Office of Financial Management Washington State Major Project Status Report June 8, 2015 Agency Number: 699 Agency: State Board for Community & Technical Colleges Project Number: 08-2-701 School/Campus: Tacoma Community College Project Title: Health Careers Center (re-named: Harned Center for Health Careers) Bill Reference(s): 497-09-5204 Contact name, ph. number, email: Elizabeth Hyun - (253) 566-5151 – ehyun@tacomacc.edu Project Description: The design and construction of a 69,715 square foot LEED Gold Health Careers Center to accommodate the increased demand for health care education. The new facility will provide modern teaching facilities for existing programs as well as instructional space for additional high demand program offerings. Existing programs include: Diagnostic Medical Sonography, Emergency Medical Care, Health Information Management, Human Services, Nursing, Radiologic Sciences, and Respiratory Therapy. The new building will include instructional space for a shared simulation lab, computer labs, and much needed classroom space. The new facility not only meets the needs of prospective students being turned away for the lack of program space, but also addresses existing facilities that are beyond their design life, cramped, and do not have the infrastructure to support modern teaching technologies and methods. This facility was designed to be a 50 year LEED Gold building to meet all current safety, seismic, ADA, fire, and all other building codes. Square footage: 69,715 Scope changes: There have been minor design changes to better meet the needs of the programs planned within the building. These were paid for from the construction contingency. No square footage was added to the building as a result of these minor scope changes. Project Total Cost: Phase Predesign Design prior to bid (SD, DD, CD) Design bid assistance and CA Construction (incl. tax and contingency) Other (FF&E, Art, Permits, etc) Total Biennium 2007-09 2009-11 2011-13 2011-13 & 13-15 2011-13 & 13-15 Appropriation I49 J15 K20 K20 K20 Amount 255,000 1,751,148 1,975,003 27,873,312 3,914,344 35,768,807 Maximum Allowable Construction Cost (MACC) = $28,183,025 Schedule: Predesign Complete Start Design Budget Schedule June 2008 Aug 2009 1 Actual/Forecast June 2008 October 2009 Var. (wks) 0 10 Bid Date – Early Site Pkg. NTP – Early Site Package Bid Date – Building Notice to Proceed - Bldg 50% Complete Substantial Completion Final Acceptance June 2011 August 2011 June 2011 August 2011 June 2013 Sept 2013 May 2012 July 2012 August 28, 2012 Nov. 12, 2012 August 2013 August 2014 July 2015 47 47 60 64 64 172 Project Status and discussion of Critical Path for Construction: Schematic Design was completed in February 2010. The Design Development phase was completed in December 2011. The Construction Documents for the building were completed in August, 2012. Throughout this time the architects met with the college design team on a regular basis to discuss progress and work on design issues. Two bid packages were requested and completed. The first bid package went to bid in May of 2012. It was delayed from the original project schedule due to state funding issues at that time. The first bid package focused on the underground utilities including: water, sewer, storm water management, geothermal well fields, data communications, and fire hydrants so that this portion of the work could be completed prior to actual construction of the building itself and during the dry summer months. The second portion of the project, the actual building itself and site work, went out to bid in July, 2012. The bid opening was on August 28, 2012, and notice to proceed was on November 12, 2012. There was a delay due to the City of Tacoma’s Plan review and permitting process. Construction completed in August of 2014 in time for fall quarter classes. Final acceptance is pending sign off on commissioning of all systems. LEED certification is still in process. A condition of the building permit from the City of Tacoma included a requirement to make landscape improvements along Mildred Street, a sidewalk extension, and street entrance/traffic improvements along South 19th Street. There is also some parking mitigation that is part of the overall project scope. Notice to Proceed on the required landscape improvements along Mildred Street was given on November 13, 3013. This work reached substantial completion in April 2014. The parking mitigation went out to bid in February 2014 with a bid opening on March 13, 2014. This project began construction in June 2014 and completed construction in September 2014. The City of Tacoma’s required street entrance/traffic improvements, which includes a new traffic signal, is still in design negotiations with the cities of Tacoma and Fircrest. Contract Award History A/E Agreement with NBBJ Architects Original Agreement - Basic Svr. $ 1,732,172.23 Increased Basic Services $ 55,517.22 Total Basic Services $ 1,787,689.40 State shift of design services $ - (536,974.40) Construction Contract (excluding sales tax) Early Site Pkg. Bid Award: $ 2,025,670 Early Site Pkg. Change Orders: $ 82,445 Bldg. Bid Award Amount: $19,465,734 Bldg. Change Orders to date: $ 1,881,386 Total Basic Services up to bid $ 1,250,715.00 Basic Services for bid and CA $ 487,060.00 Amendments for Extra Services $ 1,599,221.00 Total Design Services $ 3,336,996.00 Mildred Landscape Bid Award: $ 92,000 Mildred Landscape Change Orders: 9,235 Parking Mitigation Bid Award: $ 673,021 Parking Mitigation Change Orders: 26,000 City Required Sidewalk Extension: 12,000 2 19th Street Traffic Improvements: TBD A/E Agreements with other Consultants Value Engineering – OAC Services Ground well test bore – Hargis Engineers Soils Investigation – Otto Rosenau Site Survey – Reid Middletion Commissioning up to bid – Keithly Barber Additional Survey – City Required Constructability Review – OAC Services Testing – Early Site Package Testing – Building Construction Total of other design services to date $ 43,450 $ 11,500 $ 18,877 $ 46,211 $ 79,082 $ 3,140 $ 38,600 $ 7,720 $ 50,765 $ 299,346 Total for design services to date = $3,891,342 (including pre-design services for $255,000) Current Design Budget Design Contingency $ 3,725,319 $ 255,832 Current est. Construction $ 28,836,508 (incl. tax) Construction Contingency $ 2,269,733 Potential for Project Cost Overruns/Claims: None anticipated at this time Discussion of Project Quality: A thorough Pre-Design was conducted in 2008 which defined the project criteria. That document and funding request was based on the design of a quality building. Included in the Pre-Design document was a LEED check list. This was used during the design process to ensure a building that exceeds LEED Silver standards in sustainability, energy efficiency, and quality of construction. The design architects actually designed the building to qualify for a LEED Gold rating. The mandate to the design team was clearly articulated during the Pre-Design process and the building will be designed to a 50 year design life meeting all current city, state, and federal building codes for fire, electrical, structural, seismic, ADA compliance, mechanical, energy efficiency, storm water management, environmental protection, life safety, and others. Project Photographs: Near the end of the Construction Document phase NBBJ Architects created the following rendering. 3 Site location on the Tacoma Community College campus Below is a view of the Lower Level Floor Plan In the ‘Lower Level’ three major programs are located including: Diagnostic Medical Sonography, Emergency Medical Care, and Radiologic Sciences 4 Below is a view of the First Floor Plan Below is a view of the Second Floor Plan 5 Below is a view of the Third Floor Plan The early site work included drilling 150 wells to provide for geo-thermal piping. Below are a couple of photos showing that work in progress in early August, 2012. 6 City required storm water vault completed in October, 2012 On December 24, 2012 the foundations for the building were poured. Forms for Lower Level walls on January 16, 2013 7 Steel erection in progress - April 27, 2013 Progress of building - June 15, 2013 8 April, 2014 May, 2014 - Site work at East side of building May, 2014 – Interior Atrium space 9 August, 2014 – Building Main Entrance September, 2014 – Harned at Night 10 September, 2014 – Harned at Sunrise Report Prepared by: Elizabeth Hyun, Capital Projects Manager Tacoma Community College June 8, 2015 11