Gordon State College Facilities Goals, Outcomes and Evidence of Improvement 2011-2015

advertisement
Gordon State College
Facilities
Goals, Outcomes and Evidence of Improvement
2011-2015
http://www.gordonstate.edu/facilities/home
Mission Statement
As the chief provider of information technology services and support on campus, the Gordon State
College Information Technology Department is committed to the enhancement of education through
the use of technology to support the College's vision of becoming a leader in the integration of
technology with teaching and learning. The Information Technology department implements and
maintains hardware and software configurations on campus, the college network infrastructure and
security, Internet services and application systems, the Banner student information system, email
services, and multimedia technologies.
Unit Outcomes Assessment Results Report
2014-2015
Goals
1. Maintain clean facilities.
2. Provide a safe environment for our campus community.
3. Seek, prioritize and allocate capital resources to meet the strategic priorities of Gordon State
College.
Outcomes
1. Develop a plan to standardize when and how certain cleaning tasks are performed in order to
reach the Association of Physical Plant Administrators' (APPA) appearance level 2 for all
buildings.
2. Label/inventory chemicals used on campus.
3. Undertake full review and update of GSC master plan. (Note: Current master plan was delivered
in December 2007 and was updated in February 2011. This update focused mainly on parking
and vehicular travel within the campus footprint.)
Review of Outcomes
1. Completed
2. Completed
3. In Progress
Evidence of Improvement
1. All information is shared with staff and will improve productivity and accountability.
2. The chemicals are managed by the Science Department. Recourses were not received.
3. Master Plan will be finalized and sent to the BOR for approval by fall 2015.
Goals
1.
2.
3.
4.
5.
1.
2.
3.
4.
5.
2013-2014
Renovate Russell Hall, including furniture
Renovate Instructional complex, including furniture
Replace desks in all classrooms of IC building
Renovation and addition to dining facility
Explore library renovation and/or addition
Outcomes
Provided faculty offices and furniture for new academic organizational structure
Provided faculty offices and furniture for new academic organizational structure
Provide for a better learning environment by increasing work surface of desks.
Provide a better dining experience for faculty staff, and students.
Upgrade library to 21st century technology
Review of Outcomes
1. Completed
2. Completed
3. Completed
4. Completed
5. Completed
Evidence of Improvement
1. Renovation complete
2. Renovation complete
3. Desks purchased
4. Renovation/addition complete
5. Small capital project approved, library renovation due to be completed in March 2016
2012-2013
Goals
1. Renovate Russell Hall, including furniture
2. Renovate Instructional complex, including furniture
3. Replace desks in all classrooms of IC building
4. Renovation and addition to dining facility
5. Explore library renovation and/or addition
Outcomes
1. Provided faculty offices and furniture for new academic organizational structure
2. Provided faculty offices and furniture for new academic organizational structure
3. Provide for a better learning environment by increasing work surface of desks.
4. Provide a better dining experience for faculty staff, and students.
5. Upgrade library to 21st century technology
Review of Outcomes
1. Completed
2. Completed
3. Completed
4. Completed
5. Completed
Evidence of Improvement
1. Renovation complete
2. Renovation complete
3. Desks purchased
4. Renovation/addition complete
5. Small capital project approved, library renovation due to be completed in March 2016
2011-2012
Goals
1.
2.
3.
4.
5.
I – 10 Lab Renovation
Rework Lambdin Green Quadrangle
Renovation of Smith Hall
Renovation of Student Center
Signage Project
Outcomes
1. Professors & students will be able to perform research in the field of Biology by converting this
classroom.
2. The desired results will be to improve foot traffic control while allowing access to green space.
3. Refurbish building for the Department of Education to support its Baccalaureate Program.
4. Complete the renovation of student center, including a new student auditorium.
5. Update signage on campus to ensure that all buildings are properly marked and that directions
are clear and visible.
Review of Outcomes
1. Completed
2. Completed
3. Completed
4. Completed
5. Completed
Evidence of Improvement
1. Renovation complete
2. Rework complete
3. Renovation complete
4. Renovation complete
5. Signage is now properly marked and directions are clear and visible
Download