American University East Campus Community Meeting September 17, 2015 1 Agenda I. Project Status Update II. 6-Month Look Ahead III. Saturday work IV. Q & A 2 Status update • Geo-pier installation nearing completion • Below grade structure installation has commenced • Offsite facade pre-fabrication has commenced • Site utilities have commenced 3 Status update Below grade structure 4 Status update Below grade structure 5 Status update Façade prefabrication 6 Look Ahead East Campus Project Six Month Look-Ahead Schedule Phase September Offsite - Precast façade fabrication Foundations & Garage Structure Below slab utilities Above grade structure Precast façade Installation Interior MEP 7 2015 October November 2016 December January February Saturday Work Daily Precipitation (days) 14 • 11.2 days of precipitation more than normal • 6.01 total inches of precipitation more than normal • 33 total work days impacted by precipitation • 44 Saturdays remaining in the schedule 12 10 8 6 4 2 0 April May June Monthly Normals July 2015 Source: NOAA Dalecarlia Reservoir Observation Station 8 August Precipitation impact on work April 2015 May 2015 July 2015 9 June 2015 August 2015 Remaining Schedule American University - East Campus Project Remaining Schedule Legend: Exterior work activities potentially impacted by weather Interior work activities not impacted by weather Revised completion date of task Task # of work days (excluding Saturday) # of work days with precipitation Precip days as a % # of work days Below Grade Structure Excavation Geo-piers Concrete Site Utilities Building 6 Above ground structure Interior work (rough-in and finishes) Enclosure/Envelope Building 4 Above ground structure Interior work (rough-in and finishes) Enclosure/Envelope Building 2 Above ground structure Interior work (rough-in and finishes) Enclosure/Envelope Building 1 Above ground structure Interior rough-in and finishes Enclosure/Envelope Building 3 Above ground structure Interior work (rough-in and finishes) Enclosure/Envelope Fixture, Furniture & Equipment 10 Feb Mar 21 23 na na ####### ####### Apr 22 8 36% May 21 3 14% Jun 22 9 41% 2015 Jul 23 9 39% Aug 21 4 19% Sep 22 0 0% Oct 22 0 0% Nov 21 0 0% Dec 23 0 0% Jan 21 0 0% Feb 21 0 0% Mar 23 0 0% Apr 21 0 0% May 22 0 0% 2016 Jun 22 0 0% Jul 21 0 0% Aug 23 0 0% Sep 25 0 0% Oct 27 0 0% Skanska Onsite Team David Coleman Elias Bezabhe Project Executive Project Manager Steve Griffin EriK Henson Assistant Superintendent Superintendent 301-955-6296 AUEC@skanska.com 11 American University Team Andrew Huff Robert van Hoek Onyel Bhola Director of Community Relations Senior Project Manager Project Coordinator 202.440.2221 ahuff@american.edu 202.885.1123 vanhoek@american.edu 240.565.7707 onyel@american.edu American University Public Safety 202-885-2527 12 Q&A 13