September 17 American University East Campus Community Meeting , 2015

advertisement
American University East Campus
Community Meeting
September 17, 2015
1
Agenda
I.
Project Status Update
II. 6-Month Look Ahead
III. Saturday work
IV. Q & A
2
Status update
• Geo-pier installation nearing completion
• Below grade structure installation has commenced
• Offsite facade pre-fabrication has commenced
• Site utilities have commenced
3
Status update
Below grade structure
4
Status update
Below grade structure
5
Status update
Façade prefabrication
6
Look Ahead
East Campus Project
Six Month Look-Ahead Schedule
Phase
September
Offsite - Precast façade fabrication
Foundations & Garage Structure
Below slab utilities
Above grade structure
Precast façade Installation
Interior MEP
7
2015
October
November
2016
December
January
February
Saturday Work
Daily Precipitation (days)
14
•
11.2 days of precipitation
more than normal
•
6.01 total inches of
precipitation more than
normal
•
33 total work days impacted
by precipitation
•
44 Saturdays remaining in
the schedule
12
10
8
6
4
2
0
April
May
June
Monthly Normals
July
2015
Source: NOAA Dalecarlia Reservoir Observation Station
8
August
Precipitation impact on work
April 2015
May 2015
July 2015
9
June 2015
August 2015
Remaining Schedule
American University - East Campus Project
Remaining Schedule
Legend:
Exterior work activities potentially impacted by weather
Interior work activities not impacted by weather
Revised completion date of task
Task
# of work days (excluding Saturday)
# of work days with precipitation
Precip days as a % # of work days
Below Grade Structure
Excavation
Geo-piers
Concrete
Site Utilities
Building 6
Above ground structure
Interior work (rough-in and finishes)
Enclosure/Envelope
Building 4
Above ground structure
Interior work (rough-in and finishes)
Enclosure/Envelope
Building 2
Above ground structure
Interior work (rough-in and finishes)
Enclosure/Envelope
Building 1
Above ground structure
Interior rough-in and finishes
Enclosure/Envelope
Building 3
Above ground structure
Interior work (rough-in and finishes)
Enclosure/Envelope
Fixture, Furniture & Equipment
10
Feb
Mar
21
23
na
na
####### #######
Apr
22
8
36%
May
21
3
14%
Jun
22
9
41%
2015
Jul
23
9
39%
Aug
21
4
19%
Sep
22
0
0%
Oct
22
0
0%
Nov
21
0
0%
Dec
23
0
0%
Jan
21
0
0%
Feb
21
0
0%
Mar
23
0
0%
Apr
21
0
0%
May
22
0
0%
2016
Jun
22
0
0%
Jul
21
0
0%
Aug
23
0
0%
Sep
25
0
0%
Oct
27
0
0%
Skanska Onsite Team
David Coleman
Elias Bezabhe
Project Executive
Project Manager
Steve Griffin
EriK Henson
Assistant Superintendent
Superintendent
301-955-6296
AUEC@skanska.com
11
American University Team
Andrew Huff
Robert van Hoek
Onyel Bhola
Director of Community Relations
Senior Project Manager
Project Coordinator
202.440.2221
ahuff@american.edu
202.885.1123
vanhoek@american.edu
240.565.7707
onyel@american.edu
American University
Public Safety
202-885-2527
12
Q&A