AGENDA ITEM 8-E ACTION ITEM TO: CHAIRMAN COVINGTON AND THE VRE OPERATIONS BOARD FROM: DOUG ALLEN DATE: SEPTEMBER 21, 2012 RE: AUTHORIZATION TO APPROVE A CONTRACT AMENDMENT FOR RESURFACING THE EXISTING BROOKE STATION PARKING LOT AND RESTRIPING THE LEELAND STATION PARKING LOT _____________________________________________________________________ RECOMMENDATION: The VRE Operations Board is being asked to authorize the Chief Executive Officer to amend the contract with Tavares Concrete, of Lorton, Virginia, for the re-surfacing of the existing Brooke station parking lot and restriping of the existing Leeland station parking lot and increase the contract by $189,654, plus a 10% contingency of $18,965, for a total contract value not to exceed $2,561,191. BACKGROUND: Due to significant increases in ridership, VRE, in conjunction with Stafford County, initiated parking lot expansions at both the Brooke and Leeland VRE stations. The Brooke project includes the addition of 234 parking spaces located to the south of the existing lot and access road. The Leeland Road project includes the addition of approximately 196 parking spaces located to the west of the existing lot. At the September 2011 Operations Board meeting, a construction contract was awarded to Tavares Concrete for the Brooke and Leeland Road parking lot expansion projects. The authorization was in the amount of $2,352,572, which included a 10% contingency. Due to unforeseen site conditions, much of the subsoils at Brooke needed to be undercut and replaced with offsite materials. This effort utilized the majority of the allocated contingency under the original Board authorization. Through this project, VRE staff identified substandard conditions at both of the existing Brooke and Leeland parking lots requiring immediate attention. In 2008, the existing Brooke parking lot was restriped to add approximately 45 spaces. Due to the condition of the pavement and life expectancy of the materials used for the striping, the lot is in need of resurfacing and restriping. At the Leeland lot, the pavement is in acceptable condition but the old striping has also become faded requiring restriping. Performing this rehabilitation work while the expansion project is underway is more cost effective than initiating an independent effort. FISCAL IMPACT: Funding for both the Brooke and Leeland projects are included in VRE’s Capital Improvement Program using CMAQ and RSTP grants. No local match is required. The additional funding requested in this action is available in the total project budget of $4.4M. TO: FROM: DATE: RE: CHAIRMAN COVINGTON AND THE VRE OPERATIONS BOARD DOUG ALLEN SEPTEMBER 21, 2012 AUTHORIZATION TO APPROVE A CONTRACT AMENDMENT FOR RESURFACING THE EXISTING BROOKE STATION PARKING LOT AND RESTRIPING THE LEELAND STATION PARKING LOT RESOLUTION 8E-09-2012 OF THE VIRGINIA RAILWAY EXPRESS OPERATIONS BOARD WHEREAS, due to increases in ridership, VRE has initiated parking lot expansions at both the Brooke and Leeland Road VRE stations; and, WHEREAS, in September of 2011, the Operations Board authorized the award of a contract to Tavares Concrete for construction of parking lot expansions at both locations; and, WHEREAS, through the expansion projects, it was discovered that the existing parking lot at the Brooke station is in need of resurfacing and restriping and that the existing parking lot at the Leeland Road station is in need of restriping. NOW, THEREFORE, BE IT RESOLVED THAT, the VRE Operations Board authorizes the Chief Executive Officer to amend the contract with Tavares Concrete, of Lorton, Virginia, for the re-surfacing of the existing Brooke station parking lot and restriping of the existing Leeland station parking lot and increase the contract by $189,654, plus a 10% contingency of $18,965, for a total contract value not to exceed $2,561,191.