Office of Financial Management Washington State Major Project Status Report

advertisement
Office of Financial Management
Washington State Major Project
Status Report
Agency Number:
699
Agency: Highline Community College
Project Number: COP
Project Title: Student Union Building Remodel
Bill Reference: Section 907 (7) (c), Chapter 26, Laws of 2003, Capital Budget 2003-05
Project Description:
Demolish existing structure and construct a new 33,980 assignable square foot building
consisting of a food services area, conference and study rooms with data support, a bookstore, and
student government and services offices. The Student Union will act as a central hub for the campus
community.
Project Total Cost:
Phase
Pre-design
Design/Construction
Biennium
Appropriation
99-01
*
01-03 & 03-05
*#
Total
Amount
$
80,000
$ 16,173,563
$ 16,341,563
* Local funds and a COP will be used
# Contracts plus other costs
Schedule:
Budget
Schedule
Predesign Complete
Start Design
Bid Date
Notice to Proceed
50% Complete
Substantial Completion
Final Acceptance
HCC Student Union Building Remodel
7/01/01
7/01/02
6/01/02
5/01/03
1/30/04
2/28/04
1
Actual/Forecast
6/01/01
11/27/01
4/17/03
8/01/03
4/01/04
1/01/05
12/1/05
A
A
A
A
A
A
A
Variance
(weeks)
0
22
41
46
48
48
198
Major Project Report 6/30/05
Project Status and Discussion of Critical Path for Construction:
Northwest Architectural Company and Opsis were the firms for the design through bidding
phase and S. M. Stemper was selected for the construction through close out phases of this project.
The project is now complete at this time.
Contract Award History
A/E Agreement
NAC/Opsis
S.M. Stemper
Design
Contingency
Total
Construction Contract (excl. sales tax)
Contract
$ 9,890,000
Change Orders
1,510,839
Construction
Contingency
$
0
Total
$ 11,400,839
$ 1,180,522
379,302
$
0
$ 1,559,824
Potential for Project Cost Overruns/Claims
Little potential remains as project is complete.
Discussion of Project Quality
Design, materials and workmanship are very good. Overall project quality is excellent.
HCC Student Union Building Remodel
2
Major Project Report 6/30/05
Project Photograph
HCC Student Union Building Remodel
3
Major Project Report 6/30/05
HCC Student Union Building Remodel
4