Issue Date: January 21, 2014 RE: HGTC Renovations to Bldg. 200 Science Labs Rooms 206 & 208 Project No. : H59-N819-CA ADDENDUM NO. 2 Attachments: Dumpster/Parking Diagram P101 Item Revision/Clarification 1 Clarification: There are no restrictions on work hours. The awarded bidder will be required to provide a schedule showing extended working hours (if opted) to the Architect and Owner for review and coordination. 2 Clarification: Refer to the attached Dumpster/Parking Diagram. General parking for construction personnel will be located in southernmost overflow parking lot. There will be an option to place a dumpster in location A or B as indicated on the map for a period of 1 week. The dumpster shall then be moved to the southernmost overflow parking lot as indicated by the owner. 3 Revision: Refer to A1/A101. The General Contractor will be responsible for demolishing the shelving in Storage Closet 209 and Storage Closet 210. 4 Revision: Refer to A1/A101. The General Contractor will be responsible for repairing the damaged wall Storage Closet 207. 5 Clarification: Refer to A1/102. Drawing should be referred to as “Reflected Ceiling Plan”. Both 2x4 troffers in Storage Closet 207 shall be new fixtures and replaced in the existing location. 6 Clarification: Refer to the General Notes, note number 2, on sheet P101. The existing concrete slab shall only be saw cut in the areas indicated for new work. 7 Clarification: Refer to P1/P101 and attached sheet P101. The existing concrete slab will need to be saw cut in the areas outlined in red. Exact location of existing waste lines shall be established in the field. 8 Revision: Refer to Schedule of Plumbing Fixtures & Specialty Equipment on P301. Marks S-1 and S-2 should be revised to “TABLE, SINK, TRAP & FAUCET INSTALLED BY GC. TRAP, STOPS, AND CONNECTIONS BY PLUMBING CONTRACTOR”. 9 Revision: Refer to Schedule of Plumbing Fixtures & Specialty Equipment on P301. Mark S-4, fume hood, shall be relocated from building 1100 and installed in location shown. e3 studio 4728 Jenn Dr. Suite 101 Myrtle Beach, SC 29577 843.213.1672 www.e3-studio.com 10 Revision: Refer to Schedule of Plumbing Fixtures & Specialty Equipment on P301. Mark S-5, fume hood, will be purchased by the Owner/Agency and installed by the General Contractor. 11 Revision: Refer to sheet M101. Drawing should be labeled “M1/M101 Mechanical Plan”. 12 Revision: Refer to sheet M101. The new fume hood shall be located in SCIENCE LAB 206 and the relocated fume hood shall be installed in SCIENCE LAB 208. 13 Clarification: The delivery schedule for the furniture provided by the Agency/Owner for General Contractor to install will be coordinated with the General Contractor’s submitted schedule. END OF ADDENDUM e3 studio 4728 Jenn Dr. Suite 101 Myrtle Beach, SC 29577 843.213.1672 www.e3-studio.com CONSTRUCTION UPDATE August 29, 2013 Areas 1 & 3 will be fenced off from Monday, September 2 to Monday, November 2 for renovations to the Loop Road and parking areas. Dumpster / Parking Diagram CONWAY CAMPUS - AUGUST 2013 dumpster location A Dumpster Location B Project access point Designated parking