Technical Specification for Interoperability - Application Issues Log for TSIs applicable from 2015 Updated: March 2016 Guidance on completing each column: For type of issue, select from: TSI reference should include both the name of the TSI and its OJEU reference. Refer to the Scope should indicate which parts of the UK railway system are affected by the issue (eg, is the issue one which only affects the GB mainline railway, or does it also affect HS1?) Conflict with other rule Economic achievability Technical error in TSI list of TSIs Typographical error in TSI Conformity with TSI Compatibility with existing system Ambiguity in TSI requirement Lead industry contact will where necessary, further normally be someone at DfT information should be set or RSSB out in a short document available from a hyperlink within this issues log file. The hyperlink should be included in this column. Describe progress made in resolving the issue Is the issue open, closed or is it a potential issue for the future? Once there is a formally agreed solution to the issue, this will normally be included as a hyperlink to an ERA Technical Opinion, a derogation statement or other document on the DfT website Lack of detail in TSI Issue ref. number TAIL2015-001 Date added TSI reference TSI clause Type of issue Key words Scope 02/12/2014 ENE TSI Chapter 6, Commission Interoperability Regulation (EU) No constituents 1301/2014 of 18/11/2014 Conflict with other rule Interoperability constituents GB mainline Explanation Organisations involved / affected It is not possible to certify an interoperability constituent that requires the use of specific Contracting Entity, NoBo, case. The problem applies to at least the following "overhead contact line", "Pantograph", ORR, NR "wheelset" and possibly other elements. Proposed resolution Industry lead contact Supporting document? The resolution will require the ERA to change the rules applicable to RSSB, David Knights interoperability constituent that requires the use of specific case. Adobe Acrobat Document Robin Groth (LOC&PAS TSI and possibly others) Adobe Acrobat Document ERA Technical Opinion Adobe Acrobat Document Progress to date Issue status Agreed solution to issue The problem was identified by at least two NoBos, and has been raised with the ORR. RSSB hosted a meeting to bring all parties together. The ORR, DfT, affected manufacturers, NoBos discussed the issues this raised. ORR confirmed that there is a genuine issue and undertook to raise it with DfT (as Member State) and ERA. Meeting held between ORR and ERA. NoBo Forum raised the issue at RISC. Closed To address the concerns that the interoperability framework did not contain a clear methodology for ICs that need to comply with UK specific cases, a National Procedure was recommended and has been published by the Rail Executive on 24 June 2015. The process removes the need to repeat tests each time the same component is used in subsequent projects. The corrigendum to the ENE TSI (Reg.1301/2014) has been published in the Official Journal. Closed Corrigendum to ENE TSI Appendix D — Specification of the pantograph gauge, point D.1.1.3 —Symbols and abbreviations, table, last row: for: ‘Sj Sum of the (horizontal) safety margins covering some random phenomena (j = 1, 2 or 3) for the pantograph gauge m’ read: ‘Σj Sum of the (horizontal) safety margins covering some random phenomena (j = 1, 2 or 3) for the pantograph gauge m’ Appendix D — Specification of the pantograph gauge, point D.1.2.1.7 —Allowances: for: ‘The sum of the abovementioned allowances is covered by Sj.’, read: ‘The sum of the abovementioned allowances is covered by Σj.’; Appendix D — Specification of the pantograph gauge, point D.1.4 — Calculation of maximum lateral deviation of contact wire: for: ‘dl = bw,c + bw + b′ h,mec’, read: ‘dl = bw,c + bw – b′ h,mec’. As at 21/10/2015 work is ongoing to resolve this issue. Closed The solution was to produce a prioritised list of changes that relate to ETCS Baseline 3 Maintenance Release 2. This issue is addressed through the new consolidated version of the CCS TSI ST36EN02 and the annex (final version awaiting publication). RSSB National TAIL2015-002 22/01/2015 ENE TSI Appendix D Commission Regulation (EU) No 1301/2014 of 18/11/2014 Typographical error in Appendix D TSI TAIL2015-003 28/01/2015 CCS TSI Commission Decision (EU) No 2015/14 of 05/01/2015 Compatibility with existing system Fully TSI complaint railways Typographical error in published version corrected by a published amendment. The UK has Contracting Entity, NoBo, a specific case in this area. ORR, NR The corrigendum to the ENE TSI (Reg.1301/2014) has been published in the Official Journal: http://eur-lex.europa.eu/legalcontent/EN/TXT/PDF/?uri=OJ:L:2015:013:FULL&from=FR RSSB, David Knights There is a lack of clarity on the content of ETCS Baseline 3 Maintenance Release 2 (due RISC, ERA and Member end of 2015). It is understood that RISC in November 2014 agreed to changes that do not States (UK, Netherlands, compromise backwards-compatibility with earlier versions of Baseline 3. UK, Netherlands, Denmark, Germany) Denmark and Germany raised strong concerns at RISC and bilateral meetings have been held between ERA and these Member States (additionally France). UK/NL/DK have worked collaboratively to produce a prioritised list of changes that are required and there is apparent support from Sweden and Belgium as well. Some of these changes could compromise backwards compatibility with earlier versions of Baseline 3. RSSB, Tom Lee ENE TSI error and some more Recent publications.pdf These additional CRs are necessary for economic and effective deployment of Baseline 3 in UK. If not agreed there are cost implications and the need for National Technical Rules (as the CCS TSI will contain ‘critical errors’ in respect of the change request that is not implemented. TAIL2015-004 13/02/2015 INF TSI Several Commission Regulation (EU) No 1299/2014 of 18/11/2014 Ambiguity in TSI requirement GB mainline Numeric values in the TSI have been written in 'European' style with ',' as the decimal Projects, NoBos point and ' ' (space) as the thousands delimiter. This may cause confusion. For example in Table 2 the value '22,5' is 22.5, In Table 4 the value '3,80' is 3.8m, in Clause 4.2.4.1 the value '1 435' is 1435mm etc. Explanation will also be included in the GB Guidance Note GI/GN7608 when this is updated. Projects / NoBos to ensure that they interpret numeric values correctly. On 10/02/16, the CCS TSI received a favourable opinion from the Commission established in accordance with Article 29(1) of Directive 2008/57/EC. RSSB, Bridget Eickhoff Open 1 of 7 Technical Specification for Interoperability - Application Issues Log for TSIs applicable from 2015 Updated: March 2016 Issue ref. number Date added TAIL2015-005 13/02/2015 INF TSI 4.2.10.3 Ballast pick- Technical error in TSI Commission up Regulation (EU) No 1299/2014 of 18/11/2014 Ballast pick-up GB mainline The view of the Aerodynamics Experts in CEN TC256 WG6 is that ballast pickup is only an issue for speeds greater than or equal to 250km/h and not the 200km/h stated in this clause. As this is an open point, and there is no national rule, projects have to determine their own approach. TAIL2015-006 06/05/2015 SRT TSI Commission 4.2.1.2 Fire Regulation (EU) No Resistance of 1302/2014 of Tunnel Structures 18/11/2014 Fire resistance GB mainline It would be helpful to define the extent of the structure of the tunnel where the specified Contracting Entity, NoBo, fire resistance is required to be demonstrated. Essentially, this would be the structure of ORR, NR the tunnel directly exposed to the train fire (eg main bore tunnel lining) and other parts of the tunnel, such as safe areas and cross passages which are more remote from a train fire source, but which also require fire resistance to be provided to the extent that this is compatible with the time required for evacuation. TSI reference TSI clause Type of issue Ambiguity in TSI requirement Key words Scope Explanation Organisations involved / affected Projects, NoBos The ERA Application Guide does make it clear that the emergency doors do not have to comply with 4.2.1.2 a) and b) but it is silent on other parts of the tunnel. The choice of phrasing between 4.2.1.2 a) and b) is inconsistent i.e. in a) the phrase 'integrity of the tunnel lining' and in b) 'the tunnel main structure shall withstand the temperature'. In a) the intention is to ensure integrity of the tunnel lining but the rest of the tunnel structure also has to remain resistant to fire until evacuation of passengers and intervention of the emergency response services can take place. In b) the intention is also to ensure that the temperature of the fire can be resisted without collapse by all tunnel parts which could contribute to the collapse of 'neighbouring structures'. The general intention is the same i.e. that affected tunnel parts remain sufficiently resistant to fire without collapsing before rescue and evacuation is complete. Suggest that this inconsistency be addressed and the scope of the tunnel parts affected be clarified. TAIL2015-007 06/05/2015 SRT TSI Commission 4.2.1.4 Fire Regulation (EU) No detection in 1302/2014 of technical rooms 18/11/2014 Ambiguity in TSI requirement Fire detection GB mainline Proposed resolution Supporting document? Progress to date RSSB, Bridget Eickhoff Amend the existing text in 4.2.1.2 a) and b) as suggested: RSSB, John Lane Proposed resolution will be followed and conclusions reported. Open RSSB, John Lane Proposed resolution will be followed and conclusions reported. Open ‘(a) In the event of fire, the integrity of the main tunnel structurelining shall be maintained for a period of time that is sufficiently long to permit self-rescue, evacuation of passengers and staff and intervention of the emergency response services. That period of time shall be in accordance with the evacuation scenarios considered and reported in the emergency plan. CEN TC256 WG6 have formally written to ERA on this issue. See BSI document RAE/1_15_0052, CEN TC256 N 4414. Issue status For speeds between 200km/h and 250km/h it is proposed, and supported by ERA, that no further action is required but work is required to determine methods to close this open point for higher speeds. Agreed solution to issue Open (b) In the cases of immersed tunnels and tunnels which can cause the collapse of important neighbouring structures, the integrity of the main tunnel main structure of the tunnel shall be maintainedwithstand the temperature of the fire for a period of time that is sufficient to allowing evacuation of the endangered tunnel zones and neighbouring structures. This period of time shall be reported in the emergency plan.’ Provide a definition for ‘main tunnel structure as follows’: ‘The areas of the tunnel which are necessary for operation of trains, for evacuation of people to a safe area, and for access/egress of the emergency response services.’ 4.2.1.4 (a) of the SRT TSI states: Contracting Entity, NoBo, 'Technical rooms shall be equipped with detectors which alert the infrastructure manager ORR, NR in case of fire'. Provide guidance on what might constitute a technical room and permit the use of the Common Safety Method to determine the requirements for fire detection, as indicated below: 'Technical rooms' are defined in the SRT TSI as: 'Technical rooms are enclosed spaces with doors for access/egress inside or outside the tunnel with safety installations which are necessary for at least one of the following functions: self-rescue, evacuation, emergency communication, rescue and fire fighting, signalling and communication equipment, and traction power supply.' ‘Technical rooms are purpose built spaces which are not exposed to the tunnel environment. Where safety installations necessary for self-rescue, evacuation, emergency communication, rescue and fire fighting, signalling and communication equipment, and traction power supply, are provided within spaces which are exposed to the tunnel environment (e.g. cross passages), the need for fire detection may be determined using the Common Safety Method on risk assessment.’ This has raised a question concerning what constitutes a 'technical room'? The Crossrail project proposes to include 'tunnel equipment' within cross passages and have queried whether this constitutes a 'technical room' or not. Industry lead contact Clearly, if the equipment to be placed in the cross passage complies with the definition for 'technical rooms', then fire detection is necessary. However, provision of fire detection may not be appropriate in all cases and a risk-based approach, taking into account the potential likelihood of and impact of fire, would be reasonable. Furthermore, fire detection equipment in tunnel environments is susceptible to false alarm, and this could in itself create a safety risk. 2 of 7 Technical Specification for Interoperability - Application Issues Log for TSIs applicable from 2015 Updated: March 2016 Issue ref. number Date added TAIL2015-008 06/05/2015 SRT TSI Commission 4.2.1.5.2 (c) (d) & Regulation (EU) No (e) Access to the 1302/2014 of safe area 18/11/2014 TSI reference TSI clause Type of issue Ambiguity in TSI requirement Key words Access, safe area Scope GB mainline Explanation 4.2.1.5.2 c), d) and e) of the SRT TSI states: ‘(c) Doors giving access from the escape walkway to the safe area shall have a minimum clear opening of 1,4m wide and 2,0m high. Alternatively it is permitted to use multiple doors next to each other which are less wide as long as the flow capacity of people is demonstrated to be equivalent or higher. Organisations involved / affected Contracting Entity, NoBo, ORR, NR (d) After passing the doors, the clear width shall continue to be at least 1,5m wide and 2,25m high. (e) The way in which the emergency response services access the safe area shall be described in the emergency plan.’ Proposed resolution The intention of the SRT TSI requirements should be clarified by amendment to 4.2.1.5.2 (c) as follows: ‘Doors placed parallel to the track giving access from the escape walkway to the safe area shall have a minimum clear opening of 1,4m wide and 2,0m high. Alternatively it is permitted to use multiple doors next to each other, and doors that are placed in a different orientation to the track, which are less wide, as long as the flow capacity and safety of people is demonstrated to be equivalent or higher using the Common Safety Method on risk assessment.’ Industry lead contact Supporting document? Progress to date Issue status RSSB, John Lane Proposed resolution will be followed and conclusions reported. Open Enhance the guidance in the ERA Application Guide to make it clear RSSB, John Lane that this option is only intended for existing tunnels where the cost of widening the tunnel may be prohibitive. Proposed resolution will be followed and conclusions reported. Open Agreed solution to issue Minimum ‘escape walkway’ widths are required to be 0.8m in accordance with 4.2.1.6. This is clearly satisfactory where the escape doorway is placed parallel to the track, but is not compatible with a minimum escape access doorway width of 1.4m, where the doors are placed at 90º (or a lesser angle) to the line of the track. It therefore seems clear that this requirement was intended for the usual situation where doors to cross passages or lateral/vertical exits are provided parallel to the track. In this orientation, a single line of passengers evacuating along a walkway would need to turn left or right through the door, depending in which direction they are evacuating from the tunnel. The required width for doors that are placed at 90º to the line of the track, should be based upon demonstration that a minimum equivalent safety level is achieved using the Common Safety Methods on risk assessment , as permitted for ‘Alternative technical solutions’ in 4.2.1.5.2(3). The impact of not allowing this, is that increased walkway width would be necessary where doors are placed at 90º (or a lesser angle) to the line of the track, as is the case for the Crossrail project, resulting in a significant cost increase being necessary for a larger than necessary tunnel. TAIL2015-009 06/05/2015 SRT TSI Commission 4.2.1.6 Escape Regulation (EU) No walkways 1302/2014 of 18/11/2014 Ambiguity in TSI requirement Escape, walkway GB mainline Contracting Entity, NoBo, Clause 2.3.11 of the ERA Application Guide (Version 8, dated 15th April 2014) states: ‘In single bore tunnels equipped with at least 2 slab tracks supported by a concrete slab, it ORR, NR may be acceptable to use the adjacent track as a walkway, provided the slab track meets the requirements for walkways in the TSI.’ This is a significant benefit for the Crossrail project, where the existing 550m long Connaught tunnel comes within the scope of the TSI, and it is not possible to install escape walkways adjacent to the existing tunnel walls without widening the tunnel. Suggest ERA Application Guide amended as follows: ‘In existing single bore tunnels equipped with at least 2 slab tracks supported by a concrete slab, it may be acceptable to use the adjacent track as a walkway, provided the slab track meets the requirements for walkways in the TSI.’ However, there is a concern that the advice given in the application guide may be assumed to be acceptable for new tunnels. 3 of 7 Technical Specification for Interoperability - Application Issues Log for TSIs applicable from 2015 Updated: March 2016 Issue ref. number Date added TAIL2015-010 06/05/2015 SRT TSI Commission Regulation (EU) No 1302/2014 of 18/11/2014 TSI reference TSI clause 4.2.2.4 Requirements for electrical cables in tunnels Type of issue Ambiguity in TSI requirement Key words Scope Fire, electrical GB mainline cables, flammability Explanation Organisations involved / affected From experience on the Channel Tunnel Rail Link and Crossrail projects, there are notable Contracting Entity, NoBo, instances where such fire performance requirements are not desirable or feasible for ORR, NR cables in tunnels. Such cables are not necessarily resilient to UV exposure at tunnel portals. The options to address this may be to cover the cable to protect from UV, or to make the transition from fire compliant cable to normal cabling at some point just inside the tunnel. The latter option is preferable option from a maintenance and operational view point. Additionally, there are manufacturing difficulties for high voltage cables (eg 25kV), to achieve all of the requirements. Low Smoke Zero Halogen high voltage cables that are currently available on the market, may not meet the requirements of “low flammability and low fire spread”. Proposed resolution Clause 4.2.2.4 (a) currently states: ‘In case of fire, exposed cables shall have the characteristics of low flammability, low fire spread, low toxicity and low smoke density. These requirements are fulfilled when the cables fulfil as a minimum the requirements of classification B2CA, s1a, a1, as per Commission Decision 2006/751/EC.’ Industry lead contact Supporting document? Progress to date Issue status RSSB, John Lane Proposed resolution will be followed and conclusions reported. Open The following additional text is proposed for revision of 2.3.12 of the ERA Application Guide: 'For a particular tunnel project, such as one where 'alternative technical solutions' are adopted for provision of access to the safe area, the adequacy of the standing surface may be demonstrated through application of the Common Safety Methods on risk assessment.' RSSB, John Lane Proposed resolution will be followed and conclusions reported. Open There needs to be a corresponding change to the wording of the last two entries relating to 4.2.12 ERTMS/ETCS DMI in the UK specific case section 7.2.9.3 changing the reference from Index 51 to Index 6. RSSB, Tom Lee This issue will be commented on during consultation on the CCS TSI revisions. Open Agreed solution to issue Suggest that a new clause 4.2.2.4 (b) be added to state: ‘Alternatively, non-compliant cables are permitted as long as they comply with the first sentence of 4.2.1.3 (c). The equivalent level of safety for passengers and staff shall be demonstrated using the Common Safety Methods on risk assessment. ‘ With regard to “low flammability, low fire spread, low toxicity and low smoke” cables, it would be logical to permit the use of non-compliant cables as long as it can be shown that the cables would not ‘contribute significantly to a fire load’ as permitted for building material in 4.2.1.3 (c). Decision 2006/751/EC, requirements B2ca call up the following standards: pr EN 50399-2-1 Common test methods for cables under fire conditions – Heat release and smoke production measurement on cables during flame spread test - Part 2-1: Procedure for classification in Euroclasses C and D. EN60332-1-2 Tests on electric and optical fibre cables under fire conditions Part 1-2: Test for vertical flame propagation for a single insulated wire or cable. EN 61034-2 Measurement of smoke density of cables burning under defined conditions Part 2: Test procedure and requirements. EN 50267-2-3 replaced by: EN 60754-1:2014 Tests on gases evolved during combustion of materials from cables. Determination of the halogen acid gas content. EN 60754-2:2014 Tests on gases evolved during combustion of materials from cables. Determination of acidity (by pH measurement) and conductivity. These standards together appear to cover the requirements for ‘low flammability, low fire spread, low toxicity and low smoke density’ but are there unresolved issues with application of these standards? TAIL2015-011 06/05/2015 SRT TSI Commission 4.2.1.7 Fire fighting Ambiguity in TSI Regulation (EU) No points requirement 1302/2014 of 18/11/2014 Safe area, standing GB mainline surface 4.2.1.7 (e) (2) states: Contracting Entity, NoBo, ‘The safe area that is paired with the fire fighting point shall offer a sufficient standing ORR, NR surface relatively to the time passengers are expected to wait until they are evacuated to a final place of safety .’ The concept of the “sufficient standing surface” relates to the length of time that the passengers using are expected to remain there for evacuation. The guidance in 2.3.12 of the ERA Application Guide elaborates on this by giving examples but does not confirm how this must be demonstrated. One way of doing this might be to ensure that it is included within the Common Safety Method activities related to the safe areas. Perhaps this could be clarified within the application guide. TAIL2015-012 17/07/2015 CCS TSI Consolidated version of 2012/88/EU, 2012/696/EU and 2015/14/EU 4.2.12 ERTMS/ETCS Technical error in TSI DMI ERTMS, ETCS, Driver GB mainline Machine Interface When 2012/696/EC was implemented there was a change in the way in which the DMI Contracting Entity, NoBo, specification is referenced; it moved from Index 51 to Index 6. This change does not seem ORR, NR to have been fully reflected in both the DMI basic parameter 4.2.12 and consequently the UK specific cases in 7.2.9.3. Extract from CCS TSI for UK specific cases.docx.pdf Basic parameter 4.2.12 should refer to Index 6 in Annex A table A 1 (4.2.12a), if it does not it seems odd that the basic parameter for the ETCS DMI does not refer at all to the ETCS DMI specification (ERA_ERTMS_015560). There needs to be a corresponding change to the wording of the last two entries relating to 4.2.12 ERTMS/ETCS DMI in the UK specific case section 7.2.9.3 changing the reference from Index 51 to Index 6. 4 of 7 Technical Specification for Interoperability - Application Issues Log for TSIs applicable from 2015 Updated: March 2016 Issue ref. number TAIL-2015-013 TAIL-2015-014 Date added TSI reference 27/11/2014 CR INF TSI (2011/275/EU) 13/10/2015 LOC&PAS TSI 1302/2014 (Regulation) TSI clause Type of issue 4.2.7.3 Resistance Ambiguity in TSI of new structures requirement over or adjacent to tracks 4.2.6.2.4 Compatibility with existing system Key words Aerodynamics, Track Crosswind Scope GB mainline GB mainline Explanation Clause 4.2.7.3 should be revised to clarify the intent as the TSI refers to clauses 6.6.2 to 6.6.6 of EN 1991-2:2003. This is unnecessary and misleading as the overall clause which references clauses 6.6.2 to 6.6.6 and importantly allows the National annex to be used instead, is not referenced, that is clause 6.6.1(3). This is as follows: Organisations involved / affected Contracting Entity, NoBo, ORR, NR 28/10/2015 WAG TSI 321/2013 7.3.2.4 (Regulation) TAIL-2015-016 02/02/2016 INF TSI Commission Regulation (EU) No 1299/2014 of 18/11/2014 Typographical error in Dynamic behaviour GB mainline TSI 7.3.1 (Upgrading of Ambiguity in TSI a line) requirement 7.3.2 (Renewal of a line) Traffic code, Infrastructure Upgrade, Renewal, projects on Axle load, Gauge existing lines Industry lead contact Existing text of clause 4.2.7.3 RSSB, Bridget 'Aerodynamic actions from passing trains shall be taken into Eickhoff account as set out in EN 1991-2:2003/AC:2010 paragraphs 6.6.2 to 6.6.6 inclusive ' (3) The actions may be approximated by equivalent loads at the head and rear ends of a train, when checking ultimate and serviceability limit states and fatigue. Characteristic values of the equivalent loads are given in 6.6.2 to 6.6.6. NOTE The National Annex or the individual project may specify alternative values. The values given in 6.6.2 to 6.6.6 are recommended. Revise clause 4.2.7.3 to: 'Aerodynamic actions from passing trains shall be taken into account as set out in EN 1991-2:2003/AC:2010, paragraph 6.6.1'. LOC&PAS TSI sets out a transitional arrangement for rules relating to aerodynamic effects - Contracting Entity, NoBo, cross wind. Relevant sections in the TSI are: 4.2.6.2.4, 7.1.1.7 and 7.5.1.2. ORR, NR 4.2.6.2.4 states: '... (3) For units of maximum design speed equal to or higher than 250 km/h the crosswind effects shall be evaluated according to one of the following methods: (a) determined and complying with the specification of the HS RST TSI 2008 clause 4.2.6.3, or (b) determined by the assessment method of the specification referenced in Appendix J-1, index 37. The resulting characteristic wind curve of the most sensitive vehicle of the unit under assessment shall be recorded in the technical documentation as per clause 4.2.12. The transitional measure set out in 7.1.1.7 of the TSI should be used Hugh O'Neill until the TSI is revised: Section 7.5.1.2. aerodynamic effects - cross wind (clause 4.2.6.2.4) sets out an aspect that has to be considered in the revision process or in other activites of the Agency. 7.5.1.2. states: 'Requirements on 'cross wind' have been set up for units of maximum design speed equal to or higher than 250 km/h with 2 options: - in consistency with the TSI HS RST 2008, or - in consistency with the TSI CR LOC&PAS 2011. This will need to be reviewed when the merging of the 2 sets of characteristics wind curves specified in the TSI HS RST 2008 will be finalised.' TAIL-2015-015 Proposed resolution Progress to date Proposed resolution will be followed and conclusions reported. Issue status Agreed solution to issue Open As at 05/10/2015 Clause 4.2.7.3 remains unchanged as this issue was raised in November 2014 when the new INF TSI had already been developed and was in the process of publication. Clause 4.2.7.3 will be revised when the INF TSI is next under revision. Open '(1) For units of maximum design speed higher than or equal to 250 km/h intended to be operated on the High Speed TEN network, it is permitted to apply requirements defined in clause 4.2.6.3 'Crosswind' of the HS RST TSI 2008, as specified in clause 4.2.6.2.4 of the present TSI. (2) This transitional measure is applicable until revision of the clause 4.2.6.2.4 of the present TSI.' . 7.3.2.4 Running dynamic behaviour (point 4.2.3.5.2) duplicates 7.3.2.3 Safety against Contracting Entity, NoBo, derailment running on twisted track (point 4.2.3.5.1). 7.3.2.4 will be revised when the TSI ORR, NR is next under revision to state: 'For technical compatibility with the existing network it is permissible to use national technical rules amending EN 14363:2005 and the ERA/TD/2012-17/INT requirements and notified for the purpose of running dynamic behaviour. This specific case does not prevent the access of TSI compliant rolling stock to the national network. The modifications to tests and procedures of EN 14363 clause 5 shall additionally include: Base condition for use of simplified measuring method shown in EN 14363:2005 clause 5.2.2.2 should be extended to static axle loads up to 25.4 t (~250 kN)'. Solution is revise 7.3.2.4 when the TSI is next under revision to Neil Halliday state: 'For technical compatibility with the existing network it is permissible to use national technical rules amending EN 14363:2005 and the ERA/TD/2012-17/INT requirements and notified for the purpose of running dynamic behaviour. This specific case does not prevent the access of TSI compliant rolling stock to the national network. The modifications to tests and procedures of EN 14363 clause 5 shall additionally include: Base condition for use of simplified measuring method shown in EN 14363:2005 clause 5.2.2.2 should be extended to static axle loads up to 25.4 t (~250 kN)'. The issue is there is a lack of clarity in the wording of the TSI with the potential for misunderstanding. Projects should be categorised as either 'Upgrade' or 'Renewal' Bridget Eickhoff based on an objective assessment of whether the 'overall performance of the sub-system' is improved in line with sub-clause (1) rather than a rigid application of sub-clause (2). Clause 7.3.1 states: '(1) In accordance with Article 2(m) of Directive 2008/57/EC, 'upgrading' means any major modification work on a subsystem or part of a subsystem which imrpoves the overall performance of the subsystem. (2) The infrastructure subsystem of a line is considered to be upgraded in the context of this TSI when at least the performance parameters axle load or gauge, as defined in point 4.2.1, are changed in order to meet the requirements of another traffic code.'. Supporting document? Infrastructure managers, other project entities EN 14363:2005 is currently being revised - the intention is to publish the new version in 2016. The revised TSI should align with the new EN 14363:2016. ERA Application Issue discussed at ISCC Guide to the INF TSI Open Open Guidance will be added to GI/GN7608 Any project which is not covered by 7.3.3 'Substitution in the framework of maintenance' must be categorised as either 'Upgrade' or 'Renewal'. Sub-clause (2) is intended to provide clarification on the interpretation of the general subclause (1) in the context of this TSI. Unfortunately, because of the GB Specific Cases and permissions within the TSI, a pedantic application of Sub-clause (2) could imply that no project on the existing GB mainline is an 'upgrade'. This is because the classification used for 'axle load' in the core TSI is EN15528 whilst GB has permission (see INF TSI clause 4.2.7.4 (4)) to use the RA system for existing bridges, and the GB specific case for 'gauge' (7.7.17.2) also allows use of National Rules for this purpose in place of the EN15273 used in the core TSI. 5 of 7 Technical Specification for Interoperability - Application Issues Log for TSIs applicable from 2015 Updated: March 2016 Issue ref. number Date added TAIL-2015-017 09/03/2016 CCS TSI: Draft Commission Regulation 08/57ST36 Version EN02 Annex, 12/2/2016 tbc Ambiguity in TSI requirement Pre-indication TAIL-2015-018 09/03/2016 CCS TSI: Draft Commission Regulation 08/57ST36 Version EN02 Annex, 12/2/2016 6.1.2 Principles for testing ETCS and GSM-R Ambiguity in TSI requirement TAIL-2015-019 09/03/2016 CCS TSI: Draft Commission Regulation 08/57ST36 Version EN02 Annex, 12/2/2016 tbc Economic achievability TAIL-2015-020 09/03/2016 CCS TSI: Draft Commission Regulation 08/57ST36 Version EN02 Annex, 12/2/2016 09/03/2016 CCS TSI: Draft Commission Regulation 08/57ST36 Version EN02 Annex, 12/2/2016 TAIL-2015-022 09/03/2016 CCS TSI: Draft Commission Regulation 08/57ST36 Version EN02 Annex, 12/2/2016 Annex A Subset 026 Conflict with other rule TAIL-2015-023 15/03/2016 SRT TSI Commission 4.2.1.5.1 Safe area Regulation (EU) No 1302/2014 of 18/11/2014 TAIL-2015-024 TSI reference TSI clause Type of issue Key words Scope Organisations involved / affected Proposed resolution Industry lead contact Supporting document? Issue status Work is ongoing. ERA has been remitted to produce a technical document to incorporate the CR1249 requirements into the TSI. Presentation by ERA is expected at June 2016 RISC meeting. Open RISC, ERA ERA have committed to provide a technical report to RISC. Tom Lee Availability of ETCS trackside trackside scenarios installations There is a lack of clarity on the requirements and management arrangements for engineering rules and operational scenarios. There is no practical experience of this process and it will be law when the TSI is published. ERA will consult on scenarios. ERA Work proactively with ERA to better understand and influence the process. Tom Lee GB is developing relevant material and will work with sector groups and ERA to try and influence an outcome acceptable to GB. Open Additional change requests ETCS trackside and onboard Additional change requests necessary for economic and effective deployment of ETCS in GB. ERA EECT meeting will prioritise in March. EC has indicted that they will Tom Lee consider compatible changes, and adoption might be optional. Wait until outcome of change control process (ERA EECT meeting). Ideally these changes will be incorporated into an ETCS release version. However, if this is not achieved by the time that these change requests will have a material impact on GB, then an alternative route will be sought, likely to involve a technical opinion and NTRs. Open 6.2.3 Table 6.1 Technical error in TSI RAMS - Elimination of systematic failures RAMs, systematic ETCS onboard The approach to manage systematic failures appears to be dependent on identifying issues once they have appeared. This is inconsistent with principles in EN50126 (which seek to design out systematic failures). ERA Apply principles of EN50126 and EN50128. Tom Lee 7.4.4 National Implementation Plans National Implementation Plan ETCS trackside and onboard National Implementation Plan required 12 months after application of TSI. Unclear how this will be addressed. Expect work in Digital Railway will largely inform this. DfT, Digital Railway Anticipate Digital Railway work, especially that driving the IIP for CP6 will inform this. Tom Lee Level NTC, SH mode, Railway Safety Regulations 1999 ETCS onboard In Level NTC operation in SH mode when the STM interface is used, it inhibits class B train ECRG, EEIG, EUG, ERA (EECT)Change request EEIG 227 protection systems. Operation without a train protection system is in contravention of the Railway Safety Regulations 1999. Ambiguity in TSI requirement Ventilation GB mainline The ERA Guide for the application of the SRT TSI cites circumstances where cross passage Contracting Entity, NoBo, spacing may be increased. They cite tunnels of any geometry where the distance ORR, NR between the access points to the safe areas is greater than 500/1000 m, but this is balanced by additional safety measures providing at least the same safety level as the specified solutions in the TSI, such as a ventilation system, additional access points in a given area, larger walkways, etc. This implies that a tunnel ventilation system is an additional safety measure and that there would be no expectation of a tunnel ventilation system for an otherwise compliant tunnel. However, for twin bore tunnels where the nonincident bore is used as a safe area it is not clear how any non-incident bore can be maintained as tenable without either cross passage pressurisation fans or a tunnel ventilation system to pressurise the non-incident bore. The definition of a safe area eludes to ventilation by means of ... The lay-out of an undergound safe area and its equipment shall take into account the control of smoke ... It would be very useful for the SRT TSI to be more definitive in John Lane terms of expectations for tunnel ventilation for smoke control and how non-incident bores when used as safe areas are expected to be maintained as tenable. We note that tunnel ventilation systems are common on longer European tunnels. Open 15/03/2016 SRT TSI Commission 2.3.3 Regulation (EU) No 1302/2014 of 18/11/2014 Lack of detail in TSI Tunnel environment GB mainline The SRT TSI provides no guidance on limiting thermal conditions within both the incident Contracting Entity, NoBo, and non-incident tunnels such that passenger evacuation may take place. This may occur ORR, NR during a prolonged stop, as per clause 2.2.3. It would be useful for the TSI to also consider the thermal safety of John Lane passengers in long and warm tunnels. Open TAIL-2015-025 15/03/2016 SRT TSI Commission 4.2.3 Regulation (EU) No 1302/2014 of 18/11/2014 Lack of detail in TSI Train environment GB mainline Contracting Entity, NoBo, ORR, NR It would be useful for the TSI to also consider the thermal safety of John Lane passengers in long and warm tunnels. Open TAIL-2015-026 15/03/2016 SRT TSI Commission 4.2.1.5.2 Regulation (EU) No 1302/2014 of 18/11/2014 Lack of detail in TSI Cross passage doors GB mainline The SRT TSI and LOC&PAS TSI provide guidance on maximum carbon dioxide concentration in trains, but does provide requirements or guidance on maximum thermal conditions in trains when they stop in tunnels or outside and what, if any, technical measures are expected on the rolling stock and in the infrastructure to manage passenger thermal safety. The SRT TSI provides no guidance on expected maximum door opening forces for cross passage doors within tunnels. There are a variety of national standards that might be used, but some might not be appropriate for this application. Contracting Entity, NoBo, ORR, NR Further requirements or guidance would be useful. Open Conformity with TSI Tom Lee John Lane Change Request CR1249 Progress to date There is a lack of clarity in the requirements for display of pre-indication in response to Change Request 1249. TAIL-2015-021 Onboard compliant with BL3R2 Explanation Agreed solution to issue To produce a prioritised list of changes that relate to future ETCS release versions. Open Change Request EEIG 447 ERTMS Implementation Plans exist but are out-ofdate. Work is underway by the Digital Railway to revise them. Open Loss of protection in Level NTC SH has been classified as an 'enhancement' which will protract solution (compared to being classified as an 'error'). Open 6 of 7 Technical Specification for Interoperability - Application Issues Log for TSIs applicable from 2015 Updated: March 2016 Issue ref. number Date added TAIL-2015-027 15/03/2016 SRT TSI Commission 4.2.2.1 Regulation (EU) No 1302/2014 of 18/11/2014 TSI reference TSI clause Type of issue Ambiguity in TSI requirement Key words Scope Sectionalisation GB mainline Explanation Organisations involved / affected Clause 4.2.2.1 requires traction power switching at least every 5 km if the signalling Contracting Entity, NoBo, system permits the presence of more than one train in the tunnel on each track ORR, NR simultaneously. It is inferred from this requirement, and other requirements, that the risk of smoke from one train on fire affecting another train on fire is acceptable as long as the non-affected train is at least 5 km away from the incident train and can then be moved out. It can be inferred from the ERA guidance that there are no other requirements for tunnel ventilation. The rationale for the 5 km separation is not given and the cited inference may be incorrect. Proposed resolution It would be beneficial to provide further guidance on the intent of this requirement and how it relates to smoke movement. Industry lead contact RSSB, John Lane Supporting document? Progress to date Issue status Agreed solution to issue Open 7 of 7