CDP1
Doris
Production/
Drilling
TotalFinaElf
(Norway)
98
1975
4,850
415,700
no
no
2004
Frigg TP1
Sea Tank
Production
TotalFinaElf
(Norway)
103
1976
7,840
162,000
no
no
2004
Dunlin A
Andoc
Drilling/
Production
Shell
151
1977
19,294
228,611
838,200
no
2009
Ninian
Central
Doris
Drilling/
Production
Kerr-McGee
135
1978
39,000
584,000
1,000,000
no
2009
Cormorant A
SeaTank
Drilling/
Production
Shell
150
1978
25,678
294,655
1,000,000
no
2010
Brent B
Condeep
Drilling/
Production
Shell
139
1975
23,424
165,664
1,100,000
no
2011
Brent C
SeaTank
Drilling/
Production
Shell
141
1978
29,874
287,542
600,000
no
2011
Brent D
Condeep
Production/
Drilling
Shell
142
1976
23,097
177,809
1,100,000
no
2011
North
Ravensburn
Arup
Production
BP
43
1989
6,250
58,500
no
yes
2014
Harding
(34m base
caisson)
Technip
Drilling/
Production
BP
110
1995
23,000
134,300
no
yes
2015
Beryl A
Condeep
Drilling
Production
ExxonMobil
117
1975
20,000
494,000
900,000
no
2018
MCP01
Doris
Current use:
Riser platform
TotalFinaElf
(UK)
94
1976
13,000
376,000
no
no
2020
©  OGP

International Association of Oil & Gas Producers
Concrete gravity based structures in Denmark and Netherlands
Field
Type
Operator
Water
Depth
(m)
Instal.
date
Topsides
Weight
(Te)
Substructure
Weight (Te)
incl. Ballast
Oil
Storage
(bbl)
Designed
for
Removal
Planned
decom
date
South Arne
Blocks
5604/29 +
5604/30 Denmark
Drilling/
Production
Amerada
Hess
Denmark
61
1999
7,100
100,000
550,000
F/3
Block F/3 Netherlands
Drilling/
Production 71.4x81.4m
concrete
caisson
NAM
Netherlands
42
1992
9,500
49 200 (excl. steel
columns)
189,000
yes
2032
Halfweg
Block Q/1 Netherlands
Wellhead
Unocal
Netherlands
30
1995
650
including
legs
3,014
no
yes
2007
Note:
SouthArne:
Halfweg:

Platform
Function
Concrete Gravity Base with a steel lattice drilling tower
Concrete base with a four leg jack-up which can be disconnected and refloated
©  OGP
2011
Disposal of disused offshore concrete gravity platforms in the OSPAR Maritime Area
Appendix  Concrete Gravity Platforms outside
the OSPAR Maritime Area
Concrete gravity based structures outside the OSPAR Maritime Area
Field
Type
Platform
function
Operator
Water
depth
(m)
Instal.
date
Topsides
weight
(Te)
Substructure
weight (Te)
incl. ballast
Oil
storage
(bbl)
Designed
ror
removal
Planned
decom
date
Bream
Gippsland
Basin, SE
Australia
ExxonMobil
Australia
61
1996
800
44,200
West Tuna
Gippsland
Basin, SE
Australia
ExxonMobil
Australia
61
1996
7,000
88,000
Wandoo
WA-14-L - NW
Shelf - Western
Australia
Production
ExxonMobil
Australia
55m
1996
6,500
81,000
400,000
Schwedeneck-See
Baltic Sea, DCS
Production
RWE-DEA
Germany
26
1984
1,300
16,000
no
Yes
2002
Schwedeneck-See
Baltic Sea, DCS
Production
RWE-DEA
Germany
16
1984
1,300
14,000
no
Yes
2002
Hibernia
Offshore
Newfoundland
Drilling/
Production
Mobil
Canada
80
1997
37,000
900,000
1,300,000
©  OGP

International Association of Oil & Gas Producers
Reference List


OGP (. EP F) : “Decommissioning of Concrete Gravity Based Structures”, Report no. ./
, June 

OSPAR Decision / on the Disposal of Disused Offshore Installations, issued in July .

Ekofisk  Disposal: Impact Assessment, Environmental and Societal Impacts, dated  October .

Ekofisk Tank Substructures, A summary of Disposal Option Assessments, dated  March .

Frigg Field Cessation Plan, Second Draft, dated November .

Summary report for Phase I and II: “Removal of Offshore Concrete Structures” , rev. , dated .., D.
. O O, Oslo

Joint Industry Project: UKCS Decommissioning Study”, report No. -ER, dated  January , W.A.
A, Aberdeen

“Guide to the classification of environmental quality in ords and coastal waters” , issued by the Norwegian
State Pollution Agency, SFT ..

Norwegian Act of  November  No.  relating to petroleum activities

e United Kingdom Petroleum Act 

“Guidance Notes for Industry - Decommissioning of Offshore Installations and Pipelines under then Petroleum
Act ”, issued in .

“Durability of high-strength offshore concrete structures” , presented at the th International Symposium on
Utilisation of High strength/high performance Concrete, June , Sandeord, Norway, by S M.
B, D. T. O O, N  J E C, Selmer ASA, Norway.
©  OGP
What is OGP?
e International Association of Oil & Gas Producers encompasses the world’s leading
private and state-owned oil & gas companies, their national and regional associations, and
major upstream contractors and suppliers.
Vision
• To work on behalf of all the world’s upstream companies to promote responsible and
profitable operations.
Mission
• To represent the interests of the upstream industry to international regulatory and
legislative bodies.
• To achieve continuous improvement in safety, health and environmental performance
and in the engineering and operation of upstream ventures.
• To promote awareness of Corporate Social Responsibility issues within the industry
and among stakeholders.
Objectives
• To improve understanding of the upstream oil and gas industry, its achievements and
challenges and its views on pertinent issues.
• To encourage international regulators and other parties to take account of the industry’s views in developing proposals that are effective and workable.
• To become a more visible, accessible and effective source of information about the
global industry - both externally and within member organisations.
• To develop and disseminate best practices in safety, health and environmental performance and the engineering and operation of upstream ventures.
• To improve the collection, analysis and dissemination of safety, health and environmental performance data.
• To provide a forum for sharing experience and debating emerging issues.
• To enhance the industry’s ability to influence by increasing the size and diversity of
the membership.
• To liaise with other industry associations to ensure consistent and effective approaches
to common issues.
209-215 Blackfriars Road
London SE1 8NL
United Kingdom
Telephone: +44 (0)20 7633 0272
Fax: +44 (0)20 7633 2350
165 Bd du Souverain
4th Floor
B-1160 Brussels, Belgium
Telephone: +32 (0)2 566 9150
Fax: +32 (0)2 566 9159
Internet site: www.ogp.org.uk
e-mail: reception@ogp.org.uk
Download