Site Evaluations Simpson Creek Site Information Site Location: Willamette NF, Forest Rd 21 MP 21.1 Year Installed: 1995 Lat/Long: 122°23’48.74”W 43°29’48.24”N Watershed Area (mi2):11.3 Stream Slope (ft/ft)1: 0.0516 Channel Type: Step-pool Bankfull Width (ft): 25 Survey Date: 1 March 22, 2007 Water surface slope extending up to 20 channel widths up and downstream of crossing. Culvert Information Culvert Type: Open-bottom arch Culvert Material: Annular CMP Culvert Width: 22 Outlet Type: Mitered Culvert Length: 114 Inlet Type: Mitered Pipe Slope (structure slope): 0.083 Culvert Bed Slope: 0.044 (First hydraulic control upstream of inlet to first hydraulic control downstream of outlet.) Culvert width as a percentage of bankfull width: 0.89 Alignment Conditions: Online with natural channel. Bedform Conditions: Coarse material forming many continuous steps in culvert. Pipe Condition: Good condition. Little to no rust or open joints. No footing scour. Hydrology Discharge (cfs) for indicated recurrence interval 25% 2-yr 2-year Qbf2 5-year 10-year 50-year 100-year 65 258 330 407 511 751 858 2 Bankfull flow estimated by matching modeled water surface elevations to field-identified bankfull elevations. Simpson Creek A—391 Culvert Scour Assessment Points represent survey points Figure 1—Plan view map. A—392 Simpson Creek Site Evaluations History The Simpson Creek culvert was installed in 1995. The previously installed culvert had a 14-foot diameter, a 3- to 4-foot perch and a sediment wedge was apparent at the culvert inlet (Kim Johansen, personal communication). According to the designer (Kim Johansen), class VII riprap was specified, which would have had the largest particles 1.6 feet in diameter. Local pit material was actually placed in the culvert, which contained a more well-graded but fine-lean mix. This included up to 24-inch-diameter boulders. It also included 3.5- to 4.5-foot “fish rest stop rocks” placed at 16-foot intervals in two rows 11 feet apart centered in the structure and offset by 8 feet from one another. There was 12 inches of screened aggregate approximately 2-inch to 1/2inch was placed on top of the constructed bed. The spread footing is 5 feet deep and 5 feet wide. There was a 7-foot-deep scour pool below the old culvert. The downstream scour pool was filled placing a group of 3- to 5-foot-diameter boulders in the bottom, then pulling tailout material into the hole to restore a long profile. The channel exhibited at least two major historic channels downstream within the delta area downstream of the culvert. The culvert experienced the February 1996 flood, which was estimated to be a 100-year flood on Simpson Creek. The flood resulted in upstream channel incision and deposition in the culvert. which is followed by a large drop and a plunge pool at the inlet. Evidence of channel incision upstream of the culvert can be observed along both banks, but is most apparent on the actively eroding left bank. The Simpson Creek culvert is a bottomless arch that is mitered to conform to the roadfill. The channel through the crossing consists of a series of steep riffles and steps interspersed by turbulent plunge pools. Assuming the culvert and culvert bed were originally installed on the same grade, there has been bed adjustment within the pipe consisting of incision in the upstream portion and/or aggradation in the downstream portion. The above information was provided by Kim Johansen. Downstream of the culvert, the channel remains relatively flat, opening to a braided reach. An abandoned channel runs along the right valley wall. The channel splits at an island below the culvert. Below the island, gradient picks up and the reach consists of steep riffles and steps interspersed with turbulent plunge pools. The substrate here is finer than in the culvert and in the channel upstream of the culvert, and is comprised of large cobbles and small-to-medium boulders. A more extensive and well-defined flood plain exists in the downstream reach compared to the upstream reach. This is largely a depositional area as the Simpson Creek valley transitions into the broad valley of the mainstem Middle Fork Willamette. Small wood pieces have accumulated along the margins of the stream. A gravel road runs along the left bank. Site Description The upstream channel consists of a high gradient step-pool channel with a low but narrow active flood-plain surface. The channel sits in a confined and narrow valley and at times abuts the valley walls. Boulder steps are interspersed by turbulent plunge pools. Downed trees stretched across the channel while some in-channel wood forms jams along the edges. The upstream channel flattens as it enters the culvert. There appears to be some material that has deposited upstream of the inlet, Survey Summary Fifteen cross sections and a longitudinal profile were surveyed along Simpson Creek in March 2007 to characterize the culvert, the upstream channel, and the downstream channel. Four cross sections were measured upstream of the culvert to characterize the upstream channel. Four cross sections were measured downstream of the culvert to characterize the channel downstream of the crossing. In the culvert, cross sections were taken through a step and Simpson Creek A—393 Culvert Scour Assessment between steps. Two additional cross sections were surveyed downstream of the culvert to characterize the outlet and the expansion of flow. Another cross section was surveyed upstream to characterize the inlet and the contraction of flow. Six pebble counts were taken at crosssection locations. The cross-section locations and pebble-count locations are depicted on the map (figure 1) Profile Analysis Segment Summary The profile analysis resulted in 10 profile segments (figure 2). The culvert consisted of one profile segment (F). The culvert segment matched the gradient of a representative segment in the upstream channel (H), which is affected by channel incision; interpretations of results take this into account. Another representative segment in the upstream channel (J) had a gradient difference of 35 percent, but was included as a potential comparison segment due to similarities in bed morphology (closely spaced step-pool sequences) (table 1). The inlet transition segment (G) has comparable gradient to two downstream channel segments (A and C) and one upstream segment (J). The outlet transition segment has comparable gradient to segment H, with the same caveats mentioned above. Segment comparisons must consider that throughout this reach is a geomorphic transition from the narrow Simpson Creek valley into the broad Middle Fork Willamette River valley. This transition is characterized by a downstream widening of the valley and a concave longitudinal profile shape. Geomorphic influences, such as gradient and valley width that change throughout this reach are taken into consideration when interpreting comparisons between segments. A—394 Scour Conditions Observed conditions Footing scour – There was no observed scour undermining footings or threatening structure integrity. Culvert-bed adjustment – Assuming that the culvert structure and culvert bed were originally constructed at the same gradient, the culvertbed profile has flattened since construction. This flattening appears to be mostly due to aggradation within the downstream portion of the culvert, with potentially some inlet scour within the upstream portion of the culvert. Approximately 100 cubic yards were estimated to have been entrained during the 1996 flood, depositing downstream of the culvert into the mainstem Middle Fork Willamette River and extending upstream to aggrade the entire culvert bed and about 30 feet of upstream channel. Since then, the upstream extent of deposits has moved downstream to the midpoint of the culvert. Inlet contraction during other smaller flood events has maintained transport of material through the inlet region (Kim Johansen, personal communication). Profile characteristics – The profile has a concave shape through the crossing (figure 2). This shape reflects channel incision in the upstream channel and scour at the inlet region, combined with aggradation in the downstream portion of the culvert and in the channel downstream of the culvert. Incision in the upstream channel potentially resulted from a headcut propagating upstream from inlet scour. In the absence of the culvert, natural concavity of the profile would be expected based on the geomorphic valley transition through this reach. The adjustments observed at this site may reflect the tendency towards this concave profile condition. Simpson Creek Residual depths – Culvert residual depths ranged from 0.11 feet to 1.17 feet and were within the range of the comparable slope segment J (figure 21). The upstream transition segment was also within the range of comparable slope segments. Residual depth in the downstream transition segment was within a few inches of that found in the comparable slope segment H. These results suggest no significant local scouring at the channel-unit scale beyond what is found in the channel outside of the crossing. Substrate – Culvert bed material distributions are similar to segments in the channel outside of the crossing. Culvert substrate is slightly coarser than channel pebble counts, reflecting large rocks placed in the culvert during construction. Culvert substrate generally has less material in the fine size classes. Pebble counts are provided at the end of this summary. Predicted conditions Cross-section characteristics – Cross-section characteristics appear to be affected by the culvert (figures 5 through 7 and 12 through 17). In the absence of the culvert, we might expect a gradual change in cross-section characteristics as the reach transitions into the broader valley of the Middle Fork Willamette. However, for widthto-depth ratio, wetted perimeter, and top width, the culvert is an anomaly in that trend. With the exception of flow area, the range of values for the culvert differs from that of comparable slope segments for nearly all of the cross-section metrics. For all the cross-section metrics, the upstream transition segment (G) is mostly within the range of values of the upstream comparable segment (J). However, downstream segments with comparable gradient (A and C) differ substantially, especially at the higher flows. Although these discrepancies may be partly due to culvert influences, they are also likely affected by the natural change in valley width between these segments. Simpson Creek Site Evaluations The downstream transition segment (E) is substantially different for nearly all crosssection metrics than segment H. It is difficult to distinguish the effect of the culvert from the influence of transitioning valley width and gradient through this reach. Segment H also has potential influence from channel incision, which limits its utility for comparisons. Shear stress – The culvert (F) has lower shear stresses than the upstream comparative segments (H and J) (figures 10 and 19). Lower shear stress may be attributable to a lower energy slope in the pipe that is caused by outlet control conditions related to reduced pipe capacity from aggradation in the downstream portion of the pipe. The upstream transition segment (G) has similar shear to the upstream comparable segment (J) at the Q10 and below but less shear above the Q10. Shear is comparable between G and the downstream segments with similar gradient (A and C). The downstream transition segment (E) has lower shear than comparable segment H. Excess shear – The excess-shear analysis suggests that the potential for bed mobilization in the culvert is within the range of the downstream channel (figure 20) but is lower than the upstream channel. Higher channel shear in the upstream channel and slightly smaller D84 contribute to higher estimated bed mobility in the upstream channel when compared to the culvert. Velocity – The variation of velocity in the culvert segment is more similar to the upstream channel than the downstream channel (figures 11 and 18). Culvert velocity is generally similar to the comparative segments H and J for all modeled flows. The range of velocity in the upstream transition segment (G) does not substantially differ from the comparable slope segments (A, C, and J). Velocity in the downstream transition segment (E) is generally lower than the comparative segment H, especially at the higher flows. A—395 Culvert Scour Assessment Scour summary The culvert shows no significant bed scour. However, assuming the culvert and culvert bed were originally constructed at the same gradient, there has been bed adjustment. This adjustment is believed to be primarily related to the February 1996 flood event (approximately a 100-year flood), which resulted in profile adjustment through aggradation in the downstream portion of the pipe (Kim Johansen, personal communication). Some culvert capacity has been lost as a result. This is reflected in the model, with elevated water surface profiles through the culvert due to outlet control conditions. Despite this slight capacity reduction, this large culvert is at low risk of significant backwater or overtopping. Conditions indicate a low risk for future scour in the culvert. There is likely to be a continued upstream supply of material as the channel continues to widen in response to the 1996 incision. Continued aggradation may occur downstream of the outlet where the valley widens and the slope flattens. Continued aggradation in the culvert is possible, especially at high flows where outlet control conditions reduce the energy slope in the pipe. AOP Conditions Cross-section complexity – The sum of squared height differences in the culvert cross sections are both within the range of those in the channel cross sections (table 3). Profile complexity – Vertical sinuosity in the culvert segment (F) and in the upstream transition segment (G) are greater than their comparable channel segments (table 4). This reflects a higher frequency of steps through these segments. Vertical sinuosity in the downstream transition segment (E) is the same as comparative segment H. A—396 Depth distribution – There is less channel margin habitat in the culvert compared to the channel at the 25 percent Q2 (table 5). Habitat units – There is a similar habitat-unit composition between the culvert and the channel outside the crossing (table 6). There is slightly more pool habitat in the culvert and less step habitat. The number of steps in the culvert is high but they are shorter steps than the natural channel with more pool habitat in between. This could result in more turbulent conditions in the short pools during high flows, with less resting habitat compared to the channel where pools are longer and more pool area is outside the influence of turbulence created by the upstream step. Residual depths – Culvert-residual depths ranged from 0.11 feet to 1.17 feet and were within the range of the comparable slope segment J (figure 21). The upstream transition segment was also within the range of comparable slope segments. Residual depth in the downstream transition segment (E) was within a few inches of that found in the comparable slope segment H. Bed material – Bed-material distributions are similar in the culvert compared to the channel (see pebble-count data provided at end of this site summary). There are slightly less gravels in the culvert. The size and frequency of the large particles in the culvert are similar to the upstream channel but greater than the downstream channel. This partly reflects the gradient transition through the crossing but also reflects the large rocks that were placed during construction. Culvert bed material sorting values are all within the range found in the stream channel (table 7). Sorting values indicate “poor” sorting, which is typical for step-pool systems. The bed material skewness value in the upstream cross section Simpson Creek in the culvert is less than any skewness values in the channel. The low value indicates a nearly normal (symmetrical) distribution, which is due to a lack of material in most of the smaller size classes (less than 22.6 millimeters). The distribution among the larger size classes is similar to that found in the channel cross sections. Large woody debris – There was no LWD present in the culvert (table 8). The representative channel had very high LWD abundance, but most of the wood was smaller pieces of alder along the channel margins, with occasional large pieces creating lateral scour pools. This channel margin wood would provide velocity refuge for fish at high flows. This condition was not present in the culvert. AOP summary Measurements and observations suggest that the Simpson-Creek culvert has similar conditions to the natural channel with respect to AOP, with potential passage issues only at higher flows when turbulence and lack of margin areas in the culvert may reduce passability. Cross-section complexity in the culvert is within the range of that found in the channel. Culvertresidual depths are also similar to the channel; however, the vertical sinuosity in the culvert (and in the upstream transition) is greater, which indicates a different bedform pattern in the culvert region. This is likely related to the large material that was placed at frequent intervals in the culvert during construction, including the “fish rest stop” rocks. At lower fish passage flows (i.e., an average spring, summer, or fall flow) these frequent steps could provide ample velocity refuge for passage; however, at larger flows the frequent steps could create turbulence within the adjoining small pools, potentially limiting the availability of low energy areas for fish to Simpson Creek Site Evaluations hold during migration. Furthermore, based on the depth-distribution analysis, suitable channel margin areas would not be available during these higher events. Bed-material composition is similar between the culvert and the channel segments, with only slight differences that can be explained by the gradient transition through the reach and the placement of boulders during construction. These similar bed compositions suggest that AOP is not impaired by the characteristics of the culvert bed material. Design Considerations Despite moderate bed adjustments, this design has functioned well, especially considering that it experienced an approximate 100-year flood within 5 months following installation. It is uncertain the degree to which channel incision is related to the culvert design as opposed to naturally occurring incision during the Q100 flood. In either case, over 10 years later the culvert appears capable of conveying flood flows without overtopping, scouring, or significantly altering channel hydraulics. Hydraulic modeling indicates that even at the Q100, the total culvert diameter would only be submerged 50 percent at the inlet and less than 75 percent at the outlet, which exceeds standard design criteria. An increase in channel margin areas (i.e., through bank construction within a wider culvert) could benefit fish passage by creating shallower flows along channel margins during high fish passage flows (e.g., 25 percent Q2). Additionally, lengthening the pool/step sequence in the culvert so that it better matches the spacing found in the channel could improve passability by reducing the inter-step (pool) turbulence. A—397 A—398 Relative elevation (ft) 122 47 42 26 172 F G H I J 800 700 (rif fle ) Pe b b le c o u n t A 3 600 (s te p /rif fle ) Pe b b le c o u n t B 4 C 0 .0 6 8 0 .0 4 2 0 .0 9 7 0 .0 7 1 0 .0 4 4 0 .0 3 4 0 .0 9 4 0 .0 5 8 0 .0 2 9 6 H J J A C H G G G D o w n s trea m T ra n s itio n E U ps trea m T ra n s itio n 400 (p o o l) 17.6% 4.3% 16.5% 24.5% 5.1% 35.0% 9 300 (s te p /rif fle ) Pe b b le c o u n t % D ifferen c e in G ra d ien t 8 C ulvert Pe b b le c o u n t 7 F D is ta nc e a long bed (feet) 5 F F 500 E R epres en ta tiv e C h a n n el S eg men t D Split channel through this section C u lv ert S eg men t Table 1—Segment comparisons Figure 2—Simpson Creek longitudinal profile. 80 85 90 1 72 E 2 37 69 C D Representative Channel 72 B 0 .0 8 5 G r a d ie n t 22 A Relative elevation (feet) 95 100 105 110 115 120 125 130 S egm en t S egm ent L e n g th ( f t) S egm ent G 10 11 H I 200 12 (s te p ) Pe b b le c o u n t 13 J 100 Representative Channel 14 (p o o l) Pe b b le c o u n t 15 0 Culvert Scour Assessment Simpson Creek Simpson Creek n o i t a v e l E ) t f ( 0.1138 – 0.1143 0.115 – 0.1164 0.1147 – 0.127 0.105 – 0.1299 0.0903 – 0.1409 0.1309 – 0.1376 0.117 – 0.131 A C E F G H J SegmentRange of Manning’s n values1 2 2 3 3 1 1 1 # of measured XSs 12 4 4 16 9 5 4 # of interpolated XSs Elevation (ft) 80 90 100 110 120 130 0 . . . 3 3 3 3 . 1 . . . 6 6 6 6 . 1 * 5 2 5 . . 2 2 2 1 . 3 3 * 2 . 3 * 3 . 3 * 5 . 3 100 * 4 . 3 * 6 . 3 * 7 . 3 Figure 3—HEC-RAS profile. 1 * 8 1 . 4 * 5 2 . 4 * 9 3 . 4 200 * 2 3 . 4 * 6 4 . 4 * 3 5 . 4 6 . 4 * 6 6 . 4 * 2 7 . 4 * 8 7 . 4 * 4 8 9 . . 4 4 * 3 3 3 3 5 . 5 8 . 5 5 7 . 6 8 7 . 6 8 . 6 7 4 . 7 5 . 7 8 400 5 2 2 . . 8 8 Main Channel Distance (ft) 300 * 6 6 6 6 2 . 5 5 . 8 * 3 3 3 3 3 . 9 * 6 * 6 5 6 * 2 6 5 1 6 . . . 0 0 1 1 9 1 1 1 1 * 5 2 . 1 1 5 . 1 2 1 1 500 * 5 7 3 . 1 1 5 . 2 3 1 1 3 1 . 3 1 5 2 . 3 1 * 5 7 3 . 3 1 * 5 . 3 1 Stations with decimal values are interpolated cross sections placed along the surveyed profile. 8 . 3 * 9 . 3 4 * 5 0 1 . 4 * 5 2 6 . 3 1 5 . 4 1 600 5 7 . 3 4 1 1 7 . 4 1 * 5 8 . 4 1 5 1 1 . 5 1 700 Ground WS 65 cfs WS Bnkfl WS Q10 WS Q50 WS Q100 L eg en d Obtained using equation from Jarrett (1984): n = 0.39S0.38R-0.16, where S=stream slope; R=hydraulic radius. Jarrett’s equation only applied within the following ranges: S = 0.002 to 0.08, R = 0.5 ft to 7 ft. For cross-sections outside these ranges, n was computed either from adjacent sections that fell within the ranges, using the guidance of Arcement and Schneider (1987), or from the HEC-RAS recommendations for culvert modeling. Table 2—Summary of segments used for comparisons Site Evaluations A—399 ) t f ( A—400 Elevation (ft) n o i t a v e l E ) t f ( n o i t a v e l E 110 112 -40 -20 -20 0 0 20 .1301 Station (ft) .1301 RS = 13 Station (ft) 20 . 1 3 1 40 40 .1301 60 60 80 80 Bank Sta Ground WS 65 cfs WS Bnkfl WS Q10 WS Q50 WS Q100 Legend Bank Sta Ground WS 65 cfs WS Bnkfl WS Q10 WS Q50 WS Q100 Legend n o i t a v e l E ) t f ( n o i t a v e l E Elevation (ft) 0 20 20 40 .117 80 60 100 80 WS Q50 WS Q100 Legend 110 -20 112 114 116 118 120 122 124 .1309 .1309 Station (ft) 40 60 .1309 RS = 12 Bank Sta Ground WS 65 cfs WS Bnkfl WS Q10 WS Q50 WS Q100 Legend 116 Station (ft) Bank Sta 118 0 Ground 120 -20 WS Bnkfl WS 65 cfs 122 WS Q10 -40 .117 RS = 14 124 126 128 130 .117 Figure 4­—Cross-section plots. Only measured cross sections are included. Manning’s n values are included at the top of the cross section. The stationing (RS) corresponds to the stationing on the HEC-RAS profile. Green arrows define the ineffective flow areas. Black arrows represent points identified in the field as the bankfull channel boundary. Only those points identified in the field and supported by hydraulic and topographic analyses are shown below. Elevation (ft) 114 116 118 -40 .131 RS = 15 Elevation (ft) 120 122 124 120 122 124 126 128 130 132 134 .131 ) t f ( Culvert Scour Assessment Simpson Creek Simpson Creek Elevation (ft) n o i t a v e l E ) t f ( n o i t a v e l E ) t f ( 0 20 40 RS = 9 60 .128 40 80 60 100 80 WS Bnkfl WS Q10 WS Q50 WS Q100 Legend 106 -20 Station (ft) Bank Sta Ineff n o i t a v e l E ) t f ( n o i t a v e l E Elevation (ft) 104 -40 106 108 110 112 114 116 118 106 108 110 112 -20 20 0 60 RS = 8 Station (ft) .115 Station (ft) 20 40 Note: n v alues f or f irs t prof ile. 40 80 100 80 120 60 Bank Sta Ground WS 65 cfs WS Bnkfl WS Q10 WS Q50 WS Q100 Legend Bank St a Ground WS 65 c fs WS Bnkf l WS Q10 WS Q50 116 114 L e ge nd WS Q100 .1409 118 0 RS = 10 .1409 120 .1409 Figure 4­—Cross-section plots. Only measured cross sections are included. Manning’s n values are included at the top of the cross section. The stationing (RS) corresponds to the stationing on the HEC-RAS profile. Green arrows define the ineffective flow areas. Black arrows represent points identified in the field as the bankfull channel boundary. Only those points identified in the field and supported by hydraulic and topographic analyses are shown below. (continued) Elevation (ft) 108 110 .128 Station (ft) 20 Ground 0 Bank Sta Ground WS 65 cfs WS Bnkfl WS Q10 WS Q50 WS Q100 Legend WS 65 cfs .128 -20 .1326 112 -40 .1326 RS = 11 Elevation (ft) 114 116 118 120 108 110 112 114 116 118 120 122 .1326 ) t f ( Site Evaluations A—401 ) t f ( A—402 Elevation (ft) n o i t a v e l E ) t f ( n o i t a v e l E 0 .127 0 40 20 40 60 .127 80 98 20 60 80 100 120 Station (ft) Bank Sta Ineff Levee 102 n o i t a v e l E ) t f ( Elevation (ft) .1152 .1152 60 80 100 120 WS Bnkfl WS Q10 WS Q50 WS Q100 Legend 90 92 94 96 98 100 102 104 100 102 20 40 Station (ft) 60 RS = 4 Station (ft) 80 100 .1152 120 Bank Sta Ground WS 65 cfs WS Bnkfl WS Q10 WS Q50 WS Q100 Legend Bank Sta Ineff Ground 40 .1124 WS 65 cfs 20 .1124 104 0 RS = 6 106 108 110 112 114 .1124 Figure 4­—Cross-section plots. Only measured cross sections are included. Manning’s n values are included at the top of the cross section. The stationing (RS) corresponds to the stationing on the HEC-RAS profile. Green arrows define the ineffective flow areas. Black arrows represent points identified in the field as the bankfull channel boundary. Only those points identified in the field and supported by hydraulic and topographic analyses are shown below. (continued) Elevation (ft) 100 Ground WS 65 cfs WS Bnkfl WS Q10 WS Q50 WS Q100 Legend 104 106 108 .127 RS = 5 Bank St a Ground n o i t a v e l E Elevation (ft) 110 112 114 102 -40 104 Station (ft) WS Bnkf l 108 106 WS Q10 110 WS 65 c fs WS Q50 -20 L e ge nd WS Q100 112 114 116 .116 RS = 7 Note: n values for first profile. ) t f ( Culvert Scour Assessment Simpson Creek Simpson Creek Elevation (ft) n o i t a v e l E ) t f ( n o i t a v e l E ) t f ( 84 0 0 20 .1115 20 40 .1138 60 Station (ft) 40 .1115 RS = 1 Station (ft) 60 RS = 3 .1115 80 80 .1138 100 100 WS Bnkfl WS Q10 WS Q50 WS Q100 Legend Bank Sta Ground WS 65 cfs 120 Bank Sta Ground WS 65 cfs WS Bnkfl WS Q10 WS Q50 WS Q100 Legend n o i t a v e l E Elevation (ft) 86 88 90 92 94 96 98 100 0 .1145 20 40 .1145 Station (ft) 60 RS = 2 80 .1145 100 120 Bank Sta Ground WS 65 cfs WS Bnkfl WS Q10 WS Q50 WS Q100 Legend Figure 4­—Cross-section plots. Only measured cross sections are included. Manning’s n values are included at the top of the cross section. The stationing (RS) corresponds to the stationing on the HEC-RAS profile. Green arrows define the ineffective flow areas. Black arrows represent points identified in the field as the bankfull channel boundary. Only those points identified in the field and supported by hydraulic and topographic analyses are shown below. (continued) Elevation (ft) 86 88 90 92 94 96 98 88 90 92 94 96 98 100 102 .1138 ) t f ( Site Evaluations A—403 A—404 . P . W l a t o T 0 50 100 150 200 250 300 0 A 100 B C 0 0 A 100 B Figure 6—Wetted perimeter. W.P. total (ft) 20 40 60 80 100 120 C Figure 5—Flow area (total) profile plot. Flow area (sq ft) ) t f ( w o l F a e r A q s ( ) t f 200 D 200 D 300 400 Culvert F 300 400 Culvert F Main Channel Distance (ft) E Main Channel Distance (ft) E G G 500 H 500 H Flow I Flow I 600 J 600 J 700 700 W.P. Total 65 cfs W.P. Total Bnkfl W.P. Total Q10 W.P. Total Q50 W.P. Total Q100 Legend Flow Area 65 cfs Flow Area Bnkfl Flow Area Q10 Flow Area Q50 Flow Area Q100 Legend Culvert Scour Assessment Simpson Creek Simpson Creek p o T h t d i W 0 1 2 3 4 5 0 A 100 B 0 0 A Figure 8—Top width. Top width (ft) 20 40 60 80 100 120 100 B Figure 7—Hydraulic radius. Hydrauliic radius (ft) ) t f ( r d y H s u i d a R ) t f ( C C 200 D 200 D E 300 400 Culvert F 400 Main Channel Distance (ft) 300 F Culvert Main Channel Distance (ft) E G G H 500 500 H I I Flow Flow J 600 600 J 700 700 Top Width 65 cfs Top Width Bnkfl Top Width Q10 Top Width Q50 Top Width Q100 Legend Hydr Radius 65 cfs Hydr Radius Bnkfl Hydr Radius Q10 Hydr Radius Q50 Hydr Radius Q100 Legend Site Evaluations A—405 r a e h S n a h C 0 1 2 3 4 5 6 7 8 0 A 100 B A—406 0 A 100 B C C 200 D 200 D Figure 10—Shear stress (channel) profile. Shear channel (lb/sq ft) 0 10 20 30 40 Figure 9—Maximum depth. Maximum channel depth (ft) q s / b l ( ) t f x a M l h C h t p D ) t f ( 300 Culvert F 400 300 400 F Culvert Main Channel Distance (ft) E Main Channel Distance (ft) E G G 500 H 500 H I I 600 J Flow 600 J Flow 700 700 Shear Chan 65 cfs Shear Chan Bnkfl Shear Chan Q10 Shear Chan Q50 Shear Chan Q100 Legend Max Chl Dpth 65 cfs Max Chl Dpth Bnkfl Max Chl Dpth Q10 Max Chl Dpth Q50 Max Chl Dpth Q100 Legend Culvert Scour Assessment Simpson Creek Simpson Creek l e V l n h C ) s / t f ( 0 0 A 100 B C 200 Figure 11—Velocity (channel) profile plot. Velocity channel (ft/s) 2 4 6 8 10 12 D 400 Culvert F Main Channel Distance (ft) 300 E G 500 H I 600 Flow J 700 Vel Chnl 65 cfs Vel Chnl Bnkfl Vel Chnl Q10 Vel Chnl Q50 Vel Chnl Q100 Legend Site Evaluations A—407 Flow area (ft2) A C J J F (Culv) E (DS Trans) 25% Q2 E (ds trans) G (us trans) H H F (culv) G (US Trans C Figure 12—Flow area (total). 0 50 A Flow Area (ft2) 100 150 200 250 300 A C G (US Trans F (Culv) F (culv) J Qbf A 50% of the values J H E (DS Trans) E (ds trans) G (us trans) H 100% of the values C A H J 10 A Minimum value 25th percentile C F (culv) H J J H E (DS Trans) 50 E (ds trans) G (us trans) F (Culv) Median (aka 50th percentile) J H E (ds trans) G (us trans) E (DS Trans) C 75th percentile F (culv) F (Culv) Maximum value G (US Trans C A A—408 G (US Trans Box Plot Explanation A C F (culv) J J H G (US Trans F (Culv) E (DS Trans) 100 E (ds trans) G (us trans) H Culvert Scour Assessment Simpson Creek C A C A F (Culv) E (DS Trans) 25% Q2 C F (culv) H 25% Q2 E (ds trans) G (us trans) F (Culv) A A C C J E (DS Trans) H J Qbf E (ds trans) G (us trans) F (culv) Qbf A E (ds trans) G (us trans) F (culv) H A A C C C A A G (US Trans Figure 14—Hydraulic radius. 0 C C C J F (culv) 10 H J 10 A E (ds trans) G (us trans) F (culv) H E (ds trans) G (us trans) E (DS Trans) C Hydraulic Radius (ft) 1 2 3 4 5 J E (ds trans) G (us trans) F (culv) A E (DS Trans) F (Culv) H J F (Culv) G (US Trans J G (US Trans H J A H J H E (DS Trans) F (Culv) J A F (Culv) G (US Trans C G (US Trans H G (US Trans H Figure 13—Wetted perimeter. A A A C C A C C J F (culv) 50 H J 50 A E (ds trans) G (us trans) F (culv) H E (ds trans) G (us trans) E (DS Trans) 0 E (DS Trans) F (Culv) H J F (Culv) G (US Trans 40 G (US Trans H J A H J 20 Perimeter (ft) Wetted Hydraulic radius (ft) C A A C C 60 C C H J F (culv) 100 H J E (ds trans) G (us trans) F (culv) H J 100 E (ds trans) G (us trans) E (DS Trans) 80 E (DS Trans) F (Culv) J A F (Culv) G (US Trans 100 G (US Trans H Simpson Creek J Wetted perimeter (ft) E (DS Trans) Site Evaluations A—409 E (DS Trans) A C F (culv) H J 25% Q2 E (ds trans) G (us trans) Figure 16—Maximum depth. 0 2 A C F (culv) J C E (DS Trans) H J Qbf E (ds trans) G (us trans) F (culv) Qbf A E (ds trans) G (us trans) H C A A C A C A Max Depth (ft) 4 6 8 A F (Culv) G (US Trans 25% Q2 F (Culv) Figure 15—Top width. Maximum depth (ft) C F (culv) C C C F (culv) J F (culv) 10 H J 10 A E (ds trans) G (us trans) H E (ds trans) G (us trans) E (DS Trans) C E (DS Trans) G (US Trans H E (ds trans) G (us trans) A E (DS Trans) F (Culv) H J F (Culv) G (US Trans J G (US Trans H J A H J H E (DS Trans) F (Culv) J A F (Culv) G (US Trans C G (US Trans H A C A A C 0 C C F (culv) J F (culv) 50 H J 50 A E (ds trans) G (us trans) H E (ds trans) G (us trans) E (DS Trans) 20 E (DS Trans) F (Culv) H J F (Culv) G (US Trans 40 G (US Trans H J A H J Top Width (ft) C A A C 60 C C F (culv) H G (US Trans J F (culv) 100 H J E (ds trans) G (us trans) H J 100 E (ds trans) G (us trans) E (DS Trans) 80 E (DS Trans) F (Culv) J A F (Culv) G (US Trans A—410 H Top width (ft) J 100 Culvert Scour Assessment Simpson Creek E (DS Trans) H G (US Trans F (Culv) 25% Q2 Velocity (ft/sec) A—411 A H J 25% Q2 E (ds trans) G (us trans) F (culv) F (Culv) A C C J H J Qbf E (ds trans) G (us trans) F (culv) Qbf E (ds trans) G (us trans) F (culv) H A A C C C C C C C G (US Trans Figure 18—Velocity (channel). 0 Velocity 3 (ft/sec) 6 9 12 H Figure 17—Width-to-depth ratio. E (DS Trans) J J F (Culv) F (Culv) E (ds trans) G (us trans) C G (US Trans G (US Trans F (culv) A A A H H J E (DS Trans) E (DS Trans) J J H J H J 10 E (ds trans) G (us trans) F (culv) 10 E (ds trans) G (us trans) F (culv) F (Culv) F (Culv) H G (US Trans G (US Trans C A A H H A A A C C C C 0 E (DS Trans) E (DS Trans) J J H J H J 50 E (ds trans) G (us trans) F (culv) 50 E (ds trans) G (us trans) F (culv) F (Culv) F (Culv) 20 G (US Trans G (US Trans Width-to-Depth Ratio A A H H 40 E (DS Trans) E (DS Trans) J J 60 A A C C C C A A A A H J J H J 100 E (ds trans) G (us trans) F (culv) 100 E (ds trans) G (us trans) F (culv) F (Culv) F (Culv) 80 G (US Trans G (US Trans 100 E (DS Trans) E (DS Trans) H H Simpson Creek J Width-to-depth ratio C Site Evaluations A—412 Shear stress (lbs/ft2) A C H G (US Trans E (DS Trans) J 25% Q2 A 200 D is c h ar g e (c fs ) 400 C F (culv) J J H G (US Trans F (Culv) E (DS Trans) 800 Qbf 1000 A C F (culv) J J G (US Trans F (Culv) E (DS Trans) 10 E (ds trans) G (us trans) H H C A DS channel (DS pebble count - riffle) DS channel (US pebble count - step/riffle) Culvert (US pebble count - step/riffle) US channel (DS pebble count - step) E (ds trans) G (us trans) H Figure 20—Excess shear stress. A A C Excess shear stress is the channel shear divided by the critical shear for bed entrainment of the D84 particle size. Values of excess shear greater than 1 indicate bed movement for the D84 particle size. Excess shear (Applied/tcrit) 0 Excess Shear (Applied / tcrit) 0 1 2 3 4 5 6 A A 600 E (ds trans) G (us trans) H J Figure 19—Shear stress (channel). C F (culv) F (Culv) Shear Stress (lbs/ft2) 0 10 20 30 40 C H G (US Trans F (Culv) F (culv) J J E (DS Trans) 50 E (ds trans) G (us trans) H A C H G (US Trans F (Culv) F (culv) J J E (DS Trans) 100 E (ds trans) G (us trans) H Culvert Scour Assessment Simpson Creek C A C Site Evaluations Table 3—Sum of squared height difference Reach XSUnit Location type Culvert Sum of squared height difference Within range of channel conditions? US Step 0.04 Yes DS Pool 0.13 Yes US Pool 0.03 DS Step 0.19 US Step 0.03 DS Riffle 0.03 Upstream Downstream Table 4—Vertical sinuosity Segment LocationVertical Sinuosity (ft/ft) A DS channel 1.007 B DS channel 1.001 C DS channel 1.008 D DS channel 1.003 E DS Transition 1.005 F Culvert 1.015 G US Transition 1.015 H US channel 1.005 I US channel 1.024 J US channel 1.009 Table 5—Depth distribution Reach Culvert XS 25% Q2 Location Within range of channel conditions? US 0 No DS 0 No US 5 DS 10 US 5 DS 9 Upstream Downstream Simpson Creek A—413 Culvert Scour Assessment Table 6—Habitat unit composition Percent of surface area Reach Pool Glide Riffle Step Culvert 53% 0% 39% 8% Upstream Channel 47% 0% 30% 23% Downstream Channel 20% 0% 63% 26% 1.4 1.2 1.0 0.8 Segment G (US Transition) Segment F (Culvert) Segment E (DS Transition) Segment D Segment C Segment B Segment A 0.0 Segment I 0.2 Segment J Residual depth (ft) 0.4 Segment H 0.6 (culvert) Segment ASegment BSegment CSegment D Segment F Segment HSegment I Segment J Segment E Segment G (DS transition) (US transition) Figure 21—Residual depths. Table 7—Bed material sorting and skewness Reach XSUnit Sorting Location Type Culvert Within range Skewness of channel conditions? Within range of channel conditions? US Step 1.45 Yes 0.03 No DS Pool 1.53 Yes 0.13 Yes US Pool 1.95 0.12 DS Step 1.71 0.14 US Step 1.46 0.31 DS Riffle 1.21 0.12 Upstream Downstream A—414 Simpson Creek Site Evaluations Table 8—Large woody debris Reach Pieces/Channel Width Culvert 0 Upstream 4.13 Downstream 5.12 Terminology: US = Upstream DS = Downstream RR = Reference reach XS = Cross section View upstream towards outlet. View downstream towards inlet. View upstream from roadway. Upstream reference reach. Simpson Creek A—415 Culvert Scour Assessment Upstream reference reach – upstream pebble count, pool. Upstream reference reach – downstream pebble count, step. Downstream reference reach. Downstream reference reach – downstream pebble count (riffle). Downstream reference reach – View upstream in culvert. upstream pebble count (riffle/step). A—416 Simpson Creek Site Evaluations Cross Section: Upstream Reference Reach – Upstream Pebble Count Material sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock S ize C las s (mm) <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 Bedrock C ount Item % C umulative % 2 3 1 3 1 6 5 7 8 9 14 7 7 13 11 7 3 0 0 0 2% 3% 1% 3% 1% 6% 5% 7% 7% 8% 13% 7% 7% 12% 10% 7% 3% 0% 0% 0% 2% 5% 6% 8% 9% 15% 20% 26% 34% 42% 55% 62% 68% 80% 91% 97% 100% 100% 100% 100% 16 100% 14 90% Frequency 70% 10 60% 8 50% 40% Frequency 6 30% 4 20% Bedrock 2048-4096 512-1024 1024-2048 362-512 256-362 180-256 128-180 64-90 90-128 45-64 32-45 22.6-32 16-22.6 8-11.3 Cumulative Frequency 2-4 4 - 5.7 5.7 - 8 32 -45 45-64 64- 90 8 - 11.3 90 - 128 Bedrock 11.316- 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 Particle Size Category (mm) 1024 2048 - 2048 - 4096 Particle Size Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 5.3 19.92 80 300 457 700 Simpson Creek 11.3-16 <2 5.7-8 0% 4-5.7 0 <2 10% 2-4 2 Cumulative Frequency 80% 12 Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 2% 40% 38% 20% 0% Sorting Coefficient: 1.95 Skewness Coefficient: 0.12 A—417 Culvert Scour Assessment Cross Section: Upstream Reference Reach – Downstream Pebble Count Material sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock S ize C las s (mm) C ount Item % C umulative % 0 1 1 2 1 1 5 3 7 6 10 8 15 9 9 6 6 3 0 0 0% 1% 1% 2% 1% 1% 5% 3% 8% 6% 11% 9% 16% 10% 10% 6% 6% 3% 0% 0% 0% 1% 2% 4% 5% 6% 12% 15% 23% 29% 40% 48% 65% 74% 84% 90% 97% 100% 100% 100% <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 Bedrock 16 100% 14 90% Frequency 70% 10 60% 8 50% 40% Frequency 6 30% 4 20% Cumulative Frequency Bedrock 2048-4096 512-1024 1024-2048 362-512 256-362 180-256 128-180 64-90 90-128 45-64 32-45 22.6-32 16-22.6 8-11.3 11.3-16 <2 5.7-8 0% 4-5.7 0 <2 10% 2-4 2 Cumulative Frequency 80% 12 2-4 4 - 5.7 - 8 32 -45 45-64 64- 90 8 - 11.3 90 - 128 Bedrock 11.316- 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 Particle Size Category (mm) 1024 2048 - 2048 - 4096 Particle Size Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 13 35 130 365.6 682 1200 A—418 Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 0% 29% 45% 26% 0% Sorting Coefficient: 1.71 Skewness Coefficient: 0.14 Simpson Creek Site Evaluations Material sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock S ize C las s (mm) <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 Bedrock C ount Item % C umulative % 1 0 3 0 0 0 0 6 5 6 16 8 11 7 16 12 8 0 0 0 1% 0% 3% 0% 0% 0% 0% 6% 5% 6% 16% 8% 11% 7% 16% 12% 8% 0% 0% 0% 1% 1% 4% 4% 4% 4% 4% 10% 15% 21% 37% 45% 57% 64% 80% 92% 100% 100% 100% 100% 18 100% 16 90% 14 80% 70% Frequency 12 60% 10 50% 8 Frequency 6 40% 30% 4 20% 2 10% Cumulative Frequency Bedrock 2048-4096 512-1024 1024-2048 362-512 256-362 180-256 128-180 64-90 90-128 45-64 32-45 22.6-32 16-22.6 8-11.3 11.3-16 5.7-8 <2 4-5.7 <2 0% 2-4 0 Cumulative Frequency Cross Section: Culvert – Upstream Pebble Count 2-4 4 - 5.7 - 8 32 -45 45-64 64- 90 8 - 11.3 90 - 128 Bedrock 11.3 16- 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 Particle Size Category (mm) 1024 2048 - 2048 - 4096 Partic le Siz e Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 25 50 140 403.2 610 800 Simpson Creek Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 1% 20% 42% 36% 0% Sorting Coefficient: 1.45 Skewness Coefficient: 0.03 A—419 Culvert Scour Assessment Cross Section: Culvert – Downstream Pebble Count Material sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock S ize C las s (mm) <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 Bedrock C ount Item % C umulative % 0 0 0 2 0 1 3 1 12 5 10 11 9 18 8 10 7 0 0 0 0% 0% 0% 2% 0% 1% 3% 1% 12% 5% 10% 11% 9% 19% 8% 10% 7% 0% 0% 0% 0% 0% 0% 2% 2% 3% 6% 7% 20% 25% 35% 46% 56% 74% 82% 93% 100% 100% 100% 100% 20 100% 18 14 60% Frequency 12 10 40% 8 Frequency 20% 6 4 Cumulative Frequency 80% 16 Cumulative Frequency 0% 2 Bedrock 2048-4096 512-1024 1024-2048 362-512 256-362 180-256 128-180 64-90 90-128 45-64 32-45 22.6-32 16-22.6 8-11.3 11.3-16 5.7-8 <2 4-5.7 <2 -20% 2-4 0 2-4 4 - 5.7 - 8 32 -45 45-64 64- 90 8 - 11.3 90 - 128 Bedrock 11.316- 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 Particle Size Category (mm) 1024 2048 - 2048 - 4096 Particle Size Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 21.6 40 140 386.4 554 720 A—420 Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 0% 25% 49% 26% 0% Sorting Coefficient: 1.53 Skewness Coefficient: 0.13 Simpson Creek Cross Section: Downstream Reference R Site Evaluations Material S ize C las s (mm) sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 Bedrock C ount Item % C umulative % 1 1 1 0 1 1 5 3 6 2 12 8 17 17 17 7 2 0 0 0 1% 1% 1% 0% 1% 1% 5% 3% 6% 2% 12% 8% 17% 17% 17% 7% 2% 0% 0% 0% 1% 2% 3% 3% 4% 5% 10% 13% 19% 21% 33% 41% 57% 74% 91% 98% 100% 100% 100% 100% 18 100% 16 90% 14 80% 70% Frequency 12 60% 10 50% 8 Frequency 6 40% 30% 4 20% 2 10% Cumulative Frequency Bedrock 2048-4096 512-1024 1024-2048 362-512 256-362 180-256 128-180 64-90 90-128 45-64 32-45 22.6-32 16-22.6 8-11.3 11.3-16 5.7-8 <2 4-5.7 <2 0% 2-4 0 Cumulative Frequency Cross Section: Downstream Reference Reach – Upstream Pebble Count 2-4 4 - 5.7 - 8 32 -45 45-64 64- 90 8 - 11.3 90 - 128 Bedrock 11.316- 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 Particle Size Category (mm) 1024 2048 - 2048 - 4096 Particle Size Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 20 40 160 340 470 900 Simpson Creek Reach – Downstream Pebble Count Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 1% 20% 53% 26% 0% Sorting Coefficient: 1.46 Skewness Coefficient: 0.31 A—421 Culvert Scour Assessment Cross Section: Downstream Reference Reach – Downstream Pebble Count Material sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock S ize R ange (mm) C ount Item % C umulative % 3 0 0 0 1 1 3 10 6 9 25 8 20 5 6 2 1 0 0 0 3% 0% 0% 0% 1% 1% 3% 10% 6% 9% 25% 8% 20% 5% 6% 2% 1% 0% 0% 0% 3% 3% 3% 3% 4% 5% 8% 18% 24% 33% 58% 66% 86% 91% 97% 99% 100% 100% 100% 100% <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 > 4096 30 100% 90% 25 70% 20 Frequency 60% 15 50% 40% Frequency 10 30% 20% 5 10% Cumulative Frequency Bedrock 2048-4096 1024-2048 362-512 512-1024 256-362 180-256 128-180 64-90 90-128 45-64 32-45 22.6-32 11.3-16 16-22.6 5.7-8 8-11.3 2-4 <2 4-5.7 0% <2 0 Cumulative Frequency 80% 2-4 4 - 5.7 5.7 - 8 > 4096 32 -45 45-64 64- 90 8 - 11.3 90 - 128 11.316 - 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 1024 2048 - 2048 - 4096 Particle Size Category (mm) Particle Size Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 19.75 30 82.5 171.6 281 600 A—422 Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 3% 30% 58% 9% 0% Sorting Coefficient: 1.21 Skewness Coefficient: 0.12 Simpson Creek