O The purpose of this document is to provide a... management process for Information and Communications Technology. A...

advertisement
Project Management Process
OVERVIEW
Purpose
The purpose of this document is to provide a high level overview of a standard project
management process for Information and Communications Technology. A full project
management process will be developed in the future as we implement our Project Portfolio
Office.
Project Life Cycle
The following diagram highlights the five key stages of any project: initiation, planning,
execution, closure, and asset maintenance. It shows the flow of events across these stages from
the perspective of the project flow, the decision-making steering committee, and the
appropriate control mechanisms.
-- 1 --
Project Management Process
Key project flow events
Initiation phase: development of the project charter
•
•
•
•
Project charter is required for new projects over 20 person days or $5,000
Purpose of project charter
o Business case to justify the project
o Document project parameters
o Guide project development
o Acquire formal authorization to proceed to the next step in the project
o Authorize the use of resources to develop detailed project plan
o Sufficient information to help the steering committee make their decision
Standard template shown in subsequent section
Generally brief: 5 pages maximum
Planning phase: development of project plan
•
•
•
•
•
•
•
Project plan is required for any project over 40 person days
It is a document used to used to:
o Guide project execution and control
o Document project planning assumptions
o Facilitate communication amongst stakeholders
o Define key management review activities
o Provide a baseline for project measurement and control
Standard template shown in subsequent section
Second stage of approval process for steering committee
Changes over time as project circumstances dictate
Scalable
Sufficient level of detail for:
o Steering committee to commit resources
o Project manager to run the project
Execution phase: reporting and change requests
•
•
•
Project manager responsible for implementing project according to project plan
Required to submit regular project status updates covering accomplishments for the
current reporting period, plans for the next reporting period, and challenges that
could prevent the project from meeting its objectives
Change requests must be submitted for any material modification of the project
plan
-- 2 --
Project Management Process
o
o
A material request means any change to the budget, scope, schedule,
quality, risk, or resourcing of the project that could impact the project
objectives
A change request template is included in a subsequent section
Closure phase
•
•
•
•
•
•
A lessons-learned document is produced for every project
Template shown in subsequent section
Purpose is stop re-inventing the wheel every time for every project
All projects are expected to document their lessons learned
Must store those ideas in a re-useable form
New projects are expected to review lessons learned from previous similar projects
and apply appropriate knowledge to the current project
-- 3 --
Project Charter
April 6, 2015
PROJECT CHARTER TEMPLATE
Template Purpose
The following document outlines the content and format of project charters to be used for all projects. A project
charter should be written for each project requiring authorization or funding. A charter could also be completed
for smaller-scope projects if there is a departmental preference or obligation to mitigate risk. Any project
requiring over 20 person days (one month) of effort or $20,000 of funding requires a project charter.
All sections are mandatory. Please replace the existing text with your own.
Each project charter is intended to clearly document the project parameters, guide project development, and
acquire formal approval to proceed with the project. The charter will be reviewed by the ICT Leadership Team,
and potentially brought to the appropriate stewardship committee for further approval. There must be sufficient
information in this document for these groups to make a decision.
The decision will be one of the following:
i. Approval in principle
• Approval in principle to proceed with the project subject to certain conditions. These conditions
require follow-up with the steering committee before proceeding with project plan development
or project execution.
ii. Approval to plan
• Approval to spend the resources necessary to develop a detailed project plan (large, complex
projects)
iii. Approval to execute
• Approval to proceed with project execution (small, inexpensive, shorter projects)
iv. On hold
• Approval in principle with the project concept, but further work is put on hold until certain
conditions are met. No work is to proceed on the project until the steering committee judges all
of the criteria are met.
v. Rejection
• The project charter does not meet the project evaluation criteria and all work on the project will
halt.
Note: If you are seeking Approval to Plan, please ensure you clearly indicate so. Example: Indicate which costs
are for developing the plan, versus which are necessary for executing the project.
Project charters must be submitted to the ICT Project Portfolio Office. You must submit 1 week prior to the ICT
Leadership meeting you would like to present at. These meetings are usually held every two weeks.
Remove this page from your project charter before submission.
The total number of pages in the final document must not exceed 5 pages.
Project Plan
April 6, 2015
PROJECT CHARTER
Meaningful, yet concise
Automatically assigned by the ICT SharePoint Project Inventory:
Project ID:
https://itshares.usask.ca/projects/SitePages/Home.aspx
Author(s) of Charter: Author(s) and contributors
Project Name:
Project Manager:
Name
Submission Date:
Date submitted
Summary
Sponsor:
Completion Date:
Name
Total Monetary
Planned OneTime Costs:
$
$
Planned Recurring
Costs:
$
$
Month, Day, Year
Other projects with
Linkages:
dependencies
Total Asset Consumption
Planned Person
Total Person Days
Days:
PURPOSE
What are the reasons for undertaking the project? What is the purpose for doing it? Identify the key needs that the project is
designed to meet. Include background material on reasons why these needs have arisen. On larger projects it is helpful to describe
the overall mission of the project.
This charter is a request to the ICT Leadership committee for permission to proceed with work.
Choose one of the following options and state your request:
1. Approval in principle
2. Approval to plan
3. Approval to execute
SPONSOR
Define who wants the project to be implemented. These individuals are known as project sponsors or owners. Who will own and
manage the project results once it is completed? These individuals provide key sources of funding for the project.
CLIENT(S) & KEY STAKEHOLDERS
What are the departments in the organization that will utilize the results of the project? Identify the key users of the system and
where in the University they are located.
What will the impact of this project be on administrators, educators, learners, researchers, and/or the community?
BENEFITS & SUCCESS CRITERIA
From the perspective of a return on investment, why should ICT undertake this project?
Example benefits:
• Lower the cost to operate the organization
• Deliver products and services faster
• Handle more work with same resources
• Improve customer service and satisfaction
Project Plan
April 6, 2015
What exactly are the direct and indirect benefits to the University? How are the benefits to be achieved? When will we know if the
overall project was a success?
Benefit (What?)
Strategy (How?)
Success Criteria (When?)
1.
IN SCOPE
What features and functions will the project deliver? Identify all the major deliverables of the project. Describe the final product or
process to be created by the project.
This section forms the agreement between the project manager and the sponsor about the expected results of the project.
OUT OF SCOPE
Identify what is not part of the project. These are features that are not part of the project but may be mistaken to be part of the
project. This section is included to help clarify the boundary between what is in the project and what is not.
WORK BREAKDOWN STRUCTURE
What are the key deliverables for the project? When are they expected and what should be delivered on these dates? Only the
first or second level of the Work Breakdown Structure (WBS) needs to be documented at this point in the project (but milestones
must be included in your WBS).
Focus on what and when, not how; how is for your Project Plan (if applicable). If you are seeking Approval to Plan, you will include
only the work required for the planning stage.
WBS #
1.0
2.0*
3.0
4.0*
5.0*
What
Project Management
1.1*
Project Charter
1.2*
Project Plan
1.3
Monitoring
1.4*
Close-Out Report
Requirements Gathering
2.1
Use Case Documentation
2.2
Technical Specification
Develop System
System Test
4.1
Testing Report
4.2
User Acceptance Testing
Move To Production
5.1
Production Checklist
5.2
System Deployment
* = Milestones
By When
2015-09-31
2015-08-01
2015-08-10
2015-09-31
2015-09-31
2015-08-02
2015-08-20
2015-09-05
2015-09-15
RESOURCES
Based on the work breakdown structure, identify the resources required and document approximately how many person-days will
be needed to complete the project. This list should include the project manager, functional analysts, and technical analysts who will
contribute to the project throughout the life of the project. It also includes any subject matter experts to be included on a part-time
basis as needed.
This section is mandatory and must be supplied for all project charters. If reasonably accurate numbers cannot be determined,
estimates must be supplied with a statement explaining the degree of confidence in the estimates. If you are seeking Approval to
Plan, you will include only the work required for the planning stage.
Project Plan
WBS #
1.0
2.0
April 6, 2015
Resource
Project Manager
Systems Administrator
Function
Management of the project
Acquisition/build of test server
Name
M. Jagger
K. Richards
Person Days:
Effort
Confidence
25
5
30
95%
75%
COSTS
Monetary costs represent cash expenses paid to do the work, upgrade infrastructure, purchase software, outsource, or hire external
resources. One-time monetary costs are incurred during the life of the project and are paid for by the project budget. Postimplementation costs of maintaining the project results are also identified here as recurring monetary costs (always identified
annually). For example:
Monetary Costs: One-Time
WBS #
3.1
4.1
Monetary Costs: Recurring
WBS #
5.1
Description
3 IBM Server
Contract programmer
Recovery from?
ICT capital
ICT base budget
Total One-Time:
Description
Vendor service agreement
Recovery from?
Total Cost
$10,000 +/- 5%
$50,000 +/- 10%
$60,000 +/- 10%
Total Cost
ICT base budget
Total Recurring:
$250 / year
$250 / year
Asset consumption costs represent resources consumed that are not paid for by the project budget. One-time asset consumption
costs are incurred during the life of the project. Recurring asset consumption costs are incurred after the project is complete. For
example:
Asset Consumption Costs: One-Time
WBS #
Description
5.0
5.0
Initial disk storage
Initial tape backup
Asset Consumption Costs: Recurring
WBS #
Description
4.1
5.0
IT application support
Server hosting (x3)
Units Consumed
Total Cost
25GB
50GB
Total One-Time:
Units Consumed
20 person days / year
$600 / server / year
Total Recurring:
$6,000
$2,000
$8,000
Total Cost
$40,000 / year
$1,800 / year
$41,800 / year
2014/15 ASPA (Specialist/Professional/IT/Managerial) Full Position Costing Estimates (Target Salary/Per Year):
$69,000 (Phase 1), $87,000 (Phase 2), $108,000 (Phase 3).
ALTERNATIVES
What other approaches have been considered? List the alternative project strategies available to develop the project such as
outsourcing, purchasing off-the-shelf software, customized code development, etc. and why they were not selected.
CONSTRAINTS
What are the strategic directives that will guide decision-making throughout the life of the project (if any)? Document the
overarching project themes. Typically, but not necessarily, these themes cover cost, timeliness, and quality.
RISKS
What are the risks that may impact successful completion of the project? For each risk, identify the probability of occurrence and
expected impact of the risk if it occur. Use H/M/L for High/Medium/Low. For example:
Project Plan
April 6, 2015
Description
Probability
Impact
M
H
Lack of available resources
Furthermore, please document the risks to the institution if ICT does not deliver on this project, or if the project is unsuccessful.
SUPPLEMENTAL PROJECT CONSIDERATIONS
Metric
Will this project be exposed to - or be expected to manage - sensitive
personal or institutional information?
For example, does the project have HIPA, PCI or PIPEDA implications?
Does this project align with the principles of ICT’s enterprise architecture?
Value
(Yes, No, Unsure)
If “yes” or “unsure”, please contact
ICT Access & Compliance
(Yes, No, Unsure)
If “no” or “unsure”, please contact the
ICT Enterprise Architect
(Your completed project charter must not exceed 5 pages in length)
Project Plan
April 6, 2015
PROJECT PLAN TEMPLATE
Template Purpose
The following document outlines the content and format of project plans to be used for major projects. Any
project requiring greater than 40 person days of effort requires a project plan. A project plan should be written
for each project charter granted approval to plan by a stewardship committee. Completed project plans are
submitted to the ICT Management Team and if approved will be escalated to the appropriate stewardship
committee for formal approval. There must be sufficient information in this document for these groups to make
a decision.
The project plan is a formal, approved document used to manage project execution. The project plan is a
document or collection of documents that should be expected to change over time as more information becomes
available about the project. There are many ways to organize and present the project plan, but all of the sections
identified in this document should be included.
Each project plan is intended to clearly document how the project will be executed and will serve as guide during
the execution phase of the project. There must be sufficient information in this document to help the steering
committee make their decision to proceed with the project, as well as sufficient detail to enable the project
manager to run the project. Project plans should be submitted to the ICT Project Portfolio Office. You must
submit 2 weeks prior to the meeting you would like to present at. These meetings are usually held every two
months.
As the project progresses through the execution phase and project circumstances change, this document will be
updated to reflect these changes. These changes must be submitted to the steering committee for approval.
The document shell outlined below identifies the key sections needed for any project plan. Anything in red Italics
is simply a description of the kind of information that should be entered. All text in red Italics in this document is
instructional and should be removed from the final version of each project plan.
Remove this page from your project charter before submission. The total number of pages in the final document
is not restricted.
Project Closeout
April 6, 2015
PROJECT PLAN
Project Name:
Project Code:
Meaningful, yet concise
Assigned by ICT
Author(s) of Charter:
Author(s) and contributors
Author(s) of Plan:
Author(s) and contributors
Project Manager:
Name
Submission Date:
Date submitted
Summary
Sponsor:
Completion Date:
Name
Month, dd, yyyy
Other projects with
Linkages:
dependencies
Total Monetary
Total Asset Consumption
Planned One-Time
Costs:
$
$
Planned Recurring
Costs:
$
$
Planned Person
Days:
Total Person Days
Project Strategy ......................................................................................................................................................................................... 2
Scope.......................................................................................................................................................................................................... 2
Scope Statement .................................................................................................................................................................................... 2
Scope Management Plan ....................................................................................................................................................................... 2
Schedule ..................................................................................................................................................................................................... 2
Schedule Baseline .................................................................................................................................................................................. 2
Schedule Management Plan .................................................................................................................................................................. 2
Budget ........................................................................................................................................................................................................ 3
Cost Baseline .......................................................................................................................................................................................... 3
Cost Management Plan .......................................................................................................................................................................... 3
Quality Management ................................................................................................................................................................................. 4
Quality Definition ................................................................................................................................................................................... 4
Quality Management Plan ..................................................................................................................................................................... 4
Resources ................................................................................................................................................................................................... 4
Staff Baseline ......................................................................................................................................................................................... 4
Staffing Management Plan..................................................................................................................................................................... 4
Asset Management Plan ........................................................................................................................................................................ 4
Communications ........................................................................................................................................................................................ 4
Communications Strategy ...................................................................................................................................................................... 4
Communications Management Plan ...................................................................................................................................................... 4
Risks ........................................................................................................................................................................................................... 5
Risk Management Plan .......................................................................................................................................................................... 5
Risk Response Plan ................................................................................................................................................................................. 5
Procurement Management Plan................................................................................................................................................................ 5
Stakeholder Management Plan……………………………………………………………………………………………………………………………………………………………6
Supporting Detail ....................................................................................................................................................................................... 6
Page 1 of 6
Project Closeout
April 6, 2015
PROJECT STRATEGY
Describe the project management approach or strategy. Provide a summary of the relationship between the project and
organization strategy and policy.
SCOPE
Scope Statement
The objective of the scope statement is to refine the project boundaries originally outlined in the Project Charter.
Develop the Work Breakdown Structure (WBS) to the level at which management control will be exercised and
the WBS becomes the project’s baseline scope document.
Include the project objectives and the prime project deliverables.
Scope Management Plan
Describes how project scope will be managed and how scope changes will be integrated into the project. Include
an assessment of the expected stability of the project scope (i.e. likelihood, frequency, and quantity of changes).
The Scope Management Plan should also include a clear description of how scope changes will be identified and
classified.
SCHEDULE
Schedule Baseline
The project schedule lists planned dates for performing activities and meeting milestones identified in the project
plan. It includes the following:
• Start and finish dates for each task in the Work Breakdown Structure (WBS)
• All dependencies amongst tasks in the WBS
• Resources assigned to each task in the WBS
Schedule Management Plan
Define how changes to the schedule will be managed.
Note: You will likely find it easiest to use a tool such as Microsoft Project for your schedule.
Page 2 of 6
Project Closeout
April 6, 2015
BUDGET
Cost Baseline
Estimate the cost of each deliverable in the WBS. Present it as an easy-to-read table that includes separate
columns for One-time Monetary, One-Time Resource Consumption, Recurring Monetary, and Recurring Resource
Consumption.
Cost Management Plan
Define how cost variances will be managed (including the different responses to major versus minor problems)
and how they will be reported. Determine how budget revisions or forecasts will be developed and how
frequently they will be made.
The Project Manager must:
• Explain how this project will be funded and describe this information here;
• Separate capital and operating costs;
• Use estimate confidence numbers for uncertain estimates (e.g. +/-10%);
• If applicable, specify the source for funding; and,
• Include all applicable taxes.
Example of monetary costs:
Monetary Costs: One-Time
WBS #
Description
3.1
4.1
3 IBM Server
Contract programmer
Budget Code
Computer hardware
Temporary salary
Recovery from?
ICT capital
ICT base budget
Total One-Time:
Monetary Costs: Recurring
WBS #
Description
5.1
Vendor service agreement
Budget Code
Hardware maintenance
Recovery from?
ICT base budget
Total Recurring:
Example of asset consumption costs:
Asset Consumption Costs: One-Time
WBS #
Description
5.0
5.0
Initial disk storage
Initial tape backup
Asset Consumption Costs: Recurring
WBS #
Description
4.1
5.0
5.0
5.0
IT application support
Storage growth
Backup growth
Server hosting
Units Consumed
Total Cost
$10,000 +/- 5%
$50,000 +/- 10%
0 +/- 10%
Total Cost
$250 / year
$250 / year
Total Cost
25GB
50GB
Total One-Time:
Units Consumed
20 person days / year
100GB / year
100GB / year
$600 / server / year
Total Recurring:
$6,000
$2,000
$8,000
Total Cost
$40,000 / year
$300 / year
$100 / year
$1,800 / year
$42,200 / year
Page 3 of 6
Project Closeout
April 6, 2015
QUALITY MANAGEMENT
Quality Definition
Describe how the project will implement its quality policy. Test matrices and plans are considered part of the
quality management process. The project quality system includes the organizational structure, responsibilities,
procedures, processes, and resources needed to implement quality management.
Quality Management Plan
The quality management plan must address quality control, quality assurance, and quality improvement for the
project. Define what quality means to customers in the context of this project and specifically how it will be
measured.
This plan must address benefits realization. What are the metrics to measure how benefits will be realized?
Define the process by which these benefits will be measured the person(s) responsible for turning promised
customer benefits into reality.
RESOURCES
Staff Baseline
Identify the key or required staff and their expected cost and/or effort. Document the organizational structure of
project.
Staffing Management Plan
Define when and how human resources will be added to and removed from of the project team.
Asset Management Plan
Define facility, technical, and physical resources needed to support the project.
COMMUNICATIONS
Communications Strategy
Define the key messages to be sent externally and internally and identify stakeholders to receive messaging.
Communications Management Plan
Page 4 of 6
Project Closeout
April 6, 2015
The communications plan is a description of the information to be distributed, including format, content, level of
detail, and conventions/definitions to be used. It includes production schedules showing when each type of
communication will be produced and who will receive the information. A method for updating and refining the
communications management plan as the project progresses and develops should also be included.
RISKS
Risk Management Plan
Identify key risks including constraints and assumptions, and determine planned responses and contingencies for
each risk.
Risk Response Plan
Risk response plans should:
• Identify risks, their descriptions, the area(s) of the project affected, their causes, and how they may affect
project objectives;
• Assign risk owners and their responsibilities;
• Document results from the qualitative and quantitative risk analysis processes;
• Identify agreed upon or approved responses including avoidance, transference, mitigation, or acceptance
for each risk in the risk response plan;
• Identify the level of residual risk expected to remain after the strategy is implemented; and
• Document specific actions required to implement the chosen response strategy, including budget and
times for responses, and contingency plans and fall back plans.
PROCUREMENT MANAGEMENT PLAN
Describe how the procurement processes will be managed. Processes include:
• Vendor solicitation
• Source selection
• Contract administration
• Contract close-out
Key questions to answer in the plan include:
• What types of contracts will be used?
• If independent estimates will be needed as evaluation criteria, who will prepare them and when?
• How will the project management team work with the Purchasing department?
• How will multiple providers be managed?
• How will procurement be coordinated with other project aspects, such as scheduling and performance
reporting?
Page 5 of 6
Project Closeout
April 6, 2015
STAKEHOLDER MANAGEMENT PLAN
Identify the people, groups or organizations that could impact or be impacted by the project.
Analyze those stakeholders’ expectations and their impact on the project, and to develop appropriate management
strategies for effectively engaging stakeholders in project decisions and execution.
Depending on the individual’s power and influence in relation to the project, decide on whether to monitor them, keep
them informed, keep them satisfied or to closely manage them.
SUPPORTING DETAIL
Supporting details for the project plan include:
• Outputs from other planning processes that are not included in the project plan.
• Additional information or documentation generated during development of the project plan.
• Technical documentation; such as requirements history, specifications, and conceptual designs.
• Documentation of relevant standards.
• Specifications from early project development planning.
• Open issues and pending decisions.
Page 6 of 6
Project Closeout
April 6, 2015
PROJECT CLOSURE TEMPLATE
Template Purpose
The following document outlines the content and format of project closeout reports to be used for major
projects. A closeout report should be written for all completed projects. Completed closeout reports will have
been circulated for consultation and then submitted to the appropriate steering committee for review before
sign-off and for archival by Project Portfolio Office.
The project closeout report is a document used to formally complete project execution. Stakeholder sign-off is
required in order to declare the project closed. The closeout report must include every section described in this
document.
Each closeout report is intended to clearly document how the project proceeded and will serve as a guide to
improve performance on future projects. There must be sufficient information in this document to satisfy
stakeholders that the project is complete and sufficient detail to enable improvement in future projects. The
expected benefits section of the closeout report is very important for future benefits tracking.
The document shell outlined below identifies the key sections needed for any project closeout report. Anything in
red Italics is simply a description of the kind of information that should be entered. All text in red Italics in this
document is instructional and should be removed from the final version of each project closeout report. Remove
this page from your final closeout report.
Always start by looking at existing Project Closeout Reports and always use the latest version of the template
from the ICT Project Portfolio Office.
Page 7 of 1
Project Closeout
April 6, 2015
PROJECT CLOSEOUT REPORT
Project Name:
Project Code:
Meaningful, yet concise
Assigned by ICT
Author(s) of Charter:
Author(s) and contributors
Author(s) of Plan:
Author(s) and contributors
Author(s) of Closeout:
Author(s) and contributors
Project Manager:
Name
Submission Date:
Date submitted
Summary
Sponsor:
Completion Date:
Linkages:
Name
Month, dd, yyyy
Other projects with
dependencies
Total Monetary
Total Asset Consumption
Actual One-Time
Costs:
$
$
Actual Recurring
Costs:
$
$
Actual Person
Days:
Total Person Days
PROJECT SUMMARY
Provide a brief summary of the project as completed. This is especially important if the project, as carried out, differs
from what was presented in the project plan.
DELIVERABLES
Use the WBS from the final project plan to list the major deliverables achieved during the project; note that these may
differ from the original planned deliverables.
DOCUMENTATION
List all documentation that was generated as a result of this project, including who wrote it, where it is stored, and how
to access it.
EXPECTED BENEFITS
Now that the project is complete, what benefits were realized? What benefits can we still expect to realize? List the
benefits included in your original Project Charter and indicate whether they were realized or will they be realized in the
future. If any new benefits have emerged, list them here as well.
Offer recommendations on how to perform benefits tracking; use the Success Criteria from the Project Charter for this
purpose. Was the overall project a success? This will be presented to the steering committee.
Page 1 of 3
Project Closeout
April 6, 2015
LESSONS LEARNED
Present a numbered list of lessons learned in the following format:
1
Challenge:
Successes:
Lessons:
What was the problem encountered?
How you were able to overcome or work around the problem and continue with the project?
What you would do differently in future projects, or what you would pass on to future project managers?
2
Challenge:
Successes:
Lessons:
What was the problem encountered?
How you were able to overcome or work around the problem and continue with the project?
What you would do differently in future projects, or what you would pass on to future project managers?
CHANGE SUMMARY
Use your list of change request forms to present a table of changes that were approved during the course of the project.
Change #
0000
Description
Short description of the change
Impact
Effect of the change on the project
Date
Date approved
VARIANCES
Scope
How is your project scope different from the original plan?
Cost
Present baseline/actual cost differences here; justifications are not necessary.
Schedule
Present baseline/actual schedule differences here; justifications are not necessary.
TRANSITION TO OPERATIONS
If the project has created a new service, record how this product or service is to be operationally managed now that the
project is over. Indicate if any Service Level Agreements (SLAs) or Operational Level Agreements (OLAs) have been
created. Note what steps have been taken to transition to operations, as well as any recommendations for the future.
It is highly recommended that you include a Responsibility Assignment Matrix using the RACI (Responsible, Accountable,
Consulted, Informed) model.
Responsibility Matrix
Operational Activity
Operational Activity
Operational Activity
Operational Activity
Functional Area
R
A
C
C
Functional Area
A
A
I
Functional Area
A
Functional Area
C
I
I
I
Page 2 of 3
Project Closeout
April 6, 2015
NEXT STEP OPPORTUNITIES
Describe any future opportunities created by this project; include any information, which may be relevant in terms of
initiating new future projects.
Do you feel that this project is newsworthy?
Yes
No
Completed projects that are considered to be “noteworthy” will be forwarded on to Marketing and Communications for
advertising; they will determine where it should be published.
SIGN OFF
List the stakeholders signing off on the project and have them sign and date this report. A signed paper copy should be
presented to the Project Portfolio Office for storage in the project repository.
Sponsor
Name Type the name here before printing this document out for signature.
Signature
Date
Comments
Any comments on the project, project team, this report, etc.
Project Manager
Name Type the name here before printing this document out for signature.
Signature
Date
Comments
Any comments on the project, project team, this report, etc.
Stakeholder(s)
Name Type the name here before printing this document out for signature.
Signature
Date
Comments
Any comments on the project, project team, this report, etc.
Page 3 of 3
ICT Project Management
Process
April 6, 2015
PROJECT CHANGE REQUEST TEMPLATE
Template Purpose
The following document outlines the content and format to be used for change requests for chartered projects
that are in the monitoring phase.
All sections are mandatory.
Prior to submission to the steering committee, the Change Request must be approved by the sponsor and
stakeholders listed in the Client Approvals section. The request should be submitted to ICT Management and it
can be submitted at any time during the execution of a project.
This document shell identifies the key sections needed for any Project Change Request. Anything in red italics is
simply a description of the kind of information that should be entered and should be removed from the final
version.
Remove this page from your project charter before submission. The total number of pages in the final document
must not exceed 5 pages.
ICT Project Management
Process
April 6, 2015
PROJECT CHANGE REQUEST
Project Name:
Project Code:
Author(s) of Charter:
Meaningful, yet concise
Assigned by ICT
Author(s) and contributors
Project Manager:
Name
Submission Date:
Date submitted
Summary
Sponsor:
Completion Date:
Linkages:
Name
Month, dd, yyyy
Other projects with
dependencies
Total Monetary
Total Asset Consumption
Planned One-Time
Costs:
$
$
Planned Recurring
Costs:
$
$
Planned Person
Days:
Total Person Days
PROPOSED CHANGE
Description of change:
Explain the details of the proposed change.
Benefit of making the change:
Define the reasons for making the proposed change.
Consequence of not making the change:
What are the consequences to the project and the sponsor if the change is not implemented?
CHANGE IMPACTS
Answer each of the following questions that apply to the change request.
1. What are the fiscal or base budget funding changes required as a result of this change?
2. What is the effect of this change on the project schedule, sequence of tasks, and key milestones?
3. How will this change affect project resources?
4. How will the change affect the outcome of any project deliverables?
Page 1 of 2
ICT Project Management
Process
April 6, 2015
5. What is the impact of this change on project quality?
6. How does the request affect any of the risks identified in the project plan?
7. Will this change impact the technical, procedural, or physical security posture?
8. Will this change have an impact on any production functions or services provided?
9. Will there be a Change Advisory Board (CAB) request associated with this change?
CLIENT APPROVALS
Seek approval for your change request from the sponsor and affected stakeholders.
Sponsor/stakeholder
Name of Individual
Name of Individual
Name of Individual
Approved
Yes/no
Yes/no
Yes/no
Date
Current date
Current date
Current date
Page 2 of 2
Download