Office of Financial Management Washington State Major Project Status Report Agency Number

advertisement
Office of Financial Management
Washington State Major Project Status Report
June 8, 2015
Agency Number: 699
Agency: State Board for Community & Technical Colleges
Project Number: 08-2-701
School/Campus: Tacoma Community College
Project Title: Health Careers Center (re-named: Harned Center for Health Careers)
Bill Reference(s): 497-09-5204
Contact name, ph. number, email: Elizabeth Hyun - (253) 566-5151 – ehyun@tacomacc.edu
Project Description:
The design and construction of a 69,715 square foot LEED Gold Health Careers Center to accommodate the
increased demand for health care education. The new facility will provide modern teaching facilities for
existing programs as well as instructional space for additional high demand program offerings. Existing
programs include: Diagnostic Medical Sonography, Emergency Medical Care, Health Information
Management, Human Services, Nursing, Radiologic Sciences, and Respiratory Therapy. The new building
will include instructional space for a shared simulation lab, computer labs, and much needed classroom
space. The new facility not only meets the needs of prospective students being turned away for the lack of
program space, but also addresses existing facilities that are beyond their design life, cramped, and do not
have the infrastructure to support modern teaching technologies and methods. This facility was designed to
be a 50 year LEED Gold building to meet all current safety, seismic, ADA, fire, and all other building codes.
Square footage: 69,715
Scope changes: There have been minor design changes to better meet the needs of the programs planned
within the building. These were paid for from the construction contingency. No square footage was added
to the building as a result of these minor scope changes.
Project Total Cost:
Phase
Predesign
Design prior to bid (SD, DD, CD)
Design bid assistance and CA
Construction (incl. tax and contingency)
Other (FF&E, Art, Permits, etc)
Total
Biennium
2007-09
2009-11
2011-13
2011-13 & 13-15
2011-13 & 13-15
Appropriation
I49
J15
K20
K20
K20
Amount
255,000
1,751,148
1,975,003
27,873,312
3,914,344
35,768,807
Maximum Allowable Construction Cost (MACC) = $28,183,025
Schedule:
Predesign Complete
Start Design
Budget Schedule
June 2008
Aug 2009
1
Actual/Forecast
June 2008
October 2009
Var. (wks)
0
10
Bid Date – Early Site Pkg.
NTP – Early Site Package
Bid Date – Building
Notice to Proceed - Bldg
50% Complete
Substantial Completion
Final Acceptance
June 2011
August 2011
June 2011
August 2011
June 2013
Sept 2013
May 2012
July 2012
August 28, 2012
Nov. 12, 2012
August 2013
August 2014
July 2015
47
47
60
64
64
172
Project Status and discussion of Critical Path for Construction: Schematic Design was completed in
February 2010. The Design Development phase was completed in December 2011. The Construction
Documents for the building were completed in August, 2012. Throughout this time the architects met with
the college design team on a regular basis to discuss progress and work on design issues.
Two bid packages were requested and completed. The first bid package went to bid in May of 2012. It was
delayed from the original project schedule due to state funding issues at that time. The first bid package
focused on the underground utilities including: water, sewer, storm water management, geothermal well
fields, data communications, and fire hydrants so that this portion of the work could be completed prior to
actual construction of the building itself and during the dry summer months. The second portion of the
project, the actual building itself and site work, went out to bid in July, 2012. The bid opening was on
August 28, 2012, and notice to proceed was on November 12, 2012. There was a delay due to the City of
Tacoma’s Plan review and permitting process. Construction completed in August of 2014 in time for fall
quarter classes. Final acceptance is pending sign off on commissioning of all systems. LEED certification is
still in process.
A condition of the building permit from the City of Tacoma included a requirement to make landscape
improvements along Mildred Street, a sidewalk extension, and street entrance/traffic improvements along
South 19th Street. There is also some parking mitigation that is part of the overall project scope. Notice to
Proceed on the required landscape improvements along Mildred Street was given on November 13, 3013.
This work reached substantial completion in April 2014. The parking mitigation went out to bid in February
2014 with a bid opening on March 13, 2014. This project began construction in June 2014 and completed
construction in September 2014. The City of Tacoma’s required street entrance/traffic improvements, which
includes a new traffic signal, is still in design negotiations with the cities of Tacoma and Fircrest.
Contract Award History
A/E Agreement with NBBJ Architects
Original Agreement - Basic Svr. $ 1,732,172.23
Increased Basic Services
$
55,517.22
Total Basic Services
$ 1,787,689.40
State shift of design services
$ - (536,974.40)
Construction Contract (excluding sales tax)
Early Site Pkg. Bid Award:
$ 2,025,670
Early Site Pkg. Change Orders: $
82,445
Bldg. Bid Award Amount:
$19,465,734
Bldg. Change Orders to date:
$ 1,881,386
Total Basic Services up to bid
$ 1,250,715.00
Basic Services for bid and CA $ 487,060.00
Amendments for Extra Services $ 1,599,221.00
Total Design Services
$ 3,336,996.00
Mildred Landscape Bid Award: $
92,000
Mildred Landscape Change Orders:
9,235
Parking Mitigation Bid Award: $ 673,021
Parking Mitigation Change Orders:
26,000
City Required Sidewalk Extension: 12,000
2
19th Street Traffic Improvements: TBD
A/E Agreements with other Consultants
Value Engineering – OAC Services
Ground well test bore – Hargis Engineers
Soils Investigation – Otto Rosenau
Site Survey – Reid Middletion
Commissioning up to bid – Keithly Barber
Additional Survey – City Required
Constructability Review – OAC Services
Testing – Early Site Package
Testing – Building Construction
Total of other design services to date
$ 43,450
$ 11,500
$ 18,877
$ 46,211
$ 79,082
$ 3,140
$ 38,600
$ 7,720
$ 50,765
$ 299,346
Total for design services to date = $3,891,342 (including pre-design services for $255,000)
Current Design Budget
Design Contingency
$ 3,725,319
$ 255,832
Current est. Construction $ 28,836,508 (incl. tax)
Construction Contingency $ 2,269,733
Potential for Project Cost Overruns/Claims: None anticipated at this time
Discussion of Project Quality:
A thorough Pre-Design was conducted in 2008 which defined the project criteria. That document and funding
request was based on the design of a quality building. Included in the Pre-Design document was a LEED check
list. This was used during the design process to ensure a building that exceeds LEED Silver standards in
sustainability, energy efficiency, and quality of construction. The design architects actually designed the
building to qualify for a LEED Gold rating. The mandate to the design team was clearly articulated during the
Pre-Design process and the building will be designed to a 50 year design life meeting all current city, state, and
federal building codes for fire, electrical, structural, seismic, ADA compliance, mechanical, energy efficiency,
storm water management, environmental protection, life safety, and others.
Project Photographs:
Near the end of the Construction Document phase NBBJ Architects created the following rendering.
3
Site location on the Tacoma Community College campus
Below is a view of the Lower Level Floor Plan
In the ‘Lower Level’ three major programs are located including: Diagnostic Medical Sonography,
Emergency Medical Care, and Radiologic Sciences
4
Below is a view of the First Floor Plan
Below is a view of the Second Floor Plan
5
Below is a view of the Third Floor Plan
The early site work included drilling 150 wells to provide for geo-thermal piping. Below are a couple of
photos showing that work in progress in early August, 2012.
6
City required storm water vault completed in October, 2012
On December 24, 2012 the foundations for the building were poured.
Forms for Lower Level walls on January 16, 2013
7
Steel erection in progress - April 27, 2013
Progress of building - June 15, 2013
8
April, 2014
May, 2014 - Site work at East side of building
May, 2014 – Interior Atrium space
9
August, 2014 – Building Main Entrance
September, 2014 – Harned at Night
10
September, 2014 – Harned at Sunrise
Report Prepared by: Elizabeth Hyun, Capital Projects Manager
Tacoma Community College
June 8, 2015
11