RÉGIE DE L’ÉNERGIE HYDRO-QUÉBEC TRANSÉNERGIE FOR THE REQUEST RELATIVE TO THE MODIFICATION OF HYDRO-QUÉBEC’S TRANSMISSION SERVICE CONDITIONS FILE R-3549-2004 PHASE 2 EVIDENCE OF WILLIAM HARPER ECONALYSIS CONSULTING SERVICES ON BEHALF OF: OPTION CONSOMMATEURS OCTOBER 18, 2005 TABLE OF CONTENTS 1 2 3 INTRODUCTION .......................................................................................................................1 PURPOSE OF EVIDENCE......................................................................................................2 HQT’S CURRENT TRANSMISSION TARIFFS ..................................................................4 3.1 Basis for the Current Transmission Tariffs ..................................................................4 3.2 Use of Transmission Services Since 2001..................................................................6 3.2.1 Native Load Service .................................................................................................7 3.2.2 Network Integration Service....................................................................................7 3.2.3 Long-term Firm Point to Point Service .................................................................7 3.2.4 Short Term Point to Point Service.........................................................................8 3.2.5 Use of Interconnections...........................................................................................9 3.2.6 Ancillary Services....................................................................................................11 4 COST ALLOCATION METHODOLOGY ............................................................................12 4.1 Background.......................................................................................................................12 4.2 Definition of Cost Functions..........................................................................................13 4.2.1 Generation Connection..........................................................................................14 4.2.2 Network .....................................................................................................................15 4.2.3 Customer Connection ............................................................................................16 4.2.4 Interconnections......................................................................................................17 4.2.5 Support and Control Centre Costs......................................................................18 4.3 Cost Functionalization....................................................................................................19 4.3.1 Functionalization of Rate Base ............................................................................19 4.3.2 Functionalization of Cost of Service ...................................................................25 4.4 Classification of Costs....................................................................................................32 4.5 Allocation of Functionalized Costs to Services.........................................................34 4.5.1 Services Provided ...................................................................................................34 4.5.2 Allocation Factors....................................................................................................37 4.6 Impact of Comments Regarding HQT’s Cost Allocation Methodology ...............46 5 HQT’S PROPOSED TRANSMISSION SERVICE PRICING METHODOLOGY .......48 5.1 Overview............................................................................................................................48 5.2 Treatment of Short-Term PTP Revenues ..................................................................49 5.3 Allocation of Revenue Requirement between Native Load/Network Integration Service and Long-term PTP Service .......................................................................................51 5.4 Determination of Long-term Point to Point Service Rates .....................................53 5.5 Determination of Native Load/Network Integration Service Rates.......................53 5.6 Determination of Short-term Point to Point Service Rates.....................................58 5.7 Consistency with Cost of Service Allocation Results..............................................61 5.8 Ancillary Service Rates ..................................................................................................63 6 CONCLUSIONS.......................................................................................................................68 6.1 HQT’s Cost Allocation Methodology ...........................................................................68 6.2 HQT’s Derivation of Transmission Service Rates....................................................71 Appendix: CV for ECS Consultant Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 1 INTRODUCTION 2 3 On September 30th, 2004 Hydro-Québec TransÉnergie (HQT) filed an 4 Application with the Régie de l’énergie (the “Régie”) for approval of a revised 5 revenue requirement and transmission tariffs effective January 1st, 2005. For 6 purposes of review, HQT separated the Application into two phases. Phase 1, 7 which was the subject of the September 2004 Application, dealt with the 8 determination HQT’s rate base and revenue requirement for 2005. Following an 9 oral hearing, the Régie issued decisions D-2005-50 and D-2005-63 which 10 approved a rate base of $14,657.1 M and a revenue requirement of $2,581.0 M 11 for HQT for 2005. On June 22, 2005, HQT filed its Application for Phase 2 which 12 dealt with the allocation of HQT’s approved revenue requirement to services; the 13 fixing of the amount to be billed to Hydro-Québec Distribution (HQD) for 14 transmission services and the setting of rates for point to point transmission 15 service and other ancillary services effective January 1st, 2005. 16 17 HQT’s current transmission rates have been in effect since January 2001 and are 18 the result of the Régie’s first (and only) proceeding and decision (R-3401-1998 19 and D-2002-95) regarding HQT’s transmission tariffs. 20 1 Evidence of William Harper 1 2 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 PURPOSE OF EVIDENCE 2 3 After reviewing HQD’s Application and the Procedural Order1 issued by the 4 Régie, Option Consommateurs (OC) retained Econalysis Consulting Services 5 (ECS), a Canadian consulting firm offering regulatory services to clients in the 6 electricity and natural gas sectors to provide evidence that would assist OC and 7 the Régie in assessing HQT’s proposals with respect to transmission cost 8 allocation and rate design. 9 10 The Evidence was prepared by Bill Harper who, prior to joining ECS in July 2000, 11 worked for over 25 years in the energy sector in Ontario, first with the Ontario 12 Ministry of Energy and then, with Ontario Hydro and its successor company 13 Hydro One. Since joining ECS, he has assisted various clients participating in 14 regulatory proceedings on issues related to electricity and natural gas utility 15 revenue requirements, cost allocation/rate design and supply planning. Mr. 16 Harper has served as an expert witness in public hearings before the Manitoba 17 Public Utilities Board, the Manitoba Clean Environment Commission, the Régie, 18 the Ontario Energy Board, the Ontario Environmental Assessment Board and a 19 Select Committee of the Ontario Legislature on matters dealing with electricity 20 regulation, rates and supply planning. His most recent experience with cost 21 allocation and rate design matters includes: • 22 The preparation of evidence and appearance as an expert witness on 23 behalf of OC in both Phase 1 and Phase 2 of Régie proceeding (R-3492- 24 2002) dealing with HQD’s 2002 and 2003 cost allocation proposals. • 25 The preparation of evidence and appearance as an expert witness on 26 behalf of OC in the Régie proceeding (R-3541-2004) dealing with HQD’s 27 2004 rate design proposals. • 28 The preparation of evidence and appearance as an expert witness before the Manitoba Public Utilities Board with respect to its review of proposals 29 1 D-2005-123 2 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 filed by Manitoba Hydro in both 2002 and 2004 regarding cost allocation 2 and rate design. 3 • Providing expert advice and support to clients in British Columbia 4 participating in the BCUC proceedings dealing with BCTC’s 2004 Open 5 Access Transmission Tariff (OATT) Application. 6 • Member of the OEB’s 2005 Technical Advisory Team regarding cost allocation for Ontario electricity distributors. 7 8 9 A full copy of Mr. Harper’s CV is attached in Appendix A. 10 11 The evidence generally follows the structure of HQT’s Application and, after 12 providing a brief overview of HQT’s current transmission rates and past usage, 13 reviews: 14 • revenue requirement between services, 15 16 • HQT’s approach to determining point to point (PTP) transmission service rates and setting of proposed rates for various forms of PTP service, 17 18 HQT’s proposed cost allocation methodology for allocating the approved • HQT’s methodology for establishing the revenue to be recovered annually 19 from HQD (and other potential Native Load/Network Integration service 20 customers), 21 22 • HQT’s proposed rates for Ancillary Services and the modifications to their Tariffs and Conditions. 23 Applicable comments are noted throughout the text and summarized in 24 concluding section. 25 3 Evidence of William Harper 1 3 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 HQT’S CURRENT TRANSMISSION TARIFFS 2 3.1 3 Basis for the Current Transmission Tariffs 4 5 In 1996, the Québec Government approved2 the principle of open access on 6 Hydro-Québec’s transmission system and, subsequently, in 1997 introduced the 7 functional separation of Hydro-Québec’s transmission activities from its 8 distribution and generation activities with the creation of Hydro-Québec 9 TransÉnergie (HQT). Soon thereafter, An Act respecting the Régie de l’énergie 10 came into effect requiring HQT to obtain approval from the Régie for its 11 transmission tariffs. 12 13 HQT’s current transmission tariffs have been in place since January 1, 2001 and 14 are the result of an Application by HQT in 1998 (R-3401-1998) and a Régie 15 decision issued in May 2002 (D-2002-95). This Application was the first 16 transmission rate Application to be considered by the Régie. Prior to January 1, 17 2001, HQT’s rates had been established via an Order in Council3. 18 19 The rates approved by the Régie in 2002 followed the form and structure of 20 FERC’s direction regarding Open Access Tariffs4. To this end, HQT’s open 21 access tariff includes: • 22 Rates for Native Load service, Network Integration service and long-term firm PTP service that are established on a comparable basis. 23 • 24 Rates for Native Load service and individual Network Integration service customers based on annual load ratios. 25 2 Hydro-Québec Byl aw number 652 respecting the conditions and rates for wholesale electric transmission service. 3 Order in Council 276-97, March 5, 1997 (Approved Hydro-Québec Bylaw 659) 4 HQT-4, Document 3, page 13. See also FERC Order 888-A, page 256 and FERC’s Pricing Policy for Transmission Service found at 69 FERC 61,086 4 Evidence of William Harper • 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Rates for short term service (firm and non-firm) that are derived from the annual long-term firm PTP service rates. 2 • 3 Ancillary Service rates for the various “supporting” services required by 4 PTP users of transmission service and provided by either transmission or 5 generation facilities. 6 7 The rates are also compliant with the Act regarding the need for uniform rates 8 through out the territory5 served and direction from the Régie regarding: • 9 The development of rates based on average costs for a prospective test year 6, 10 • 11 The use of 1-CP (as an interim measure) to allocate the transmission revenue requirement and determine long-term firm PTP rates7, 12 13 • The use of the long-term PTP rates to establish short term PTP rates8, 14 • The basis for distinguishing between firm and non-firm short term PTP service rates9. 15 16 Finally, the Régie determined that a more detailed cost allocation study was 17 required before it could conclude that HQT’s approach to determining the current 18 transmission rates for Native Load service, Network Integration service and long- 19 term firm PTP was appropriate from a longer term perspective.10 5 D-2002-95, page 244 and Section 49, paragraph 1, subparagraph 11 of the Act. D-2005-95, page 244 7 D-2005-95, page 244 8 D-2005-95, page 265 9 D-2005-95, page 265 10 D-2002-95, pages 210-215 6 5 Evidence of William Harper 1 3.2 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Use of Transmission Services Since 2001 2 3 Table 1 below sets out the extent to which the three transmission services have 4 used HQT’s system since 2001 and the projected use for 2005. 5 TABLE 1 USE OF HQT'S TRANSMISSION SERVICES Service Category 2001 2002 2003 2004 2005 29346 32211 31171 32244 34487 33735 35514 34295 n/a 34060 0 0 0 0 Long Term Firm PTP (MW Reserved) 3982 3306 1878 405 405 Short-Term PTP - Monthly Firm PTP (MW Reserved) - Monthly Non-Firm PTP - Weekly Firm PTP (MW Reserved) - Weekly Non-Firm PTP - Daily Firm PTP (MW Reserved) - Daily Non-Firm PTP (MW Reserved) - Hourly Non-Firm PTP (TWh) 2080 0 480 0 0 0 0.1 925 0 1057 0 913 74 1.6 402 0 132 0 153 0 2.7 430 0 0 0 5227 0 7 0 0 0 0 5882 0 9.3 Native Load Service - Maximum Annual Peak (MWs) - Normalized Coincident Peak (MWs) Network Integration Service 0 Sources: a) The 2001-2005 data is based on HQT-6, Document 1, page 12, Table 8.1 6 6 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 3.2.1 Native Load Service 3 HQD is HQT’s only Native Load service customer11. While providing for a 4 network integration type of service, the Tariffs and Conditions for Native Load 5 service recognize the unique arrangements between HQD and HQP regarding 6 the provision of Heritage Pool energy and Ancillary Services12. Native Load 7 service provides HQD with the transmission services required to13: 8 • Obtain delivery of Heritage Pool Energy from HQP, 9 • Obtain delivery of any imports it has contracted for (or will contract for) to meet its domestic customers’ requirements, and 10 • 11 Obtain delivery of generation purchased from 3rd parties in Québec to meet its domestic customers’ requirements. 12 13 Native Load service also covers the transmission service required by HQP in the 14 event that it must purchase imports to meet its Heritage Pool obligations. As a 15 result, HQD does not contract for short term PTP service14. 16 17 18 3.2.2 Network Integration Service 19 HQT currently has no Network Integration service customers15. 20 21 3.2.3 Long-term Firm Point to Point Service 22 Since 2002, HQP has been HQT’s only long-term firm PTP service customer16. 23 For 2005, HQP has four long-term PTP service contracts with HQT. Two of the 24 contracts (totaling 100 MW) are for points of receipt in Quebec and delivery to an 25 interconnection point with another network in Quebec (i.e., Cedar Rapids 26 Limited). The other two are for delivery from points inside Quebec to the New 11 HQT-6, Document 7, Question 32 c) D-2002-95, pages 336-337 13 HQT-6, Document 7, Question 32 d) & f) 14 HQT-6, Document 7, Questions 2 b); 21 b): 32 d) & e) 15 HQT-2, Document 1, page 10 16 HQT-6, Document 7, Question 13 a) 12 7 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 England or New York systems17. Only one of the four contracts (45 MW with 2 Cedar Rapids) extends beyond the end of 200518. 3 4 5 3.2.4 Short Term Point to Point Service 6 While there are a number of customers that have contracted with HQT for short 7 term PTP transmission service, HQP accounts for most of the contracted MW 8 and resulting revenues19. Furthermore, in the case of HQP, the contracts for 9 short-term service would all be for deliveries to either customers/systems in 10 Quebec, other than HQD, or to neighbouring systems since use of transmission 11 for delivery to HQD is covered by Native Load service20. 12 13 Over the years 2001 through 2003, revenues from parties other than HQP 14 accounted for between 17.6% to and 26.4% of total short-term PTP revenues 21. 15 However, in 2004, HQP accounted for 93.9% of these revenues and, for 2005, 16 the percentage is projected to be even higher22. Indeed, for 2005, the only 17 projected use of HQT’s transmission services by parties other than HQP is 0.4 18 TWh of hourly service and what appears to be a minimal requirement for daily 19 service. In contrast, HQP is expected to require short-term PTP service to move 20 roughly 9 TWh23 in 2005. 17 HQT-6, Document 7, Question 13 b) HQT-6, Document 7, Question 19 a). Note: The 45 MW contract figure excludes losses. 19 HQT-6, Document 7, Question s 16 b) and 18 b) 20 HQT-6, Document 7, Questions 21 a)-c) and 24 b) 21 HQT-6, Document 7, Question 16 b) 22 Based on HQT-2, Document 2, page 10, Table 5 and HQT-4, Document 1, page 21, Table 6 23 HQT-2, Doc 2, page 10, Table 5 and HQT-6, Document 1, page 12, Question 8.1 18 8 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 3.2.5 Use of Interconnections 3 In its evidence, HQT uses the term “interconnections” to refer to both 4 connections with networks inside Quebec (such as CRT and Brascan), as well as 5 connections with neighbouring networks in other provinces and the US24. 6 7 According to HQT’s evidence25, from 2001 to 2004, most of the deliveries over 8 these interconnections were for HQP transactions and all of the receipts over the 9 interconnections were for HQP transactions. 10 11 Comment 12 13 This information is somewhat contradictory to that published26 by the National 14 Energy Board (NEB) which indicates that from 2001 to 2004, parties other than 15 HQP have used HQT’s international inter-ties for both imports and exports. 16 Table 2 summarizes the imports and exports reported by the NEB for the same 17 period – broken down between those by HQP and other parties. The response 18 to OC Information Request 17.a) is also at odds with HQT’s evidence27 19 elsewhere that there is third party use of transmission service for the purpose of 20 wheeling through power through HQT from one interconnection point to another 21 (which would result in transactions where the interconnections were a point of 22 receipt). 24 HQT-6, Document 7, Question 13 b) and HQT-6, Document 1, pages 39- 40, Question 16.1 HQT-6, Document 7, Question 17 a) 26 National Energy Board, Electricity Exports and Imports (http://www.neb.gc.ca/Statistics/ElectricityExportsImports/index_e.htm#Year2004) 27 HQT-6, Document 8, page 21, Question 14.1; HQT-6, Document 7, page 27, Question 21.a); HQT-6, Document 7, page 30, Question 23.a) and HQT-2, Document 5, page 13, Table 1 25 9 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 TABLE 2 Quebec Exports and Imports Reported by the NEB Exports HQP Others Total HQP 2001 2002 2003 2004 13.56 13.58 7.49 7.72 1.26 1.16 1.55 1.76 14.82 14.74 10.04 9.48 3.38 2.30 3.35 3.20 Imports Others Total 0.07 0.25 0.58 0.26 3.45 2.55 3.92 3.46 Source: Electricity Imports and Exports (http://www.neb.gc.ca/Statistics/ElectricityExportsImports/index_e.htm#Year2004) Note: 1) Includes firm and interruptible exports 2) Values reported are in TWh 1 2 3 Regardless of the inconsistencies noted above, from a comparison of Table 2 4 and the information provided by HQT, one can conclude that: • 5 The vast majority of the transactions involve HQT’s interconnections with neighbouring systems in the US28, 6 • 7 The majority of the receipts and deliveries to HQT’s interconnections are for transactions by HQP29, and 8 • 9 Exports to neighbouring systems outside of Quebec (as opposed to 10 wheeling deliveries to networks located inside Quebec or wheeling 11 through between networks located outside of Quebec30) account for most 12 of HQP’s use of short-term PTP services. 13 What remains unclear is the nature of the use of HQT’s transmission services by 14 3rd parties. 28 Compare HQT-2, Document 2, page 9, Table 4 with Table 2 above HQT-6, Document 7, Question 17 a), Table R.17.a 30 HQT-2, Document 3, page 14 29 10 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 3.2.6 Ancillary Services 3 Of the six Ancillary Services provided for in FERC’s pro-forma Open Access 4 Transmission Tariff (OATT) 31 and offered by HQT in its 2001 approved Tariffs, 5 point to point customers are required to purchase two of them (System Control 6 and Voltage Control) from HQT. Point to point customers can also obtain the 7 other four services (Frequency Control, Energy Imbalance, Spinning Reserve 8 and Non-Spinning Reserve) from HQT or “self supply” by obtaining a comparable 9 service from other providers located in HQT’s control area. In the case of 10 System Control, the service is not billed for separately but, rather, included in the 11 transmission service rates32. 12 13 In the case of Native Load service, HQD (as the Native Load customer) is 14 responsible for providing all of the identified ancillary services with the exception 15 of System Control service which is provided by HQT33. 16 17 HQP self-supplies the Ancillary Services required to support its PTP service 18 contracts with HQT34. However, the other customers purchasing PTP 19 transmission service from HQT do not “self-supply” and, instead, purchase their 20 requirements for these four services from HQT35. 21 22 Of the six Ancillary Services, HQT only self-provides one of them (System 23 Control), the other five are provided by HQP 36. In addition, only the costs for 24 System Control are reflected in HQT’s revenue requirement. The costs for the 25 other five services are not included as they are effectively a “pass-through” from 26 HQP – based on the tariffs approved by the Régie37. 31 HQT-2, Document 1, page 11 HQT-4, Document 1, page 29 33 HQT-6, Document 7, Question 62 a) 34 HQT-6, Document 7, Question 3 a) 35 HQT-6, Document 7, Question 3 b) 36 HQT-6, Document 7, Question 35 c.1) 37 HQT-6, Document 7, Question s 35 c.1) and 64 a) 32 11 Evidence of William Harper 1 4 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 COST ALLOCATION METHODOLOGY 2 4.1 3 Background 4 5 Typically, rates are established for regulated utilities following a three-stage 6 process in which: a) the revenue requirement is first determined; b) a cost 7 allocation study is then undertaken to apportion the revenue requirement to the 8 utility’s various service/customer classes; and c) rates are designed for each 9 service/customer class, taking into consideration the results of the cost allocation 10 study and other rate setting objectives. Cost allocation studies are used as a 11 guide in establishing both rate level and rate design by customer classes, given 12 that one of the principle considerations in setting fair and reasonable rates is that 13 the rates are cost-based. Traditionally, cost allocation studies also employ a 14 three-step process where: • 15 The revenue requirement is functionalized according to the services the utility provides, 16 • 17 The costs in each function are classified according to the system design or operating characteristics that caused the costs to be incurred, and then 18 • 19 The costs in each function are allocated to the various customer classes based on each class’ contribution to the specific cost driver selected38. 20 21 22 The determination of rates based on FERC’s pro-forma OATT does not require a 23 full cost allocation study to be carried out39. However, in its first decision 24 regarding HQT’s rates, the Régie concluded40 that such a study should be 25 undertaken. The Régie also provided a number of specific directives as to how 26 the cost allocation methodology should be structured and which HQT has 27 summarized in its current Application41. 38 D-2002-95, page 210 HQT-6, Document 9, pages 53-54, Questions 42.1 & 43.1 40 HQT-3, Document 1, pages 5-6 41 HQT-3, Document 1, pages 7-8 39 12 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 4.2 2 Definition of Cost Functions 3 4 HQT’s proposed cost allocation methodology separates the revenue requirement 5 (and rate base) into six functions42. There are four main functions (Generation 6 Connection, Network, Customer Connection and Interconnections), each of 7 which are broken down into a number of sub-functions. The two other functions 8 (Control Centre and Support) are not broken down into sub-functions. In 9 addition, the costs assigned to both the Control Centre and Support functions are 10 pro-rated over the four main functions prior to the step where costs are allocated 11 to services. 12 13 Comments 14 15 The functional groupings proposed by HQT generally utilize the same asset 16 categories as presented43 in R-3401-98 and deemed by the Régie, in its 17 subsequent decision, to be a reasonable starting point. The most notable 18 exception is the separation of Churchill Falls interconnection costs which is a 19 direct response to Régie’s finding in D-2002-9544. 20 21 Also, as noted by HQT, this functionalization is similar to that suggested by 22 NARUC for transmission facilities45. It is also similar to the functionalization of 23 transmission assets as proposed by both Nova Scotia Power46 and New 24 Brunswick Power47 in their recent applications for approval of open access 25 transmission tariffs and subsequently approved by their respective regulators. 42 HQT-3, Document 1, pages 13-14 and page 17 R-3401-98, HQT-10, Document 1, page 3 44 D-2002-95, page 212 45 HQT-3, Document 1, page 11 46 Application by NSPI for Approval of an Open Access Transmission Tariff, May 12, 2004 47 NB Power Transmission Tariff Design, June 2002 43 13 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 4.2.1 Generation Connection 3 The Generation Connection function includes the step-up sub-stations used to 4 convert power to higher voltages for purposes of transmission along with 5 transmission lines used to connect a generation plant to the transmission 6 network. As a result, it consists of two sub-functions: a) Step-up Substations 7 and b) Connection Lines48. 8 9 Comments 10 11 In other jurisdictions49, these types of facilities are generally referred to as 12 Generation-Related Transmission Assets (GRTAs) and are often excluded from 13 the transmission revenue requirement used to determine their open access 14 tariffs. However, in HQT’s case the assets concerned are specifically designated 15 as “transmission” under the Act50 and are therefore recoverable through 16 transmission charges. 17 18 Furthermore, in BC and Manitoba, GRTAs include various types of facilities that 19 HQT has chosen to include in Networks function. In particular, while HQT 20 functionalizes the extra-high voltage lines and the high voltage direct current 21 (HVDC) lines that connect generation as “Network” facilities, in both BC and 22 Manitoba similar facilities are treated as GRTAs. In the case of these two 23 jurisdictions, the distinction is important as the costs associated with GRTAs are 24 treated as generation costs and excluded from the Transmission revenue 25 requirement used to derive the transmission tariffs51. The significance of the 26 categorization of GRTAs by HQT as Generation Connection vs. Network facilities 27 will depend upon whether there are any differences in how each of the two 48 HQT-3, Document 1, page 13 and HQT-6, Document 7, Question 36 a) For example, Nova Scotia and New Brunswick 50 HQT-3, Document 1, page 12 51 Instead the costs are treated as generation costs and recovered from the generators and, where generation is regulated, the associated rates. 49 14 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 functions are allocated and to which services they are allocated – both of which 2 are discussed below. 3 4 5 4.2.2 Network 6 In general, the Network function consists of those lines (and associated 7 transformers) that operate at a high voltage (44 kV and above) and are not 8 dedicated to the connection of either a generation plant or a high voltage 9 customer52. More specifically, the Network function consists of those 10 transmission facilities53 that: • 11 Operate at extra-high voltage and are used to carry electricity from 12 generation zones to centres of consumption and interconnections (the 13 Extra-High Voltage Transmission sub-function), • 14 Constitute the 450 kV direct current (DC) link between James Bay’s 15 Radisson sub-station and the Nicolet sub-station (the 450 kV 16 Transmission sub-function), or • 17 Form the shared transmission network and associated transforming equipment (the High Voltage Transmission sub-function). 18 52 53 HQT-6, Document 7, Question 36 a) HQT-3, Document 1, page 13 15 Evidence of William Harper 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 4.2.3 Customer Connection 2 3 The Customer Connection function consists of the following of equipment used to 4 connect the transmission network to the distribution network and to individual 5 customers receiving service at high voltage (HV): • 6 High voltage transformation stations that connect to distribution lines (the Step-down Stations sub-function), and 7 • 8 High voltage lines put in place to supply a specific high voltage customer or plant (the HV Customer Connection sub-function). 9 10 Furthermore, for purposes of this definition, HQD is not considered to be a high 11 voltage customer, as it is not supplied at a transmission voltage but, rather, at a 12 distribution voltage54. 13 14 Comments 15 16 It would appear from the definitions provided and the illustrative examples set out 17 in OC’s information requests55 that, while the Customer Connection function 18 includes the cost of the high voltage transformation stations servicing HQD, the 19 function does include the cost of any “radial” HV lines that may be required to 20 connect these transformation stations to HQT’s transmission network. Such lines 21 serve essentially the same function as “direct connection lines” to HV customers 22 except that they connect to a high voltage transformation station owned by HQT 23 instead of one owned by a “customer”. There is insufficient information on the 24 record to establish the costs associated with such facilities but, in principle, these 25 facilities should be identified and assigned to the Customer Connection function. 26 Such an approach would be consistent with the practice in Ontario and Nova 27 Scotia. 54 55 HQT-6, Document 7, Questions 36 d) and 36 g) HQT-6, Document 7, Question 36 16 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 4.2.4 Interconnections 3 The Interconnections function consists of equipment used to connect HQT’s 4 transmission network with a neighbouring transmission network56. It is made up 5 of: • 6 Lines and sub-stations that connect the Churchill Falls generating station in Labrador to HQT’s system (the Churchill Falls sub-function), and 7 • 8 Lines and other facilities used for interchange with neighbouring systems (the Other Interconnections sub-function). 9 10 11 Comments 12 13 The separation of the Churchill Falls interconnection from other interconnection 14 facilities was done in response to direction from the Régie57 regarding the need 15 to recognize the different role such facilities play on HQT’s overall system relative 16 to other interconnection facilities. However, it is questionable as to whether the 17 facilities used to integrate the power from Churchill Falls into HQT’s transmission 18 network should be considered part of the Interconnections function. In terms of 19 the role they play on HQT’s system they are more akin to the Generation Related 20 Transmission Assets (GRTAs) discussed earlier. However, as long as the cost is 21 tracked in a separate sub-function, the question of which “function” they are 22 assigned to is moot. What is critical is how the costs of the sub-function are 23 ultimately allocated to services (i.e., customers). 56 57 HQR-6, Document 7, Question 37 b) D-2002-95, page 212 17 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 4.2.5 Support and Control Centre Costs 3 During the initial stages of HQT’s cost allocation methodology, the costs 4 associated with the System Control Centre and the Telecontrol Centres are 5 identified and tracked in a separate “Control Centre” function. Similarly, the costs 6 of support activities are assigned to a “Support” function. However, before the 7 various functions’ costs are allocated to services, the costs accumulated in these 8 functions are pro-rated over the other four main functions using on the “rate 9 base” directly allocated to each of the functions58. 10 11 Comments 12 13 The prorating of support activities across the main cost allocation functions is 14 consistent with direction given by the Régie in its last transmission rate decision59 15 and is a generally accepted approach60 for allocating such costs. The underlying 16 principle is that the associated activities support all the primary functions of the 17 utility and there is generally no clear cost driver that can be associated with the 18 function due to the wide variety of activities reflected in the costs. 19 20 However, in the case of the Control Centre function, the activities involved and 21 the services provided are more clearly defined and it may be possible to allocate 22 them on a more direct basis. This issue will be discussed further in the 23 subsequent sections. 58 HQT-3, Document 1, page 17 and HQT-3, Document 6, page 4 D-2005-95, page 214 60 NARUC Cost Allocation Manual, page 105 59 18 Evidence of William Harper 4.3 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Cost Functionalization 2 3 4 4.3.1 Functionalization of Rate Base 5 HQT’s approved rate base for 2005 is $14,657.1 M and the authorized weighted 6 average cost of capital is 8.34%61. The rate base consists of the following items: 7 • Fixed Assets 8 • Intangible Assets (Actifs Incorporels) 9 • Unamortized Expenses 10 • Working Capital (including inventories and an allowance for working funds). 11 12 HQT’s approved rate base reflects the average value of assets expected to be in- 13 service throughout 2005. However, HQT’s accounting records do not provide the 14 monthly detail necessary to categorize the assets by function. So, instead, the 15 year-end value of the rate base is assigned to functions (and sub-functions) and 16 the results are used to allocate the authorized return on capital to the various 17 functions and sub-functions62. 18 19 Fixed Assets 20 21 HQT’s fixed assets consist of lines, stations, other network assets and support 22 assets: 23 • In the case of lines and stations, the assets are allocated directly to the four main functions. 24 • 25 In the case of the other network assets, the assets associated with the 26 System Control Centre and the Telecontrol Centres are directly assigned 27 to the Control Centre function. The balance of the other network assets 61 62 HQT-1, Document 1, page 6 HQT-3, Document 1, page 15 and HQT-6, Document 7, Questions 39 a) & b) 19 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 are directly assigned to either one of the major four functions or the 2 Support function. • 3 In the case of support assets, the costs are assigned directly to the Support function. 4 5 6 Intangible Assets 7 8 HQT is able to directly assign the intangible assets to the various functions63. 9 10 Unamortized Expenses 11 12 Unamortized expenses consist of employee future benefits, staff reduction costs, 13 development expenses and outstanding government refunds (regarding the ice 14 storm): 15 • Employee future benefits are allocated across the functions based on the salary costs associated with each. 16 • 17 Staff reduction costs are also allocated to across the functions based on the salary costs associated with each. 18 • 19 Development expenses are allocated across the functions based on the fixed assets associated with each function. 20 • 21 The outstanding government refund is allocated across functions based 22 on the value of overhead lines in the Southern Territory associated with 23 each function64. 63 64 HQT-3, Document 1, page 15 and HQT-3, Document 6, page 7 HQT-3, Document 1, page 16 and HQT-3, Document 6, pages 7-8 20 Evidence of William Harper 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Working Capital 2 3 The working cash portion of working capital is allocated to the functions based on 4 the direct gross expenditures assigned to each function, while the inventory 5 portion of working capital is allocated to the functions based on the fixed and 6 intangible assets assigned to each function65. 7 8 9 Comments 10 11 The components of HQT’s rate base are very similar to those of HQD (i.e., fixed 12 assets, intangible assets, unamortized expenses and working capital). Since the 13 HQD cost allocation methodology has gone through extensive consultation with 14 stakeholders and review by the Régie, it is useful to look at the approach used by 15 HQD in assigning its rate base to functions. In response to an OC information 16 request66, HQT provided a comparison of the methods used by itself and HQD to 17 assigned rate base to functions. The resulting schedule is replicated below. 65 66 HQT-3, Document 6, page 8 HQT-6, Document 7, Question 40 a) 21 Evidence of William Harper 1 2 3 4 5 6 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 TABLE 3 Tableau 40.a - Comparison of the HQT and HQD Methodologies – Rate Base Assets Capital Assets in operation Intangible Assets Distributor Transmission Company Direct assignment except for some support assets (actifs de soutien) Direct assignment except for some intangible assets Direct assignment salary costs (or payroll) salary costs salary costs salary costs salary costs salary costs Direct assignment Net capital assets + net intangible assets – NOTE 1 Net capital assets aerial lines South Terr. - NOTE 2 Direct assignment Non-amortized expenses and other assets Future social advantages - active Future social advantages - passive Measures for the reduction of the FTEs Development fees and other deferred fees Government reimbursement Direct assignment Working Capital Cash balance Materials, fuel and supplies 7 8 9 10 11 12 13 14 15 16 17 Direct Gross Expenses; taxes; bad credit Direct assignment Direct gross expenses – NOTE 3 Net capital assets + net intangible assets – NOTE 4 Note 1: The deferred fees for HQD and HQT are not of the same nature. Note 2: Direct attribution for HQD and then allocation according to capital assets and intangible assets of the aerial distribution network. For HQT, attribution according to the net capital assets of the aerial lines of the Southern Territory. Note 3: Allocation of HQD’s cash balance according to different line items of the cash balance, and, in the case of HQT, on the basis of gross direct charges, taking into account the insignificance of its cash balance. Note 4: Direct attribution, for HQD as well as for HQT, and then allocation according to capital assets and net intangible assets. 18 The only significant points of difference between the methodologies of the two 19 business units are in the areas of unamortized development expenses and 20 working capital: • 21 For unamortized development expenses, HQD is able to directly attribute 22 them to functions whereas in HQT’s case they must be allocated67 to 23 functions. • 24 HQD’s assignment methodology for working capital is also more detailed as it uses an inventory analysis to assign inventories to functions and, in 25 67 Note: In reality, costs that HQD directly attributes to distribution network assets must be “allocated” to individual sub-functions and this is generally done on the basis of net book value. 22 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 the case of working cash, the individual components are assigned 2 separately based on the assignment of the associated expense. In 3 contrast, HQT’s methodology uses a simpler and more aggregate 4 approach to assigning these rate base components. 5 6 The Régie, in its D-2003-93 decision, acknowledged that there was a need for a 7 balance between the level of analysis of cost allocation and the oversimplification 8 of the methods used.68 It observed that the method must simultaneously reflect a 9 sufficient degree of precision and take into account available data. Applying this 10 principle to the treatment of working capital, it is worth noting that the details 11 which would allow for direct assignment of inventories are not available69 and 12 that the type of inventory analyses undertaken by HQD could require a significant 13 effort on the part of HQT. Therefore, HQT’s proposed approach is reasonable. 14 15 In contrast, the information is readily available for HQT to undertake a finer 16 allocation of working cash requirements similar to that performed by HQD. HQT 17 rationalizes the simpler treatment of working cash on the basis of materiality70. 18 However, given that the information is readily available and modelling a more 19 precise treatment would require minimal to no effort, this argument is not 20 compelling. 21 22 The evidence71 filed by HQT in Phase 1 provides a detailed breakdown of the 23 sources of the working cash requirements. Over half the requirements are due to 24 the working cash needed to manage the revenue tax payments to the Québec 25 government while the next two largest contributors are for salaries (15%) and 26 capital taxes (10%). Based on these facts it is not clear why HQT selected direct 27 gross charges72 as the allocation factor for working cash requirements. The fixed 28 and intangible assets attributed to each function better reflect the relative 68 D-2003-93, page 144 HQT-6, Document 7, Question 45 b) 70 HQT-6, Document 7, Question 40 a), Table 40.a, Note #4 and HQT-6, Document 7, Question 45 c) 71 HQT-7, Document 1, page 34 of R-3549-2004 - Phase 1 72 HQT-3, Document 6, page 8 69 23 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 proportion of the overall revenue requirement by function73 and are also a 2 reasonable basis for allocating capital taxes. The use of fixed and intangible 3 assets as the allocation factor would also be consistent with the way the 4 allocation methodology assigns the expenses associated with capital and 5 revenue taxes to functions74. 6 7 Another factor which should be taken into account when determining the level of 8 precision required is the purpose of the cost allocation study in terms of what the 9 results of the study will be used for. In HQD’s case, the results are used to judge 10 the appropriateness of the relative rate levels of the various customer classes 11 served and can lead to rate adjustments that will impact on the customers 12 concerned. The results are also used to guide the rate design for each customer 13 class. As a result, a fair degree of precision is required. Similarly, if the intent is 14 to directly use the dollars assigned to each category of transmission service in 15 determining the “rates” then a fair degree of precision is desirable. 16 17 However, if the purpose of the analysis is to gauge the reasonableness of HQT 18 using the approach set out in FERC’s pro-forma OATT for assigning costs to 19 services and developing rates (but not as the basis for actually setting the rates) 20 then precision of the results may not be as critical (relative to ease of application) 21 in determining the procedures to be used in the cost allocation methodology. 22 23 It was not totally clear from the Régie’s Decision (D-2002-95) which of these two 24 purposes it had in mind when requesting the study. In its Application, HQT has 25 adopted the latter of these approaches and used the results of the cost allocation 26 methodology to demonstrate the reasonableness of its proposed rate 27 methodology and the resulting rates75. 73 Return on rate base and amortization represent a larger portion of the revenue requirement than direct gross charges. 74 HQT-3, Document 6, page 16 75 HQT-4, Document 1, pages 22-25 24 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 4.3.2 Functionalization of Cost of Service 3 HQT’s approved revenues for 2005 (excluding return on capital) are $1,368.1 4 M76. 5 This revenue requirement consists of the following items: 6 • Operating Expense 7 • Shared Services (including a return to the supplier) 8 • Capitalized Costs (represents a credit) 9 • Internal Billings 10 • Purchases of Electricity and Transmission Services 11 • Depreciation and Amortization 12 • Taxes 13 • Corporate Expenses 14 • Interest Related to Outstanding Government Refund (credit) 15 • Revenue from External Invoicing. 16 17 Operating Expense 18 19 HQT’s operating expense is tracked by cost centre77 and, subsequently, 20 assigned to the cost allocation functions as follows: • 21 The costs for the support units in the Corporate Centre (e.g., human 22 resources, planning & management, regulatory affairs, etc.) are assigned 23 directly to the Support function. • 24 The costs of the Energy Dispatch Control directorate within the Corporate Centre are assigned directly to the Control Centre function. 25 • 26 The costs for the support units in Facilities Operations are allocated across all the functions (including the Support and Control Centre 27 76 77 HQT-3, Document 6, page 23 HQT-3, Document 1, R-2549-2004 – Phase 1 25 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 functions) based on the hours of maintenance on the assets associated 2 with each function78. • 3 The costs of the Telecontrol Centres in Facilities Operations are allocated directly to the Control Centre function. 4 • 5 The costs for each territorial unit in Facilities Operations are allocated to 6 functions based on the hours of maintenance on the assets associated 7 with each function. 8 9 Shared Services Costs and Supplier Return / Capitalized OM&A / Internal Billings 10 11 These expenses are also tracked by cost centre and assigned to functions in the 12 same way as operating expenses. The only exception is capitalized OM&A costs 13 which are assigned to the functions based on the investment hours associated 14 with each function79. 15 16 Electricity Purchases 17 18 These purchase costs are assigned directly to the Support function. 19 20 Transmission Service Purchases 21 22 These are assigned directly to the Other Interconnections function. 23 24 Depreciation and Amortization 25 26 The depreciation associated with fixed and intangible assets is assigned directly 27 to the function based on the types of assets associated with each function. 78 79 Maintenance hours is defined in HQT-6, Document 7, Question 46 a.1) HQT-6, Document 7, Question 46 b.1) 26 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 The amortization of other costs (and credits) is allocated to the functions based 2 on the net book value of the fixed and intangible assets assigned to each 3 function. 4 5 Taxes 6 7 Municipal and school taxes are assigned directly to the Support function while 8 revenue and capital taxes are allocated to all functions based on the net book 9 value of the fixed assets and intangible assets associated with each function. 10 11 Corporate Expenses 12 13 Corporate expenses are allocated to the functions based 50% on the assignment 14 of direct OM&A to functions and 50% on the assignment of net fixed assets. 15 16 Interest on the Government Refund 17 18 The interest credit is allocated on the same basis as the unamortized balance for 19 the Government refund (under Rate Base). 20 21 External Invoices 22 23 24 External billings are tracked by cost centre and then assigned as follows: • The external billings to the support units in the Corporate Centre (e.g., 25 human resources, planning & management, regulatory affairs, etc.) are 26 assigned directly to the Support function. 27 • Corporate Centre are assigned directly to the Control Centre function. 28 29 30 The external billings to the Energy Dispatch Control directorate within the • The external billings for the support units in Facilities Operations are allocated across all the functions (including Support and Control Centre) 27 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 based on the hours of maintenance for the assets associated with each 2 function80. • 3 The external billings for the Telecontrol Centres in Facilities Operations are allocated directly to the Control Centre function. 4 • 5 The external billings for each territorial unit in Facilities Operations are 6 allocated to functions based on the hours of maintenance for the assets 7 associated with each function. 8 9 Comments 10 11 The components of HQT’s cost of service are also very similar to those of HQD 12 (i.e., direct OM&A, shared services, corporate costs, depreciation and 13 amortization, taxes, etc.). As with the allocation of rate base, it is useful to look 14 at the approach used by HQD in assigning its cost of service to functions. In 15 response to an OC information request81, HQT provided a comparison of the 16 methods used by itself and HQD to assign rate base to functions. The resulting 17 schedule is replicated below. 80 81 Maintenance hours is defined in HQT-6, Document 7, Question 46 a.1) HQT-6, Document 7, Question 41 a) 28 Evidence of William Harper 1 2 3 4 5 6 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 TABLE 4 Tableau 41.a - Comparison of HQD and HQT Methods – Expenses Necessary to the Cost of Service Distributor Transmission Company Direct assignment except for some support units according to average FTEs, salary costs and use of services same Direct assignment or according to the shared services expenses Direct assignment except for some support units according to average FTEs Direct assignment except for some support units according to salary costs Direct assignment and maintenance hours – NOTE 1 Expenses necessary to the cost of service Net operating expenses Gross direct expenses Shared services expenses Supplier return Capital costs Facturation interne émise same same same same Other Expenses Transmission services purchases Electricity purchases Depreciation and declassification of capital and intangible assets Depreciation and declassification – others Municipal & School Taxes Other taxes Corporate charges Interest related to government reimbursement Facturation externe (external billing) 7 8 9 10 11 12 13 14 15 16 17 18 N/a Direct assignment Direct assignment except for some support units according to average FTEs, salary costs and use of services Direct assignment except for some support units according to average FTEs, salary costs and use of services Direct assignment except for some support units according to salary costs Direct assignment, net capital assets and intangible assets 50% gross expenses & 50% net capital assets Direct assignment and net capital assets and intangible assets aerial lines Direct assignment Direct assignment Direct assignment Direct assignment Net capital assets + net intangible assets – NOTE 2 Direct assignment Net capital assets + net intangible assets 50% gross expenses & 50% net capital assets Net capital assets and aerial lines Southern Territory – NOTE 3 Maintenance hours – NOTE 1 Note 1: Accounting information from HQT not available by function with the exception of Corpo. Support, Corpo. CMÉ and Téléconduite (Remote Management). Allocation based on hours of maintenance or on hours of investments allows an approximation with direct attribution. Note 2 : Difficult for HQT to directly attribute these depreciations to corresponding functions, hence the use of the best available inductor, i.e. fixed capital and net intangible assets. Note 3: Direct attribution for HQD and, as a result, allocation according to fixed capital and net intangible assets of the lines of the aerial network. For HQT, attribution according to the net capital assets of the aerial lines of the Southern Territory. 29 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 The major differences between the two cost allocation methodologies are in the 2 allocation of direct OM&A expenses, depreciation of fixed assets, amortization of 3 other expenses and external billings. Most of these differences are due to the 4 fact that HQT’s functions are virtually all “asset based” whereas HQD’s functions 5 are a mix of asset based functions (e.g., distribution network – primary lines) and 6 activity based functions (e.g. customer care and accounting). 7 8 In the case of direct OM&A, HQD allocates the costs associated with distribution 9 networks across the various sub-functions based on net book value. In contrast, 10 HQT uses maintenance hours as its allocation factor in assigning maintenance 11 costs from cost centres to functions. Indeed, maintenance hours are likely a 12 more appropriate “allocator” than net book value. However, in the case of HQD 13 such information is not likely to be readily available. A similar observation 14 applies for shared services (including the service provider’s return), internal 15 billings and external billings82. 16 17 In the case of fixed asset depreciation, HQT is able to directly assign the 18 depreciation to functions – since the assets associated with each function and 19 sub-function are clearly defined and tracked. In contrast, in some cases, HQD 20 has to allocate the depreciation associated with a cost centre to functions and/or 21 sub-functions (e.g., the cost centres for Customer Care - Support; Networks - 22 Support and Networks - Operations). 23 24 In the case of amortization of other expenses, HQT allocates the total to 25 functions based on the net book value of the fixed and intangible assets 26 associated with each function. In contrast, HQD uses a variety of allocators 27 selected according to the nature of the costs associated with each of the 28 components of its amortization of other expenses (e.g., the amortization of the 29 government refund is based on the overhead lines associated with each 30 function). 82 HQT-6, Document 7, Questions 46 a.3); 46 c); and 46 e) 30 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 HQT claims that it is difficult for it to directly attribute the amortization of its 3 individual line items for unamortized expenses to functions and, therefore, a 4 single global allocator is used83. While, direct attribution may be difficult, the rate 5 base values associated with many of these line items are assigned separately by 6 HQT and, in each case, a unique allocator is used based on the nature of the 7 costs. Furthermore, it is interesting to note that while HQT uses the net book 8 value of fixed and intangible assets to allocate the amortization of the 9 government refund to functions, the interest credit on the outstanding balance is 10 allocated based on the net book value of the overhead lines of the Southern 11 Territory associated with each function84. There is no reason why the same 12 allocator could not be used to assign the annual amortization associated with 13 each rate base item as is used by HQT to allocate the outstanding unamortized 14 balance. This would yield, with very little additional effort, more accurate results 15 in terms of cost causality. 16 17 Finally, there is an inconsistency in HQT’s evidence regarding how the external 18 billings associated with the four territorial units in Facilities Operations are 19 allocated to functions: • 20 The text in the evidence suggests that the allocation is done based on the 21 net book value of the fixed and intangible assets associated with each 22 sub-function85, whereas • 23 The schematic provided in the evidence suggests that the allocation is done based on the hours of maintenance associated with each function86. 24 83 HQT-6, Document 7, Question 41 a), Table 41.a, Note 3 HQT-3, Document 6, page 16 85 HQT-3, Document 6, page 16 86 HQT-3, Document 6, page 17 84 31 Evidence of William Harper 4.4 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Classification of Costs 2 3 The purpose in “classifying” the costs in each function (and sub-function) is to 4 establish, based on system design and operating characteristics, the major 5 drivers that determine the level of cost the utility has incurred or will incur for 6 each function. These cost drivers will then be used to allocate the cost in each 7 function to customer classes (or in HQT’s case - classes of services). Functions 8 are typically classified as either: • 9 Demand costs – considered to be those incurred to meet customers’ maximum system usage, 10 • 11 Energy costs – considered to be those incurred to provide energy over a period of time, or 12 • 13 Customer costs – considered to be those related to the number of customers or contracts served by the utility’s system. 14 15 16 In its evidence, HQT asserts87 that transmission assets are designed, planned, 17 operated and maintained in order to meet the maximum power requirements of 18 its customers. As a result, HQT proposes to classify all of the costs in its various 19 cost allocation functions as demand-related. HQT goes on to explain88 that the 20 classification of transmission assets as demand-related applies equally to 21 generation connection assets and to network assets, as the former are designed 22 to allow for the integration of the capacity of the generating stations. 23 24 Comments 25 26 The classification of transmission costs as demand-related is consistent with the 27 industry practice as outlined in the NARUC manual89 and seen in Canadian 28 utilities prior to the unbundling of service and the wide-spread adoption of 87 HQT-3, Document 1, pages 20-21 HQT-3, Document 1, page 23 89 1992 NARUC Electric Utility Cost Allocation Manual, page 75 88 32 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 FERC’s pro-forma OATT90. Furthermore, the rationale for classifying 2 transmission costs by these utilities as demand-related was the same as that 3 currently put forward by HQT – the system was designed and operated to meet 4 customer and system peak demand requirements. To a large extent, the assets 5 and services provided by HQT are similar to those of “transmission” as defined in 6 a traditional bundled utility environment and thus this traditional rationale 7 continues to apply. However, given the unbundling of transmission and 8 generation services and the statutory definition of transmission in Québec, there 9 is a need to carefully reconsider whether it is appropriate to classify all of HQT’s 10 costs as demand-related. 11 12 The first area where this occurs is with respect to HQT’s System Control Centre 13 and Telecontrol Centres. While larger systems likely require larger and more 14 costly control centres and telecontrol support, it is not evident that system 15 demand is any more a defining factor than say system energy requirements. 16 Furthermore, since the control centres manage the operation of the system 17 throughout the year91, they serve to deliver both capacity and energy. Finally, 18 prior to “unbundling” and open access, generation dispatch and transmission 19 system management/control were typically performed as one activity. Indeed, in 20 various jurisdictions,92 this continues to be the case. As a result, one could 21 question whether, conceptually, HQT’s Control Centre function should be pro- 22 rated over the four main functions and, ultimately, classified as demand-related – 23 as proposed by HQT. As discussed later in Section 4.5.2, this Evidence 24 concludes that the Control Centre function should be classified as energy-related 25 and its costs allocated directly to services. 26 27 Generation Connection is another area that requires some reflection with respect 28 to the appropriateness of the proposed classification, as noted by the Régie in D90 Note: Implementation of the FERC pro-forma OATT does not require a full and comprehensive cost allocation study as evidenced by HQT’s first Tariff Application. 91 HQT-6, Document 1, page 34, Question 13.1 92 For example, BC and Ontario 33 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2002-9593 . As discussed above in Section 4.2.1, generation integration costs 2 are often considered to be “generation” costs and are not included in 3 transmission for purposes of cost allocation94 or open access tariff design95. 4 Their inclusion as transmission cost by HQT arises as a result of the statutory 5 definition of transmission. As generation costs, the costs of these facilities would 6 likely be classified as both energy and demand-related. However, since there is 7 no generally accepted method for doing so96 and the impact on the overall results 8 of the cost allocation methodology would likely be minimal97, HQT’s proposal to 9 treat them as demand-related should be acceptable. 10 4.5 11 Allocation of Functionalized Costs to Services 12 13 14 4.5.1 Services Provided 15 As discussed in Section 3.2, the services provided by HQT are Native Load 16 service, Network Integration service and PTP service. Furthermore, point to 17 point service is broken down as between long-term firm PTP service and various 18 short-term PTP services of terms lasting less than one year. For purposes of its 19 cost allocation methodology, HQT groups all PTP services together and treats 20 them as a single service98. Also, since there have never been and there are not 21 expected to be any customers taking Network Integration service, this service is 22 not considered separately in the cost allocation methodology,99 but rather 23 grouped with Native Load service. 93 page 213 Examples would be BC and Manitoba 95 Examples would be New Brunswick and Nova Scotia 96 Just as there is no generally accepted method for classifying generation related costs. See also HQT-6, Document 1, page 46 (second bullet point) 97 HQT-6, Document 1, page 47, Question 19.2 a) 98 HQT-6, Document 1, Question 17.1, page 42 99 HQT-3, Document 1, page 27 94 34 Evidence of William Harper 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Comments 2 3 Typically, in establishing customer classes or services for purpose of cost 4 allocation (and, ultimately rate design), a utility will group together customers (or 5 services) that use the utility’s system and its various cost allocation functions in a 6 similar manner. 7 8 In HQT’s case, Native Load service and PTP service customers are 9 fundamentally different in terms of how they contract for service, what services 10 they are charged for, and how they are billed. As a result, it is appropriate to 11 separate them for cost allocation purposes. 12 13 Furthermore, while there are currently no Network Integration customers, the 14 treatment of such customers more closely matches that of Native Load Service 15 than PTP service. As a result, should a customer request Network Integration 16 service it would be reasonable for HQT to group such customers with Native 17 Load Service for purposes of cost allocation. 18 19 However, HQT’s grouping of all PTP customers and defining them as one 20 “service” for cost allocation purposes, ignores the fact that there are fundamental 21 differences between the nature of the service provided to the different types of 22 PTP customers: • 23 Customers contracting for non-firm short-term PTP service have a lower 24 service priority than those contracting for firm short-term PTP service. In 25 turn, customers contracting for long-term PTP service have a higher 26 service priority than those contracting for short-term firm PTP service and, 27 indeed, long-term firm PTP customers have equal service priority with 28 Native Load and Network Integration service100. • 29 In the case of requests for firm PTP service, HQT is required to use due diligence to expand or modify its transmission system to provide the 30 100 HQT-6, Document 1, Question 35.1 and HQT-5, Document 1, page 13, Table 1 35 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 requested firm PTP transmission Service, provided the transmission 2 customer agrees to compensate HQT in accordance with a prescribed 3 capital contribution policy101. However, for practical purposes, it is unlikely 4 that HQT would be able to expand its system to meet requests for short- 5 term PTP service, unless such requests were made well in advance of the 6 timelines required under the current terms and conditions of service102. 7 8 In reality, short-term PTP service customers (both firm and non-firm) will typically 9 be served from existing available capacity and the objective in offering such 10 services is to improve the utilization of (and the revenue generated by) the 11 transmission system 103. In contrast, the loads associated with long-term firm 12 PTP service are incorporated into the utility’s planning processes (like Native 13 Load and Network Integration service) and used to determine future capacity 14 needs and the resulting facilities required. Put another way, customers receiving 15 short-term service (firm and non-firm) generally utilize a transmission system 16 designed and constructed to meet the needs of long-term firm PTP, Native Load 17 service and Network Integration service customers. Short-term service is 18 provided if the utility determines that the transmission capacity needed to meet 19 their service requests is not otherwise required104. 20 21 In order to reflect this fundamental difference, short-term and long-term PTP 22 service need to be addressed separately in the cost allocation methodology. 23 Some may argue that it is possible to retain the long-term and short-term PTP 24 customers as a single customer class and recognize these differences in the 25 nature of the service provided through the factors used105 in the allocation of the 101 HQT-5, Document 3, Section 13.5 HQT-6, Document 9, Questions 52.5 and 52.6 103 HQT-3, Document 1, pages 30-31and HQT-4, Document 1, page 11 104 This could be due to either the existence of excess transmission capacity overall and/or the fact that the service requirements of long-term firm PTP, Native Load service and Network Integration service customers will vary throughout the year. 105 For example, if short-term PTP customers are not considered in determining the network facilities required then their requirements would not be included in the allocation factors used to assign the costs of the network function to PTP services. 102 36 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 functionalized transmission costs. However such an approach would also credit 2 all of the revenues from short-term PTP customers to the PTP service category 3 for purposes of benchmarking revenues and costs for Native Load/Network 4 Integration service and PTP service. This would be inappropriate since: • 5 The rates for short-term PTP service are not strictly cost-based and to some extent are based on opportunity pricing106, and 6 • 7 Allocating all of the revenues arising from short-term PTP service to the 8 PTP service category fails to recognize that the revenue arose as a result 9 of short-term service customers utilizing a transmission system built to serve both Native Load and long-term PTP customers107. 10 11 Indeed, HQT’s proposed derivation of Native Load and long-term PTP service 12 rates properly recognizes this point and removes short-term PTP service 13 revenues from the total revenue requirement before determining the annual 14 rates108 for either Native Load service or long-term PTP service. 15 16 In order to properly reflect short-term PTP service in the cost allocation 17 methodology: • 18 It needs to be separated out as a different service category from long-term PTP service, and 19 • 20 The net revenue (i.e., total short-term PTP service revenues less any 21 allocated costs) from short-term PTP service should be “allocated” to both 22 Native Load/Network Integration service and long-term PTP service, 23 thereby reducing the costs for both classes of service. 24 25 26 4.5.2 Allocation Factors 27 In the previous stage, HQT categorized all the costs assigned to each of the cost 28 allocation functions as being demand-related. For purposes of actually allocating 106 HQT-4, Document 3.1, page 7 HQT-6, Document 9, Question 46.5 108 HQT-4, Document 1, page 15, Table 3. 107 37 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 each function’s costs to services, HQT proposes to directly assign costs where 2 possible and then to use each service’s contribution to the annual transmission 3 system peak to allocate the remaining costs. This methodology is referred to as 4 the 1-CP (i.e. one coincident peak) method, as it looks at each service’s load 5 coincident with the annual (or single) system peak. The loads actually included 6 in the 1-CP allocation factor for each “function” are then based on the services 7 utilizing the assets assigned to the function109. 8 9 Selection of 1-CP 10 11 HQT acknowledges that there are other allocation factors besides 1-CP that are 12 used elsewhere to allocate costs categorized as demand-related110 and, in 13 particular, notes the use of 3-CP, 4-CP and even 12-CP elsewhere for purposes 14 of allocating such costs. However, HQT argues that the predominance of electric 15 space heating distinguishes its system from others in that its annual load 16 significantly exceeds its average annual demand. HQT goes on to note that the 17 results of various FERC tests conducted by its expert, Dr. Ren Orans, clearly 18 show that 12-CP should be rejected and that 1-CP is appropriate111. 19 20 Comments 21 22 Some form of coincident peak allocation factor is the most common method of 23 allocating transmission-related costs. This is supported both by practice in the 24 US (as reported112 by Dr. Ren Orans) and the practice of many Canadian utilities 25 both in the cost allocation methodologies supporting their retail rates113 and those 26 supporting their open access transmission tariffs114. 109 HQT-3, Document 1, pages 25-27 HQT-3, Document 1, pages 26-27 111 HQT-3, Document 1, page 29 112 HQT-4, Document 3, page 15 113 Based on Consultant’s review of practices approved by regulators in other Provinces most use some form of CP as the allocation factor for transmission costs in their cost allocation methodologies supporting retail rates. 114 HQT-6, Document 7, Question 49 a) 110 38 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 However, as noted by Dr. Orans115, the actual CP allocation factor approved by 3 FERC varies across US utilities from 12-CP (i.e., the average contribution of 4 each service to the 12 monthly peaks of the transmission system) to 3 or 4-CP 5 (i.e., the average contribution of each service to the monthly peaks in the 3 or 4 6 months of the year with the highest transmission peaks) to 1-CP. Dr. Orans 7 observes that if a utility experiences a pronounced peak during 1, 3 or 4 months, 8 then FERC precedent supports the use of an allocation factor other than 12-CP. 9 However, according to Dr. Orans, the examples of the use of 1-CP appear to be 10 limited116. 11 12 In contrast to FERC practice, data published by NARUC117, indicates that even 13 for US states which are strictly winter or summer peaking, the state regulators 14 using coincident peak allocation tend to have adopted 4-CP and 12-CP as 15 frequently as 1-CP (i.e., there was roughly an equal use of all three methods). 16 17 In Canada, the majority of the other utilities, using the FERC pro-forma OATT, 18 utilize 12-CP to allocate costs between Network and PTP customers118. In 19 contrast, 1-CP appears to be the predominant allocation factor used for 20 transmission costs in cost allocation studies performed in support of retail 21 rates119. 22 23 The conclusion to be drawn from the preceding observations is that there are no 24 hard rules or clear precedents to direct when 1-CP vs. 3- or 4-CP vs. 12-CP 25 should be used. A good example of this is the methodology used to derive 26 BCTC’s open access tariff. As Dr. Orans has noted120, the methodology used by 27 the BCTC OATT is even more extreme than the 1-CP allocation factor. 115 HQT-6, Document 7, Question 51 d) and HQT-4, Document 3, pages 15-16 HQT-6, Document 7, Question 51 d); HQT-4, Document 3, page 15 and HQT-6, Document 9, Question 56.1 117 NARUC, Utility Regulatory Policy in the United States and Canada 1995-1996, page 495 118 Of the five utilities – four use 12-CP. 119 Based on the Consultant’s understanding of various provincial utility practices. 120 HQT-6, Document 7, Question 51 d) 116 39 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 However, application of the FERC tests to BCTC data would appear to support 2 the use of the 12-CP allocation factor121. 3 4 Overall, Dr. Orans rejection122 of 12-CP in the case of HQT is reasonable – in 5 light of the winter peaking nature of the system and the monthly variation in 6 transmission system peaks123. Dr. Orans also suggests that while the choice as 7 between 1-CP and 3- or 4-CP is not as clear124, the application of the FERC tests 8 generally support a 3- or 4-CP allocation125. As a result, while HQT and Dr. 9 Orans support the continued use of 1-CP126, there are equally compelling 10 reasons for adopting a 3-CP allocation factor, including: • 11 The relatively close proximity of the December, January and February 12 transmission system peak requirements127 and Dr. Orans’ observation that 13 the coldest day of the year can fall in any of these three months128, • 14 The fact that over the past 4 winters the maximum utilization of the transmission system has occurred in December, January or February 129, 15 • 16 US state regulatory practice to adopt 1-CP, 3- or 4-CP and 12-CP for utilities with single seasonal peaks130, and 17 • 18 The lack of any broad adoption of 1-CP for purposes of setting transmission tariffs. 19 20 When issues of year-to-year stability are also taken into account, it would be 21 prudent for the Régie to adopt the 3-CP allocation factor. 121 HQT-6, Document 7, Question 74 e) HQT-4, Document 3, page 17 123 HQT-6, Document 7, Question 50.a) and HQT-4, Document 3, page 18, Table 3 124 HQT-6, Document 9, Question 52.3 125 HQT-6, Document 9, page 68, Question 52.3 126 HQT-6, Document 9, page 63, Question 50.1 127 HQT-6, Document 7, Question 50 a) and HQT-6, Document 9, Question 55.1 128 HQT-4, Document 3, page 19 129 HQT-6, Document 1, page 35, Question 14.1.a). 130 NARUC, Utility Regulatory Policy in the United States and Canada 1995-1996, page 495 122 40 Evidence of William Harper 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Allocation of Generation Step-Up Function Costs 2 3 HQT’s proposal is to allocate the costs assigned to the Generation Step-Up 4 function between Native Load Service and PTP service based on: • 5 Native Load’s forecasted demand (MW ) at the time to the transmission 6 system peak – less the capacity of the Churchill Falls interconnection 7 point131, and • 8 9 The anticipated MW of contracted long-term PTP service. HQT explains132 that the capacity of the Churchill Falls interconnection is 10 excluded from Native Load since Churchill Falls’ costs are allocated elsewhere 11 as part to the Interconnections function. 12 13 Comments 14 15 As mentioned earlier, the role of the Churchill interconnection more closely 16 matches that of facilities which integrate generation into the utility’s transmission 17 system network (than facilities that interconnect two neighbouring systems). 18 However, it is not immediately evident that the power from Churchill Falls is used 19 exclusively to service Native Load as opposed to being used to meet HQP’s 20 other delivery obligations. As a result, it would be more appropriate to “allocate” 21 the Generation Step-Up function costs between Native Load/Network Integration 22 and PTP service based on the total requirements of each service.133 23 24 Allocation of Network Function Costs 25 26 HQT’s proposal is to allocate the costs of this function between Native Load 27 service and PTP service based on: 131 HQT-3, Document 1, page 31 HQT-6, Document 7, Questions 53 a) & b) 133 Allocation Factor “B” from HQT-3, Document 6, page 23, Table 10 132 41 Evidence of William Harper • 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Native Load’s forecasted demand (MW ) at the time to the transmission 2 system peak – including the capacity of the Churchill Falls interconnection 3 point134, and • 4 The anticipated MW of contracted long-term PTP service. 5 6 Comments 7 8 Inclusion of all service loads is appropriate since all transmission services utilize 9 the network facilities. 10 11 Allocation of Connection Function Costs 12 13 HQT’s proposal is to directly allocate the costs of transformer stations connecting 14 to distribution lines135 and the cost of lines dedicated to the connection of a high 15 voltage customer136 to Native Load service. 16 17 Comments 18 19 This is reasonable as, by definition, all of the facilities in the function are used 20 specifically by HQD and its customers for the receipt of power. 134 HQT-3, Document 1, page 31 HQT-6, Document 7, Question 36 h) 136 HQT-6, Document 7, Question 36 b) 135 42 Evidence of William Harper 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Allocation of Interconnection Function Costs 2 3 HQT’s proposal is to allocate the costs assigned to the Churchill Falls sub- 4 function between Native Load Service and PTP service based on: • 5 Native Load’s forecasted demand (MW ) at the time of the transmission 6 system peak – including the capacity of the Churchill Falls interconnection 7 point137, and • 8 9 10 The anticipated MW of contracted long-term PTP service. However, the costs assigned to the Other Interconnections sub-function would be allocated between Native Load Service and PTP service based on: • 11 The import capability of the Interconnections (as the allocation factor for Native Load), and 12 • 13 The export capability of the Interconnections (as the allocation factor for PTP service).138 14 15 16 Comments 17 18 As discussed above, the power from Churchill Falls could be used (by HQP) to 19 meet either Native Load requirements or fulfill its obligations to other customers. 20 As a result, the proposed allocation of the Churchill Falls inter-tie costs is 21 reasonable. 22 23 In the case of the facilities associated with the Other Interconnections sub- 24 function, they can be used either as a point of receipt or a point of delivery for 25 HQT’s transmission service. If used as a point of receipt (i.e., for the import of 26 power to Quebec), the facilities could be supporting either PTP or Native Load 27 service. However, if used as a point of delivery (i.e., for the export of power from 28 Quebec), the facilities are only supporting PTP service. As a result, it is 137 138 HQT-3, Document 1, page 31 HQT-3, Document 1, page 31 43 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 appropriate to split the cost of the sub-function between imports and exports, as 2 HQT has done. But then the two parts should be allocated as follows: • 3 The 39.57% 139 associated with imports should be allocated to both Native 4 Load and PTP service based on their total requirements (as opposed to 5 just Native Load as proposed by HQT); while • 6 The remaining 60.43% associated with exports should be allocated solely to PTP service. 7 8 9 Allocation of the Support Function and Control Centre Function Costs 10 11 As mentioned earlier, the HQT pro-rates the costs of these two functions over the 12 four major functions - prior to the costs of the four functions being classified and 13 allocated to customers. 14 15 Comments 16 17 In the case of the costs assigned to the Support function, this approach is 18 reasonable and consistent with industry practice for allocating such costs140 and 19 the directions of the Régie from D-2002-95141. 20 21 However, in the case of the Control sub-function, such an approach would result 22 in the cost allocation methodology failing to recognize that while short-term PTP 23 service does not impact on the total facilities required by HQT (i.e., short-term 24 PTP utilizes lines, stations, etc. constructed based on Native Load and long-term 25 PTP service requirements), the level of activity and requirements of the system 26 control centre are likely driven by all transactions on HQT’s system – including 27 short-term transactions. 139 HQT-6, Document 7, Question 54 a) and HQT-3, Document 6, page 23, Table 10 NARUC Cost Allocation Manual, page 105 141 D-2002-95, page 214 140 44 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 As a result it would be appropriate to retain the Control Centre function through 2 the classification and allocation steps of the cost allocation methodology and, 3 ultimately, allocate a portion of the function’s costs to short-term PTP service as 4 well. 5 6 Such an approach means an appropriate allocation factor must be identified for 7 assigning the Control function costs to Native Load service, long-term PTP 8 service and short-term PTP service. While some variation of coincident peak 9 demand is a reasonable allocation factor for the four main functions, such a 10 factor is not appropriate in the case of the Control Centre function. Given the 11 role of system control in managing all the transactions on HQT’s system 142, a 12 broader measure of “system usage” is required that considers the whole year 13 and is not focused just on usage at the time of the system’s monthly peaks or 14 annual peak. 15 16 There are a number of possible alternatives including 12-NCP by service class, 17 total contracted volume by class (i.e., contracted MW times contract period), and 18 total energy transmitted by service class. Of these, total contracted volume by 19 class is the recommended allocation factor. It provides the best measure of the 20 transactions associated with each service class that must be managed by system 21 control. 22 23 Once the costs attributable to short-term PTP service have been identified, the 24 net revenues associated with the service (i.e., projected short-term PTP 25 revenues less allocated costs) should be pro-rated over the other two services 26 based on the total costs already assigned to both. 142 HQT-6, Document 7, Question 35 c.2) 45 Evidence of William Harper 1 4.6 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Impact of Comments Regarding HQT’s Cost Allocation Methodology 2 3 Table 5 sets out the allocation of 2005 total cost service to Native Load and long- 4 term PTP service using the foregoing recommendations regarding the allocation 5 of each function and sub-function’s costs. The table does not reflect the impacts 6 of any of the suggested changes as to how cost should be allocated to functions. 46 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 TABLE 5 Generation Step-Up - Stations - Lines Network - Very High Voltage - 450 kV - High Voltage 596.4 409.6 25.4 161.3 9,859.3 812.4 1408.8 1584.4 0.9879 0.0121 0.0000 1565.2 19.2 0.0 Customer Connections - Stations - HV Customer 203.3 181.6 21.6 1,863.4 153.6 356.9 401.3 1.0000 0.0000 0.0000 401.3 0.0 0.0 Interconnections - Churchill Falls - Others 79.4 16.2 63.2 815.5 194.0 621.6 67.2 16.0 51.2 146.6 32.2 114.4 164.9 36.2 128.7 0.9879 0.3909 0.0121 0.6091 0.0000 0.0000 35.8 50.3 0.4 78.4 0.0 0.0 Control Centre 158.3 159.6 13.2 171.5 192.8 0.9391 0.0127 0.0483 181.1 2.4 9.3 Support 252.8 417.9 34.4 287.2 Sub-Total 1368.1 14,840.6 1222.9 2591.0 2591.0 2478.3 103.4 9.3 -78.0 0.0 0.0 -78.0 2513.0 2478.3 103.4 -68.7 ST PTP Revenues Total Recovery From NLS and LT PTP Rate Allocated Base Return ($M) ($M) 1,724.8 142.1 Total Costs ($M) 220.1 Total Costs with Support ($M) 247.6 Initial Service Allocation Factor Initial Cost Allocation Native LT ST Native LT ST Load PTP PTP Load PTP PTP ($M) ($M) ($M) 0.9879 0.0121 0.0000 244.6 3.0 0.0 Cost of Service ($M) 78.0 66.2 11.7 Final Cost Allocation Native LT Load PTP ($M) ($M) 2412.3 100.7 47 Evidence of William Harper 1 5 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 HQT’S PROPOSED TRANSMISSION SERVICE PRICING METHODOLOGY 2 3 4 5.1 Overview 5 6 HQT’s transmission service pricing for Native Load and firm PTP service is not 7 based on a detailed cost allocation analysis but rather follows the approach set 8 out by FERC in its pro-forma OATT 143. According to Dr. Orans’ direct 9 testimony144, this involves the following seven-step process: 1. Determine HQT’s TRR for the appropriate forward test year period, which 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 2. 3. 4. 5. 6. 7. 143 144 is calendar year 2005 for this application. The TRR was approved by the Régie in Phase 1 of the current case. Estimate the revenues to be collected from ST-PTP sales over the same test year period. Subtract the ST-PTP revenues from the TRR from Step 1 to develop an estimate of the Net TRR to be collected from NITS, NLS and LT-PTP customers. Estimate the transmission system’s single coincident peak (1-CP), the total transmission load at the time of the transmission system’s annual peak. This step entails estimating the coincident peak loads of the LTPTP, NITS and NLS customer classes. The peak load estimates of NLS are based on a normal weather forecast and include losses. The LT-PTP forecast is based on reservations. Divide the Net TRR by the 1-CP load from Step 4 to develop the annual LT-PTP rate. Estimate the LT-PTP revenues as the product of LT-PTP rate times an annual forecast of LT-PTP reservations. Subtract the LT-PTP revenues from the Net TRR to develop an estimate of the network revenues. Network revenues are then allocated to each network customer, who may receive NITS or NLS, based on the customer’s load ratio share of HQT’s 1-CP. HQT-4, Document 3, page 13 and HQT-6, Document 9, page 56, Question 46.1 HQT-4, Document 3, pages 13-14 48 Evidence of William Harper 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Comments 2 3 Table 6 sets out how HQT’s proposed seven steps align with the traditional 4 three-stage rate setting process of revenue requirement determination; cost 5 allocation and rate design (see Section 4.1). 6 7 Table 6 8 Comparison of Rate Setting Processes 9 Tradition Rate Setting Process HQT’s Transmission Service Rate Setting Process Stage 1 – Revenue Requirement Steps #1 and #2 Determination Stage 2 – Cost Allocation Steps #3 and #4 Stage 3 – Rate Design Steps #5, #6 and #7 10 11 12 5.2 Treatment of Short-Term PTP Revenues 13 14 HQT subtracts the anticipated revenues from short-term PTP service from the 15 total approved revenue requirement prior to allocating the costs between Native 16 Load/Network Integration service and long-term PTP service. 17 18 Comments 19 20 Using the revenues from short-term PTP service to offset the costs used to 21 derive firm transmission rates is consistent with FERC’s application of its pro- 22 forma tariff145 and practice elsewhere146. It is also consistent with the fact that: 145 146 Order 888-A, page 256 HQT-6, Document 9, page 54, Question 46.5 49 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 a) HQT’s transmission facilities are designed to meet its service 1 2 commitments to Native Load/Network Integration service and long-term 3 PTP service147, b) the objective in offering short-term service is to improve the utilization of 4 5 the overall transmission system and generate additional revenues that will 6 offset the costs otherwise recovered from long-term firm customers148, and 7 c) short-term PTP service rates are frequently discounted in order to achieve the objectives set out in (b) 149. 8 9 10 In its Application, HQT noted that by marketing of both long-term and short-term 11 PTP transmission service, it can optimize the use of the system and obtain 12 additional revenues to reduce the share of the revenues that must be borne by 13 Native Load service. Moreover, HQT observed that in the absence of PTP 14 service, the entire cost of service would have to be borne by native load150. 15 HQT’s expert, Dr. Orans, has also indicated151 that the typical allocation between 16 Native Load/Network Integration service and long-term PTP service entails 17 subtracting short-term PTP revenues from the total revenue requirement prior to 18 determining the rates for both service categories. However this practice is not 19 universal. In its recent application for an open access tariff, BCTC took the 20 position, when dealing with this issue, that since its Network Customers (the 21 rough equivalent to HQT’s Native Load service) “backstop the entire 22 Transmission Revenue Requirement”152, it was appropriate for short-term 23 revenues to be credited against the revenue to be paid by network customers 24 (and not long-term PTP service customers). 147 HQT-6, Document 9, page 71, Question 52.6 HQT-4, Document 1, page 11 149 HQT-4, Document 3.2, pages 7-8 150 HQT-4, Document 1, page 11 151 HQT-6, Document 7, Question 49 a) 152 BCTC Response to BCOAPO 8.0.g 148 50 Evidence of William Harper 1 5.3 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Allocation of Revenue Requirement between Native Load/Network Integration Service and Long-term PTP Service 2 3 4 As described above, HQT allocates the net revenue requirement (i.e., the total 5 revenue requirement less short-term PTP revenues) between Native 6 Load/Network Integration service and Long-term PTP service based on the 7 contribution of each to the transmission system’s annual peak load (i.e., based 8 on 1-CP). HQT’s rationale for using 1-CP to allocate the revenue requirement 9 between these two services is similar to that put forward to support the use of 1- 10 CP in HQT’s proposed cost allocation methodology – namely, that the 11 transmission system is designed to meet the system peak153. Furthermore, 12 HQT’s expert, Dr. Ren Orans, notes154 that “if a utility experiences a pronounced 13 peak, during 1, 3 or 4 months, the FERC precedent supports the use of another 14 CP method” (i.e., other than 12-CP) and, subsequently, concludes that the 15 standard tests developed by FERC provide a basis for rejecting the 12-CP 16 method in HQT’s case155. Dr. Orans then presents the results of various 17 supplementary analyses and concludes that “it is reasonable to allocate HQT’s 18 transmission revenue requirement according to each transmission service class’ 19 contribution to the single system coincident peak load in January”156. 20 21 Comments 22 23 As the Comments offered in Section 4.5.2 indicate, when practice across 24 Canada, FERC and US state regulators is considered, there is no clear and 25 consistent precedent for the use of 1-CP versus 3- or 4-CP versus 12-CP for 26 allocating transmission costs – even for seasonal peaking utilities. However, in 27 cases such as HQT’s, it is reasonable to conclude157 that use of a 12-CP 28 allocation factor would be inappropriate given the wide variation in monthly 153 HQT-4, Document 1, pages 23-24 HQT-4, Document 3, page 15 155 HQT-4, Document 3, page 17 156 HQT-4, Document 3, page 20 157 As the application of the FERC tests demonstrates (HQT-4, Document 3, page 16). 154 51 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 system peaks throughout the year. Furthermore, while the original FERC pro- 2 forma tariff158 would appear to support the use of 12-CP, the Commission has 3 made it clear that utilities are free to propose alternative allocation factors, 4 provided they are consistent with the utility’s transmission system planning and 5 would not result in an over-collection of the utility’s revenue requirement159. 6 7 However, the choice between 1-CP and, say, 3-CP becomes more judgmental. 8 Therefore, while it may be “reasonable” to allocate transmission costs using 1-CP 9 (as concluded by Dr. Orans), there are compelling reasons for using 3-CP as 10 already discussed in Section 4.5.2. Table 7 sets out the determination of the 11 annual rate for 2005 based on a 3-CP allocation factor. 12 13 Table 7 14 2005 Annual Transmission Service Rate 15 Based on 3-CP 16 Approved Required Revenues (a) Short-term Point to Point Revenues (b) Residual Revenues Required (a) Native Load Service (c) 17 18 19 20 21 22 $2,591 M $78 M $2,513 M 33,168 MW Long-term PTP Transmission Service (a) 405 MW Total Transmission Service Requirements 33,573 MW Annual Rate $74.85 / kW Sources: 158 159 a) HQT-4, Document 1, page 15 b) HQT-4, Document 1, page 15. Assumes short-term rates unchanged. If these rates were adjusted in accordance with the annual rate then the annual rate would be slightly lower, i.e. $74.79 / kW c) HQT-6, Document 7, page 79, Question 52.a) Order 888, page 296 and Order 888, Appendix D, Section 34 FERC Order 888-A, pages 239 and 258. 52 Evidence of William Harper 1 5.4 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Determination of Long-term Point to Point Service Rates 2 3 HQT sets the annual rate for long-term PTP service by dividing the net 4 transmission revenue requirement (i.e., total approved revenue requirement less 5 revenues from short-term PTP service) by the combined peak (i.e., annual peak) 6 for Native Load, Network Integration and long-term PTP service160. This is the 7 same “divisor” HQT uses to allocate the net revenue requirement between Native 8 Load/Network Integration service and long-term PTP service. Payments for long- 9 term PTP service are actually made monthly, based on 1/12th of the annual 10 demand charge times the reserved capacity for the year. 11 12 Comments 13 14 The HQT approach is equivalent to one where the rate is derived by taking the 15 net revenue requirement allocated to long-term PTP service and dividing it by the 16 forecasted level of long-term firm PTP service used in the initial allocation (i.e., 17 step 4 of the seven step process). This is the approach used by many (but not 18 all161) Canadian utilities in setting their long-term PTP service rates. Overall, the 19 HQT approach to setting rates for long-term PTP service is reasonable. 20 21 5.5 Determination of Native Load/Network Integration Service Rates 22 23 HQT’s charges for Native Load service are not specified in terms of a “rate”, 24 which is then applied to a monthly or annual billing determinant, but rather as an 25 annual fixed dollar amount, which is billed to the Distributor in 12 equal monthly 26 payments, until modified in a subsequent rate application. The proposed annual 27 charge is $2,483.3 M for 2005. 160 HQT-4, Document 1, page 14 This approach is used by New Brunswick and Nova Scotia but not British Columbia. See also HQT-4, Document 3.1, page 5 161 53 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 Comment 3 4 Based on a 3-CP allocation factor the annual charge for Native Load Service 5 would change to $2482.6 M162. 6 7 HQD is HQT’s only Native Load customer and HQT has no Network Integration 8 service customers. As a result, there is currently no need for HQT to “divide” up 9 the costs between Native Load and Network Integration service. All of the costs 10 are recoverable from Hydro Quebec Distribution – the Native Load Service 11 customer. However, the question arises as to how, in principle, the revenue 12 requirement would be charged if there was more than one Native Load/Network 13 Integration customer. In the Tariffs and Conditions, HQT provides for the 14 situation where other network customers may emerge in that the amount payable 15 by HQD is “less any amount payable during the month by a customer whose load 16 was previously part of the Distributor’s Native Load and who has reserved, to 17 supply such load, a Transmission Service under Part II (Point to Point service) or 18 Part III (Network Integration Service) herein, until such time as the exclusion of 19 such load from the Distributor’s Native Load has been taken into account by the 20 Régie in determining applicable transmission rates under the provisions 21 herein”163. 22 23 Furthermore, in the Tariffs and Conditions164, HQT establishes how new Network 24 Integration customers would be charged: 25 26 27 28 29 Monthly Demand Charge: The Network Customer shall pay a monthly demand charge, which shall be determined by multiplying its Load Ratio Share times onetwelfth (1/12) of the Transmission Provider's annual transmission revenue requirement specified in Attachment H herein. A new Network Customer shall 162 Based on the annual charge of $74.79/kW and a Native Load of 33,168 MW. HQT-5, Document 3, Section 42.1 164 HQT-5, Document 3, Sections 1.27, 34.1, 34.2 and 34.3 163 54 Evidence of William Harper 1 2 3 4 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 pay the monthly demand charge commencing on the first day of the month during which Network Integration Transmission Service is initiated. Where the various terms used are defined as follows: 5 6 7 8 9 “Load Ratio Share: The ratio of the annual load of the Network Integration Transmission Service customer to the annual load of the Transmission System, both computed in accordance with Sections 34.2 and 34.3 concerning the Network Integration Transmission Service under Part III herein.” 10 11 12 13 14 15 16 17 18 19 Network Customer's Annual Load: The Network Customer’s annual load corresponds to the projected annual peak demand of that Network Customer over the calendar year during which Network Integration Transmission Service is provided. Transmission Provider's Annual Transmission System Load: The Transmission Provider’s Annual Transmission System Load corresponds to the projected annual peak demand for the Native Load plus the sum of the projected annual peak demand for each of the Network Customers. 20 The overall effect is that the total revenue requirement allocated to Native 21 Load/Network Integration service would be distributed amongst individual 22 customers (if there were more than one) on the basis of their relative annual 23 peaks regardless of when they occurred (i.e., based on a 1-NCP allocation 24 factor)165. This interpretation of the current (and proposed) wording of the Tariffs 25 and Conditions differs from Dr. Ren Orans’ evidence which indicates166 that HQT 26 is proposing to allocate costs between network customers on the basis of 1-CP 27 (as opposed to 1-NCP). 28 29 There are a couple of issues arising from HQT’s proposal: • 30 First, is it appropriate to use a different determinant for rate design as opposed to cost allocation, and 31 • 32 Second, if so, is 1-NCP the appropriate billing determinant for Native Load/Network Integration Service? 33 165 166 HQT-4, Document 1, pages 19-20 HQT-4, Document 3, page 14 55 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 This distinction between cost allocation and rate design is well recognized by 2 regulators – including the Régie167. 3 objectives associated with each. While cost allocation focuses primarily on cost 4 tracking and cost causality, rate design considers a number of other objectives 5 such as economic efficiency, stability, practicality, etc168. Also, it is interesting to 6 note that there are a number of Canadian utilities169 which, like HQT, utilize a 7 different method for designing the rates to individual network service customers 8 than is used for purposes of allocating the revenue requirement between Native 9 Load/Network Integration service and long-term PTP service. It is also useful to 10 observe that a similar phenomenon exists on the retail side in terms of the rate 11 setting practices for these Canadian utilities. While most use 1-CP170 to allocate 12 transmission costs to their retail rate classes, for rate-setting purposes demand- 13 billed customers are virtually all charged based on their monthly NCP. Indeed, there are frequently different 14 15 Therefore, it is not necessary for HQT to adopt the same approach when 16 designing rates for Native Load and Network Integration service as was used to 17 initially allocate costs. 18 19 HQT’s proposal to use 1-NCP at the billing parameter for Native Load/Network 20 Integration Service is at odds with the practice by other Canadian utilities with 21 OATT-type transmission tariffs: • 22 Nova Scotia Power: Billed monthly based on each network service’s monthly non-coincident peak (12-NCP). 23 • 24 New Brunswick Power: Billed monthly based on each network service’s 12-NCP. 25 • 26 Saskatchewan Power: Billed monthly based on each network service’s 12-CP. 27 • 28 Manitoba Hydro: Billed monthly based on each network service’s 12-CP. 167 D-2002-0095, page 210 Phillips Jr., Charles F. The Regulation of Public Utilities, page 410 169 Specifically, BCTC, New Brunswick and Nova Scotia 170 Nova Scotia uses 3-CP and Manitoba Hydro uses 2-CP 168 56 Evidence of William Harper • 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 British Columbia: Billed monthly based on each network service’s 12-CP. 2 HQT’s 1-NCP and Dr. Orans’ 1-CP also both differ from the standard practice in 3 the US which is to use 12-CP (as per the FERC’s pro-forma tariff)171. 4 5 Furthermore, there are a number of the traditional rate design objectives for 6 which the use of either 12-CP or 12-NCP would be preferable to the use of 1-CP 7 (or 1-NCP) as a billing parameter: • 8 Stability: The year-to-year rates for Native Load/Network Integration service are likely to be more stable if based on either 12-CP or 12-NCP 9 10 (which effectively involves taking an average of 12 monthly peaks) as 11 opposed to 1-CP (which effectively involves relying on the value for just 12 one month). • 13 Acceptability: Use of 12 months recognizes the fact that the transmission 14 assets are “used and useful” for 12 months of the year and avoids 15 concerns regarding “free-riders” that frequently arise when rates are 16 developed using coincident peak. Also, NCP is frequently considered 17 more acceptable as a billing determinant perspective since it is a value 18 over which the customer has total accountability. Customers do not have 19 the same degree of self-responsibility for their contribution to the utility’s 20 overall peak, since they frequently don’t know (in advance) when the peak 21 will occur and, indeed, in trying to avoid the peak could actually create a 22 new system peak for the utility. • 23 Economic Efficiency: As noted in the last sentences of the previous point, 24 the use of CP billing and, particularly 1-CP billing, could lead to a 25 phenomenon known as “peak chasing” where customers, in seeking to 26 avoid the peak, actually create a new system peak and, therefore their 27 response to the price signal provides no benefit to the transmission 28 system overall. 171 HQT-4, Document 3.2, page 9 57 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 Overall, it would be more appropriate for HQT to adopt, in principle, either 12-CP 2 or 12-NCP, as the basis for billing Native Load/Network Integration customers 3 and revise its Tariffs and Conditions accordingly. 4 5 5.6 Determination of Short-term Point to Point Service Rates 6 7 HQT derives its short-term PTP service rates from its annual long-term PTP 8 service rate as follows172: 9 • Monthly Firm Rate = Annual Rate/12 months 10 • Monthly Non-Firm Rate = Annual Rate/12 months 11 • Weekly Firm Rate = Annual Rate/52 weeks 12 • Weekly Non-Firm Rate = Annual Rate/52 weeks 13 • Daily Firm Rate = Annual Rate/52 weeks/5 days 14 • Daily Non-Firm Rate = Annual Rate/365 days 15 • Hourly Non-Firm Rate = Daily Non-Firm Rate/24 Hours 16 HQT does not offer hourly firm PTP service rates. 17 18 Comments 19 20 For firm short-term PTP service rates, the approach used by HQT is similar to 21 that adopted by most Canadian utilities173. It is also consistent with FERC ‘s pro- 22 forma tariff and the Appalachian method adopted by FERC for pricing peak 23 period service. Under Appalachian pricing, firm hourly rates are based on usage 24 for 16 hours per day, five days a week, and 52 weeks per year. While HQT does 25 not offer firm hourly rates, the principles underlying the Appalachian pricing 26 method support the derivation of the daily firm rate based on 5 days per week (as 27 opposed to seven). 28 172 173 HQT-4, Document 1, page 21, Table 6 HQT-6, Document 7, Question 78 a) and HQT-4, Document 3, pages 37-38 58 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 For non-firm PTP service rates, the approach used by HQT is fundamentally 2 different from that of other Canadian utilities. For other utilities, the non- firm 3 rates are “capped” at the firm rates and discounted from there as required to 4 improve system usage174. In contrast, HQT’s non-firm rates were initially 5 proposed as predetermined levels – with no provision for flexible discounting175. 6 The proposal reflected the following considerations: 7 1. The Régie’s conclusions176 in D-2002-95 that it could not approve a 8 flexible discounting policy for HQT (similar to that used in other 9 jurisdictions), due to the statutory requirements of Act, and 10 2. HQT’s conclusions, following its analysis of its past discounting practices, 11 that fixed discounts would lead (overall) to a lower short-term PTP service 12 revenues177. 13 HQT indicated178, in its initial application, that for a discount policy to be 14 successful in improving system utilization and revenues, it would have to meet 15 the following criteria: • 16 It would have to be based on the prices differences in neighbouring 17 jurisdictions and calibrated so as to allow customers to undertake 18 transactions that would otherwise not occur, and • 19 The prices would have to be able to vary by “path” in order to avoid a loss of revenues. 20 21 Subsequent to the initial filing, the Régie requested179 that HQT file a discounting 22 proposal that would meet these criteria and HQT did so on August 10th, 2005180. 23 24 This evidence does not include an assessment of HQT’s new discounting 25 proposal, which would apply to the hourly off-peak short-term PTP service. It is 26 our understanding that evidence being prepared by other parties will address this 174 HQT-6, Document 7, Question 78.a and HQT-4, Document 3.1, page 7 HQT-4, Document 2, page 3 176 D-2002-95, page 282 177 HQT-2, Document 1, page 21 and HQT-2, Document 3, page 19 178 Find reference in original application other than HQT-2, Doc 5 179 HQT-2, Document 5, page 6 180 HQT filed HQT-2, Document 5. 175 59 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 topic and, therefore, this evidence has continued to focus on the topics initially 2 identified by the client. 3 4 Apart from the proposed discounting policy, a question arises as to whether HQT 5 should adopt an on-peak hourly pricing formula similar to that used by other 6 utilities (i.e., based on the Appalachian pricing formula). Based on HQT’s rate 7 derivation, such an approach would yield an on-peak hourly rate181 of 8 $17.52/MWh. Theoretically, such a rate could contribute significantly to HQT’s 9 overall revenues since hourly PTP service accounts for over 98% of total 10 projected short-term PTP revenue for 2005182 and 80% of total hourly short-term 11 service reservations (and roughly 90% of HQP’s hourly short-term service 12 reservations) are for the peak period183. 13 14 However, the evidence provided by HQT indicates that most of the use of hourly 15 short-term PTP service (in both the peak and off-peak) has been by HQP for 16 purposes of exporting power184. In such cases, the type of analyses undertaken 17 by Dr. Orans (although not perfect185) provides an indication as to the value of 18 transmission service. Dr. Orans original analyses suggested that increasing the 19 on-peak rate would raise the percentage of blocked hours from 2.5% to over 20 30%. However, based on updated information regarding transmission service 21 pricing in neighbouring jurisdictions, Dr Orans revised his analyses186. The new 22 results suggest that the currently proposed hourly transmission service rate of 23 $8.33 / MWh would block trade aimed at arbitraging between peak and off-peak 24 prices almost 20% of the time; while increasing the rate to $17.52 is likely to 25 block such trades roughly 60% of the time. This suggests that roughly doubling 26 the rate would cut in half the period of time when peak/off peak arbitrage would 181 Based on annual rated of $72.90/kW divided by 4,160 hours. HQT-4, Document 1, page 21 183 HQD-2, Document 3, page 13 184 HQT-6, Document 8, pages 27-28, Question 18.4, Table R18.4 and HQT-2, Document 3, page 14. 185 Limited by the fact that all neighbouring jurisdictions do not have “markets” and some exports could arise simply due to an overall available surplus. See also OC 80.f) and OC 23.c) 186 HQT-6, Document 7, Question 22 b) 182 60 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 be economic such that there would be little overall benefit to HQT implementing a 2 higher on-peak hourly rate187. 3 4 Finally, the revised hours of blocked transactions in Dr. Orans analyses188 (up 5 from 2.5% to 19.4% of the time) give rise to the question of whether or not HQT 6 should consider introducing a discount policy for hourly peak period transactions. 7 However, reducing the rate by 25% (to $6.25 / MWh) would only reduce blocked 8 hours to 12% - such that the increase in volume would not make for the loss in 9 unit revenue. Therefore, introducing a discount policy for hourly peak PTP 10 service would not be appropriate. 11 12 5.7 Consistency with Cost of Service Allocation Results 13 14 Table 8 compares the anticipated revenues for Native Load and Long-term PTP 15 service with cost allocation results from Table 5 above. 16 17 Table 8 18 Transmission Service Revenues and Costs 19 Costs Revenue 1-CP 3-CP Native Load Service $2412.3 M $2483.5 M $2482.7 M Long-term PTP Service $100.7 M $29.5 M $30.3 M - $78 M $78 M $2591 M $2591 M Short-term PTP Net Transmission Service $2513 M Costs Total Transmission Service $2591 M Costs and Revenue 187 This analysis is similar to that performed by Dr. Orans – see HQT-6, Document 4, page 25, Question 23.1 188 HQT-6, Document 7, Question 22 b) 61 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 While Native Load revenues exceed allocated costs by slightly less than 3%, the 3 revenues from Long-term PTP service cover less than 30% of the allocated 4 costs. 5 6 These results are dramatically different than those presented by HQT189 which 7 suggested that: • 8 Native Load Service revenues were slightly less than allocated costs (i.e., 99.9%), and 9 • 10 Point to Point services revenues more than covered allocated costs (i.e., 102%). 11 12 The differences in results arise from two factors. The first factor is the proposed 13 changes in the allocation factors for the cost of service allocation put forth in this 14 Evidence. The second, and more significant, is the fact that HQT has combined 15 the revenues for short-term and long-term PTP service when presenting the 16 results. Given that no costs are allocated to short-term PTP service in HQT’s 17 methodology, HQT’s presentation of the results tends to mask the under 18 recovery of costs associated with long-term PTP service. 19 20 It is inappropriate to include short-term PTP revenues with long-term PTP 21 revenues for purposes of comparing revenues and costs for the following 22 reasons: 23 • First, this approach is inconsistent with the way the revenues from short- 24 term PTP service are treated by HQT (and the FERC pro-forma OATT) in 25 the derivation of the proposed transmission rates. In the derivation, short- 26 term PTP revenues were used to reduce the total revenue requirement to 27 be recovered from both Native Load and long-term PTP service 28 customers 190. 189 190 HQT-4, Document 1, page 25 HQT-6, Document 9, page 57, Question 46.5 62 Evidence of William Harper • 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Second, the approach is inconsistent with principle that both Native Load 2 and long-term PTP service customers should both benefit from the 3 offering of short-term PTP service191. 4 5 Based on these results the rates for long-term PTP service would have to be 6 increased significantly relative to those proposed by HQT in order for long-term 7 PTP service to be priced in accordance with the cost allocation results. 8 However, it should be noted that while short-term PTP rates tend to track long- 9 term PTP rates192, the FERC pro-forma tariff permits discounting for such rates 10 and, as a result, the currently proposed short-term rates could be retained even if 11 long-term PTP rates were adjusted upwards. 12 13 5.8 Ancillary Service Rates 14 15 For 2005, HQT proposes to continue to offer the six existing Ancillary Services 16 and to introduce a new Ancillary Service – Energy Receipt Imbalance service 17 which would be applicable to point to point transactions where the point of receipt 18 is located within HQT’s control area193. Since the costs of the System Control 19 service are embedded in the rates for Native Load/Network Integration and PTP 20 service, a separate charge is not required. For the remaining Ancillary Services, 21 HQT determines the rates using the same methodology as approved by the 22 Régie194 for the 2001 rates. However, the costs of generation have been 23 updated by HQP to 7.5 cents/kWh195 in order to reflect the cost of new supply as 24 per the April 2004 call for tender. In the case of the new Energy Receipt 25 Imbalance service, the methodology used mirrors that used to set the rates for 26 the already existing Energy Delivery Imbalance service196. 191 HQT-4, Document 1, page 14 HQT-6, Document 9, page 80, Question 57.1 193 HQT-4, Document 1, page 33 194 D-2002-95, page 285 195 HQT-4, Document 1, pages 28-29 196 HQT-4, Document 1, page 33 192 63 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 Finally, under HQT’s proposal the rates for Frequency Control, Spinning Reserve 3 and Non-Spinning Reserve would apply, for the first time, to PTP service where 4 the point of receipt is within HQT’s control area197. 5 6 Comments 7 8 In developing the existing Ancillary Service rates, HQT used the cost of Heritage 9 Pool energy (2.79 cents/kWh) to price the facilities supporting Voltage Control, 10 Frequency Control, Spinning Reserve and Non-Spinning Reserve services198. In 11 the current Application, HQP has used a value of 7.5 cents / kWh to set these 12 rates199. The 7.5 cents per kWh is reasonable value as it corresponds to the cost 13 of new supply for 2005 as used by HQD in its latest rate Application200. 14 15 In adjusting the Ancillary Service rates to reflect the increase in cost of supply 16 from 2.79 to 7.5 cents per kWh, it was also necessary for HQT to account for the 17 fact that the 2.79 cents is based on the point of delivery to customers whereas 18 the 7.5 cents is based on the point of delivery to the transmission system. While 19 loss factors have improved since the development of the initial Ancillary Service 20 rates, it was necessary for HQT to retain in the calculation the original loss 21 factor201 (8.74%) in order to properly adjust to the new cost of supply. 22 23 It is not clear why the original calculation202 of the rate for Frequency Control did 24 not include a loss factor adjustment. However, since the proposed rate is based 25 on a ratio of the current 7.5 cents/kWh cost and the 2.79 cents/kWh used in the 26 original calculation203, the resulting rate is correct. 197 HQT-6, Document 1, page 7, Question 4.2 HQT-6, Document 7, Question 65 a) 199 HQT-4, Document 1, pages 28-29 200 R-3541-2004, HQD-8, Document 2, pages 5-6. Note: The reported 8.06 cents/kWh must be adjusted for losses of 7.5% to yield the cost of energy delivered to the transmission system. 201 R-3401-98, HQT-10, Document 1, page 51 202 R-3401-98, HQT-10, Document 1, page 53 203 HQT-4, Document 1, Table 9 – see footnote 198 64 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 2 In the case of the Energy Imbalance service rates, the current Energy Imbalance 3 Delivery rates apply to PTP transactions where the point of delivery is within 4 HQT’s control area. Where the quantity of energy consumed (i.e., taken at the 5 delivery point) is greater than scheduled, the cost of the imbalance (i.e., the 6 additional energy delivered) is priced at the cost of generation plus 50%. When 7 the quantity of energy consumed at the delivery point is less than scheduled, a 8 credit is granted based on 50% of the cost of Heritage Pool energy. 9 10 In its current proposal, HQT has updated the cost of generation used to value 11 deliveries greater than scheduled from the 6.94 cents/kWh underpinning the 12 existing rates204. However, HQT has failed to update the cost of Heritage Pool 13 energy (at the point of delivery to the transmission system). In the original 14 calculation the cost of Heritage Pool energy was adjusted for losses of 8.64% to 15 yield a price of 2.57 cents per kWh – prior to the 50% reduction. Current losses 16 on the transmission and distribution systems are estimated at 7.5%205. As a 17 result, the current proposal should have reflected this new information, which 18 would have yielded a credit for delivery of less than the scheduled amount of 19 $1.30 per kWh206. 20 21 HQT’s current and proposed practice of charging different rates when the 22 deliveries are greater than scheduled versus when they are less than scheduled 23 is consistent with the practices of other Canadian utilities with OATT-style 24 tariffs207. The objectives in offering the different rates are to encourage users to 25 properly schedule their usage of the transmission system and to prevent users 26 from arbitraging (where possible) between the price for energy imbalance 27 services and the price such energy can command elsewhere208. 28 204 R-3401-98, HQT-10, Document 1, page 55 R-3541-2004, HQT-8, Document 2, page 5 206 Calculated as (2.79/1.075) * 50% 207 For example, Nova Scotia, New Brunswick, Saskatchewan, Manitoba and British Columbia 208 HQT-6, Document 1, pages 49-50, Questions 20.1 and 20.2 205 65 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 HQT’s proposal includes the same rates for its new Energy Imbalance Receipt 2 Service as for its Energy Imbalance Delivery service209. As a result, the 3 comments from the earlier paragraph regarding the need to update the loss 4 factor used in the calculation also apply to the proposed credit to be paid to 5 customers when the quantities received are greater than the quantity scheduled. 6 7 The requirement that users pay for imbalances between the energy scheduled 8 and the actual energy received by the transmission provider is a departure from 9 “Energy Imbalance Service” as set out in the FERC’s pro-forma tariff which just 10 deals with delivery imbalances. However, when parties raised with the FERC the 11 fact that energy imbalance could exist at the point of generation (i.e., receipt) as 12 well as delivery FERC’s response210 was: 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 Although we agree that the second type of mismatch can occur, we will not designate as Energy Imbalance Service a mismatch between energy scheduled and energy generated. Energy Imbalance Service in this Rule applies only to the obligation of the transmission provider to correct the first type of energy mismatch, one caused by load variations. In general, the amount of energy taken by load in an hour is variable and not subject to the control of either a wholesale seller or a wholesale requirements buyer. The Energy Imbalance Service that we require as our ancillary service has a bandwidth appropriate for load variations and should have a price for exceeding the bandwidth that is appropriate for excessive load variations. Although NIMO states correctly that, where two control areas are involved, there can also be a mismatch between energy scheduled and energy generated, NIMO has not explained why this mismatch should have the same bandwidth and price as our Energy Imbalance Service. Indeed, we believe it should not. A generator should be able to deliver its scheduled hourly energy with precision. If we were to allow the generator to deviate from its schedule by 1.5 percent without penalty, as long as it returned the energy in kind at another time, this would discourage good generator operating practice. A generation supplier could intentionally generate less power when its generating cost is high and make it up when its cost is lower if the second type of mismatch is included in our Energy Imbalance Service. Instead, a generator will have an interconnection agreement with its transmission provider or control area operator, and we expect that this agreement will specify the requirements for the generator to meet its schedule, and for any 209 210 HQT-4, Document 1, page 33 FERC Order 888-A, page 164 66 Evidence of William Harper 1 2 3 4 5 6 7 8 9 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 consequence for persistent failure to meet its schedule. This agreement will be tailored to the parties' specific standards and circumstances, and, although such arrangements must not be unduly preferential or discriminatory (e.g., must be comparable for all wholesale sellers, including the transmission provider's own wholesale sales), we prefer not to set these standards generically for all parties. As a result, implementing an Energy Receipt Imbalance service that sets out the 10 consequences of a generator not meeting its schedule is compatible with the 11 FERC pro-forma tariff. However, HQT should monitor the use of service and 12 report back to the Régie during its next Rate Application, as to whether use of a 13 common deviation band for Energy Delivery and Energy Receipt services is 14 appropriate. 15 16 Finally, HQT proposes that the rates for Frequency Control, Spinning Reserve 17 and Non-Spinning Reserve be applicable to all point to point services (not just 18 those where the delivery point is located in the Quebec control zone). This 19 proposal would substantially increase the revenue accruing to HQP211 for 20 Ancillary Services. However, the bulk of the revenue will be generated by HQP, 21 who, in turn, is the service provider to whom the revenues are to be remitted. 22 The net increase in revenue (due to use of point to point services by 3rd parties) 23 appears to be in the order of $300,000. 24 25 HQT’s rationale is that transmission customers, using its system to deliver power 26 to other inter-connected networks not in its control area, also benefit from these 27 services and should pay for them. Again, this proposal differs from the FERC 28 pro-forma tariff wherein such services are only invoiced when the load is in the 29 Transmitter’s control area. However, there is a rationale for charging both types 30 of transactions, since proper frequency must be maintained for all electricity 31 carried by the transmitter and the spinning reserves are to ensure the integrity of 32 the transmission system for all users. 211 HQT-6, Document 1, page 7, Question 4.2, Table R.4.2 67 Evidence of William Harper Hydro-Québec TransÉnergie R-3549-2004 Phase 2 1 6 CONCLUSIONS 2 A summary of the key comments and conclusions is set out below. 3 4 6.1 HQT’s Cost Allocation Methodology 5 6 Definition of Functions and Sub-Functions 7 8 • statutory definition of transmission, which includes generation-related 9 transmission assets. 10 11 The cost allocation functions proposed by HQT are reasonable given the • The assignment of the Churchill Falls connection to the Interconnections 12 function, as opposed to the Generation Connection function, is questionable 13 but manageable provided the costs continue to be tracked in a separate 14 sub-function. 15 • The assignment of transmission assets that carry electricity from generation 16 zones to the Network function is also questionable. However, reassigning 17 the assets to the Generation Connection function will not impact on the 18 results unless the Régie determines that Generation Connection facilities 19 should be allocated to services based on demand and energy 20 considerations. 21 • transformer stations serving HQD. 22 23 Customer Connections should also include radial lines that connect to HV • The Control Centre function should be considered a “main function” and the 24 costs allocated through to services (as opposed to being pro-rated over the 25 other main functions). 68 Evidence of William Harper 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Assignment of Costs to Functions 2 3 • HQT’s proposals regarding the assignment of rate base to functions are 4 reasonable except for the treatment of Working Capital, where the component 5 parts can easily be assigned using more precise factors. In particular, fixed 6 and intangible assets should be used to assign the working cash requirement 7 to functions. 8 • HQT’s proposals regarding the assignment of cost of service to functions are reasonable except for the treatment of the amortization of other expenses 9 10 where (again) the component parts can easily be assigned using more 11 precise factors. Specifically, the assignment of the component parts of the 12 annual amortization could readily be done in the same manner as the 13 assignment of the remaining unamortized balances was accomplished for the 14 rate base. 15 • Finally, there is a need to clarify the process used for assigning External Billings associated with Facilities Operations. 16 17 18 Classification of Cost Functions 19 20 • HQT’s proposal to classify transmission costs as demand-related is generally 21 reasonable. One could question the treatment of Generation Connection 22 costs as 100% demand-related. However, the impact on the overall 23 allocation results would be minor and there is no generally accepted way to 24 classify generation connection costs (or indeed generation costs overall) as 25 demand and energy-related. 26 • The only exception to the 100% demand classification is the Control Centre 27 function. Classification of this function’s costs as energy-related would better 28 reflect the role of the associated activities. 69 Evidence of William Harper 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 Allocation of Costs to Services 2 3 • The allocation methodology needs to specifically (and separately) recognize 4 short-term PTP service so as to properly manage any costs associated with it 5 and properly allocate the benefits (i.e., the net revenues) from short-term PTP 6 service. 7 • purposes of allocating demand-related costs to services. 8 9 The use of 3-CP (December, January and February) is preferable to 1-CP for • The costs in the Generation Connection and Network functions should each 10 be allocated to Native Load and long-term PTP service based on the total 3- 11 CP loads for each – where long-term PTP loads are determined based on 12 reservations. 13 • Service, as proposed by HQT. 14 15 • • The costs in the Support function should be pro-rated over the other five functions – prior to the costs in each of the five being allocated to services. 18 19 The costs in the Control Centre function should be allocated to Native Load, long-term PTP and short-term PTP services based on energy. 16 17 Customer Connection costs should be directly assigned to Native Load • The net revenues attributable to short-term PTP service (i.e., revenues less 20 allocated costs) should be pro-rated over the other two services based on the 21 total costs allocated to each. 70 Evidence of William Harper 6.2 1 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 HQT’s Derivation of Transmission Service Rates 2 3 Allocation of Revenue Requirement Between Native Service and Long-Term PTP 4 Service 5 6 • both Native Load and long-term PTP service is appropriate. 7 8 HQT’s use of revenue from short-term PTP service to reduce the rates for • The use of 3-CP (December, January and February) is preferable to 1-CP for purposes of allocating the net revenue requirement between Native Load and 9 long-term PTP service. 10 11 12 Long-Term PTP Service Rates 13 14 • As per HQT’s proposal, the long-term PTP service rate should reflect the 15 annual rate derived from the foregoing allocation of the revenue requirement 16 between services. 17 18 Native Load/Network Integration Service Rates 19 20 • potential Network Integration customers based on 1-CP or 1-NCP. 21 22 There is a need to clarify whether HQT’s proposal allocates costs between • It would be preferable to allocate the transmission costs between Native Load and Network Integration customers based on 12-NCP (or failing this 12-CP). 23 24 25 Consistency with Cost Allocation Methodology 26 27 28 29 30 • A comparison of the revenues derived from rates based on FERC’s pro-forma OATT and the results of the cost allocation methodology indicates that: o Native Load Service revenues are only slightly above allocated costs, but 71 Evidence of William Harper o Long-term PTP revenues are significantly below allocated costs. 1 2 Hydro-Québec TransÉnergie R-3549-2004 Phase 2 • This result is considerably different from that presented in HQT’s evidence 3 primarily due to the treatment of revenues from short-term PTP service which 4 HQT combined with long-term PTP service for purposes of comparing costs 5 and revenues by service. In the case of HQT’s proposal, this treatment of 6 short-term PTP revenues offsets the higher cost allocated to long-term PTP 7 service, by virtue of the unique allocation treatment of Churchill Falls and the 8 interconnections. 9 10 Short-Term PTP Rates 11 12 • HQT’s proposed short-term PTP rates are reasonable. 13 14 Ancillary Service Rates 15 16 • HQT’s proposed Ancillary Service rates are reasonable with the following 17 exception of the proposed Energy Receipt and Energy Delivery Imbalance 18 rates where the rate derived from the cost of the Heritage Pool needs to be 19 updated for the most recent loss estimates. This would impact the Energy 20 Receipt Imbalance rate when more energy is received by the transmission 21 system than scheduled and the Energy Delivery Imbalance rate when less 22 energy is taken from the transmission system than scheduled. 72 APPENDIX A CV FOR ECS CONSULTANT 73 ECONALYSIS CONSULTING SERVICES William O. Harper Mr. Harper has over 20 year experience in the design of rates and the regulation of electricity utilities. He has testified as an expert witness on rates before the Ontario Energy Board from 1988 to 1995, and before the Ontario Environmental Assessment Board. He was responsible for the regulatory policy framework for Ontario municipal electric utilities and for the regulatory review of utility submissions from1989 to 1995. Mr. Harper coordinated the participation of Ontario Hydro (and its successor company Ontario Hydro Services Company) in major public reviews involving Committees of the Ontario Legislature, the Ontario Energy Board and the Macdonald Committee. He has served as a speaker on rate and regulatory issues for seminars sponsored by the APPA, MEA, EPRI, CEA, AMPCO and the Society of Management Accountants of Ontario. Since joining ECS, Mr. Harper has provided consulting support for client interventions on energy and telecommunications issues before the Ontario Energy Board, Manitoba Public Utilities Board, Québec’s Régie de l’énergie, British Columbia Utilities Commission, and CRTC. He has also appeared before the Manitoba’s Public Utilities Board, the Manitoba Clean Environment Commission and Quebec’s Régie de l’énergie. Bill is currently a member of the Ontario Independent Electricity Market Operator’s Technical Panel. EXPERIENCE Econalysis Consulting Services- Senior Consultant 2000 to present • Responsible for supporting client interventions in regulatory proceedings, including issues analyses & strategic direction, preparation of interrogatories, participation in settlement conferences, preparation of evidence and appearance as expert witness (where indicated by an asterix). • Electricity o IMO 2000 Fees (OEB) o Hydro One Remote Communities Rate Application 2002-2004 o OEB - Transmission System Code Review (2003) o OEB - Distribution Service Area Amendments (2003) o OEB – Regulated Asset Recovery (2004) o OEB – 2006 Electricity Rate Handbook Proceeding* o BC Hydro IPP By-Pass Rates o WKP Generation Asset Sale o BC Hydro Heritage Contract Proposals o BC Hydro’s 2004/05 and 2005/06 Revenue Requirement Application o BC Transmission Corporation – Open Access Transmission Tariff Application 2004 o BCTC’s 2005/06 Revenue Requirement Application o BC Hydro’s CFT for Vancouver Island Generation – 2004 74 o o o o o o o o o o o BC Hydro’s 2005 Resource Expenditure and Acquisition Plan Fortis BC’s 2005 Revenue Requirement Application Hydro Québec-Distribution’s 2002-2011 Supply Plan* Hydro Quebec-Distribution’s 2002-2003 Cost of Service and Cost Allocation Methodology* Hydro Québec-Distribution’s 2004-2005 Tariffs* Hydro Québec – Distribution’s 2005/2006 Tariff Application* Hydro Québec – Distribution’s 2005-2014 Supply Plan* Manitoba Hydro’s Status Update Re: Acquisition of Centra Gas Manitoba Inc.* Manitoba Hydro’s Diesel 2003/04 Rate Application* Manitoba Hydro’s 2004/05 and 2005/06 Rate Application* Manitoba Hydro/NCN NFAAT Submission re: Wuskwatim* • Natural Gas Distribution o Enbridge Consumers Gas 2001 Rates o BC Centra Gas Rate Design and Proposed 2003-2005 Revenue Requirement o Rate of Return on Common Equity (BCUC) o Terasen Gas (Vancouver Island) LNG Storage Project (2004) • Telecommunications Sector o Access to In-Building Wire (CRTC) o Extended Area Service (CRTC) o Regulatory Framework for Small Telecos (CRTC) • Other o Acted as Case Manager in the preparation of Hydro One Networks’ 2001-2003 o Distribution Rate Applications § Supported the preparation of Distribution Rate Applications for various Ontario municipal electric utilities. o Supported the implementation of OPG’s Transition Rate Option program prior to Open Access in Ontario o Prepared Client Studies on various issues including: § The implications of the 2000/2001 natural gas price changes on natural gas use forecasting methodologies. § The separation of electricity transmission and distribution businesses in Ontario. § The business requirements for Ontario transmission owners/operators. § Various issues associated with electricity supply/distribution in remote communities o Member of the OEB’s 2004 Regulated Price Plan Working Group 75 Hydro One Networks Manager - Regulatory Integration, Regulatory and Stakeholder Affairs (April 1999 to June 2000) • Supervised professional and administrative staff with responsibility for: o providing regulatory research and advice in support of regulatory applications and business initiatives; o monitoring and intervening in other regulatory proceedings; o ensuring regulatory requirements and strategies are integrated into business planning and other Corporate processes; o providing case management services in support of specific regulatory applications. • Acting Manager, Distribution Regulation since September 1999 with responsibility for: o coordinating the preparation of applications for OEB approval of changes to existing rate orders; sales of assets and the acquisition of other distribution utilities; o providing input to the Ontario Energy Board’s emerging proposals with respect to the licences, codes and rate setting practices setting the regulatory framework for Ontario’s electricity distribution utilities; o acting as liaison with Board staff on regulatory issues and provide regulatory input on business decisions affecting Hydro One Networks’ distribution business. • Supported the preparation and review before the OEB of Hydro One Networks’ Application for 1999-2000 transmission and distribution rates. Ontario Hydro Team Leader, Public Hearings, Executive Services (APR. 1995 TO APR. 1999) • Supervised professional and admin staff responsible for managing Ontario Hydro’s participation in specific public hearings and review processes. • Directly involved in the coordination of Ontario Hydro’s rate submissions to the Ontario Energy Board in 1995 and 1996, as well as Ontario Hydro’s input to the Macdonald Committee on Electric Industry Restructuring and the Corporation’s appearance before Committees of the Ontario Legislature dealing with Industry Restructuring and Nuclear Performance. Manager – Rates, Energy Services and Environment (June 1993 to Apr. 95) Manager – Rate Structures Department, Programs and Support Division (February 1989 to June 1993) • Supervised a professional staff with responsibility for: o Developing Corporate rate setting policies; o Designing rates structures for application by retail customers of Ontario Hydro and the municipal utilities; o Developing rates for distributors and for the sale of power to Hydro’s direct industrial customers and supporting their review before the Ontario Energy Board; o Maintaining a policy framework for the execution of Hydro’s regulation of municipal electric utilities; 76 • • • o Reviewing and recommending for approval, as appropriate, municipal electric utility submissions regarding rates and other financial matters; o Collecting and reporting on the annual financial and operating results of municipal electric utilities. Responsible for the development and implementation of Surplus Power, Real Time Pricing, and Back Up Power pricing options for large industrial customers. Appeared as an expert witness on rates before the Ontario Energy Board and other regulatory tribunals. Participated in a tariff study for the Ghana Power Sector, which involved the development of long run marginal cost-based tariffs, together with an implementation plan. Section Head – Rate Structures, Rates Department November 1987 to February 1989 • With a professional staff of eight responsibilities included: o Developing rate setting policies and designing rate structures for application to retail customers of municipal electric utilities and Ontario Hydro; o Designing rates for municipal utilities and direct industrial customers and supporting their review before the Ontario Energy Board. • Participated in the implementation of time of use rates, including the development of retail rate setting guidelines for utilities; training sessions for Hydro staff and customers presentations. • Testified before the OEB on rate-related matters. Superintendent – Rate Economics, Rates and Strategic Conservation Department February 1986 to November 1987 • Supervised a Section of professional staff with responsibility for: o Developing rate concepts for application to Ontario Hydro’s customers, including incentive and time of use rates; o Maintaining the Branch’s Net Revenue analysis capability then used for screening marketing initiatives; o Providing support and guidance in the application of Hydro’s existing rate structures and supporting Hydro’s annual rate hearing. Power Costing/Senior Power Costing Analyst, Financial Policy Department April 1980 to February 1986 • ?Duties included: o Conducting studies on various cost allocation issues and preparing recommendations on revisions to cost of power policies and procedures; o Providing advice and guidance to Ontario Hydro personnel and external groups on the interpretation and application of cost of power policies; o Preparing reports for senior management and presentation to the Ontario Energy Board. • Participated in the development of a new costing and pricing system for Ontario Hydro. Main area of work included policies for the time differentiation of rates. 77 Ontario Ministry of Energy Economist, Strategic Planning and Analysis Group April 1975 to April 1980 • ?Participated in the development of energy demand forecasting models for the province of Ontario, particularly industrial energy demand and Ontario Hydro’s demand for primary fuels. • Assisted in the preparation of Ministry publications and presentations on Ontario’s energy supply/demand outlook. • Acted as an economic and financial advisor in support of Ministry programs, particularly those concerning Ontario Hydro. EDUCATION Master of Applied Science – Management Science • University of Waterloo, 1975 • Major in Applied Economics with a minor in Operations Research • Ontario Graduate Scholarship, 1974 Honours Bachelor of Science • University of Toronto, 1973 • Major in Mathematics and Economics • Alumni Scholarship in Economics, 1972 78