August 27, 2009 12 Noon, Room 1506 In attendance: See sign-in sheet Meeting Minutes: from May 28, 2009 were distributed. It was noted that the report indicating that the committee favored the marquee sign with one column was incorrect. The committee favored the two-column design. Special Reports A. Marquee-Horner distributed mock up of marquee. It was pointed out (see minutes 5/28) that the two pier design had been preferred by the Facilities committee. B. Room Numbering-Discussion ensued regarding both room and building numbering. It was agreed that IOB should be bldg. 400. CSSC should be building 600/700. New PE complex will be re-numbered to 4000. Numerical sequencing employed in classroom bldgs. remodels as standards (51-99 upper stories) (01-50 on lower stories) will still be employed with odd and even sides of the corridor when possible. Not enough numbers available in either the IOB or the CSSC as there are more than 50 rooms on each floor. A proposal to use Alpha (A-Z) numbering associated with rooms is currently being proposed. Collins/Horner will bring back the number model for these buildings. Project Status Update Doug Horner reviewed status of all open/active projects currently under bid or in construction… IOB-Still on schedule for January ’10 move in. Questions surrounding occupancy ensued. President has indicated desire to occupy a suite, along with Vice President pending outcome of tBP Faculty Office study that Facilities Committee initiated Spring ‘09. Discussion of this relative to Master Plan ensued. Some consensus reached on need to re-evaluate the Master Plan soon. CSSC-Still on schedule for January ’10 move in. Float days have been lost so this project has no room for leeway, and will be tight. Chabot College Facilities and Sustainability Committee Minutes Page 2 500/1900-Progressing forward Horner to supply to Wagoner verification on availability for Spring. 2200-Under construction, still on time for 10/1 finish. PE Complex-Still under Design. 4000-Still awaiting DSA approval. Bleachers-phase 1completed and classes commence 8/29. 1200/1300-Architect selected, negotiations for contract in stalemate. Noyes asked whether the selection should be re-visited. Horner responded that this could potentially create longer delays in project, and said that negotiations should be allowed to be completed before this decision is undertaken. Rumor Control Concerns raised regarding furniture and workstation accommodations in CSSC by Linzmeyer, and Shimada. Shimada also supplied a letter from Kritscher from Counseling expressing needs for ergogenic stations. Fouquet also indicated that accommodations were part of the faculty contract, and had to be supplied if requested for Health reasons. Horner to verify the specifications through Dovetail. Fouquet indicated that the wall on northwest corner of 2200 is temporary. Some had expressed concerns regarding access to bathrooms. The wall will be gone prior to opening of the building making these facilities accessible to campus. (Wall removed on 9/8). Other Matters Initiated Bob Buell asked if the State furloughs were delaying our projects. Horner affirmed this as to the reason behind the lateness of bldg. 4000, the Gym bleachers, and the Athletic Soccer fields. This could be a problem for the campus projects moving forward. Bob Buell expressed concerns about the lack of planning in the Master Plan for a Fire Tower. The Fire Tech program may be losing their tower over in San Leandro, and need an alternate training site. He indicated a need to have this evaluated sooner rather than later. Cindy Hicks expressed concerns over who would have the final say in the planning and selection of the final architect for the bldg. 100 project. Her assessments are that the committee chose Steinberg, and she has concerns as to whether this will be changed. Horner indicated that Steinberg was in the minutes as the architect of choice. Chabot College Facilities and Sustainability Committee Minutes Page 3 Dave Fouquet distributed a list of questions that he felt should be addressed regarding the campus master facility plan as we move forward. Dave’s text is attached: Some Questions Surrounding the FMP Chabot College Facilities Committee, 27 August, 2009 — Fouquet 0. For work beyond Measure B: Go out for a new bond, or do everything by FPP? 1. Faculty Offices: a) In the current economic climate, is there sufficient dollars for a full renovation (as opposed to ‘renovation light’) of Buildings 1100, 1500 and 2000? b) Note. Previous FMP’s called for a new two-story IOB (IOB West?) at or near the site of Buildings 1500 or 2000 (The soon-to-open IOB can accommodate about 2/3 of the current faculty.) c) Note. Planning around the remaining faculty offices will have impact upon the usage of the offices in IOB that are as yet unassigned. Offices in the old buildings are 72 sf, which is smaller than the 100 sf campus standard; renovation to campus standard would significantly reduce the number of offices in those buildings. 2. Building 100 a) Renovate the old, or raze and build new? b) Use of first floor in the next five years: How many walls to be knocked down? 3. Building 200 (Is cap-loading a problem for office space?) a) If it is closed down, what will be its ultimate fate? Where would the mailroom go? b) Were will the permanent offices of the college President and VP’s be located? (Any new bldg. planned is an opportunity to answer this question.) c) Note. President and VP’s in IOB has impact on Faculty Offices discussion. 4. Building 2300, Cafeteria and Student Center: Renovate, or raze and build new? 5. Performing Arts Center (PAC) Improvements Not Covered by Measure B? 6. Replacement of Building 600: Lecture/Performance Hall Chabot College Facilities and Sustainability Committee Minutes Page 4 a) Two needs could be accommodated with one facility doubling as a lecture hall/performance hall with seating for 300-400. b) Where would it go? Suggestions include footprint of current building 200, or any of the old faculty office buildings whose function could move to a new IOB-West. (Thus, this issue also ties to Question 1.) The lecture Hall could also go in any new locally funded project. 7. Look at other facilities untouched by Measure B, starting with older buildings, e.g., 1600, 2100, upstairs of 2200, etc. Gerald Shimada distributed a paper that he authored regarding key board trays, attached: Memorandum Date: To: From: Re: August 27, 2009 Chabot College Facilities Committee Student Services Administrators Computer Workstation Ergonomic Safety Equipment Request – Adjustable/Articulating Keyboard Trays for CSSC According to several governmental and private medicine computer workstation ergonomic safety websites including the Center for Disease Control, Occupational Safety and Health Administration (OSHA), and Medicinenet.com, serious injury can occur to high frequency users of computer workstations if the set-ups are not adjustable to provide ergonomically safe position of the chair, desk, keyboard, mouse and monitor. This proposal requests adjustable or articulating keyboard trays to complete the ergonomically safe equipment set-up for the computer workstations in the new Community and Student Services Center as they were apparently not included in the equipment programming for the project. The following breakdown on the computer workstation equipment is described below: 1. Adjustable desks mostly addresses the needs of shorter and taller people (below 5'2" or so and above 6'1" or so) to have a work surface that is the correct height for them as the chair will not likely make up the difference between the desk height needed to work and their personal height. People who are not below or above these heights will likely see no added benefit to an adjustable desk as the chair can raise or lower to meet the desk surface height. I’m not advocating the remove the adjustable desk height system however, as it may have more significance than we realize in adjusting to the height of the individual. It depends on the chairs and the height of the individual. Chabot College Facilities and Sustainability Committee Minutes Page 5 2. Adjustable/Articulating keyboard trays allow for each workstation user to: - Align their seat height with their desk height with the keyboard tray - Adjust the tilt (negative is away from you, positive is toward you) – flat or negative position for the keyboard is better than a positive tilt that a keyboard placed on top of a flat desk will provide - Adjust the depth (in and out length from the desk). This is important for different vision level needs as well as arm length. - Adjustable keyboard trays are needed for everyone to make their seat, monitor and keyboard adjust to ergonomically safe positions. The chair, keyboard tray and monitor are all part of an "ergonomic system" if you will, each requiring the input of the other piece of equipment. As the cost of even one employee’s worker’s compensation claim would exceed the total cost of equipping this building with computer workstation keyboard trays, it seems a prudent financial decision to procure these safety items with the capital bond funds. Therefore, this request for adjustable keyboard trays is lodged on this Thursday, August 27, 2009 to the Chabot College Facilities Committee. Below are some online references regarding the role of keyboard trays in providing ergonomically safe computer workstation set-ups: MedicineNet.com http://www.medicinenet.com/script/main/art.asp?articlekey=22781 Center for Disease Control: http://www.cdc.gov/ = http://www.cdc.gov/od/ohs/Ergonomics/compergo.htm#KEYBOARD OSHA - http://www.osha.gov/SLTC/etools/computerworkstations/index.html Chabot College Some Questions Surrounding the FMP Chabot College Facilities Committee, 27 August, 2009 — Fouquet 0. For work beyond Measure B: Go out for a new bond, or do everything by FPP? 1. Faculty Offices: a) In the current economic climate, is there sufficient dollars for a full renovation (as opposed to ‘renovation light’) of Buildings 1100, 1500 and 2000? b) Note. Previous FMP’s called for a new two-story IOB (IOB West?) at or near the site of Buildings 1500 or 2000 (The soon-to-open IOB can accommodate about 2/3 of the current faculty.) c) Note. Planning around the remaining faculty offices will have impact upon the usage of the offices in IOB that are as yet unassigned. Offices in the old buildings are 72 sf, which is smaller than the 100 sf campus standard; renovation to campus standard would significantly reduce the number of offices in those buildings. 2. Building 100 a) Renovate the old, or raze and build new? b) Use of first floor in the next five years: How many walls to be knocked down? 3. Building 200 (Is cap-loading a problem for office space?) a) If it is closed down, what will be its ultimate fate? Where would the mailroom go? b) Were will the permanent offices of the college President and VP’s be located? (Any new bldg. planned is an opportunity to answer this question.) c) Note. President and VP’s in IOB has impact on Faculty Offices discussion. 4. Building 2300, Cafeteria and Student Center: Renovate, or raze and build new? 5. Performing Arts Center (PAC) Improvements Not Covered by Measure B? 6. Replacement of Building 600: Lecture/Performance Hall a) Two needs could be accommodated with one facility doubling as a lecture hall/performance hall with seating for 300-400. b) Where would it go? Suggestions include footprint of current building 200, or any of the old faculty office buildings whose function could move to a new IOB-West. (Thus, this issue also ties to Question 1.) The lecture Hall could also go in any new locally funded project. 7. Look at other facilities untouched by Measure B, starting with older buildings, e.g., 1600, 2100, upstairs of 2200, etc. Chabot College