Estates Office Asbestos Management Process: Project / Job Workflow Asbestos Manager Project / Job Manager / Team Identify the Need for Work Project / Job Manager Identify Change of Scope Receive & check full Project Specific R&D Survey, copy to Asbestos Manager Detailed Description of Scope of Works Continue with Project Instruct Asbestos Surveyor Identify Asbestos Surveyor NO Analysis / Investigation Asbestos Manager Minimum 20 days notice Removal Contractor proceeds with removal work monitored by analyst Discuss proposed Method of Work with removal Contractor / DLO Instruct removal contractor Specify mitigation by management or removal. Agree preliminary timings with Depts. Removal Contractor issues 14 day Notice to HSE Receive Method Statement Agree timing of work Obtain and check Completion Information form independent analyst Approval to Proceed Works Impact on ACM’s Update Register YES Appoint Independent Analyst Depts. To communicate to staff