Culvert Scour Assessment Pine Creek Site Information Site Location: Willamette NF, Road 21 Year Installed: Circa 1999 Lat/Long: 122°27”21.67”W Watershed Area (mi2): 1.91 43°33’16.38”N Stream Slope (ft/ft) : 0.062 Channel Type: Step-pool Bankfull Width (ft): Survey Date: 1 1 13 March 21 2007 Water surface slope extending up to 20 channel widths up and downstream of crossing. Culvert Information Culvert Type: Pipe arch Culvert Material:Annular CMP Culvert Width: 13 Outlet Type: Mitered Culvert Length: 60 ft Inlet Type: Mitered Pipe Slope (structure slope): 0.05 Culvert Bed Slope: 0.038 (First hydraulic control upstream of inlet to first hydraulic control downstream of outlet.) Culvert width as a percentage of bankfull width: 1.03 Alignment Conditions: Inlet appears to be further south than natural channel alignment. Bank scour on right bank upstream of inlet may be partially related to alignment. Bed Conditions: Large cobble/boulder steps in upstream end of pipe. Pipe Condition: Structure joints open in places on culvert walls. Cannot see pipe bottom. Hydrology Discharge (cfs) for indicated recurrence interval 25% 2-yr 2-year Qbf2 5-year 10-year 50-year 100-year 15 58 65 91 113 165 188 2 Bankfull flow estimated by matching modeled water surface elevations to field-identified bankfull elevations. A—358 Pine Creek Site Evaluations Points represent survey points Figure 1—Plan view map. Pine Creek A—359 Culvert Scour Assessment History The Pine Creek culvert was installed in 1999. Bed material was placed inside the culvert during construction. The gradation used was similar to the upstream channel. Pebble counts following construction revealed similar D84 and D16, and low D50 compared to the upstream channel. Very few fines were present. No bed material sorting, bedform construction, or bank construction was performed. As for horizontal alignment, the culvert was centered in the existing channel. For vertical alignment, the pipe was placed intermediate between the upstream and downstream profiles. Following construction, about 50 percent of the placed bed material scoured out of the structure but sediments redeposited within the pipe, raising the bed to near the constructed-bed elevation. In addition, channel sediment that aggraded upstream of the culvert transported through the structure. No significant maintenance has occurred at the site since construction. The above information was furnished by Kim Johansen, USFS. An assessment of nearby stream gauges suggests that nothing more than a 5-year recurrence interval event has occurred in the region since construction. Pine Creek culvert post construction (Fall 1999, Kim Johansen, U.S. Forest Service). The previous culvert at this site was included in the 1987 Western Federal Lands Highway Division (WFLHD) “Oregon Culvert Fish Passage Survey.” The field survey for the WFLHD study was conducted on December 1, 1987. The previous culvert was a 7.5-foot-diameter corrugated metal pipe with an additional 36-inchdiameter pipe installed for flood relief. Oregon Department of Fish and Wildlife (ODFW) staff rated the previous culvert as a “good” installation for fish passage but WFLHD staff noted high velocities (nearly double that of the natural channel) and a 2- to 3-foot-deep scour hole, and considered the pipe to not be a good installation for fish passage. The following are photos of the previous culvert from the WFLHD study: Culvert inlet. A—360 Pine Creek Site Evaluations Typical stream channel. Site Description The Pine Creek culvert is a large bottomless arch mitered to conform to the roadfill. The site is characterized by a high-gradient step-pool/ cascade channel extending approximately 50 feet upstream of the inlet. The high gradient flattens out as it enters the culvert. A steep riffle/step at the entrance transitions into a relatively flat scour pool along the right footing. Grade drops off again downstream of the outlet, which soon enters the broader flood plain of the Middle Fork Willamette River. Two upstream representative reaches were identified at the site; a lower gradient upper one and a steeper lower one. A long cascade and wood jam separate representative reach one (downstream) from representative reach two (upstream). Below this cascade, representative reach one consists of a series of steps and pools. Large fallen trees are present through this reach, generally along the banks and flood plain. Gradient through this reach is much higher than that found through the culvert or in representative reach two. Upstream of the cascade, reference reach two runs through a series of riffles, pools, and steps. As a flatter reach, this segment of channel is wider with bars of gravels and some cobbles. A similar flood-plain surface exists as that found in the lower representative reach. Large fallen trees also line the banks and have a small influence in the channel. Pine Creek Survey Summary Sixteen cross sections and a longitudinal profile were surveyed along Pine Creek in March 2007 to characterize the culvert and two upstream reference reaches. In the culvert, representative cross sections were taken along a step and through a pool. Two additional cross sections were surveyed upstream to characterize the inlet as well as the contraction of flow. Another two cross sections were surveyed downstream of the culvert to characterize the outlet and the expansion of flow. Representative cross sections in representative reach one were taken through a step and a pool. An additional two sections were taken to characterize the upstream and downstream boundaries of the reach. Representative cross sections in representative reach two were also taken through a step and a pool. An additional two sections were taken to characterize the upstream and downstream boundaries of the reach. Profile Analysis Segment Summary The profile analysis resulted in a total of 10 profile segments. Two segments with similar gradients upstream of the inlet were not combined in order to separate out the inlet transition segment for analysis. The culvert consisted of two profile segments. The downstream segment in the culvert had comparable gradient to two representative profile segments in the upstream channel. There was no suitable comparison segment for the upstream segment in the culvert. The upstream transition segment had comparable gradient to two representative profile segments in the upstream channel. The downstream transition segment had comparable gradient to three upstream representative segments. See figure 2 and table 1. A—361 Culvert Scour Assessment Scour Conditions Observed conditions Footing scour – At least half and possibly as much as all of the originally placed material was scoured out of the pipe after construction. At the time of the survey there was scour to the culvert base at the inlet. The culvert base was exposed for 4 feet. The scour was concentrated on the left bank. The thalweg was along the left edge of the pipe at the inlet (for 10 feet) and along the right edge in the downstream half of the pipe. Culvert-bed adjustment – Most, if not all, of the original bed material installed in the culvert has scoured out (see photo of post-construction conditions in History section). Bed material has aggraded adjacent to the scour pool along the right bank and through the lower two-thirds of the pipe resulting in a relatively flat bed. The slope of the culvert bed has been reduced through scour and aggradation (assuming the original culvert bed was constructed at the same slope as the structure). Profile characteristics – The profile has a concave shape through the crossing, with the maximum concavity focused near the inlet (figure 2). This shape reflects the inlet scour and upstream channel incision combined with aggradation in the downstream portion of the channel and downstream of the outlet. Residual depths – The upstream culvert segment (C) residual depth is greater than any residual depth found in the natural channel (figure 21). This is the location of inlet scour. Residual depth in the downstream portion of the culvert (B) is within the range of residual depths in corresponding profile segments (G and J). Residual depth in the downstream transition segment (A) is within or above the range of depths in corresponding profile segments in the natural channel (G, H, and J). Residual depth A—362 in the upstream transition segment (D) is within the range of depths in corresponding profile segments in the natural channel (E and H). Substrate – The bed material distribution in the riffle in the culvert is similar to the bed material in the step in representative channel reach one (downstream) but coarser than the riffles in representative channel reach two (upstream). The bed material distribution in the glide in the culvert is similar to the glide in representative channel reach one. Culvert bed material sorting values diverge only slightly from the range of values found in the natural channel (table 7). Pebble count data is provided at the end of this summary. Predicted conditions Cross-section characteristics – Hydraulic modeling estimates that the culvert reduces flow area, top width, and wetted perimeter but increases hydraulic radius and depth (figures 5 through 7 and 12 through 19). These impacts are apparent even at the lowest modeled flow (25 percent Q2). Flow geometry in the upstream transition (D) remains mostly within the range of corresponding profile segments (E and H) at all flows. The downstream transition segment (A) exhibits greater depths and lower wetted perimeter than corresponding profile segments (G, H, and J). Shear stress – Shear stress in the culvert and in the upstream transition segment (D) spikes to higher values than in corresponding profile segments (figures 10 and 19). Shear stress in the downstream transition (A) has a wider range than that found in corresponding profile segments (G, H, and J). Excess shear – Modeling suggests that excess shear in the culvert is mostly within the range (or slightly lower) than the excess shear in the natural channel (figure 20). Pine Creek Site Evaluations Velocity – Velocity in the culvert and in the upstream transition segment (D) spikes to higher values than in corresponding profile segments (figures 11 and 18). Velocity in the downstream transition (A) has a wider range than that found in corresponding profile segments (G, H, and J). Scour summary Originally placed material scoured out of the pipe after construction. There is currently scour to the culvert base at the upstream end (inlet) of the culvert. There has been aggradation in the downstream portion of the culvert. The bed has therefore adjusted to a flatter slope than what was originally constructed (assuming the original culvert bed was constructed at the same gradient as the structure). Hydraulic modeling indicates high shear stress and velocity within the culvert, indicating potential risk of continued scour during high flow events. The culvert appears to have most likely been placed lower in the profile than the original stream. This could relate to channel adjustments from the previous culvert or may also be a result of restrictions in height imposed by the current road prism. The change in profile has caused upstream incision. Deposition of coarse material upstream of the culvert may be due to culvert backwater during a high flood event (possible debris plugging). Subsequent lateral boundary adjustment has occurred in response to this deposited material and has resulted in the lateral migration of the channel in the right bank direction. This has altered the culvert alignment, creating a sharp bend at the inlet that contributes to inlet scour. Pine Creek AOP Conditions Cross-section complexity – The sum of squared height differences in the culvert cross sections are both within the range of those in the channel cross sections (table 3). Profile complexity – Vertical sinuosity in the culvert and transition segments are within the range of those in the channel segments (table 4). Depth distribution – The upstream culvert cross section (riffle) has a depth-distribution value within the range of channel conditions but the downstream culvert cross section (glide) has a value less than channel conditions (table 5). Habitat units – The culvert has more glide habitat and less pool and riffle habitat than the natural channel (table 6). Residual depths – The upstream culvert segment (C) residual depth is greater than any residual depth found in the natural channel (figure 21). This is the location of inlet scour. Residual depth in the downstream portion of the culvert (B) is within the range of residual depths in corresponding profile segments (G and J). Residual depth in the downstream transition segment (A) is within or above the range of depths in corresponding profile segments in the natural channel (G, H, and J). Residual depth in the upstream transition segment (D) is within the range of depths in corresponding profile segments in the natural channel (E and H). Substrate – The bed-material distribution in the riffle in the culvert is similar to the bed material in the step in representative channel reach one (downstream) but coarser than the riffles in representative channel reach two (upstream). The bed-material distribution in the glide in the culvert is similar to the glide in representative channel reach one. Culvert bed material sorting values diverge only slightly from the range of values found in the natural channel (table 7). Pebble count data is provided at the end of this summary. A—363 Culvert Scour Assessment Large woody debris – There was no LWD present in the culvert (table 8). The representative channel had moderate LWD abundance. LWD formed steps and scour pools in the channel outside the crossing and played a primary role in habitat unit creation and complexity. Features in the culvert did not mimic the role of wood in the natural channel. AOP summary Site observations and complexity measures indicate that this site is moderately suitable for AOP. There is flow concentration that would allow for passage during low flows and there is some coarse material that would create velocity refuge at higher flows. The high velocity spikes indicated in the hydraulic modeling could potentially limit fish passage at high flows. The thalweg runs along the culvert edge for much of the length, limiting the roughness and associated velocity refuge that is found in the natural channel outside the crossing. There is an exposed bank on the A—364 left bank of the culvert for terrestrial organism passage, but no bank exists along most of the right bank. Design Considerations Inlet scour, upstream incision, and upstream lateral boundary adjustment could likely have been reduced by raising the invert elevation of the culvert bed; however, this may have required raising the elevation of the road prism at considerable expense. Adding stable, embedded boulders into the culvert bed would reduce risk of scour to the culvert base, which is currently occurring. Use of an open-bottom arch at this location would allow for the construction of stable bed elements while not significantly reducing culvert capacity. Creation of continuous banks along both culvert walls would reduce the smooth wall-based flow currently occurring along much of the length and would also benefit terrestrial organism passage. Pine Creek Pine Creek 500 S egment L ength (ft) 43 52 18 50 93 19 70 21 14 16 XS 7 D D A A A G H J E H G J B B U ps trea m T ra n s itio n D XS 8 25.7% 25.4% 15.4% 3.6% 21.2% 12.6% 0.6% % D ifferen c e in G ra d ien t XS 9 (s te p ) P ebble c ount XS 1 0 : D is ta n c e a lo n g b e d (fe e t) 300 (ri ffl e ) P ebble c ount XS 5 : XS 6 C R epres en ta tiv e C h a n n el S eg men t (p o o l /g l i d e ) P ebble c ount XS 4 : B C u lv e rt C u lv ert S eg men t XS 2 XS 3 D o w n s trea m T ra n s itio n Table 1­—Segment comparisons 400 XS 1 A S egment G radient 0.045 0.038 0.022 0.077 0.074 0.223 0.034 0.061 0.014 0.038 Figure 2—Pine Creek longitudinal profile. 90 95 100 Relative elevation (feet) 105 110 115 120 125 130 S egment A B C D E F G H I J E XS 1 1 : 200 (g l i d e ) P ebble c ount fo rm i n g s te p w ood jam XS 1 2 F (ri ffl e ) P ebble c ount XS 1 4 : 100 R e p re s e n ta ti ve C h a n n e l XS 1 3 G XS 1 5 : (ri ffl e ) P ebble c ount H I J XS 1 6 0 Site Evaluations A—365 n o i t a v e l E ) t f ( A—366 B D E G H J 0.1102 – 0.1107 0.1099 – 0.1117 0.1117 – 0.1147 0.1527 – 0.1578 0.1527 0.0987 – 0.1284 0.1273 – 0.1321 1 1 2 4 2 2 3 # of measured XSs 2 3 7 9 7 7 6 # of interpolated XSs 95 100 105 110 115 120 125 0 * 2 6 . . 1 1 2 * 5 . 2 5 7 8 . . 3 3 3 Figure 3—HEC-RAS profile. 1 5 . 4 * 6 6 6 6 4 7 . . 7 7 * 3 3 3 3 2 . 8 * 6 6 6 6 4 7 . . 8 8 9 * 3 3 3 3 3 . 9 0 1 6 . 0 1 * 5 1 . 1 1 200 * 3 4 . . 1 1 1 1 * 5 7 . 1 1 Main Channel Dis tance (ft) * 6 6 6 6 6 . 9 2 1 3 . 2 1 5 . 2 1 * 5 7 . 2 1 3 1 * 3 3 3 3 . 3 1 * 6 6 6 6 . 3 1 4 1 300 * 2 . 4 1 * 4 . 4 1 Stations with decimal values are interpolated cross sections placed along the surveyed profile. 5 2 . 5 * 3 3 3 3 5 2 . . 5 7 7 100 6 . 4 1 * 8 . 4 1 5 1 4 . 5 1 * 7 . 5 1 6 1 400 Ground W S 15 c fs W S Qbf W S Q10 W S Q50 W S Q100 L e ge nd Obtained using equation from Jarrett (1984): n = 0.39S0.38R-0.16, where S=stream slope; R=hydraulic radius. Jarrett’s equation only applied within the following ranges: S = 0.002 to 0.08, R = 0.5 ft to 7 ft. For cross sections outside these ranges, n was computed either from adjacent sections that fell within the ranges, using the guidance of Arcement and Schneider (1987), or from the HEC-RAS recommendations for culvert modeling. A SegmentRange of Manning's n values1 Table 2—Summary of segments used for comparisons Culvert Scour Assessment Pine Creek Pine Creek Elevation (ft) n o i t a v e l E ) t f ( n o i t a v e l E ) t f ( 60 RS = 14 30 70 .1147 Station (ft) 20 80 40 90 .1147 50 60 W S Q1 0 0 L e ge n d 119 20 120 Station (ft) 100 B a n k S ta L e ve e G ro u n d W S 1 5 c fs W S Qb f n o i t a v e l E ) t f ( n o i t a v e l E Elevation (ft) 118 119 120 122 121 123 124 126 125 120 -10 121 122 124 123 10 .1117 30 30 40 60 50 .1117 60 80 70 20 50 Station (ft) 40 .1117 RS = 13 Station (ft) 70 B a n k S ta L e ve e G ro u n d W S 1 5 c fs W S Qb f W S Q1 0 W S Q5 0 W S Q1 0 0 L e ge n d B a n k S ta L e ve e G ro u n d W S 1 5 c fs W S Qb f W S Q1 0 20 L e ge n d W S Q1 0 0 125 10 .1099 W S Q5 0 0 RS = 15 .1099 126 128 127 .1099 Figure 4—Cross-section plots. Only measured cross sections are included. Manning’s n values are included at the top of the cross section. The stationing (RS) corresponds to the stationing on the HEC-RAS profile. Green arrows define the ineffective flow areas. Black arrows represent points identified in the field as the bankfull channel boundary. Only those points identified in the field and supported by hydraulic and topographic analyses are shown below. Elevation (ft) 121 123 122 W S Q1 0 50 10 Bank St a Ground WS 15 c fs WS Qbf WS Q10 WS Q50 WS Q100 L e ge nd W S Q5 0 40 .1147 0 . 1 1 0 7 124 30 -10 .1107 Elevation (ft) 125 127 126 121 -20 122 123 125 124 126 127 129 128 .1107 RS = 16 ) t f ( Site Evaluations A—367 n o i t a v e l E ) t f ( Elevation (ft) n o i t a v e l E ) t f ( A—368 0 10 30 50 60 70 80 20 30 40 50 60 70 80 W S Q1 0 0 L e ge n d 109 110 Station (ft) B a n k S ta L e ve e G ro u n d W S 1 5 c fs W S Qb f n o i t a v e l E ) t f ( Elevation (ft) 106 -20 107 108 110 109 111 112 114 113 109 -20 110 111 113 112 114 115 117 116 -10 -10 0 0 10 .1527 10 .1551 Station (ft) 20 30 30 .1527 RS = 9 Station (ft) 20 .1551 RS = 11 . 1 5 2 7 . 1 5 5 1 40 40 50 50 60 60 L e ge nd Bank St a Ground WS 15 c fs WS Qbf WS Q10 WS Q50 WS Q100 L e ge nd Bank St a Ground WS 15 c fs WS Qbf WS Q10 WS Q50 WS Q100 Figure 4—Cross-section plots. Only measured cross sections are included. Manning’s n values are included at the top of the cross section. The stationing (RS) corresponds to the stationing on the HEC-RAS profile. Green arrows define the ineffective flow areas. Black arrows represent points identified in the field as the bankfull channel boundary. Only those points identified in the field and supported by hydraulic and topographic analyses are shown below. (continued) Elevation (ft) 111 113 112 W S Q1 0 10 .1527 114 .1527 RS = 10 Station (ft) 40 B a n k S ta L e ve e G ro u n d W S Q5 0 0 .1527 20 W S Qb f W S 1 5 c fs n o i t a v e l E Elevation (ft) 115 117 116 112 113 114 116 115 W S Q1 0 W S Q1 0 0 L e ge n d 117 .1557 W S Q5 0 .1557 118 120 119 .1557 RS = 12 ) t f ( Culvert Scour Assessment Pine Creek ) t f ( Pine Creek Elevation (ft) n o i t a v e l E ) t f ( n o i t a v e l E 20 30 RS = 6 50 50 60 60 70 W S Q1 0 0 L e ge n d 70 101 -10 102 103 Station (ft) In e ff B a n k S ta Elevation (ft) -20 -10 30 40 50 50 60 L e ge n d W S Q1 0 0 101 -30 102 103 104 105 106 107 108 109 102 -10 103 104 106 105 0 Station (ft) 10 .1124 20 RS = 5 Note: n values for first profile. Station (ft) 30 40 Bank St a Ground WS 15 c fs WS Qbf WS Q10 WS Q50 WS Q100 L e ge nd B a n k S ta In e ff G ro u n d W S 1 5 c fs W S Qb f W S Q1 0 20 .1527 W S Q5 0 10 .1527 107 0 .1527 108 110 109 RS = 7 Figure 4—Cross-section plots. Only measured cross sections are included. Manning’s n values are included at the top of the cross section. The stationing (RS) corresponds to the stationing on the HEC-RAS profile. Green arrows define the ineffective flow areas. Black arrows represent points identified in the field as the bankfull channel boundary. Only those points identified in the field and supported by hydraulic and topographic analyses are shown below. (continued) Elevation (ft) G ro u n d W S 1 5 c fs W S Qb f n o i t a v e l E ) t f ( Elevation (ft) 105 104 40 .1527 40 106 10 30 Station (ft) .1527 20 B a n k S ta L e ve e G ro u n d n o L e ge n d i W S Q1 0 0 t a W S Q5 0 v W S Q1 0 e W S Qb f l E W S 1 5 c fs W S Q1 0 .1527 10 .1527 W S Q5 0 0 0 .1527 107 109 108 104 -10 105 106 108 107 109 110 112 111 .1527 RS = 8 ) t f ( Site Evaluations A—369 n o i t a v e l E ) t f ( Elevation (ft) n o i t a v e l E ) t f ( A—370 99 -10 100 0 10 .1321 -10 0 20 30 20 Station (ft) .1321 RS = 2 Station (ft) 10 40 . 1 3 2 1 30 50 40 60 50 70 B a n k S ta In e ff L e ve e G ro u n d n o L e ge n d i W S Q1 0 t0 W S Q5 0a v W S Q1 0 e W S Qb f l W S 1 5 c fs E ) t f ( Elevation (ft) .1273 30 40 50 60 70 L e ge n d W S Q1 0 0 97 -10 98 99 101 100 102 103 105 104 99 -10 100 101 103 102 0 10 20 30 40 .1273 Station (ft) .1273 RS = 1 Station (ft) 50 60 70 B a n k S ta L e ve e G ro u n d W S 1 5 c fs W S Qb f W S Q1 0 W S Q5 0 W S Q1 0 0 L e ge n d B a n k S ta In e ff G ro u n d W S 1 5 c fs W S Qb f W S Q1 0 20 .13 W S Q5 0 10 RS = 3 104 0 .13 105 107 106 .13 Figure 4—Cross-section plots. Only measured cross sections are included. Manning’s n values are included at the top of the cross section. The stationing (RS) corresponds to the stationing on the HEC-RAS profile. Green arrows define the ineffective flow areas. Black arrows represent points identified in the field as the bankfull channel boundary. Only those points identified in the field and supported by hydraulic and topographic analyses are shown below. (continued) Elevation (ft) 101 103 102 -20 Bank St a Ground WS 15 c fs WS Qbf WS Q10 WS Q50 WS Q100 L e ge nd n o i t a v e l E Elevation (ft) 104 105 107 106 99 -30 100 101 102 103 104 105 106 107 .0987 RS = 4 Note: n values for first profile. ) t f ( Culvert Scour Assessment Pine Creek Pine Creek . P . W l a t o T 0 10 20 30 40 50 60 70 80 0 A Culvert B 100 C W.P. total (ft) 0 A Culvert B Figure 6—Wetted perimeter. 0 10 20 30 40 50 60 100 C Figure 5—Flow area (total) profile plot. Flow area (sq ft) ) t f ( w o l F a e r A q s ( ) t f D D Main Channel Distance (ft) 200 E Main Channel Distance (ft) 200 E F F 300 G 300 G Flow H I Flow H I J J 400 400 W.P. Total 15 cfs W.P. Total Qbf W.P. Total Q10 W.P. Total Q50 W.P. Total Q100 Legend Flow Area 15 cfs Flow Area Qbf Flow Area Q10 Flow Area Q50 Flow Area Q100 Legend Site Evaluations A—371 A—372 p o T h t d i W 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 0 A Culvert B 0 10 0 A Figure 8—Top width. Top width (ft) 20 30 40 50 60 Culvert B Figure 7—Hydraulic radius. Hydraulic radius (ft) ) t f ( r d y H s u i d a R ) t f ( 100 C 100 C D D Main Channel Distance (ft) 200 E Main Channel Distance (ft) 200 E F F 300 G 300 G Flow H I Flow H I J J 400 400 Top Width 15 cfs Top Width Qbf Top Width Q10 Top Width Q50 Top Width Q100 Legend Hydr Radius 15 cfs Hydr Radius Qbf Hydr Radius Q10 Hydr Radius Q50 Hydr Radius Q100 Legend Culvert Scour Assessment Pine Creek r a e h S n a h C 0 1 2 3 4 5 0 A Culvert B Pine Creek Shear channel (lbs/sq ft) A—373 0 A Culvert B 100 C 100 C Figure 10—Shear stress (channel) profile. 0 5 10 15 20 Figure 9—Maximum depth. Maximum channel depth (ft) q s / b l ( ) t f x a M l h C h t p D ) t f ( D D Main Channel Distance (ft) 200 E Main Channel Distance (ft) 200 E F F 300 G 300 G Flow H I Flow H I J J 400 400 Shear Chan 15 cfs Shear Chan Qbf Shear Chan Q10 Shear Chan Q50 Shear Chan Q100 Legend Max Chl Dpth 15 cfs Max Chl Dpth Qbf Max Chl Dpth Q10 Max Chl Dpth Q50 Max Chl Dpth Q100 Legend Site Evaluations ) s / t f ( A—374 l e V l n h C 0 0 A Culvert B 100 C Figure 11—Velocity (channel) profile plot. Velocity channel (ft/s) 1 2 3 4 5 6 7 8 D Main Channel Distance (ft) 200 E F 300 G Flow H I J 400 Vel Chnl 15 cfs Vel Chnl Qbf Vel Chnl Q10 Vel Chnl Q50 Vel Chnl Q100 Legend Culvert Scour Assessment Pine Creek 40 60 80 B (culv) G G E D (US Trans) 25%Q2 A (ds trans) D (us trans) E H H Figure 12—Flow area (total). 0 A (DS Trans) J G G E D (US Trans) B (Culv) A (DS Trans) Qbf A (ds trans) D (us trans) B (culv) E H J 100% of the values 50% of the values E E D (US Trans) B (Culv) G A (DS Trans) 10 A (ds trans) D (us trans) B (culv) G H J A (DS Trans) H J E D (US Trans) G G B (Culv) 50 A (ds trans) D (us trans) B (culv) E Minimum value 25th percentile H J J H Median (aka 50th percentile) 75th percentile Maximum value Box Plot Explanation E D (US Trans) B (Culv) B (culv) E G G 100 A (ds trans) D (us trans) A (DS Trans) Pine Creek Flow 20Area (ft2) Flow area (ft2) B (Culv) H J Site Evaluations A—375 J H J H J G D (US Trans) B (culv) G 25%Q2 A (ds trans) D (us trans) E Figure 14—Hydraulic radius. 0 0.5 Radius (ft) Hydraulic 1 1.5 2 2.5 3 E Figure 13—Wetted perimeter. G J H J G Qbf B (culv) G Qbf H H H A (ds trans) D (us trans) E A (ds trans) D (us trans) B (culv) E J J J J H J E 25%Q2 J A (DS Trans) A (DS Trans) A (ds trans) D (us trans) H H B (Culv) B (Culv) B (culv) H D (US Trans) D (US Trans) G B (culv) E G 10 E B (culv) 10 A (ds trans) D (us trans) G A (ds trans) D (us trans) A (DS Trans) A (DS Trans) E E B (Culv) B (Culv) E D (US Trans) D (US Trans) G G E E 0 H H H H 20 J J J J 30 G E G 50 A (ds trans) D (us trans) B (culv) 50 A (ds trans) D (us trans) B (culv) E H H H H 40 J J J J 50 A (DS Trans) A (DS Trans) G G B (Culv) B (Culv) A (DS Trans) A (DS Trans) B (culv) E G B (culv) G 100 A (ds trans) D (us trans) E 100 A (ds trans) D (us trans) A (DS Trans) A (DS Trans) B (Culv) B (Culv) D (US Trans) D (US Trans) B (Culv) B (Culv) Wetted 10 Perimeter (ft) Hydraulic radius (ft) D (US Trans) D (US Trans) D (US Trans) E E E E G G G G A—376 H H H H Wetted perimeter (ft) J J J J 60 Culvert Scour Assessment Pine Creek Maximum depth (ft) D (US Trans) A—377 G 25%Q2 A (ds trans) D (us trans) B (culv) E Figure 16—Maximum depth. 0 1 Maximum Depth (ft) 2 3 4 5 G G H J E G G Qbf A (ds trans) D (us trans) B (culv) E Qbf A (ds trans) D (us trans) B (Culv) E E Figure 15—Top width. H H B (Culv) B (culv) D (US Trans) D (US Trans) 25%Q2 J J E E A (ds trans) D (us trans) J A (DS Trans) A (DS Trans) G G B (culv) H H H H H J J E G G 10 A (ds trans) D (us trans) B (culv) E 10 A (ds trans) D (us trans) B (culv) B (Culv) B (Culv) G D (US Trans) D (US Trans) E J J E E 0 A (DS Trans) A (DS Trans) G G 10 H H H H J J E G G 50 A (ds trans) D (us trans) B (culv) E 50 A (ds trans) D (us trans) B (culv) B (Culv) B (Culv) 20 D (US Trans) D (US Trans) Top Width (ft) J J E E 30 H H J J J J 40 A (DS Trans) A (DS Trans) G G E G G 100 A (ds trans) D (us trans) B (culv) E 100 A (ds trans) D (us trans) B (culv) B (Culv) B (Culv) 50 D (US Trans) D (US Trans) 60 H H E E A (DS Trans) A (DS Trans) A (DS Trans) A (DS Trans) G G B (Culv) B (Culv) H H H H Pine Creek J J J J Top width(ft) D (US Trans) Site Evaluations B (Culv) D (US Trans) E G 25%Q2 A (ds trans) D (us trans) B (culv) D (US Trans) H J G B (culv) G Qbf A (ds trans) D (us trans) E Qbf H H J J J J E E Figure 18—Velocity (channel). 0 Velocity 2 (ft/sec) 4 6 8 G Figure 17—Width-to-depth ratio. H H A (ds trans) D (us trans) B (Culv) G 25%Q2 J J B (Culv) B (culv) D (US Trans) D (US Trans) B (culv) A (DS Trans) A (DS Trans) G G B (culv) E G B (culv) G 10 A (ds trans) D (us trans) E 10 A (ds trans) D (us trans) B (Culv) B (Culv) E D (US Trans) D (US Trans) A (ds trans) D (us trans) J H H J J J J E E H H H E E G A (DS Trans) A (DS Trans) G G B (culv) E G B (culv) G 50 A (ds trans) D (us trans) E 50 A (ds trans) D (us trans) B (Culv) B (Culv) E D (US Trans) D (US Trans) 0 H H E E 20 H H J J J J 40 A (DS Trans) A (DS Trans) G G B (culv) E G B (culv) G 100 A (ds trans) D (us trans) E 100 A (ds trans) D (us trans) B (Culv) B (Culv) 60 D (US Trans) D (US Trans) A (DS Trans) A (DS Trans) H H E E Width-to-depth Ratio Velocity (ft/sec) B (Culv) A (DS Trans) A (DS Trans) G G A—378 H H H H Width-to-depth ratio J J J J 80 Culvert Scour Assessment Pine Creek E G G 25%Q2 A (ds trans) D (us trans) B (culv) E H J Excess shear (Applied/tcrit) 0 50 J H 100 Dis charge (cfs ) G D (US Trans) 150 Qbf H 200 H E D (US Trans) B (Culv) G G A (DS Trans) 10 A (ds trans) D (us trans) B (culv) E J Culvert (DS pebble count) - pool/glide Culvert (US pebble count) - riffle US Channel (DS pebble count) - step US Channel (DS Mid pebble count) - glide US Channel (US Mid pebble count) - riffle H H US Channel (US pebble count) - riffle J J D (US Trans) B (Culv) Figure 20—Excess shear stress. G G A (DS Trans) 50 A (ds trans) D (us trans) B (culv) E E J B (Culv) Excess shear stress is the channel shear divided by the critical shear for bed entrainment of the D84 particle size. Values of excess shear greater than 1 indicate bed movement for the D84 particle size. 0 2 Excess Shear (Applied / tcrit) 4 6 8 10 12 14 E B (culv) E G A (ds trans) D (us trans) A (DS Trans) Figure 19—Shear stress (channel). 0 A (DS Trans) Shear Stress (lbs/ft2) 5 10 15 B (Culv) Shear stress (lbs/ft2) D (US Trans) Pine Creek 20 25 H J E D (US Trans) B (Culv) G G A (DS Trans) 100 A (ds trans) D (us trans) B (culv) E H J Site Evaluations A—379 J H J H Culvert Scour Assessment Table 3—Sum of squared height difference Reach XSUnit Location type Culvert Sum of squared height difference Within range of channel conditions? US Riffle 0.03 Yes DS Pool/glide 0.03 Yes US Riffle 0.02 DS Riffle 0.02 Upstream (1-DS) US Glide 0.08 DS Step 0.04 Upstream (2-US) Table 4—Vertical sinuosity Segment LocationVertical Sinuosity (ft/ft) A DS transition 1.008 B Culvert 1.003 C Culvert 1.013 D US transition 1.010 E US channel 1.009 F US channel 1.059 G US channel 1.003 H US channel 1.018 I US channel 1.011 J US channel 1.005 Table 5—Depth distribution Reach Culvert XS 25% Q2 Location Within range of channel conditions? US 6 Yes DS 0 No US 23 DS 18 US 1 DS 2 Upstream (2-US) Upstream (1-DS) A—380 Pine Creek Site Evaluations Table 6—Habitat unit composition Percent of surface area Reach Pool Glide Riffle Step Culvert 22% 41% 38% 0% Upstream Channel (2-US) 36% 0% 63% 1% Upstream Channel (1-DS) 49% 0% 46% 4% 1.2 1.0 0.8 0.6 0.4 Residual depth (ft) 0.2 Segment J Segment i Segment H Segment G Segment F Segment E Segment D: US Trans Segment C: Culvert Segment B: Culvert Segment A: DS Trans 0.0 DS US Culvert Culvert Transition Transition Segment F Segment GSegment HSegment I Segment J Segment A: Segment B:Segment Segment C: D: Segment E Figure 21—Residual depths. Table 7—Bed material sorting and skewness Reach XSUnit Sorting Location Type Culvert Within range Skewness Within range of channel of channel conditions? conditions? US Riffle 1.57 No 0.33 Yes DS Pool/glide 2.02 No 0.18 Yes US Riffle 1.81 0.03 DS Riffle 1.92 -0.08 US Glide 2.01 -0.10 DS Step 1.92 0.49 Upstream (2-US) Upstream (1-DS) Pine Creek A—381 Culvert Scour Assessment Table 8. Large woody debris Reach Pieces/Channel Width Culvert 0 Upstream (2-US) 1.34 Upstream (1-DS) 1.17 Terminology: US = Upstream DS = Downstream RR = Reference reach XS = Cross section A—382 Pine Creek Site Evaluations View upstream through culvert. View downstream towards culvert inlet. View downstream from roadway. View upstream from roadway. Upstream reference reach 2 (upstream). Upstream reference reach 2 (upstream) – downstream pebble count (riffle). Pine Creek A—383 Culvert Scour Assessment Upstream reference reach 2 (upstream) – View of upstream reference reach 1 (downstream). downstream pebble count (pool tail-out). Upstream reference reach 1 (downstream) – Upstream reference reach 1 (downstream) – downstream pebble count (step). upstream pebble count (between steps). View downstream towards inlet. View upstream from within culvert. A—384 Pine Creek Site Evaluations Material Frequency sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock S ize C las s (mm) <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 Bedrock C ount Item % C umulative % 4 4 3 6 8 11 12 8 6 6 10 9 19 5 3 0 0 0 0 0 4% 4% 3% 5% 7% 10% 11% 7% 5% 5% 9% 8% 17% 4% 3% 0% 0% 0% 0% 0% 4% 7% 10% 15% 22% 32% 42% 49% 54% 60% 68% 76% 93% 97% 100% 100% 100% 100% 100% 100% 20 100% 18 90% 16 80% 14 70% 12 60% 10 50% 8 Frequency 40% 6 30% 4 20% 2 10% Cumulative Frequency Bedrock 2048-4096 1024-2048 362-512 512-1024 256-362 180-256 128-180 64-90 90-128 45-64 32-45 22.6-32 11.3-16 16-22.6 5.7-8 8-11.3 2-4 <2 4-5.7 0% <2 0 Cumulative Frequency Cross Section: Upstream Reference Reach 2 – Upstream Pebble Count 2-4 4 - 5.7 - 8 32 -45 45-64 64- 90 8 - 11.3 90 - 128 Bedrock 11.3 16- 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 Particle Size Category (mm) 1024 2048 - 2048 - 4096 Partic le Siz e Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 3.65 10 34 139.6 190 290 Pine Creek Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 4% 56% 38% 3% 0% Sorting Coefficient: 1.81 Skewness Coefficient: 0.03 A—385 Culvert Scour Assessment Cross Section: Upstream Reference Reach 2 – Downstream Pebble Count Material S ize C las s (mm) sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock C ount Item % C umulative % 5 6 1 7 7 11 9 15 9 8 4 6 13 6 0 0 0 0 0 0 5% 6% 1% 7% 7% 10% 8% 14% 8% 7% 4% 6% 12% 6% 0% 0% 0% 0% 0% 0% 5% 10% 11% 18% 24% 35% 43% 57% 65% 73% 77% 82% 94% 100% 100% 100% 100% 100% 100% 100% <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 Bedrock 16 100% 14 90% 70% Frequency 10 60% 50% 8 40% Frequency 6 30% 4 20% 2 Cumulative Frequency 80% 12 Cumulative Frequency 10% Bedrock 2048-4096 1024-2048 362-512 512-1024 256-362 180-256 128-180 64-90 90-128 45-64 32-45 22.6-32 11.3-16 16-22.6 5.7-8 8-11.3 2-4 <2 4-5.7 0% <2 0 2-4 4 - 5.7 - 8 32 -45 45-64 64- 90 8 - 11.3 90 - 128 Bedrock 11.316- 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 Particle Size Category (mm) 1024 2048 - 2048 - 4096 Particle Size Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 3 8 25 130 194 250 A—386 Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 5% 68% 27% 0% 0% Sorting Coefficient: 1.92 Skewness Coefficient:-0.08 Pine Creek Site Evaluations Material sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock S ize C las s (mm) C ount Item % C umulative % 6 6 2 1 5 16 9 11 9 8 8 4 10 7 5 2 0 0 0 0 6% 6% 2% 1% 5% 15% 8% 10% 8% 7% 7% 4% 9% 6% 5% 2% 0% 0% 0% 0% 6% 11% 13% 14% 18% 33% 41% 51% 60% 67% 74% 78% 87% 94% 98% 100% 100% 100% 100% 100% <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 Bedrock 18 100% 16 90% 14 80% 70% Frequency 12 60% 10 50% 8 Frequency 6 40% 30% 4 20% 2 10% Bedrock 2048-4096 1024-2048 362-512 512-1024 256-362 180-256 90-128 128-180 64-90 45-64 32-45 22.6-32 11.3-16 16-22.6 5.7-8 8-11.3 4-5.7 <2 <2 2-4 4 - 5.7 - 8 32 -45 45-64 64- 90 8 - 11.3 90 - 128 Bedrock 11.316- 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 Particle Size Category (mm) 1024 2048 - 2048 - 4096 Particle Size Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 2 11 30 160 286 450 Pine Creek Cumulative Frequency 0% 2-4 0 Cumulative Frequency Cross Section: Upstream Reference Reach 1 – Upstream Pebble Count Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 6% 61% 27% 6% 0% Sorting Coefficient: 2.01 Skewness Coefficient:-0.10 A—387 Culvert Scour Assessment Cross Section: Upstream Reference Reach 1 – Downstream Pebble Count Material sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock S ize C las s (mm) <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 Bedrock C ount Item % C umulative % 3 3 2 0 2 2 3 3 5 8 6 7 11 12 26 11 8 0 0 0 3% 3% 2% 0% 2% 2% 3% 3% 4% 7% 5% 6% 10% 11% 23% 10% 7% 0% 0% 0% 3% 5% 7% 7% 9% 11% 13% 16% 21% 28% 33% 39% 49% 60% 83% 93% 100% 100% 100% 100% 100% 30 90% 25 70% 20 Frequency 60% 50% 15 40% Frequency 10 30% 20% 5 Cumulative Frequency 80% Cumulative Frequency 10% Bedrock 2048-4096 1024-2048 362-512 512-1024 256-362 180-256 128-180 64-90 90-128 45-64 32-45 22.6-32 11.3-16 16-22.6 5.7-8 8-11.3 2-4 <2 4-5.7 0% <2 0 2-4 4 - 5.7 5.7 - 8 32 -45 45-64 64- 90 8 - 11.3 90 - 128 Bedrock 11.316- 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 Particle Size Category (mm) 1024 2048 - 2048 - 4096 Particle Size Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 5 33.8 190 385 529 560 A—388 Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 3% 25% 32% 40% 0% Sorting Coefficient: 1.92 Skewness Coefficient: 0.49 Pine Creek Site Evaluations Cross Section: Culvert – Upstream Pebble Count Material sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock S ize C las s (mm) <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 Bedrock C ount Item % C umulative % 1 0 2 4 2 3 1 6 10 9 10 8 14 15 14 0 3 0 0 0 1% 0% 2% 4% 2% 3% 1% 6% 10% 9% 10% 8% 14% 15% 14% 0% 3% 0% 0% 0% 1% 1% 3% 7% 9% 12% 13% 19% 28% 37% 47% 55% 69% 83% 97% 97% 100% 100% 100% 100% 16 100% 14 90% Frequency 70% 10 60% 8 50% 40% Frequency 6 30% 4 20% 2 Cumulative Frequency 80% 12 Cumulative Frequency 10% Bedrock 2048-4096 1024-2048 362-512 512-1024 256-362 180-256 128-180 64-90 90-128 45-64 32-45 22.6-32 11.3-16 16-22.6 5.7-8 8-11.3 2-4 <2 4-5.7 0% <2 0 2-4 4 - 5.7 - 8 32 -45 45-64 64- 90 8 - 11.3 90 - 128 Bedrock 11.3 16- 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 Particle Size Category (mm) 1024 2048 - 2048 - 4096 Partic le Siz e Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 8 30 110 258 300 540 Pine Creek Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 1% 36% 46% 17% 0% Sorting Coefficient: 1.57 Skewness Coefficient: 0.33 A—389 Culvert Scour Assessment Material Frequency sand very fine gravel fine gravel fine gravel medium gravel medium gravel coarse gravel coarse gravel very coarse gravel very coarse gravel small cobble medium cobble large cobble very large cobble small boulder small boulder medium boulder large boulder very large boulder bedrock S ize R ange (mm) <2 2-4 4 - 5.7 5.7 - 8 8 - 11.3 11.3 - 16 16 - 22.6 22.6 - 32 32 - 45 45 - 64 64 - 90 90 - 128 128 - 180 180 - 256 256 - 362 362 - 512 512 - 1024 1024 - 2048 2048 - 4096 > 4096 C ount Item % C umulative % 6 10 1 5 7 12 7 12 4 18 7 6 5 3 0 1 0 0 0 0 6% 10% 1% 5% 7% 12% 7% 12% 4% 17% 7% 6% 5% 3% 0% 1% 0% 0% 0% 0% 6% 15% 16% 21% 28% 39% 46% 58% 62% 79% 86% 91% 96% 99% 99% 100% 100% 100% 100% 100% 20 100% 18 90% 16 80% 14 70% 12 60% 10 50% 8 Frequency 6 40% 30% 4 20% 2 10% Cumulative Frequency Bedrock 2048-4096 512-1024 1024-2048 362-512 256-362 180-256 128-180 64-90 90-128 45-64 32-45 22.6-32 16-22.6 8-11.3 11.3-16 5.7-8 <2 4-5.7 <2 0% 2-4 0 Cumulative Frequency Cross Section: Culvert – Downstream Pebble Count 2-4 4 - 5.7 5.7 - 8 > 4096 32 -45 45-64 64- 90 8 - 11.3 90 - 128 11.316 - 16 -22.6 22.6- 32 128180 - 180 256 - 256 362 - 362 - 512 512 - 1024 Particle Size Category (mm) 1024 2048 - 2048 - 4096 Particle Size Category (mm) S ize C las s S ize perc ent finer than (mm) D5 D16 D50 D84 D95 D100 1 5 25 81 159 420 A—390 Material P erc ent C ompos ition Sand Gravel Cobble Boulder Bedrock 6% 73% 20% 1% 0% Sorting Coefficient: 2.02 Skewness Coefficient: 0.18 Pine Creek