V/T SIC Programme of Work 2014 This amalgamates ongoing activities identified from: V/T SIC Programme of work update March 2013 V/T TAG programme March 2013 research areas Task name Expected duration Expected start Expected Finish Predecessors Resource % complete Priority - High, Delivery medium, low mechanisms Status/comments Started 2011 Mid 2015 V/T PPG 10 H NR Data to be used to update WLRM and make recommendations for NR curves Research completed & implemented Initial work completed No firm plans Position paper for Q4 Research completed & implemented Initial work completed No firm plans Position paper for Q4 V/T PPG 100 N/A NR HALL bush & P12 ongoing roll out ? RRUKA? V/T PPG High NR/RSSB Work done, referred to TSLG - completed in 2010. R Goodall at V/T SIC suggested S&C and Shift2Rail - EPSRC funding? V/T PPG Lead: Patric Mak. Rail squats - a significant infrastructure cost? A dominant rail defect? Squat formation arising from thermal induced effects (LUL experience). Wheel burns and squats are 86% of LUL rail defects. Suggest data capture is the first step. Good experience for a graduate programme Position paper to finish - Mark Burstow to issue Q3 2014. V/T PPG M NR/RSSB PPG Lead: M Burstow? Need well defined specification of this task; 3-6 month NR internal lit. review (Innotrack/Track 21/UoH/Other); Define work requirement and if appropriate contract supply chain. Funding route: Short-term NR internal; longer term RSSB V/T SIC sponsored research. Risk to development; Internal resource for initial research phase SIC steer required V/T PPG + Universities- eg Huddersfield & Imperial? M NR PPG Lead: M Burstow NR to support with technical expertise and data as agreed Funding route: NR working with University of Huddersfield to develop an appropriate funding stream. Risks to development: Available funding for 2013/14 1 page strategy paper for Huddersfield board meeting in September? Rail research 1 Strategic Driver 1: Up stress tolerance, Infrastructure damage/wear models HP/MHH trials Premium rail steels (and supoorting modelling) [train performance, cost efficiency] (V/T PPG Strategy Objectives work stream 3.2) 3 Track friendly vehicles - improving train design [train performance, cost efficiency] (V/T PPG Strategy Objectives work stream 3.1)- HALL bush 2 Benefits of a perfectly steering bogie [train performance, cost efficiency] (V/T PPG Strategy Objectives work stream 3.1) Find out what 11 Rail Squats & Corrugation causes squats? 16,000+ p.a. Start with a literature desk top study like T1042 wet rail. High priority. 2 Vertical Track Damage 3 V/T SIC research area 4 V/T SIC research area 10 V/T SIC research area 5 6 7 8 9 1 How does contact material react to the stress applied? NR to work with University of Huddersfield on a proposal outline of work 3 years? Low priority SIC steer activity as about required gaining knowledge. Back burner? Longer term piece of work, desirable, start when funding stream defined. V/T PPG ? Wheel/Rail Interface: Define the geometry condition of the wheel/rail interface; set out permitted track geometry; define the permitted track conditions for the type of track; identify the allowable wheelset parameters. Supports: train performance, cost P12 wheel profiles Research Research 100 P12: ongoing fleet deployment completed & completed & implemented implemented V/T SIC Short term - resolve Started Sept 2013 Work completed V/T PPG M NR/RSSB Wheel/rail interface in Switches and Crossings; Unguided length in 5 Switches and Crossings Geometry research obtuse crossings 2014 - Has this obtuse crossings; False flange criteria; Design criteria; Gauge area Medium - look at and satisfied what widening; resolve issues was needed? Key V/T PPG suggestion: R520 research idea already submitted relating to S&C part on obtuse discuss with Ken Timmis to address best way forward. damage/wear crossings R520 28 Sept VT SIC reviewed possible areas of future work and problems to delivered but agreed Network Rail was appropriate lead on S&C (inc Obtuse optimise. NR there are Crossings). A Doherty also keen to see more S&C element in JTI working with supplier operational (Shift2Rail) future programme. Engage with NR S&C and R&D base. implications eg group at NR. skates. Virtual test tracks (VTTs) [Train performance, cost efficiency] (V/T PPG Research Research V/T PPG NR Completed - useful tool for other activities. Strategy Objectives work stream 1.1) completed & completed & implemented implemented Economic' wheel profiles- thin flanges Autumn 2013 Mid 2015 PPG 25 H Collaboration with lathe operators to turn wheel profiles. Huddersfield University to undertake wear simulations Wheel profile 'rebuilding'- metal deposition Strategic Driver 2: Sustainable operating limits ?????? Improved targeting of minimum actions for cyclic top - measure, R&D. Mid 2014 End of 2015 V/T PPG 7 Noise 11 Noise [train performance, people] (V/T PPG Strategy Objectives work stream 1.1 and 2.1) Not actively planning to do anything further. Not actively planning to do anything further.. V/T PPG Ongoing Ongoing Ongoing See strategic driver 1 Completed Q2 2014 2014 End 2014 See strategic driver 1 Completed Q2 2014 Ongoing 14? Ongoing Ongoing 4, 15? NR EU Legislation & its impact. Acoustic monitoring for track condition & noise generation; In train noise generated by the interface; research and development needs presented at VT TAG 28 January 2013 - decision? Ongoing - see V/T SIC programme of work #7 Damage/wear models and maintenance 12 Strategic Driver 3: Infrastructure damage/wear models Track-Ex 13 14 Track-Ex Wear index (site validation) Whole Life Rail Model update incorporating MHH & HP (see 1.1) 15 Second Generation Track Formation Model Project 16 VTISM - Whole Life Rail Model [train performance, cost efficiency] (V/T PPG strategic Objectives work streams 1.3 and 2.3) VTISM - track quality [train performance, cost efficiency] (V/T PPG strategic Objectives work stream 1.3) 17 18 18 19 20 21 1, 3, 4, 13, 14, 19, 20? V/T PPG ? V/T PPG 1 PPG H? Ongoing software tool development: requires input from many other research tasks Feltham test site. Possibility of another test site needed? 50 M 25 H 4 Track Stiffness 100? Working Group V/T PPG M? RSSB Track Stiffness Working Group RSSB SIC needs to consider what next steps are and implementation needs. Ongoing and to be incorporated once PPG has validated. Improve VTISM & Track-Ex This is ongoing. Part of Track Stiffness Working Group/URS/Track 21 activities. Feed trak degradation models in to VTISM. Cont-Ex Software to determine wheel/rail foces for any position of wheelset (lateral and yaw) [train performance, cost efficiency] (V/T PPG strategic Objectives work streams 1.1 and 1.2) No development No development V/T PPG NR needed at needed at present. No present. No further work to further work to do. do. Wheel/Rail Interface Condition Monitoring: Utilisation of systems to monitor the condition at the wheel/rail interface; Data collected by these systems is to be analysed and distributed to the appropriate party or the monitoring of performance and program Track Monitoring - thermography [train performance, cost efficiency] (V/T Concluded 2011 Concluded 2011 V/T PPG NR Completed, not sure what else can be done. PPG strategic Objectives work stream 1.3) Strategic Driver 4: Reduce stress state, Sustainable operating limits Conicity mapping tool Q4 2014 V/T PPG 80 M Tool delivered, MB now looking at quick conicity methods and applying to particular problemes with target of possibly including in Track-Ex. Quick conicity methods Q2 2014 Q4 2014 PPG 50 M Tool delivered, MB now looking at quick conicity methods and applying to particular problemes with target of possibly including in Track-Ex. V/T SIC See position Q4 2014 V/T PPG L? . 3 Better management of maintenance renewal PPG Lead: C Sneyd? Workshop planned during M Demboski's research paper from MB visit to define the problem. Explore: 'targeted maintenance' area no further plans. through simulation with available vehicle models; compare MB to update against the standard. Explore 'targeted maintenance' through position paper Q4 comparing available measured data, compare against 2014. standard. Define project requirements and the need for 'neural networks'. Risks to development: identifying internal resource for initial desktop study Adhesion 22 23 24 25 26 27 Maintenance: Maintaining wheel/rail interface within limits to ensure safety railway; maintenance programme to implement processes to ensure railway sustainability; ensure systems exist for seasonal maintenance activities & accomodates seasonal variation Friction modifiers [train performance, cost efficiency, quality of service] (V/T SIC steer SIC steer 26 V/T PPG NR To be done - See M Burstow position paper TS-PR033-00008 PPG Strategy Objectives work stream 3.1) required required number of research opportunities. One being picked up re: lubricators on straight track. Sanding [train performance, safety] See T797 See T797 32 RSSB RSSB Ongoing - see T797 ?????? Track-Ex software tool [train performance, cost efficiency] (V/T PPG Strategic See above See above V/T PPG NR Development and application of RCF/wear predictions objectives work stream 1.1 ad 1.2) ?????? Influencing industry to adopt more effective maintenance track policies [train Depends on Depends on V/T PPG NR Ongoing performance, cost efficient] (V/T PPG Strategic Objective 4) better better management of management of maintenance maintenance see position see position paper. paper. V/T SIC See position Finish Q4 ARG RSSB Top of the rail lubrication - how does it work for: Noise, and energy; 4 Adhesion/Lubrication research paper & work on 2014…really? third body behaviour& attributes; effects of side rail lubrication. V/T area electric Ongoing- big PPG suggestion is to wait to clarify scope. lubrication. research area! Started Q2 2014 SIC decision on SIC decision on 100 V/T SIC Done. Paper completed December 2012; is further dissemination Wheel & rail wear if one side is made harder publishing paper publishing paper required - done? as completed Q2 as completed Q2 Wheel 28 Strategic Driver 4: reduce stress state Vehicle modifications: the hydrodynamic 'Hall' bush 29 Wheel profiles - Sussex P12 See strategic driver 1 above See strategic driver 1 above Strategic Driver 5: Cost re-allocation 30 VTAC model 31 32 See strategic driver 1 above See strategic driver 1 above Delivered Q1 2014 Research into the operating environment experienced by axles to enhance wheelset design and maintenance practices T923 Axle-end equipment: service accelerations and resonance Started 2011 T797 Performance and installation criteria for sanding systems 4 (for next stage of work) V/T PPG Ongoing ? 450/444 done, Mk4, 221 (part), 390, 185 possibly V/T PPG Ongoing ? 390, 395, 380 done, Sussex, Chiltern, SWT159 possibly V/T PPG V/T PPG 2015 100 ? Need to prepare for CP6- better damage models? RSSB RSSB Ongoing. Ongoing. FTC NR WMG RSSB RAIB comment; Legal consent; Highway cometitiveness; Ken Timmis knowledge search. NR PPG Suggestion: Position paper to be developed by 'best' representative of VT SIC Transfer of existing knowledge to inform further research; Overall track stability; Effects of heat on individual components. Effects of heat on individual components. V/T PPG suggestion: a position paper could be develop by Neil Halliday/A Doherty to be used to steer the direction of follow-up ressearch and lit. review V/T PPG Lead: M Burstow. WSP operation and effect on material; existing R&D proposal on wheel damage; South West Trains P12 centre band RCF; thermal effects. Outputs used to drive the way forward and develop the relationship with program #1. Note T963 delivered guidance. Ask Alan Lawton? Killed off? Annual seminar, V/T SIC handbook, RSSB research brochures, IMechE seminars, wheel conferences, WRRC, Wheel Lathe Best Practice Group. Other 33 6 Uneven Loading of Container Wagons 34 8 Track Braking - ARG MTB - check with Neil Halliday/Gladys Udeh. 35 This 9 Better understanding of Wheel Tread Damage should be damage models? 36 37 Consolida te findings from other research projects Obtain an update Obtain an update from ARG. from ARG. Completed in Follow on work 2013 - See T963 2016 - How successful is T963? RSSB 10 Predictable Optimised Braking Dissemination - Annual seminar and the book. Role of the SIC: 1. Support and inform the industry's Rail Technical Strategy including consideration of ling term vehicle/track interface strategies Provide input to TSLG and RTS 2. Established the SIC as an optimising industry stakeholder/client group for the review and development of vehicle to track interaction Dissemination of knowledge/best practice SIC bulletin (V/T PPG Strategy Objective 4) 3. Act as a principal client group for RSSB infrastructure research topic group on Vehicle Track Interaction research Carrying out role of principal client group for track projects Champion a review of the research findings from legacy research projects Colour code key Rail research Damage/wear models and maintenance Adhesion Wheel Other Main strategy topic Activity to support strategy topic