Using advanced distribution protection functions can significantly reduce faultclearing times. The electric power industry is going through significant changes due to the increased requirements for improved quality of power supplied by the utility in order to avoid costly interruptions of manufacturing or other processes caused by voltage sags, swells or unbalanced conditions when a short circuit fault occurs in the distribution system. The improvement of power quality during short circuit faults can be achieved in several different ways. Like any other problem that has to be solved, we need first to understand the nature of the problem and its effect on sensitive users. The most common short circuit faults in the system – single-phase to ground faults – are characterized by the fact that they introduce a voltage sag in the faulted phase, and at the same time they result in a voltage swell in the two healthy phases. This is clearly seen in Figure 1 that shows the recorded waveform for a single-phase to ground fault. The effects of voltage sags and swells on sensitive equipment have been studied for many years by industry organizations such as Computer and Business Equipment Manufacturers' Association (CBEMA). They record both characteristics of this power quality event – the depth of the sag and its duration. Figure 2 shows a plot of depth vs. duration known as the ITIC (Information Technology Industry Council) or CBEMA graph. The first characteristic of voltage sags – the depth – is a function of the type of fault, fault location and the system configuration. This is something that we can not control. The second characteristic of voltage sags – the duration – is the parameter that we can control by applying the advanced features of multifunctional protection relays. Monitoring the changes of the power system configuration and adapting the relay to these changing conditions can further improve the performance of the relays and reduce the effect of short circuit faults on sensitive equipment or processes. The effects of short circuit faults on the voltage profile across the distribution system may result in the shutting down of sensitive industrial processes. The performance of typical distribution feeder or substation protection systems historically has not been considered as critical as the behavior of transmission line protection devices. This is changing now, resulting in a new look at the requirements and functionality of distribution protection relays. The effect of changes of the system configuration on the performance of the protective relays is another factor that needs to be considered. Using all available protection and programmable logic functions in multifunctional protective IEDs can help us significantly reduce the effect of short circuit faults on sensitive loads supplied from the distribution substation. Adaptive protection based on detected changes in the system configuration, combination of instantaneous, definite time and inverse time-delayed phase, ground and negative sequence elements, will shorten the fault duration, resulting in changes in the voltage level/time characteristics of the fault condition and reduced probability for the costly interruption of voltage sensitive processes. Optimizing distribution protection Typical distribution feeder protection is based on phase and ground overcurrent relays set to protect the line for three-phase, phase-to-phase or phase-to-ground faults. An instantaneous relay is used to operate for close-in faults and a time overcurrent relay with inverse characteristic provides protection for most faults on the line. The time overcurrent relay has to coordinate with any fuses used to protect distribution transformers connected to the feeder. The coordination requirements for high current faults result 1 Single phase-to-ground fault 2 Inverse-time characteristics U/V 1000 50 100 - 0 I I I I I I I I -100 - 100 -50 10 VA-L2 VA-L3 10 2- 4 0 -2 I I I I I I I - IEC SI 1 RECT IEC VI 1 IEEE MI IEEE VI IEC EI IA-L1 PAC.SPRING.2009 I UK LTI Operating Time (s) VA-L1 I/V Operating Time (s) Distribution Protection cover story 20 IA-L2 IA-L3 0.1 1 10 100 0.1 1 10 US CO2 US CO8 IEEE EI 100 by Damien Tholomier, AREVA T&D Automation, Canada 21 3 ITIC (CBEMA) curve - Revised 2000 Percent of Nominal Voltage (RMS or Peak Equivalent) 500 400 300 Prohibited Region Voltage Tolerance Envelope Application to Single-Phase 120-Volt Equipment 200 140 120 100 No Interruption Function Region 80 70 110 90 No Damage Region 40 0 1 us 0.001 c 0.01 c 1c 1c 1 ms 3 ms 20 ms 100 c 0.5 s 10 s Steady State Duration in Cycles (c) and Seconds (s) 4 Inverse versus definite time overcurrent 10 Seconds in increase in the operating times for faults further down the line, with the longest times for faults at the remote end. In order to reduce the number of electromechanical or solid state relays, backup protection for bus faults or breaker failure has been traditionally provided by the transformer protection relays. Considering the fact that they also have to coordinate with the feeder relays, it is obvious that the operating times for bus faults or feeder faults with breaker failure will not meet the requirements of sensitive customers. Modern multifunctional protection relays have many features that allow significant improvements in the performance of the relays under different fault conditions. Definite Time versus Inverse Time Overcurrent Modern distribution feeder protection relays have multiple phase and ground overcurrent elements used to reduce the operating time of the relay for different fault conditions. Multiple independent stages are available for each phase overcurrent element and the two ground fault elements - one based on measured quantities and the second - on derived quantities calculated from the three phase currents. Each stage may be selected as non-directional or directional (forward/reverse). All stages usually have definite time delayed characteristics and some of the stages may also be independently set to inverse-time IEC or IEEE tripping characteristic (Figure 2). These stages have a programmable reset timer for coordination with other devices. A voltage controlled overcurrent function can be enabled on phase overcurrent elements. It provides back-up protection for remote phase faults whilst remaining insensitive to load. The directionality of the ground fault elements is provided by residual voltage or negative sequence voltage polarizing. A separate multi-stage sensitive ground fault element is provided and is selected as non-directional or directional. Figure 4 shows the inverse time characteristic of a phase overcurrent relay with the operating points for different fault locations on the protected feeder. The characteristic is coordinated with a downstream fuse. Table 1 shows a comparison of the operating times of the traditional inverse time characteristic, compared with the use of the two additional definite time delayed overcurrent elements with settings of 0.2 s and 0.35 s. The last column in the table gives the difference in the operating times. The advantages are quite significant, especially for the faults closer to the end of the line. Negative Sequence Overcurrent Protection Overcurrent elements in traditional phase overcurrent protection must be set higher than maximum load current. This limits the sensitivity of the phase relays and at the same time results in increased operating times for line end faults. Since the levels of the phase fault currents for phase-to-phase faults are lower than the levels for three-phase faults, this will result in further increase of the fault-clearing time. If we consider an example for a phase-to-phase fault at 75 % of the protected feeder, the voltage at the relay location is 0.79 Unom and the phase overcurrent relay with inverse characteristic used for Table 1 and Figure 4 will operate in 07 2. CIRED PTOCph MCG G-EI TD=0.500 CTR=100 Tap=0.25A(Dir) Inst=1000A TP=1.6667s 05 04 03 02 1 0.7 0.5 0.4 1. CIRED Fuse 153-151-050 Idiv=0.3 Minimum melt. 0.3 0.2 0.1 0.07 0.05 0.04 0.03 0.02 0.01 10 2 3 4 5 7 100 2 3 4 5 7 1000 Current (A) PAC.SPRING.2009 Damien Tholomier received a BEng in Electronic, Electrotechnique and Automation in 1990, and a Master in Electrical and Automation Engineering in 1992 from the University of Marseilles, France (Ecole Polytechnique). He joined ALSTOM T&D GmbH in Stuttgart, Germany where he worked for 5 years in the Protection & Control department. In 1997 Damien moved as Marketing Manager High Voltage Protection Business Unit with Alstom T&D Protection & Control in Lattes, France. From 2002-2006 he was Marketing Protection Relays Director for ALSTOM later AREVA T&D Automation. Damien is currently Managing Director in Canada, and he is also responsible for Protection and Automation in North America. Damien is CIGRE, IEEE, IEC TC95 and GIMELEC member. 22 Distribution Protection cover story 0.71 s. For the same three-phase fault the voltage drop seen by the relay is 0.71 Unom with operating time of 0.53 s. Any unbalanced fault condition will produce negative sequence current of some magnitude. Thus, a negative sequence overcurrent element can operate for both phase-to-phase and phase-to-ground faults. If a definite time negative sequence overcurrent element is used, it may be set to clear the same phase-to-phase fault in less than 0.3 s. This will bring the duration of the fault within the acceptable region of No Interruption in Function. Negative sequence table 1 Operating Time Comparison Fault Location TOC Time DTOC Time Time 40 % 50 % 60 % 70 % 80 % 90 % 100 % 0.24 s 0.31 2 0.39 s 0.48 s 0.59 s 0.70 s 0.82 s 0.20 s 0.20 s 0.35 s 0.35 s 0.35 s 0.35 s 0.35 s 0.04 s 0.11 s 0.04 s 0.13 s 0.24 s 0.35 s 0.47 s Distribution systems present different challenges to the prote overcurrent elements also give greater sensitivity to resistive phase-to-phase faults or high resistance phase-to-phase-toground faults, where phase overcurrent elements may not operate at all. RMS Thermal Overload Thermal overload protection based on a thermal replica using RMS load current to model heating and cooling of the protected equipment can be used with both alarm and trip stages. The heat generated within a cable or a transformer is directly proportional to current squared. The thermal time characteristic used in the relay is therefore based on current squared, integrated over time. The largest phase current should be used for input to the thermal model. The thermal element may be set with either a single time constant characteristic for the protection of cables or dry transformers, or a dual time constant characteristic to protect oil filled transformers. See the characteristic in Figure 5 bellow. Modern distribution protection relays can be used not only 5 Dual time constant thermal overload to clear short circuit faults, characteristic 10000 0 protect the equipment under emergency load conditions. Operating Time (seconds) but also to 1000 0 Time constant 1 = 5 mins Time constant 2 = 120 mins Pre-overload current = 0.9 pu Thermal setting = 1 Amp 100 0 10 0 1 0 1 1 PAC.SPRING.2009 Current as a Multiple of Thermal Setting 1 0 Distribution Bus Protection The selection of protection equipment for bus faults until recently was based on the requirements for stability of the power system. Because of that the protection of buses in the case of short circuit faults at the transmission level is usually provided by high or low impedance bus differential relays. The distribution bus protection has been done by the backup time delayed overcurrent protection of the transformers. The understanding of the effects of longer fault clearing times on sensitive industrial equipment results in a change in the philosophy on distribution bus protection. It is now based on exchange of signals between the feeder relays and the transformer protection relays. All overcurrent starting signals from the multiple feeder relays are paralleled and used to energize an opto-input of the transformer overcurrent protection relay. For a fault on any of the distribution feeders, the relay protecting the faulted feeder will start and with or without time delay (depending on the fault location) will issue a Trip signal to clear the fault. Figure 6 shows a simplified block diagram of a distribution bus protection. If the fault is on one of the feeders, the protective relay of that feeder will immediately operate an output that is wired to an input of the transformer relay. This signal will indicate a feeder fault and will block the operation of the bus protection function. If the fault is on the bus, no feeder relay will operate, thus indicating to the transformer protection relay that it is a bus fault. The overcurrent elements that are used to implement a distribution bus protection scheme have to be set with a certain time delay that allows the receiving of a signal from any of the feeder relays. At the same time each feeder relay should be able to communicate the starting of an overcurrent element that is used to block the bus protection element. The advantage of this type of scheme therefore is that it allows fast fault clearing of distribution bus faults without the 23 Multifunctional distribution protection devices can adapt to changing system conditions. Unbalanced loads and line-end phase-tophase faults require ection system. the use of negative sequence overcurrent need for installation of a distribution bus differential protection. protection. Breaker Failure Protection The requirements for improvements in the quality of power supplied to electric utility customers result in changes of the way distribution feeder protection is designed and applied. Many protection schemes that in the past have only been used at the transmission level today are common at the distribution level. One of the reasons is that they are available as some of the numerous functions in a multifunctional distribution feeder relay. One of these schemes is the Breaker Failure Protection. Breaker failure results in prolonged exposure of industrial customers to low voltages and of electrical equipment to large short circuit currents, and may lead to damage of equipment and complete shut down of the manufacturing process. This is the reason that Breaker Failure Protection has gained popularity at the distribution level of the system.The most common Breaker Failure Protection is based on monitoring of the current in the protected circuit. After a fault is detected and the relay issues a trip signal, it will also initiate the timer of the Breaker Failure Protection function. If the breaker trips as expected, the current in all three phases will go to zero, which will reset the undercurrent element used to detect the correct breaker operation. Since at the distribution level the feeder is protected by a single relay, the Breaker Failure Protection function is usually started by a built-in protection function in the protection relay. Fuse Saving Scheme The problem with fuse protection of distribution transformers is that it does not allow automatic restoration of the power supply and requires a crew to be sent to the location to replace the fuse, leading to long supply interruption. Since most short circuit faults have a temporary nature, attempting to clear the fault before the fuse burns has become a standard practice in many utilities using a Fuse Saving Scheme. It uses a low set instantaneous overcurrent element to trip the breaker in the substation immediately after the fault occurs. There is no coordination of the instantaneous overcurrent element with the downstream fuses. The breaker is tripped before the fuse protecting the faulted element will start to melt. After the reclosing, the low set instantaneous element is disabled and overcurrent elements that coordinate with the downstream protective devices are used. The advantage is that in case of a temporary fault the fuse is not going to melt, i.e. it will not require a replacement and will result in a short interruption of the load during the dead interval of the reclosing sequence. This can be very important, especially in cases where the fuse is at a remote location. The disadvantage is that all the customers supplied from the feeder will be affected by the interruption during the reclosing cycle. That is why the decision to apply the Fuse Saving Scheme should be made based on the sensitivity of the loads to voltage sags or interruptions. Selective Backup Tripping Protection of distribution feeders today is commonly provided by a single multifunctional relay. If the relay fails and at the same time there is a fault, the protection is typically provided by time-delayed overcurrent elements of the transformer protection that trips the transformer breaker. This has the negative result of first, delayed operation and second, the tripping of the source breaker leading to a voltage interruption of all feeders connected to the distribution bus. A significant improvement can be achieved by the selective backup tripping from the transformer relay. If it receives a signal that the feeder relay has failed, when a fault is detected and there is no blocking signal from any of the healthy feeder relays, the transformer relay will first send a trip signal to the breaker of the feeder with the failed relay. If the fault is on that feeder, it will be cleared, thus eliminating the need for tripping the transformer breaker and causing the voltage interruption for all feeders. Load shedding in substations Load shedding in substations can be executed based on several different principles. It also can be triggered by different system events and can serve different purposes. Load shedding is executed locally in the distribution substations and triggered by the drop of frequency below the pre-defined thresholds in accordance with the defensive plans. Load also can be shed in order to prevent the separation of the system. It is triggered by criteria implemented in a system integrity PAC.SPRING.2009 Distribution Protection cover story 24 Advanced Advanced load-shedding functions are available in modern distribution protection devices. protection scheme (SIPS) and executed in substations when they receive commands for load shedding from the SIPS. Distributed load shedding is a relatively new concept since it requires each individual distribution feeder to be equipped with an IED that measures the frequency and can perform the load shedding function. This means also that each of the feeder relays need to have voltage inputs. Such a device also provides measurements, recording and other functions. In case of distributed load shedding each individual relay belongs to a specific step of the load shedding system and usually has a more limited functionality compared to specialized IEDs used in centralized systems. The fact that each feeder can be controlled by a separate step in the load shedding system with a different setting, allows the implementation of a more flexible system that will shed load closer to the requirement for balancing load and generation in the area separated after a disturbance. Load shedding functions in multifunctional protection IEDs can be achieved using different methods and their combination in complex schemes using the programmable scheme logic that such devices typically have. Underfrequency The basic underfrequency protection is the most commonly used and is available with multiple independent definite time delayed stages – up to six in some relays. The elements are usually definite time delayed, but can also be used as instantaneous. In order to minimize the effects of underfrequency on a system, a multi stage load shedding scheme may be used with the substation loads prioritized and grouped. During an underfrequency condition, the load groups are disconnected sequentially depending on the level of underfrequency, with the highest priority group being the last one. Frequency supervised rate of change of frequency Considerable load to generation imbalance may result in relatively rapid changes of the system frequency. In such a case maintaining the system stability is an important task, and requires quick corrective action. High speed load shedding cannot be achieved by monitoring the system frequency alone and the rate of change of system frequency becomes an equally critical parameter to use. Independent rate of change of frequency This element is a plain rate of change of frequency monitoring element, and is not supervised by a frequency setting. It can be used to provide extra flexibility to a load shedding scheme in cases of severe load to generation imbalances. Since the rate of change monitoring is independent of frequency, the element can identify frequency variations occurring close to nominal frequency and thus provide early warning to the operator on a developing frequency problem. Additionally, the element could also be used as an alarm to warn operators of unusually high frequency variations. Average rate of change of frequency Variations in frequency during times of generation – load imbalance do not follow any regular patterns and are highly non-linear. Oscillations will occur as the system seeks to address the imbalance, resulting in frequency oscillations typically in the order of 0.1Hz to 1Hz, in addition to the basic change in frequency. The rate of change of frequency elements use an “instantaneous” measurement of “df/dt”. Due to the oscillatory nature of frequency excursions, this instantaneous value can sometimes be misleading, either causing unexpected operation or excessive stability. For this reason, the relays provide an element for monitoring longer term frequency trend, thus reducing the effects of non-linearity in the system and providing increased security. It is recommended that the average rate of change of frequency element is used in conjunction with the frequency element. 6 Diagram of distribution bus protection 7 Distributed load shedding system Substation I Fdr1 protection I x-er schemes allow I Fdr2 I Fdr3 Trip significant reduction in the TOC Start fault clearing Timer AND Blocking Logic time. HV Load IOC Start PIED 1 P Fdr1 PAC.SPRING.2009 PIED 2 P Fdr2 PIED i P Fdri 25 Programmable scheme logic Modern state-of-the-art numerical relays incorporate many protection and control elements. These elements can be used as building blocks to configure the device to a customer’s specific application. The Programmable Scheme Logic is the means by which the internal elements, in reality numerical algorithms, are interlinked in accordance with conventional gate logic rules. The PSL also assigns how opto inputs assert control over the enabled elements, and which outputs should change state, should a particular combination of elements operate. The PSL is used to supplement built-in protection and control schemes, such as breaker-failure protection, which are already implemented within the standard building blocks of elements. Some of the benefits offered by multifunctional devices configured in PSL include: Easy configuration of customer-specific schemes Protection reconfiguration, when required Removing the need for a programmable logic controller and circuit breaker bay controller. The user can design a logic scheme based upon three main types of logic gates: logical AND, OR, and MAJORITY gates. Any gate input or output can be inverted, allowing NOT, NAND, and NOR configurations. Auxiliary timers may be assigned at any stage of the logic for sequence of events coordination, also within feedback loops if required. Event driven PSL only writes to output contacts or front plate LEDs once all PSL re-evaluation is complete. The principle of event driven PSL is to reduce the quiescent overhead on the processor to a very low level, and to keep it low even during fault and autoreclose conditions on the power system. This ensures that fast and repeatable trip times are obtained from relays, and that non-real time tasks such as fault location and disturbance record management take place immediately afterwards. Monitoring Predictive maintenance is becoming extremely important in the efforts of utilities to deal with reduced personnel and increasing customer requirements for improved power quality and reliable supply of electric power. Modern distribution protection IEDs measure and calculate numerous analog parameters and provide additional monitoring functions that allow the transition from scheduled to event driven maintenance, without the need for specialized equipment. A variety of tools, available in microprocessor based relays can help the user to determine the need for primary or secondary substation equipment maintenance based on user defined alarm signals from the protective device. The data is divided in several categories: Breaker maintenance related data, including breaker interrupted current, breaker operation counters, fault counters and breaker opening and close time monitors Breaker auxiliary contacts and trip coil monitoring Voltage transformer supervision schemes Current transformer supervision logic Broken conductor detection All the above information is available from the relays based on built in analysis tools that process the fault data and convert it to information, thus reducing the need for protection, control and maintenance personnel in the decision process. Recording The relays need to record and time tag different events and store them in non-volatile memory. This enables the system operator to establish the sequence of events that occurred within the relay following a particular power system condition, switching sequence etc. The real time clock provides the time tag to each event, with a resolution of 1ms. The event records consist of fault flags, pre-fault and fault measurements etc. Fault location is part of the data included in the fault record. Internal failures detected by the self-monitoring circuitry, such as watchdog failure, field voltage failure etc. are logged into a maintenance report. Recording of the waveforms during a distribution system event can help with the analysis of the operation of the protection relays. The number of records that may be stored by the relay is dependent on the selected recording duration. The duration of the recording may need to be extended to several seconds in order to capture the operation of time-overcurrent protection elements. 8 Average rate of change of frequency 9 Programmable scheme logic f Supervising frequency True slope for the time t F f t t PAC.SPRING.2009 Programmable Scheme Logic developed using user-friendly engineering tools allows the implementation of application specific protection schemes .