THE 2010‐2012  PROGRAMME AND  BUDGET   

advertisement
 African Development Bank Group THE 2010‐2012 PROGRAMME AND BUDGET TABLE OF CONTENTS
EXECUTIVE SUMMARY.............................................................................................................. i 1 INTRODUCTION .................................................................................................................. 1 1.1 Context .............................................................................................................................. 1 1.2 Implementation of the 2009 Programme (see Annex 1) ................................................... 1 1.3 Implementation of the 2009 Budget.................................................................................. 2 2 CONCEPTUAL FRAMEWORK OF THE INDICATIVE WORK PROGRAMME ..... 2 2.1 Update on Relevance of the Medium Term Strategy (2008 – 2012) ................................ 2 2.2 Guiding Principles for the Work Programme ................................................................... 2 3 THE 2010-2012 INDICATIVE OPERATIONAL PROGRAMME (IOP) ....................... 3 3.1 Changing Medium Term Context ..................................................................................... 3 3.1.1 Fast-Tracking Transfer of Resources to RMCs ........................................................ 3 3.1.2 Augmenting Bank Resources .................................................................................... 4 3.2 Bank Group Lending Projections ...................................................................................... 4 3.2.1 ADB Projections ....................................................................................................... 4 3.2.2 ADF Projections ........................................................................................................ 5 3.2.3 2010-2012 Financing Targets ................................................................................... 5 3.3 Operational Areas of Focus............................................................................................... 6 3.4 Proposed Operational Programme .................................................................................... 6 3.4.1 Indicative Lending Programme ................................................................................. 6 3.4.2 Non-Financing Activities .......................................................................................... 8 3.5 Decentralization ................................................................................................................ 9 4 THE 2010-2012 INDICATIVE NON-OPERATIONAL PROGRAMME (INOP) .......... 9 4.1 Areas of Corporate Focus ................................................................................................. 9 4.2 Building Responsive Corporate Services ........................................................................ 10 4.3 Reinforcing Financial, Risk Management and Fiduciary Responsibilities ..................... 11 4.4 Improving Board Relations ............................................................................................. 12 4.5 Consolidating Budget Reforms ....................................................................................... 13 5 PERFORMANCE AND MONITORING FRAMEWORK ............................................. 13 5.1 2010–2012 Monitoring Framework ................................................................................ 13 5.2 Productivity, Savings and Efficiency Gains ................................................................... 14 5.3 Quality Assurance and Results Reporting ...................................................................... 16 6 ESTIMATE OF THE 2010-2012 BUDGETS .................................................................... 17 6.1 Proposed Allocation Criteria ........................................................................................... 17 6.2 2010-2012 Administrative Expenses Budget and Major Cost Drivers ........................... 18 6.3 Budgetary implications of the Indicative Work programme .......................................... 19 6.3.1 Work Programme Adjustments ............................................................................... 19 6.3.2 Estimates of Complexes’ Budgets .......................................................................... 20 7 THE 2010-2012 CAPITAL BUDGET ................................................................................ 21 7.1 Current Status of Implementation ................................................................................... 21 7.2 Status of 2010-2012 Capital Budgets.............................................................................. 21 8 REHABILITATION OF THE HEADQUARTERS IN ABIDJAN ................................. 22 9 RESOURCE ESTIMATES ................................................................................................. 23 9.1 Internally generated resources ........................................................................................ 23 Assumptions ............................................................................................................ 23 9.1.1 9.1.2 Sharing of Administrative Expenses by Institution ................................................ 23 9.1.3 Operational and Net Income Estimates for 2010-2012 Period ............................... 23 9.2 Bilateral and Multilateral Resources ............................................................................... 24 10 CONCLUSION AND RECOMMENDATIONS ............................................................... 24 ANNEXES...................................................................................................................................... 25 Acronyms and Abbreviations
AfDB
ADI
ADF
ADOA
APQR
ASLC
TRA
AU
AUC/ECA
BCP
BITS
BWIs
BUs
CFAA
CGSP
CIMM
CHRM
CIPSC
COBS
COO
CPAR
CPR
CRMU
CSP
CSVP
CWP
DARMS
DOC
ECA
ECON
EITI
ELF
EQY
ERCU
ERP
ESAP
ESW
FAPA
FCR
FFMA
FFCO
FNVP
FOs
GCC
GCI
GECL
GEF
GGI
GGS
GLP
African Development Bank
African Development Institute
African Development Fund
Additionality and Development Outcome Assessment
Action Plan for Quality and Results
Adjusted Short-Lived Crisis Scenario
Temporary Relocation Agency
African Union
African Union Commission/ Economic Commission for Africa
Business Continuity Plan
Broadband Integrated Telecommunication Services
Bretton Woods Institutions
Business Units
Country Financial Accountability Assessment
General Services and Procurement Department
Information Management and Methods Department
Human Resources Management Department
Capital Investment Programme Steering Committee
Strategy and Budget Department
Chief Operating Officer
Country Procurement Assessment Reports
Country Portfolio Review
Compliance Review and Mediation Unit
Country Strategy Paper
Corporate Services Vice-Presidency
Country Work Programme
Documents And Records Management System
Drawn-Out Crisis Scenario
Economic Commission for Africa
Chief Economist Complex
Extractive Industries Transparency Initiative
Emergency Liquidity Facility
Equity Participation (Private Sector)
External Relations and Communication Unit
Enterprise Resource Planning
Environmental and Social Assessment Procedures
Economic and Sector Work
Fund for African Private Sector Assistance
Fixed Cost Ratio
Financial Risk Management Department
Financial Control Department
Finance Vice-Presidency
Field Offices
Governors’ consultative committee
General Capital Increase
General Counsel and Legal Services Department
Global Environmental Fund
Grants for Institutional Support
Grants for Studies
Specific Investment Grants
GPOA
GS
GSI
GSL
GTE
GTLP
HIPC
HQ
HR
HTM
IAS
ICA
ICB
ICF
ICT
IFAD
IFC
IRM
JAS
INOP
IOP
IPPF
ISSC
IT
IWP
JAI
JEPA
JSSO
KPIs
LGA
LGI
LGS
LICs
LLC
LLP
LSI
LSL
MASSP
MDGs
MDBs
MDRI
MEFMI
MFW4A
MICs
MTS
NEPAD
NSDS
NTF
OAGL
OPEV
OpsCom
OPSM
Gender Plan of Action
General Service Staff
Sector Investment Grants
Structural Adjustment Grants
Loan Guarantee (Private Sector)
Global Trade Liquidity Programme
Highly Indebted Poor Countries
Headquarters
Human Resources
Held to Maturity
International Accounting Standards.
Infrastructure Consortium for Africa
International Competitive Bidding
Investment Climate Facility
Information and Communication Technology
International Fund for Agricultural Development
International Finance Corporation
Independent Review Mechanism
Joint Assistance Strategies
Indicative Non-Operational Programme
Indicative Operational Programme
Infrastructure Projects Preparation Facility
Information Systems Steering Committee
Information Technology
Indicative Work Programme
Joint Africa Institute
Joint Economic Performance Assessment
Joint Secretariat Support Office
Key Performance Indicators
Loans for Project Cycle Activities
Loans for Institutional Support
Loans for Studies
Low Income Countries
Lines of Credit (Private Sector)
Specific Investment Loans
Sector Investment Loans
Structural Adjustment Loans
Mutually Agreed Staff Separation Programme
Millennium Development Goals
Multilateral Development Banks
Multilateral Debt Relief Initiative
Macro Economic and Financial Management Institute
Making Finance Work for Africa
Middle Income Countries
Medium Term Strategy
New Partnership for African Development
National Statistical Development Strategies
Nigeria Trust Fund
Office of the Auditor General
Operations Evaluation Department
Operations Committee
Private Sector Department
ORPC
PBA
PBD
PBO
PCRs
PER
PL
PPF
PPP
PMG
PRST
RAG
RBCSP
RECs
RISP
RMCs
ROs
RWSSI
SAP
SECU
SEGL
SLA
SMCC
SMEs
SRF
STS
TA
TFI
TRS
UA
USD
VPU
WBS
WP
WPA
WPS
YPP
YPs
Operational Resources and Policies Department
Performance Based Assessment
Programme and Budget Document
Policy Based Operations
Project Completion Reports
Public Expenditure Review
Professional Level Staff
Project Preparation Facility
Public-Private Partnership
Performance Monitoring Group
Office of the President
Rolling Agenda of the Board
Result Based Country Strategy Paper
Regional Economic Communities
Regional Integration Strategy Paper
Regional Member Countries
Regional Operations
Rural Water Supply and Sanitation Initiative
Systems, Applications, Products
Security Unit
General Secretariat
Service Level Agreement
Senior Management Coordination Committee
Small and Medium Enterprises
Special Relief Fund
Short Term Staff
Technical Assistance
Trade Finance Initiative
Time Recording System
Unit of Account
United States Dollar
Vice-Presidency Unit (also referred to as “Complex”)
Work Breakdown Structure
Work Programme
Work Programme Agreement
Working Paper Series
Young Professional Programme
Young Professionals
EXECUTIVE SUMMARY
The 2010-2012 Programme and Budget proposals are premised on the understanding that the
Bank Group 2008-2012 Medium Term Strategy (MTS) will continue to guide the Bank’s
interventions in the Regional Member Countries (RMCs). Consequently, the key guiding
principles for the Bank’s Work Programme remain: i) selectivity and high quality operations;
ii) focus on country level outputs and outcomes; and, iii) continuous improvement of
knowledge generation and management. The Programme and Budget implementation
environment builds on key institutional activities aimed at enhancing the Bank’s development
effectiveness, notably by improving the quality assurance and results reporting systems;
strengthening the risk management and financial framework; revamping the Bank’s internal
and external communication; reinforcing the IT platform and data management capacity;
consolidating the Decentralization Programme; empowering and motivating staff;
strengthening partnerships; and, enhancing the RMCs’ capacity for improved governance and
economic development.
Operationally, the Bank will strengthen its focus on the MTS core areas of infrastructure,
governance, private sector development, and higher education, science, technology and
technical and vocational training. In so doing, the Bank will continue to promote regional
integration, enhance its support to fragile states, deepen its engagement in the MICs, and
foster high impact, selective support to agricultural development while mainstreaming the
cross-cutting issues of gender, environment, climate change, and knowledge in all its
operational work. The Bank will also continue to play a counter-cyclical role in response to
the current economic and financial crisis, particularly through fast-tracking resource transfers
to RMCs.
The financing target for the Bank Group during 2010-2012 is characterized by a degree of
uncertainty, owing to the impact of the global financial and economic crisis on the needs of
RMCs and on the Bank’s financing capacity. Tentatively, the overall 2010-2012 financing
target for the Bank Group is projected at about UA 16.968 billion: UA 5.586 billion in 2010,
UA 5.340 billion in 2011; and UA 6.042 billion in 2012. Compared with the target of the
2009-2011 PBD, this represents an increase of 29%.
According to the Medium Term Strategy, the Bank was planning to embark on discussions
toward a General Capital Increase (GCI) by 2012. However, the recent sharp increase in the
RMCs’ demand for financing has advanced the need to initiate these discussions. The
Governors Consultative Committee (GCC) met in Tunis in mid-September to discuss the
modalities for a potential GCI. In the meantime, the Bank is implementing a number of
interim measures, including restructuring of its operations and requesting shareholder support
through provision of contingent callable capital, so as to maintain its prudential ratios within
acceptable limits.
The Indicative Non Operational Programme will be tailored to provide maximum support to
the operational agenda of the Bank. At the same time, Non Operational Complexes will
continue to discharge their core corporate mandates such as: (i) corporate governance and
improved coordination; (ii) holistic approach to risk management, fiduciary responsibilities
and control environment; (iii) recruiting, training and retaining motivated and healthy staff;
(iv) scaling up internal and external communication; (v) streamlining processes for better
results, including the consolidation of budget reforms; (vi) revamped IT systems; (vii) support
to the decentralization programme; and, (viii) building responsive corporate services.
i
In terms of required resources, the MTS conservatively anticipated a yearly real budget
growth of 5% (i.e. 25 % for the period 2008-2012) of which 14.31% has already been
approved for the implementation of the 2008 and 2009 Work Programmes. This leaves a
balance of 10.69% for the remaining three years of the MTS.
Management considers 2010 as a year of consolidation of the Bank’s delivery capacity,
further optimization of the use of available resources, and leveraging on demonstrated
efficiency gains and trade offs. Consequently, resource requirements proposals for 2010 have
been prepared on the basis of a zero real growth scenario. This translates into a 4.32%
nominal growth to cater for (i) the impact of higher travel costs on missions and consultants;
(ii) other costs such as employee related costs (resettlement, recruitment), training and general
expenses (rental, electricity, repair, maintenance and communication); and, (iii) a full year
budget for all existing approved positions. The projected administrative budget for 2010 will,
therefore, amount to UA 264 million (an increase of UA 11 million over 2009 Budget) instead
of UA 281 million anticipated in the 2009-2011 PBD. Projections show a total administrative
budget amounting to UA 280.56 million (6.27% real increase in 2011) and UA 293.70 million
(4.67% real growth) in 2012.
In the case of unforeseen and very exceptional developments, Management might propose to
the Board, during the Mid-Year Review, adjustments to the Programme and Budget
Document deemed necessary to respond to the situation. Nevertheless, Management is
committed to remain within the overall growth scenario outlined in the MTS i.e. restrict total
real budget growth in 2010 – 2012 to the remaining 10.69% margin.
The proposed Capital Budget covers four corporate areas of focus: (i) interim consolidation of
the Bank’s IT system – in the light of the findings of the Infrastructure Audit and Study; (ii)
support of the Decentralization Programme; (iii) Buy/Building in Field Offices and, (iv)
rehabilitation of the Headquarters Building, Villas and Cité BAD in Abidjan.
The Bank Group’s projected operational income of UA 452.6 million, UA 450.3 million and
UA 448.2 million 2010, 2011 and 2012 respectively, is adequate to sustain the proposed
Budgets.
ii
1
INTRODUCTION
1.1
Context
Following discussions held with the Committee of the Whole on the 2nd of November 2009,
Management presents, for consideration, proposals for the 2010-2012 Indicative Work
Programme (IWP) and associated budgets.
Similar to the 2009-2011 Work Programme and Budget, this document combines the
Indicative Operational Programme (IOP) and the Indicative Non-Operational Programme
(INOP) as well as the resource requirements for the period 2010-2012.
In line with the institutional reforms launched in 2006, the proposed programme and
associated budgets are derived from a Bank wide exercise which started with agreements on
Work Programmes before the determination of the resource envelope. Alignment of the 20102012 IWP with the Institutional priorities has been strengthened and re-focused on Country
Work Programmes. This has also included improved coordination between Headquarter and
Field Offices. Deliverables of the Non-Operational Complexes have been clearly defined and
aligned with the Operational agenda.
As a necessary background, Management has critically reviewed past experiences in the
implementation of the Bank’s annual Work Programmes and Budgets. Identified lessons
have informed the proposals outlined in this document.
1.2
Implementation of the 2009 Programme (see Annex 1)
Total Bank Group financing approvals as at end of November1 reached UA 5,316.17 million,
of which UA 1,650.04 million is from the ADF window and UA 3,666.13 million from the
ADB window. The latter includes UA 1,074.25 million pertaining to ADB Private Sector
lending, which represents 128% of its 2009 target. The overall Bank Group Financing stands
at 130% of the 2009 target and projections show that the lending target will be achieved by
the end of the year2.
Eighty-nine Knowledge Management Products (CSPs, CPRs, ESWs and related papers) have
been delivered, representing an implementation rate of 64% of the yearly targets. Unrealistic
target and historically low execution of this component of the Operational Work Programme
has led Management to rethink the level of programming and to fine-tune some internal
processes in order to have more credible targets and increase the quality of the products (see
Para 3.4.2).
Disbursements point to yearly targets being achieved or surpassed by Year End. Portfolio
Management performance shows good results whilst performance on Process Efficiency
Indicators is very promising.
2
The implementation rate is set against the target set in the KPIs at beginning of the year - which excludes HIPC,
ADB special assistance SRF & Other Grants, 2009 operations (un-programmed) to respond to the Financial
Crisis (Botswana for example) and operations under the ELF and the TFI umbrellas. On the other hand, when all
these are taken into consideration, then total Bank Group approvals as at 9th of December amount to UA 7,910
billion.
1
1.3
Implementation of the 2009 Budget
The utilization rate at end November stands at 73% (UA 184.73 million) or 82% if known
commitments to the end of the year are factored in.
2
CONCEPTUAL FRAMEWORK OF THE INDICATIVE WORK PROGRAMME
2.1
Update on Relevance of the Medium Term Strategy (2008 – 2012)
The MTS was approved by the Board of Directors in December 2008. Its implementation is
underway and reflects the underlining principles articulated in the High Level Panel Report
for poverty reduction and development through growth and economic integration.
The MTS makes it clear that the Bank will focus on a number of interlocking and mutually
reinforcing areas: infrastructure, governance, promoting a more robust private sector, and
developing technical and higher level skills. These are areas in which the Bank has solid
experience, expertise, and demonstrated capacity to deliver.
During this implementation period, the role of the Bank Group has increased due to the
effects of the global crisis and the additional negative impact of limited resources and policy
space available to RMCs. The validity of the MTS is, therefore, being defined by the level of
demand which is certainly increasing, the subsequent availability of resources, the levels and
speed of disbursements and the change in risk levels for the Bank in the face of the
unprecedented demand.
During the 2009 Annual Meetings, the Board of Governors re-affirmed the Bank’s strategic
thrust under the MTS. They also endorsed the Bank’s counter-cyclical role to mitigate the
impact of the crisis. In addition, the Governors noted that the Bank had made progress in three
key areas; (i) there have been significant increases in lending and disbursements, as well as
major capacity improvements; (ii) the Bank took quick actions to prevent the financial crisis
from escalating; and, (iii) it continues to align its priorities with those of the RMCs.
However, successful implementation of the Strategy hinges on three key parameters: (i)
attending to the challenges associated with increased demand; (ii) maintain and scale-up
capacity for delivery, and increasing corporate business efficiency; and, (iii) the elimination
of bottlenecks. These issues will continue to be addressed in the 2010-12 PBD.
2.2
Guiding Principles for the Work Programme
The Bank will be guided by the following key principles:
Selectivity - by focusing on areas of added value, leaving other Partners to work where they
have comparative advantage.
High Quality Operations - continuous improvement of processes for ensuring better quality
at entry, at supervision and at exit for its operations. This will include results-based
programming tools, extending its readiness review, improving its supervision and completion
reporting for enhanced learning and accountability and reinforcing the Additionality and
Development Outcome Assessment (ADOA) for private sector operations.
Focus on Country Level Outputs and Outcomes - strengthened focus on results. To this end,
the Bank will continue to monitor key country outcomes, using adequately designed results
2
frameworks. It will also focus on enhancing the incentives and systems that drive
implementation of the Bank’s operations. This will include measures aimed at promoting
results-oriented supervision and timely preparation of completion reports, strengthening
portfolio management information systems, and rewarding staff performance.
Bank as a Knowledge Institution - The Bank will continue its efforts aimed at enhancing: (i)
the generation and management of Knowledge across its organizational units; (ii) its statistical
capacity and its existing Knowledge platforms; and (iii) internal and external communication
for a wide dissemination of Knowledge.
Capacity Building in RMCs – The Bank will pay special attention to: (i) Strengthening
Statistical Capacity: attention will be placed on designing and implementing National
Statistical Development Strategies (NSDS) which include strengthening the generation of
statistics in key sectors and areas; reinforcing in-country statistical training and statistical
training centres; improving data management and dissemination systems; and mainstreaming
data generation and results measurements into Bank’s operations; (ii) Strengthening Financial
Management Capacity in LICs and Fragile States: The Bank will continue to rely on dialogue
and training initiatives to enhance RMCs’ capacity to plan and manage public resources,
implement and supervise Bank supported operations, as well as design and manage a
conducive macroeconomic environment which attracts investment and stimulates growth.
Enhancing Institutional Effectiveness: To support the above-highlighted Operational
principles, the Bank has been implementing a number of institutional programmes aimed at
increasing its delivery capacity. Management considers 2010 as a year of consolidation of the
acquired capacity and anticipates, following demonstrated performance and quantifiable
efficiency gains, a contained increase of the Bank’s delivery capacity from 2011. In 2010, the
following areas have been identified as requiring particular attention: (i) consolidation of the
Decentralization Programme; (ii) enhancement of the Risk Management function; (iii)
strengthening IT platform and skills; (iv) improved communication; and (v) staff
empowerment and motivation. Cost savings and efficient use of resources are important
pillars of the Bank’s Programming and Budgeting framework, and Management will
strengthen its oversight in this area. Work Programmes have been reviewed to identify areas
of potential trade offs, scale down or further streamlining.
3
THE 2010-2012 INDICATIVE OPERATIONAL PROGRAMME (IOP)
3.1
Changing Medium Term Context
As discussed in para 2.1, the MTS remains a robust framework and strategic guide for the
Bank. However, the financial crisis and current high demand for Bank financing require
higher levels of lending than those under the MTS. The Bank has, therefore, adjusted the pace
of delivery of its support to the RMCs and is taking further steps to increase its financing
capacity to better respond to the additional needs of its clients.
3.1.1
Fast-Tracking Transfer of Resources to RMCs
The Bank Group has responded promptly to the crisis by supporting its RMCs in mitigating
the adverse impacts of the crisis, substantively relying on programmatic or policy based
operations to provide quick-disbursing resources. The ADF, on the other hand, used the fixed
amount of resources of its envelope for activities which were for the most part already
scheduled. Only a few operations were added to respond to the crisis. Nonetheless, the Fund
has made available some resources through: i) frontloading, notably to finance a backlog of
3
projects using resources from the Regional Operations Envelope and the Fragile States
Facility; and, ii) disbursements and portfolio restructuring. Additional instruments were also
introduced in 2009, including: the USD 1.5 billion Emergency Liquidity Fund (ELF) and a
USD 1 billion Trade Finance Initiative (TFI) (0.5 billion of this is managed by the Global
Trade Liquidity Programme - GTLP)
3.1.2
Augmenting Bank Resources
Looking ahead, the Bank Group has estimated that the demand for its financing will remain
high in the medium to long term. This will likely not be at the level of the 2009 spike in
demand, but above MTS lending scenarios. Additional steps have been undertaken to respond
to this higher demand, while preserving the Bank’s prudential ratios.
A number of the instruments used by the Bank to support RMCs during the financial and
economic crisis are fast disbursing with a higher call on risk capital. On the basis of its
Medium Term Strategy, the Bank had planned the launching of GCI discussions by 2012. The
increasing demand for financing from RMCs continues to put pressure on the Bank’s
prudential ratios, calling for additional risk capital. This has advanced the Bank’s plans for
discussions regarding a potential GCI. A meeting to this effect was held with the GCC in
mid-September. In the meantime, the Canadian and Korean authorities have granted the Bank
a contingent callable capital3 to prevent the curtailing of the Bank’s financing goals. These
developments will allow the Bank to maintain its prudential ratios within the limits up to the
end of 2010.
As requested by the ADF Deputies, the Mid-Term Review of the ADF-11 reported in
Helsinki, Finland, on the first half of the ADF-11 cycle with regards to the utilization of
resources. The Bank’s presentations were favourably received. Discussions toward the 12th
Replenishment of the ADF were also initiated. Deputies asked for information on a range of
issues including Budget Support Operations, Regional Operations and the Fragile State
Facility, among others. Responses will be provided in the next meeting to be held in Cape
Town, South Africa in early 2010.
3.2
Bank Group Lending Projections
The Bank has become more visible in RMCs, through its on-going decentralization process
and other institutional reforms; as well as its role as a key voice for Africa on the international
stage. The increased immediate needs from RMCs in the context of the crisis, combined with
enhanced capacity of the Bank and closer relationships between the Bank and its clients, has
led to an unprecedented demand for the Bank’s attention, including from the private sector.
3.2.1
ADB Projections
At the onset of the financial crisis, the Bank revised the MTS lending scenario. A Short-Lived
Crisis Scenario (ASLC)4 and a Drawn-out Crisis Scenario (DOC)5 had been developed in the
GCI-VI Issues Paper which was presented to the Boards in July 2009. The ASLC which
allowed for a sharp increase in lending in 2009 (over UA 6 billion), tapering off in 2010 and
returning to the MTS in 2011 and 2012, has been considered as the base case scenario for
3
Canada will provide the equivalent of UA 1.6 billion and Korea UA 190 million.
Under this scenario lending levels for 2009 and 2010 were projected at UA 6.984 billion and 3.565 billion,
respectively. Projections then converge to the MTS levels of 2.890 billion and 3.292 billion for 2011 and 2012.
MTS projections for 2009 and 2010 were UA 2.187 billion and 2.171 billion respectively.
5
This scenario was based on the assumption that the impact of the crisis would be longer and the Bank should
thus sustain lending levels higher than the MTS and the ASLC.
4
4
ADB lending projections. The Bank has undertaken interim measures, including (i)
restructuring and streamlining of private sector operations; (ii) monitoring the Bank’s
portfolio’s risk profile; (iii) postponing some projects; and (iv) tranching large loan
commitment. For example, the restructuring of the 2009 lending program resulted in a
reduction of some UA 815 million of the sovereign operations6 and UA 460 million of the
private sector portfolio. As mentioned earlier, the Bank has also received support in the form
of contingent callable capital. These measures will alleviate the pressure on the Bank’s risk
capital and create additional lending headroom up to 2010 as highlighted in Table 1 below.
In the medium term, the Bank will need a GCI to sustain its commitments to RMCs.
3.2.2
ADF Projections
Lending under the ADF will depend on the balance of ADF-11 resources available for 2010
and additional resources that might result from the ADF-12 replenishment. As of end October
2009, the projection for the 2010 balance was estimated at UA 1.441 billion, a significant
increase, compared to that projected in July 2009. This is the result of a restructuring of the
2009 ADF lending programme, which led to postponing some operations7 to 2010. The last
performance-based allocation exercise for ADF-11 will take place in early 2010 and will
likely impact on allocations to individual countries. For 2011 and 2012, it will not be possible
to make firm projections before completion of the ADF-12 Replenishment. Given the
uncertainty around the level of the 12th Replenishment of the ADF, MTS projections for ADF
resources for 2011-2012 are used as proxies8. These figures will be adjusted when the results
of the ADF-12 negotiations are known.
3.2.3
2010-2012 Financing Targets
The financing targets envisaged by the Bank Group during 2010-2012 are characterized by a
higher level of uncertainty than during the previous budget period. Table 1 below summarizes
the targets proposed. The ADF figure of UA 1.441 billion for 2010 represents the amount
that would be available for commitment. The ADB 2010 financing target of UA 4.145 billion
includes the headroom made possible by the adjustments of the 2009 lending program and the
contingent callable capital9.
Table 1: 2010 – 2012 Financing Targets (UA billion)
ADF*
ADB*
Bank Group
2010
1.441
4.145
5.586
2011
2.450
2.890
5.340
2012
2.750
3.292
6.042
2010-2012
6.641
10.327
16.968
* 2011 and 2012 figures are MTS projections (Refer to Table 2 below)
The aggregate 2010-2012 financing target is estimated at UA 16.968 billion, of which UA
5.586 billion in 2010, UA 5.340 billion in 2011, and UA 6.042 billion in 2012. All three
yearly lending projections for the period are significantly lower than the projected lending
6
This reduction in sovereign lending is due, among other factors, to the postponement to 2010 of the Egypt UA
645 million loan in support of financial reforms.
7
These include the Ethiopia Gibe III Power Project.
8
These projections were done in 2008, when the MTS was formulated.
9
The Bank has estimated that the callable capital availed by Canada and Korea will create additional headroom
of UA 1.8 billion.
5
levels for 200910, which is expected to reach some UA 8 billion. This much higher lending
figure in 2009 is explained by the fast-tracking of resources to RMCs and the introduction of
new financing instruments in response to the economic and financial crisis.
Table 2: 2008 - 2012 Financing Targets showing MTS Projections (UA billion)
ADF
ADB
Bank Group (ADF + ADB)
MTS Projections (ADF+ADB)
2008
1.900
1.640
3.540
3.540
2009*
2.300
5.700
8.000
4.090
2010
1.441
4.145
5.586
3.710
2011
2.450
2.890
5.340
5.340
2012
2.750
3.292
6.042
6.042
2008-2012
10.841
17.667
28.508
22.722
2010-2012
6.641
10.327
16.968
15.092
* Projected Commitments (Actual + Planned)
3.3
Operational Areas of Focus
Core Priorities - The Bank will strengthen its focus on: (i) scaling up its support to Africa’s
own efforts for infrastructure development, including by continuing to exercise leadership in
continental initiatives such as NEPAD, ICA, etc.; (ii) supporting good governance,
particularly in the management of public resources and initiatives such as ICF, EITI, and
MFW4A; (iii) private sector development with particular support to infrastructure, financial
intermediation, industries and services; (iv) seeking to increase its support to Higher
Education, Science and Technology and Technical and Vocational Training. The Bank will
also emphasize its intervention in the area of fragile states, regional integration and
agriculture, and in crosscutting issues including adaptation to climate change and gender
equality.
Response to the Financial and Economic Crisis - The Bank will continue to play a countercyclical role in response to the current economic and financial crisis, with a view to
alleviating the negative impact on RMCs. The areas of focus will include trade financing,
budget support, policy dialogue and advisory services.
3.4
3.4.1
Proposed Operational Programme
Indicative Lending Programme
Indicative Lending Programme Versus Financing Target -The 2010 indicative lending
programme amounts to UA 5.536 billion comprised of UA 4.09 billion of public operations
(ADB, ADF and other miscellaneous technical assistance funds) and UA 1.43 billion of
private sector loans (see the list of operations in Annex 2). It is about UA 50 million lower
than the financing target of UA 5.586 billion.
Distribution by Financing Instrument - Investment operations made up primarily of specific
and sector investment loans and grants will remain the major financing vehicle over the
period. Figure 1 below presents a breakdown of the indicative lending programme per
financing instrument for 2010, Investment operations will represent about 60.1%. Policybased operations (PBOs), representing about 22.8 % of resources. This reflects the continuing
significant demand for fast-disbursing assistance as a result of the economic and financial
crisis. Lines of credit, equity participation and loan guarantees, processed by the Private
Sector Department, will account for about 15.5%. Technical assistance (TA) covering mainly
10
As of end October 2009, the projected commitments to end December 2009 of both ADB and ADF are
estimated at UA 5.7 billion and UA 2.3 billion, respectively.
6
institutional support operations and project preparation makes up some 1.6% of the 2010
indicative lending programme.
Figure 1 – 2010 IOP Distribution by Financing Instruments
Technical
Assistance, 1.6%
LLC, EQY, GTE;
15.5%
Investment
Operations, 60.1%
Policy-Based
Operations, 22.8%
Note: LLC, EQY and GTE stand respectively for Lines of Credit, Equity Participation and Loan Guarantee.
Distribution by Sector - Figure 2 below presents a breakdown of the 2010 lending WP by
sector, based on the sectoral definition currently used in the Bank (see also Annex 3 for the
number of operations per sector). Infrastructure retains the top priority and represents, at
48.2%, almost half of all financing. As substantial portions of the Bank’s operations in
agriculture and rural development have infrastructure components, the infrastructure share in
the 2010 WP is much higher than indicated. The multi-sector loans and grants comprising
policy based operations in support of reforms and good governance represent a significant
share of 24.7%. This is consistent with the important portion of the PBO previously
highlighted and reflects Bank’s response to the adverse impact of the economic and financial
crisis. Other sectors receiving sizeable volumes of resources include Finance, Agriculture and
Rural Development and Social including Higher Education, with 10.5%, 6.2% and 6.4%,
respectively. Industry, Mining and Quarrying accounts for about 3.6%.
Figure 2: Distribution of the 2010 Indicative Lending Programme by Sector
Industry, Mining and
Quarrying , 3.6%
Agriculture and Rural
Development, 6.2%
Environment , 0.4%
Infrastructure, 48.2%
Multisector, 24.7%
Social, 6.4%
Finance, 10.5%
7
On the whole, the share of the private sector in the 2010 indicative lending programme is
estimated to be about 25%, with projects in almost all the sectors above.
Based on the foregoing, it can be concluded that most of the resources will go to the Bank’s
areas of focus.
3.4.2
Non-Financing Activities
Non-lending activities will continue to complement the Bank’s financing operations in the
RMCs. These include ADF resources mobilization and programming activities, economic and
sector work (ESW), portfolio management, and policy development. Within the framework of
the non-lending work programme, Management will put particular emphasis on leveraging the
resources available in the Bank to develop more rigorous analytical work.
Resources Mobilization Activities – Negotiations for the ADF-12 Replenishment were
initiated in Helsinki in October 2009 and will continue in 2010. As usual, they will require
Bank-wide involvement in the preparation of background and discussion papers and in
undertaking missions. Similarly, the Bank will undertake analyses, missions and other
activities leading to the GCI.
Programming & Pipeline Development Activities - The number of CSPs is expected to be at
the same level as in 2009. Related activities will include the preparation of Joint Assistance
Strategies (JAS), and working closely with other MDBs and development partners. Following
the approval of the Regional Integration Strategy, Management will prepare a number of
Regional Integration Strategy Papers (RISPs) aimed at guiding Bank Group’s future
engagement in the Regional Economic Communities (RECs).
Economic and Sector Work - In view of the low level of delivery on ESWs projected by end2009, the number of future ESWs will be limited and concentrated in areas supporting the
core business activities of the Bank Group. Management will put particular emphasis on
deepening the demand analysis, developing new business models, and dealing with relevant
programming issues, as well as preparing flagship knowledge products and policy notes.
Management will also accord a high priority to the dissemination of the above-noted products.
Portfolio Management - The Bank will continue to build on its Action Plan for Quality and
Results (APQR) and the enhanced decentralization process to strengthen portfolio
management, as well as making it more results-oriented. Project supervision will continue to
be strengthened, to ensure that the annual target of 40% of projects to be supervised twice a
year is met and that timely reporting is done. The number of supervision missions undertaken
and the completion reports prepared by Field Offices will be scaled up throughout the period.
In relation to this, it should be noted that the implementation of the initiative on PCRs has
already lifted 2009 performance to more than 90% of the projects exiting in 2008. This
initiative will continue during the period. Also, preparatory work is being done for a similar
initiative on supervision reporting. The number of Country Portfolio Performance Review
will slightly increase from 21 in 2009 to 22 in 2010. The portfolio cleanup will continue with
the cancellation of projects that meet the relevant criteria. Furthermore, Management will take
measures to ensure consistent measurement of portfolio performance across Countries and
Complexes.
Policy Development - The preparation of new policies and strategies, as well as the revision
of a few others, will be initiated in 2010. These will include: (i) the Policy on Streamlining
Loan conditions; (ii) the Energy Policy and the Strategy on Renewable Energy; (iii) the Credit
Policy; and (iv) the Environmental and Social Assessment Procedures and Related Safeguard
8
policies. Other key policies and strategies whose preparation are underway and are expected
to be approved in 2010 include: i) Natural Resource Management Policy; ii) Sanitation
Strategy; and, iii) Agriculture & Agro-Industry Strategy. The dissemination of operational
policies/strategies and frameworks approved over the last two years - such as the Regional
Integration Strategy approved in March 2009, the Climate Risk Management Strategy
approved in April 2009, the Integrated Urban Development Strategy, which is planned to be
approved by early 2010, will also be given careful attention.
3.5
Decentralization
The Decentralization Programme, as conceptualized in 200411, is nearing completion with the
establishment of some 26 Field Offices out of which 23 are already operational. Preparations
for opening the remaining three (Angola, Algeria and South Africa) are advanced.
Building on the recommendations of the July 2009 Report of the Independent Evaluation
Department (OPEV), Management is preparing a comprehensive roadmap which will be
presented to the Board of Directors upon its completion. In the meantime, Management is
taking action to address the major findings of the OPEV Report, including enhancement of
the Field Offices’ control environment and the procurement and fiduciary functions.
4
THE 2010-2012 INDICATIVE NON-OPERATIONAL PROGRAMME (INOP)
4.1
Areas of Corporate Focus
Information and Communication Technology Platform: As outlined in the 2009-2011
PBD, the IT function plays a key role in terms of security and risk management,
organizational effectiveness, knowledge production and dissemination and data production
and availability. Management is carrying out an extensive review of the Bank’s IT
architecture; technical skills capacity and infrastructure audit. The outcome of this review
will further inform the ongoing efforts to revamp the IT function. Meanwhile, the incoming
IT Chief Architecture Office will help promote the much needed interface between business
needs and IT development/alignment in order to leverage ICT to the maximum extent.
Finally, the SAP Functional Upgrade Project has been launched and its implementation will
allow more efficient and fully integrated processes, paving the way, among other
improvements, for a smooth implementation of UA Budgeting framework.
Decentralization: The INOP gives priority to activities providing direct support to the
development assistance programme as outlined in the IOP, one of the main pillars being
decentralization. Non Operational Complexes’ activities have been tailored to give full
support to the proposed consolidation of the decentralization programme.
Risk Management Function: (Discussion in Section 4.3 below)
Enhancing Communication: The Bank’s External Relations and Communication will
support the Institution’s strategic objective to earn recognition as the partner of choice in
Africa’s development. The Bank will increase its volume of communication activities in order
to support the institution’s priorities, in particular decentralization, MTS, ADF–12
Replenishment and the future GCI-VI. In partnership with OPSM communication specialists,
ERCU will disseminate major results of key private sector initiatives. In support of these
efforts, it is important for the Bank to show the results achieved through the implementation
11
Ref. ADB/BD/WP/2004/72/Rev.1 - ADF/BD/WP/2004/84/Rev.1
9
of Bank Group financed development projects in the RMCs. In order to achieve greater results
in communication, a clear distinction has been made between external relations and traditional
communication activities, such as media relations and knowledge dissemination.
External relations will be emphasized as a mean of increasing awareness of the Bank’s role on
the continent. Special attention will be given to networking with major communication
platforms. In this regard, Management is finalizing phases II and III of the Bank’s External
Relations and Communication Strategy. The implementation of these phases will contain a
fine audience mapping, allowing the establishment of necessary partnership with civil society,
regional and multilateral organizations, as well as with selected decision-makers
(governments, parliamentarians, political representatives at the local level. The following are
major planned activities: (i) upgrading the quality of the Bank’s website to international
standards, while paying special attention to the revamping of the intranet with a view to
ensuring that this platform is user friendly and provides accurate information to users; (ii)
building communication capacity in an effort to change internal communication behaviour
which will be highly beneficial to the institution’s external image building; (iii) direct
assistance to internal clients to ensure timely and quality communication of their efforts. A
comprehensive external relations and communication action plan will be finalized early 2010.
4.2
Building Responsive Corporate Services
In general, the Corporate Services Complex will consolidate the implementation of its reforms
approved by the Board in 2008.
The HR Strategy, approved in 2007, is at the centre of an ongoing restructured HR function
that: (i) builds capacity by attracting and developing requisite, diverse talent, (ii) manages
Performance for Results by rewarding it, (iii) promotes staff health and a conducive workenvironment, and (iv) strengthens HR Management in order to transform the HR department
into a client-oriented department supporting managerial accountability across the Bank. In
addition, Management will endeavour to increase training activities for all staff.
The Skills and Staff Surveys undertaken in 2007 enabled management to have a clearer view
of available resources and Staff expectations. In this regard, follow up actions on the 2007
Staff Survey continue. An overall review of developments will be undertaken in the first
quarter of 2010 and the next Staff Survey will start in the second quarter of 2010. In addition,
the Career Development Framework, which is planned to be launched in the first quarter of
2010, will provide a clear, transparent and objective process for personal development,
promotion and mobility across the Bank, and selection and recruitment. The framework will
ensure linkages to the new performance management system and will provide a common
language to help both individuals and managers to identify current performance levels, inform
personal development, and enable each staff member to realize their future potential. Within
the more general context of enhancing Corporate Services Delivery, ongoing HR Department
Reforms will move from the centralized HR administration model to a more client and
partnership-focused model, thus enabling the Department to provide a wider range of services
such as strategic planning and career development.
The General Services and Corporate Procurement Department will, on top of the business as
usual functions, engage itself to: (i) assist the Decentralization process, buying or leasing
office spaces as best suits different geographical locations (ii) a need for an up-to-date
working environment, (iii) accommodate an expanded work force, and (iv) to start the
medium-term project of refurbishing the Bank Headquarters.
10
4.3
Reinforcing Financial, Risk Management and Fiduciary Responsibilities
The strategic priorities of the Finance Complex will continue to centre on adding value to
Bank Group clients, ensure optimal utilization of the Bank’s risk bearing capacity and assist
in the development of Africa Bond Markets.
The Africa Bond Markets will harmonize data for market participants through the creation of
comprehensive and dynamic database. FNVP will, during 2010, assist the African Domestic
Bond Fund determine its size and mandate; create an African Domestic Bond Index; host
regional Stakeholder Workshops, African Bond Market Seminar and the first ever Pan-Africa
Domestic Bond Market Conference. All these efforts will contribute to build an enabling
environment for the development of domestic bond markets.
During 2010-2012, the main areas of focus of the FNVP Complex will include: ongoing
support for the decentralization programme, implementation and enhancement of capital
adequacy framework, improving financial capacity of the Bank through streamlining net
income allocation process and capital replenishment, enhancing commercial credit risk
assessment to ensure sustainable growth of private sector operations; enhancing treasury risk
assessment, monitoring and reporting to ensure financial soundness; and providing adequate
response to exogenous shocks. In this regard, an outside review of the Bank’s Risk
Management systems is ongoing and the procurement process of an Independent Firm is well
advanced.
In addition to Financial Risk Management outlined above, the risk management function also
involves other departments and units in the Bank as discussed below.
The current global financial turmoil has generated new opportunities and challenges in terms
of expansion and diversification of operations and financial instruments. The main pressure to
respond to demands and the increased associated risks affect, in particular, private sector
operations. The Bank will have to enhance its Risk Management function and the control
environment to ensure the integrity of its processes and assets. In this regard, a number of key
units will be strengthened in order to mitigate risks associated with our operating
environment. In terms of security, Management will continue to bolster its efforts in
providing security to the Bank’s assets through field security assessments, training
programmes and the Information Security Protection Programme. In addition, the Business
Continuity Plan launched in 2009 will, in 2010, focus on functional tests covering the
remaining Field Offices, i.e. Northern (Morocco, Algeria, Egypt and Sudan) and Southern
Africa countries (Angola, Mozambique, Madagascar, and South Africa).
The General Counsel and Legal Services Department (GECL) will continue to provide legal
services to all units of the Bank, including its decision–making organs and Senior
Management. Among the critical areas of focus during the Medium Term Strategy, GECL
will guarantee proper legal due diligence in enabling the Bank to preserve its financial
soundness and integrity, as well as ensure that its operations are financially sustainable. It will
play an important role in risk management initiatives; advise on the borrowing programmes;
participate fully in work on the sixth general capital increase (GCI-VI), and the ADF-12
negotiations during 2010. In order to increase GECL responsiveness to the needs of its clients
in the significantly changing institutional and operational environment of the Bank, the Board
recently approved a restructuring of the GECL12.
The revamped Security Unit (SECU) is expected to offer quality security support with a focus
12
ADB/BD/WP/2009/139/Rev.1
11
on strengthening the decentralization process and protect Bank’s property, information,
reputation and human resources. The Security Unit will pay special attention to: (i) security
risk assessment for all Bank locations; (ii) crisis management training, linked to BCP; (iii)
specialized risk assessment and mitigation methodology to guard against special security risks
to our core business, and (iv) Bank’s IT systems & data monitoring and securing.
The Compliance Review Mechanism Unit (CRMU) will focus on raising awareness and
review the performance of the Independent Review Mechanism (IRM) and monitoring the
implementation of decisions on action plans for 2009 requests. The review of the mechanism
itself is underway. This reassessment will provide an opportunity to appraise the IRM in order
to achieve a system of stronger accountability for any negative impact on the population
resulting from Bank financed projects.
The Office of the Auditor General (OAGL) will continue to deliver its institutional mandate
in terms of internal auditing and combating corruption and fraud. However, the coverage of
its activities will expand due to increased risks inherent in the growing and diversification of
Bank’s operations, financing instruments and Field Offices. Concomitantly, the Board has
asked for increased coverage of operations in the light of the financial and food crises and the
risks associated with the instruments that the Bank has been using (i.e. fast disbursing
instruments such as budget support) in response. Concerning auditing, OAGL is currently
covering an average of 5 to 6 FOs per year, which means visiting each FO every 4 - 5 years.
This coverage is considered low. It is, therefore, planned to reduce it to a coverage frequency
of 2 -3 years during the current planning period. In the long run, it is intended to stabilise it
at 1-2 years. Finally, there are also additional auditing needs related to the expansion of
private sector operations which have been factored into the Work Programme.
For combating corruption and investigating fraud, OAGL plans a greater involvement in the
following activities: (i) development of technology to minimize risks of fraud and corruption
in procurement and operations (procurement red flagging aspects have begun with the hiring
of a consulting firm); (ii) detailed fraud/corruption exposure reviews of selected sectors and
Bank-financed procurements; (iii) prevention and sensitization within and outside the Bank;
(iv) increasing importance of the whistle-blowing policy within and outside the Bank.
4.4
Improving Board Relations
The General Secretariat (SEGL) intends to reinforce and re-profile its internal capacity with
the aim of improving delivery. Key activities in 2010 would include the transfer of Elected
Officers related activities presently performed by CHRM, and strengthening of Protocol
Services in all countries where the Bank has offices13. An enhanced team in SEGL will
positively affect institutional governance, document processing and shareholder
relations. Increased resources would also be devoted towards anticipated discussions with
countries on membership of the Bank and participation in the Fund, as well as to: (i) enhance
the value of Annual Meetings; (ii) strengthen support for Board proceedings and
administrative activities; (iii) improve the functioning of the E-Board and other information
facilities; (iv) implement web-based centralized meeting/conference management system; (v)
staff training; and (vi) lead the Bank centralized indexation and archiving initiative. In
addition, SEGL anticipates increase in Boards of Governors and Committees meetings as a
result of the GCI-VI, ADF-XII, the Contact Group on Board composition, and election of the
President. Finally, SEGL will also host the 2010 MDBs’ Secretary Generals/Corporate
Secretaries’ Forum.
13
No specific position is planned in the Field Offices as everything will be handled through outreach efforts
from Head Office.
12
4.5
Consolidating Budget Reforms
The Board of Directors approved a set of Budget Reforms on 15 June 200714.
Implementation of these Reforms has: (i) strengthened the link between institutional priorities
and resource allocation; (ii) enhanced institutional budget flexibility through increased
fungibility and devolved authority; (iii) resulted in establishing a new accountability and
performance framework by linking deliverables to Key Performance Indicators (KPIs); and
(iv) introduced a consolidated multi-year programming and budgeting framework. The end
objective of these reforms is the transition to a fully decentralized resource management
framework through a strategy-driven Unit of Account (UA) Budgeting system which will go
live in January 2010. Among the measures to be introduced in January (subject to Board
approval), will be the removal of the staff headcount control and the introduction of rigorous
staff planning and Fixed Cost Ratios for Complexes as compensating controls. Time
Recording System, which will help improve the quality of cost data, will be re-introduced.
Overall, UA Budgeting will bolster institution wide efforts for better delivery of results on the
ground. Annex 4 recaps progress made to date on the approved budget reforms agenda and
highlights future plans for completion.
5
PERFORMANCE AND MONITORING FRAMEWORK
5.1
2010–2012 Monitoring Framework
Delivery of the 2010-2012 Work Programmes will be assessed at Complex level (monthly)
and at Institutional level (quarterly) against an agreed set of KPIs. Progress made by the PMG
will improve the quality of quarterly reports by integrating a number of tools aimed at shifting
attention from “reporting” to “monitoring” time-frames. To this end the PMG has developed
an Intranet page with monthly updates of Institutional and Complexes performances, and
dynamic maps linked to DARMS for the Knowledge Management Products (RBCSP and
CPRs). For completeness the COBS Intranet page publishes, every fortnight, updates on
budget implementation, for both the Administrative and Capital Expenditures. Final evolution
of this effort would be the creation of a dashboard for Management use (software function part
of the SAP Functional Upgrade Project). The historical quarterly budget implementation 20002009 is provided in annex 5.
Annex 6 provides the list of Institutional KPIs and yearly targets for the period 2010-2012.
The KPIs monitor Bank performance in terms of the effectiveness of internal processes and
the delivery of financial and knowledge products. They also serve as an input to the lower tier
of the Bank’s overall results measurement framework, which underpins Bank reporting on
ADF-11 commitments.
To facilitate regular and timely improvement of the monitoring framework, information about
Regional Integration, MICs and Fragile States operations will integrate the historical lending
volume KPIs. Some new KPIs have also been introduced at Complex level. However,
Management is keen to establish trend analysis and hence will maintain, for historical
benchmarking, previous years indicators over time. Management is also working to establish
reliable external benchmarking with other MDBs. (see Annex 7 for more details). A trend
comparison analysis offers some information: (i) average size of projects in the AfDB is much
smaller than in the other MDBs, (ii) AfDB lending growth is similar in pattern to experiences
in the other MDBs, (iii) AfDB disbursement volume is growing at a lower pace than in the
14
Ref. ADB/BD/WP/2006/129/Rev.1/add.2 -- ADF/BD/WP/2006/150/Rev.1/add.2
13
other MDBs - consequently, this will increase the ageing of the Bank portfolio, and (iv) AfDB
efficiency gains, both for the Lending and the Disbursement processes, are comparable with
the others. Further analysis is necessary to enable Management make conclusive judgments on
these findings.
5.2
Productivity, Savings and Efficiency Gains
Indicators to monitor efficiency gains, some of them already in use, have been further refined.
The Table below shows an example of productivity indicators’ evolution since 2008 baseline.
The introduction of the TRS will facilitate the development of a baseline for the Bank’s
Knowledge Products. In a complementary development, the introduction of the WBS element
in the Bank’s ERP system will allow for those indicators to reflect actual costing of products,
thereby enabling Management to identify high value/low cost or low value/high cost activities.
Such information will inform efforts for better prioritization of the Work Programme and
scheduling of the various deliverables.
As shown in the Table 3 below, there is evidence that the Bank is utilizing resources in a more
optimal manner. Unit costs for the delivery of core products are coming down.
Table 3: Bank Group productivity indicators
Bank Group Indicators
Total Administrative Costs
Operational Costs
Staff Costs
Consultancy Costs
Per Million UA Lending (in UA ‘000)
2008
70
37.1
43.71
5.16
2009
61.92
34.49
38.1
3.67
2010
57.18
31.61
36.18
3.16
Per Million UA Disbursed (in UA ‘000)
2008
122.12
65.17
76.4
8.88
2009
120.85
67.32
74.36
7.34
2010
75.43
41.69
47.72
4.17
Further analysis of the average budgeted costs for the lending and disbursement processes for
the period since 2006 confirms there has been persistent improvement. For every UA million
lent, administrative expenses have been declining and will further drop from UA 73,130 over
2006-2008 to UA 52,780 during 2010-2012. The same analysis for every UA million
disbursed shows a decline from UA 124,450 in 2006-2008 to UA 67,800 in 2010-2012 as
shown in figure 3 below.
14
Figure 3: Productivity Indicators (3 years average rolling series in Thousand UA)
It is expected that, during the period 2010–2012, the Bank will continue to gain efficiencies
from process re-engineering in the following areas: (i) implementation of the automated
performance evaluations and HR strategy; (ii) leveraging bilateral and multilateral resources;
(iii) ICT investments as recommended by the Enterprise Architecture Study. Savings will be
obtained through (i) closer monitoring of Operations costs and the execution of capital
projects; and (ii) cost avoidance from effective management, prudent procurement and cost
containment of general expenses.
To sustain zero real budget growth for 2010, Management will consolidate on recent budget
growth and build upon the gains expected to be realized by the measures discussed in this
document. These measures relate to Work Programme delivery; performance evaluations and
sustainable HR strategy; increasing the value for money on IT and telecommunications
investments; and management of general expenses.
Work Programmes: Complexes have identified, in their 2010-12 Work Programmes, potential
redeployment and trade-offs, e.g: (i) a more cohesive approach in planning for ESWs with the
objective of producing one flagship report per country; and, (ii) integration of portfolio
reviews in CSP completion reports for strategically focused knowledge products. Such steps
will have an immediate positive impact on the mission and consulting budgets.
Expenditure Line Items: Under UA Budgeting, spending caps on line items will be removed
but enforced on total envelopes. Management will also strengthen fiscal discipline on
missions (through compliance with flight booking guidelines); consultants (by effective
negotiation); Annual Meetings (further reductions in number of staff participants and timely
bookings); clean-up of outstanding commitments; procurement (streamlined procurement
processes through effective use of e-procurement tools); staff compensation (benchmarking),
and office rent (through market reference point and decisions to buy or construct for cost
effectiveness).
15
Streamlining Business Processes: External and internal benchmarking mechanisms will be
employed to determine cost efficiency of services; and Management will initiate plans to
continually review the functional arrangements within Complexes for realignment to business
needs. Actions would be put in place to ensure that; (i) services remain cost-efficient; (ii) no
duplicated functions; (iii) services are relevant to core-business; (iv) service levels justify
their costs; and (v) economies of scale are achieved.
Mutually Agreed Staff Separation Programme (MASSP): As discussed in the 2009 – 2011
PBD, this Programme will be used for purposes of staff performance monitoring and
workforce management and will offer appropriate incentives to reduce overall long-term
spending. It will be continuously reviewed and applied to ensure effectiveness and efficiency
by eliminating any identified staff surpluses in a timely manner. In 2010, Management will
consider a voluntary separation package for grandfathered GS staff, to address issues around
diminishing motivation for this group of staff. In addition, individual departments will
undertake, with the facilitation of CHRM, skills assessment exercises to ensure that the skills
retained are appropriate for the MTS priority areas. The reallocation of budget resources
towards priority areas will probably require the separation of staff whose skills are no longer
needed. A specific request for funds for the implementation of a MASSP will be made in the
2011 Budget. This programme will support the separation of staff due to poor fit; skills
mismatch; skills erosion, as well as special cases where separation from the service is in the
best interest of both parties.
Leveraging on Decentralization: Within the decentralization framework, FOs are increasingly
involved in all aspects of the operational activities and they have been programmed to lead
more supervision missions and preparation of PCRs. Additional professionals will either be
transferred from Head Office or locally hired to ensure that the active portfolios managed by
FO based Task Managers will progressively increase from 14% in 2010 to 20% in 2012.
Recruitment functions have also been delegated to FOs, thereby avoiding travel costs of TRA
based staff to FOs.
IT and Telecommunication: Building on continued user confidence, video conferencing
facilities will be put to increasing use for interviews and meetings. Already, this has resulted
in 2009 year-to-date savings of approximately UA 580,000 through avoided travel and perdiem expenses.
Capital Budget: Building on the comprehensive clean up carried out in 2008, Management
will, through the ISSC and CIPSC, tighten the management of Capital Projects to ensure that
projects; (i) add value; (ii) life cycles are monitored for timely closure; and (iii) balances are
clawed back and redeployed elsewhere after completion or closure. Capital portfolio
performance is now monitored through KPIs and cost/benefit analysis will continue to guide
investment priorities.
5.3
Quality Assurance and Results Reporting
Strengthening quality assurance and results is also necessary to improve products and
services. To this end the Quality Assurance and Results Department is coordinating the
implementation of the Action Plan for Quality and Results (APQR). Work will continue in
several aspect of the APQR: (i) a Readiness Review tool to enhance Quality at Entry; (ii)
building the capacity of Field Offices’ staff for greater responsibility; (iii) strengthening the
results culture of the Bank; (iv) revamping policy, procedures and formats for timely projects’
completion; (v) automated results reporting system; and, (vi) output and outcome indicators
for operations to permit more effective evaluation and reporting. Management is aware of the
16
fact that the Performance Monitoring function, with its focus on performance, outputs and
outcomes; and the Quality and Results function, focused on results and impact; are looking at
different time-frames of the Bank activities and they complement each other. It is also
recognized that further effort is required to create a continuum within the monitoring
framework with the goal of covering the whole time-frame, i.e. activities/outputs/outcomes/
results/impacts and moving to a set of Indicators with more qualitative content.
6
ESTIMATE OF THE 2010-2012 BUDGETS
This section presents Management’s proposals for the 2010 administrative expenses budget to
fund the Bank’s overall Work Programme. As indicated in the Framework Paper,
Management has kept the budget flat in real terms (i.e. UA 253 million in 2009 prices).
However, after a price adjustment of 4.32% to cater for: (i) the impact of increased mission
travel and consultants costs; (ii) inflation on other costs such as employee related costs
(resettlement, recruitment), training and general expenses (rental, electricity, repair,
maintenance and communication); and, (ii) a full year budget for all authorised positions15, the
budget is proposed to increase to UA 264 million in 2010.
At the centre of the proposal is Management’s objective to make 2010 a year of consolidation
of the gains realized in 2008 and 2009, a period over which real budget and staffing level
cumulatively grew by 14.31% and 202 respectively (Annex 8). Hence, on the basis of the
2008-2012 MTS projections, which anticipated an average budget increase of 5% in real
terms every year (i.e. 25% over 2008-2012), a zero real growth in 2010 would leave 10.69%
for 2011 and 2012. It should, however, be noted that, despite the overall zero real growth in
2010, there would be some areas which will require scaling up.
Work is still underway on the Decentralization Roadmap, the Bank’s IT network and IT skills
profile and salary adjustment. Once ready, Management will discuss the findings and way
forward with the Board.
No salary increase is envisaged in 2010. Instead, the ongoing salary review has been
expanded to address a number of issues which have been pending for some time, among
them: i) competitive entry grades for PL staff; ii) dichotomy of salaries for new staff joining
compared to staff already on board, with new staff earning much higher salaries for equal
experience and qualifications than staff on board; and, iii) impact of inflation and exchange
rate variations in the various locations which the Bank now has staff. For the Field Office
staff, this is the 1st year of the new framework; hence further work is being carried out in
terms of selected comparators and new salary grids. Furthermore, this exercise will enable
Management, starting with the 2011 Budget, to ensure that proposals for staff salary
adjustments are approved by the Board prior to inclusion in the PBD.
6.1
Proposed Allocation Criteria
With a zero real budget for 2010, the proposed administrative budget envelope has been
allocated based on the following criteria:
-
Funding of Current Staff Positions - all existing authorised positions have been
budgeted for the full year. However, as is the case in 2009, the 2010 YP intake has
15
In the 2009 Budget, existing vacant positions (i.e. carried over from 2008) were funded for nine instead of
twelve months; requested new positions for 2009 were budgeted for 6 months. The YPs were budgeted for three
months.
17
been budgeted for the last quarter of the year only;
-
Priority To Strategic Areas - funding levels are planned to be consistent with the
degree of priority proposed for the operational and institutional areas of focus. At
the same time, the indicative budget allocations to the Complexes also reflects
achieved performance, resources availability, and tradeoffs;
-
Availability Of External Funding - Bilateral and Multilateral Funds continue to
leverage Bank resources in supporting various aspects of the Work Programme, in
particular for Consultancy Services.
-
Historical Budget Utilization Rates - consideration has also been given to
demonstrated absorptive capacity of Complexes and delivery on the KPIs.
6.2
2010-2012 Administrative Expenses Budget and Major Cost Drivers
a)
Areas requiring additional capacity
The zero real growth objective notwithstanding, additional capacity, including in Human
Capital (see Annex 9), is anticipated in selected areas of focus such as: (i) Communication,
(ii) Risk Management, (iii) Decentralization, and (iv) Information and Technology Platform.
As described in sections 3 and 4 (IOP and INOP), the planned activities of these sectors will
enable the Bank to: i) deliver more efficiently; ii) enhance the control environment and
compliance to its fiduciary obligations; iii) scale up internal and external communication; and,
iv) strengthen the knowledge management platform.
b)
Cost drivers
The major cost drivers for the 2010 nominal budget increase by Category of Expenses are the
following (see Annex 10):
-
Staff Expenses: UA 15.02 million due to the full year budgeting of all the
authorised positions;
-
Facility Management: UA 1.84 million related to accommodation & office
occupancy (UA 0.88 million); and equipment/rental and maintenance (UA 0.96
million). Renting of the Berges du Lac Building (Zahrabed) generated additional
costs for equipment rental, repairs and maintenance, staff transportation between
the 3 sites, office equipment and supplies. Furthermore, prices for some
commodities such as electricity have gone up.
-
Meetings & Bank Business: UA 1.70 million - This amount is requested for the
Governors’ meetings i.e. the GCC (UA 0.47 million); the ADF replenishment (UA
0.59 million) and the Annual Meeting (UA 0.64 million).
-
RMC Training, Public Relations and Membership Fees & Contribution: UA 0.97
million.
-
IT, Treasury Information Systems Management and Indirect Borrowing Expenses:
UA 0.39 million.
-
Representation Expenses: UA 0.17 million.
18
Part of the above budget increases will be absorbed through tradeoffs, efficiency gains and
cost savings generated in several areas of the Bank, such as:
-
containment of consultants costs: UA 6.88 million: Most of Bilateral and
Multilateral Funds cover selected Operational activities. Consequently, taking
advantage of available Bilateral/Multilateral Funds, Departments and Units,
especially from Operations Complexes, have been encouraged to use Trust Funds
for at least 55% of their Consultants costs in 2010 (up from the planned 53% in
2009).
-
cost reduction for human resource management: UA 1.00 million – resulting from
the combined effect of: (i) the projected decline of the Recruitment & Assumption
of duty expenses (UA 2.02 million) – the number of vacancies has considerably
reduced and the Human Resource Management has improved its recruitment
process by using web-based tools. In addition, most of planned recruitment relates
to FOs in 2010 – and (ii) the increase in the Resettlement/Termination costs (UA
0.61 million) due to Departures of an important number of Executive Directors,
the Personnel residences security at HQ and TRA (UA 0.25 million) and the Social
welfare expenses (UA 0.1 million).
-
rationalization of the use of Temporary Staff/Short Term Staff (STS): UA 0.57
million – The use of Temporary staff/STS will be rationalized and reduced to a
minimum.
-
rationalization of missions and increased delegation of tasks to Staff in FOs: UA
0.48 million - the missions budget has gone down as a result of better planning by
the various HQ Units and increased use of FOs-based staff.
-
cost reduction of Publishing, Reproduction; External Audit Expenses and Legal &
Advisory Services Fees: UA 0.23 million.
The remaining part of the budget increase is compensated by the UA 10.93 million
corresponding to the 2010 nominal increase (4.32% over the 2009 budget).
6.3
6.3.1
Budgetary implications of the Indicative Work programme
Work Programme Adjustments
The original Complexes’ submissions were prepared in the context of a possible real budget
growth for 2010 as proposed in the 2009-2011 Programme and Budget Document. However,
following the decision on a zero real budget growth for 2010, Management adjusted the Work
Programmes and the budget allocation accordingly. More importantly, budget allocations
have been adjusted to ensure that resources are deployed towards programmes with the
highest impact and in strict alignment with the MTS.
To fit within the proposed budget envelop, the additional resources to support the scale up
programmes will come from efficiency gains and internal redeployments. In particular,
Management plans to re-prioritize planned deliverables and consolidate programs: - for
instance, Economic and Sector Work activities, where clustering is important for maximizing
synergies and results. In some cases, Management will constrain resources availability in
some Departments, in particular those which have seen significant growth in the recent past,
19
or whose contribution to the MTS objectives can still be achieved through internal
redeployments, or whose activities can be postponed to 2011 and 2012.
6.3.2
Estimates of Complexes’ Budgets
The section describes the budgetary implications emerging from the Work Programme
adjustments discussed in the preceding section. Figure 4 shows the consequent budget
evolution by Complex grouping. The detailed estimates of Complexes’ Budgets are given in
Annex 11.
Operational Complexes and OPEV: Overall funding to the four Operational Complexes and
OPEV is estimated at UA 137.20 million. ORVP will receive the largest share, UA 51.49
million, partly in reflection of the resource needs of the decentralization programme16.
Proposed allocation for OIVP amounts to UA 35.31 million, to support the Complex as it
manages the key MTS’ areas of focus. OSVP’s funding totals UA 32.63 million, to give the
Complex flexibility to increase funding for programmes relating to Fragile States and
Governance. Finally, ECON’s budget is projected at UA 13.7 million, with ADOA and efforts
to build capacity in RMCs receiving special attention.
It should be noted that, given budget fungibility, the SMCC will, throughout the year, review
allocations in the light of performance; resource pressures and unforeseen institutional
mandates.
Corporate Services, Units Reporting to the Presidency (UPRST), and the Boards: Total
funding for Corporate Services, Units Reporting to the Presidency and the Boards is expected
to increase by about UA 9.17 million. One source of budgetary pressure is a heavier workload
of Corporate Services that support the Board and priority operational areas. Whereas the
Budget for the Office of the President is projected to decrease by 5%, the budget for UPRST
is anticipated to increase, due to the enhancement of communication, security and risk
management functions; as well as expanded legal services. Furthermore, the Boards’ budget
will grow due to expanded activities foreseen for the 2010 Annual Meetings, rotation of
Members and the ADF-XII Replenishment and GCI-VI negotiations.
Finance Complex: In 2010, projected budget for Finance Complex will increase by UA 0.35
million (or 1.80% over the 2009 budget). Necessary internal budgetary adjustments through
reducing activities in non-priority areas and adopting cost saving and efficiency measures
such as those discussed in section 5.2 will be addressed.
16
However, it should be noted that the Decentralisation burden is distributed across several Cost Centres as Staff
in Field Offices are mapped to their respective Head Office Departments. For example, IT Technicians are
mapped to CIMM, Country Economists to Regional Departments, Investment Officers to OPSM, Disbursement
Officers to FFCO, Procurement and Financial Management Specialists to ORPF, etc.
20
Figure 4: 2010 Proposed Budget Allocations by Complex Grouping
Corp. Services & UPRST
UA 58 million
Finance
UA 20 million
Others **
UA 31 million
Operational Complexes & OPEV
UA 137 million
BGOV & BDIR
UA 18 million
** Includes Institutional Budget plus allocations for CBKHQ and SCOU
7
THE 2010-2012 CAPITAL BUDGET
7.1
Current Status of Implementation
Management has continued with the clean-up exercise for Capital Budget which started in
2008. This has led to the release of a total of UA 13 million as of 30 June 2009 (Ref: 2009
Mid Year Budget and Performance Report)17 out of which UA 11 million has been earmarked
to partly finance the Headquarters rehabilitation project.
The overall implementation rate on 30th September 2009 amounts to 73 % compared to 69%
in 2008.
7.2
Status of 2010-2012 Capital Budgets
The proposed Capital Expenditure Budget for the 2010-2012 period is expected to amount to
UA 83.2918 million – UA 28.78 million in 2010, UA 35.22 million in 2011 and UA 19.29
million in 2012 (see Table 4 below and details in Annex 12).
Within the total envelope of the proposed capital investment projects, UA 18.00 million (22%)
relates to the IT upgrades in areas of infrastructure improvement, storage area network and
SAP upgrade, telecom enhancement, and new equipment deployment. UA 22.52 million
(27%) is for Field Offices’ upgrade, out of which UA 20.65 million is earmarked for the
implementation of the Buy/Construct (Bank owned premises) Project19. UA 2.87 million
(3%) will be spent at the TRA, and the balance, UA 39.90 million (48%) is for HQ Building,
17 ADB/BD/WP/2009/137/Rev.1 - ADF/BD/WP/2009/102/Rev.1
18 UA93.54 million in 2010-12 Programme and Budget Proposals (Ref: ADB/BD/WP/2009/187 – ADF/BD/WP/2009/134 discussed by the Committee of the Whole on 2nd
November 2009. UA 10.25 million difference is due to the reduction in amount earmarked for Buy or Construct Bank owned premises from UA 30.90 million to UA 20.65
million for the 2010-2012 budgeting periods.
19
Implementation is subject to the Board’s approval of ADB/BD/WP/2009/156/Rev.1-ADF/BD/WP/2009/116/Rev.1 and Corrigendum on Lapse of Time basis.
21
Villas and Cité BAD renovation and rehabilitation in Abidjan.
The proposed Capital Budget has been subject to arbitration through the Information Systems
Steering Committee (ISSC) and Capital Investment Program Steering Committee (CIPSC).
Table 4: 2010-2012 Proposed Capital Investment Program (Amounts in UA Thousand)
Investment Type
Section 16 -- Office Equipment
Section 17 -- Office Furniture
Section 19 -- IT & Communications equipment
2009
approve
d
Budget
2009
Revised
Budget
2010
2011
2012
(a)
(b)
(c)
(d)
(e)
180
180
Proposed Budgets
100
150
Total
Proposed
Budget
2010-2012
FOs
(f)
(g)
100
350
TRA
HQ
(h)
(i)
IT
(j)
-
350
-
820
820
400
300
250
950
-
950
10,678
10,678
3,701
8,909
5,394
18,004
-
-
18,004
Section 20 -- Buildings & Civil Works
5,788
5,788
13,750*
24,800
13,200
61,750
20,650
1,200
Section 23 -- Other Projects
1,067
1,067
825
1,060
350
2,235
1,865
370
-
18,533
18,533
28,776
35,219
19,294
83,289
22,515
2,870
39,900
18,004
27%
3%
48%
22%
Total
Percentages
39,900
*Includes building/buying premises for Nigeria and Angola Field Offices
IT Capital Budget: Within the UA 18.00 million earmarked for IT upgrades, the following
major allocations apply; 50% has been earmarked for organizational effectiveness, including
enterprise architecture study, upgrading IT architecture and deployment of new equipment,
infrastructure improvements, and SAP functional upgrade; 16% is associated with knowledge
management, which includes enhancement of the Data Development Platform for ESTA and
the corporate data warehouse software systems; 20% will support decentralization efforts
through BITS extension and provision of additional equipment to Field Offices; and 13% is
intended for the enhancement of IT security and risk management through the acquisition of
analytical and modelling software (calculation engines) for the Summit System, project risk
and rating systems, enhancement of network cabling and monitoring systems. Also included in
the proposed IT capital budget for effective communication and secured connectivity are
requirements for corporate conference services, server consolidation, PABX & VSAT, and
INTERNET/INTRANET enhancement.
8
REHABILITATION OF THE HEADQUARTERS IN ABIDJAN
The Capital budget approved by the Board in June 2009 for the Headquarters rehabilitation
amounted to UA 47 million. Of this amount, UA 11 millions is from approved redeployment
from existing capital projects and is available for immediate use. The balance of UA 36
million is programmed as follows (in UA):
2010
2011
2012
15 million
15 million
6 million
The rehabilitation is scheduled to last for two years, starting from May 2010, and will require
the relocation of Abidjan based staff to a temporary location at an estimated cost of UA
150,000 per year. However this operation is estimated to be cost-neutral because the savings
(estimated at UA 200,000) to be generated from terminating some services and maintenance
contracts, and reduction in the usage of some public utilities will be used to finance the rent of
the temporary premises.
22
9
RESOURCE ESTIMATES
9.1
Internally generated resources
Operational and Net Income Estimates
9.1.1
Assumptions
The Bank Group’s net income estimates for 2010-2012 are based on assumptions summarised
in Annex 13(a).
The 2010–2012 projections in Annex 13(b) assumed lending levels for the Bank Group (see
para 3.2.3) and also took into account the Bank Group’s responses to the financial crisis. ADB
approvals for 2010 are projected to be around UA 4.145 billion, while ADF and NTF are UA
1.441 billion and UA 20.0 million respectively.
9.1.2
Sharing of Administrative Expenses by Institution
The Bank Group’s total administrative expenditures are shared among the three institutions
forming the Bank Group20.
The Bank Group’s budgeted administrative expenses amount to UA 253.1 million, UA 264.0
million, UA 280.5 million and UA 293.7 million for 2009, 2010, 2011 and 2012 respectively.
In 2010, UA 179.1 million shall be classified as operational expenses, UA 78.8 million as
non-operational expenses and UA 6.1 million as direct expenses.
Based on projections of each institution’s operational activities and relative size, the costsharing formula for joint expenditures is contained in Annex 13(c).
The allocation of the 2010 Bank Group Administrative Expenses by institution is provided in
Annex 13(d).
9.1.3
Operational and Net Income Estimates for 2010-2012 Period
Based on the assumptions in Annex 13(a), total operational income of the Bank Group will
vary between UA 448.2 million and UA 452.6 million over the next three years (Annex
13(e)). After providing for administrative expenditures, estimated net income is UA 183.4
million in 2010 and expected to decrease to UA 149.3 million in 2012, mainly due to the
expected deficit of the ADF resulting from a lower interest environment.
The projected net income for the Bank of UA 207.6 million in 2010, UA 197.3 million in
2011 and UA 177.4 million in 2012 compares favourably with the indicative planning range
of UA 80 million to UA 120 million. This places the Bank in a good position to continue to
strengthen its risk bearing capacity as well as maintain its net income transfers to the ADF
and for other developmental initiatives.
20
This is in accordance with an agreed pre-determined cost-sharing formula provided in an information note (ADB/BD/IF/99/330)
distributed to the Boards in November 1999. Management noted that loans cancelled as a result of MDRI will require continued
management, thereby leaving the volume of administered loans unaffected by MDRI.
23
The Net Operational & Net Income projections for 2009-2012 are summarized in Annex
13(e).
9.2
Bilateral and Multilateral Resources
Closer cooperation with the donor community and more transparent internal processes for
fund allocation will yield greater efficiency in the use of trust funds resources and help reduce
pressure on the Bank’s incomes. As a result, all available resources (internal, external, cofinancing, donor-funded Technical Assistants and Secondees) will be more readily available
to address additional financing needs.
To mobilize additional resources and expertise, the Bank had, as of April 2009, signed 65
cooperation agreements with 56 institutions and organizations. By September 2009, the Bank
has committed UA 7.2 million of Bilateral Trust Funds (approvals by donors) for use by the
different Complexes (see details in Annex 14). These funds will provide significant assistance
levels to regional member countries. The Bank will focus on increasing its resource
mobilization capacity by liaising with members of the donor community and progressively
securing their agreement to untie those bilateral Funds which still have restrictions.
The Bank will also champion the shift from bilateral funds to Multi-Donor Trust Funds. This
will be achieved through introducing new Thematic Funds – such as the Micro-finance Fund,
the Migration and Development Fund, the Governance Fund (2nd phase), the Science and
Technology Fund, and the South/South Cooperation Fund – and promoting the funding of
existing Thematic Funds, including the Fund for African Private Sector Assistance (FAPA),
Water Funds, NEPAD IPPF, Congo Basin Forest Fund and the African Fertilizer Financing
Mechanism.
The new SAP-based Trust Funds Management System, recently rolled-out across the Bank
(including Field Offices) and whose completion is expected by end of 2009, will help to
streamline the process and enable stricter monitoring of implementation progress, oversight
and fiduciary control.
The Bank will also reinforce its strategic cooperation with key stakeholders. In this regard, it
is envisaged from 2010 to move from an ad-hoc to a more structured Joint Secretariat between
AfDB, ECA and AUC. This Joint Secretariat Support Office (JSSO) will be established
according to the decision made by the Heads of the three institutions in June 2008 and will be
hosted by the ECA in Addis Ababa, Ethiopia. The JSSO will: i) service the meetings of the
Joint Secretariat; ii) serve as the focal point for coordinating the projects and programmes
between the three institutions; iii) facilitate consensus building, help determine the nature of
joint partnerships in which the three institutions would be involved; and, iv) take on
responsibility for knowledge sharing. The JSSO will also help to determine new and emerging
issues requiring strategic intervention by the three institutions. This last role is fundamental
given the close and growing working relations.
10
CONCLUSION AND RECOMMENDATIONS
Management invites the Board of Directors to consider the proposed 2010-2012 Work
Programmes; the associated resource requirements; and the indicative budget allocations.
Management considers 2010 as a year of consolidation of the acquired capacity and has opted
for a zero real growth budget. This leads to a nominal increase of 4.32 % for price adjustment
over the 2009 budget. However, in case of exceptional circumstances and based on
24
demonstrated capacity to deliver, Management might propose an adjustment of the
Programme and Budget Document during the mid-year review in July 2010. Nevertheless,
any additional resource request will remain within the MTS projections for 2008-2012.
As part of the transition to UA Budgeting and increased flexibility in resource management,
the Board is requested to approve the removal of the staff headcount control. By way of
compensatory control mechanism, rigorous staff planning and the principle of Fixed Cost
Ratio will be introduced.
Management’s proposals for 2010 for Board’s approvals consist of:
•
Administrative Expenses Budget of UA 264 million;
•
Capital Expenditure Budget of UA 28.78 million;
•
Contingency Budget of UA 2.64 million
The Boards of Directors are also invited to take note of (i) the indicative administrative
Budgets of UA 280.56 million and UA 293.68 million for 2011 and 2012 respectively and (ii)
projected capital budgets amounting to UA 35.22 million and UA 19.29 million for 2011 and
2012.
The Bank Group’s projected operational income of UA 452.6 million, UA 450.3 million and
UA 448.2 million for each of the three years, respectively, is adequate to sustain the proposed
Budget.
25
ANNEXES
Annex 1 -
Implementation of the 2009 Programme
Annex 2 -
Proposed 2010 Lending Programme
Annex 3 -
Detailed Sector Distribution of the Proposed 2010 Indicative Lending Programme
Annex 4 -
Progress made on approved budget reforms
Annex 5 -
Historical Quarterly Budget Implementation 2000 - 2009
Annex 6 -
List of Institutional KPIs and Targets for 2010-2012
Annex 7 -
Comparison with other MDBs
Annex 8 -
Staffing Level by Complex
Annex 9 -
Staff Allocation by Complex
Annex 10 - 2010 -2012 Budget Proposals by Category of expenses
Annex 11 - 2010 - 2012 Budget Proposals by Complex
Annex 12 - Proposed Capital Budget
Annex 13 - Operational and Net Income Estimates
Annex 14 - Trust Funds Utilization
25
ANNEX 1
Implementation of the 2009 Programme
Annex 1(a): Corporate KPIs and Performance as at End of November 2009
Key Performance Indicators (KPIs)
Unit
2009
Target
Achievement
November 2009
Implementation Rate
November 2009
Development Financing Operations
Total Bank Group Financing
UA million
4087
5316.17
130%
ADB Public Lending*
UA million
1347
2591.88
192%
ADB Private Lending
UA million
840
1074.25
128%
ADF Financing
UA million
1900
1650.04
87%
UA million
NA
7910.45
NA
UA million
UA million
UA million
NA
NA
NA
4271.30
1157.54
2481.61
NA
NA
NA
Number
Number
Number
10
15
21
16
7
19
160%
47%
90%
Number
92
47
51%
Total Bank Group Financing (Including All Financial
Instruments – 9 Dec 2009)
ADB Public Lending
ADB Private Lending
ADF Financing
Knowledge Management Products
New RBCSPs (1)
CSPs Related Documents (2)
CPRs
ESWs and Related Papers
Disbursements
Bank Group Disbursement Amount
UA million
3558
3464.40
97%
ADB Public Amount
UA million
593
1199.10
202%
ADB Private Amount
UA million
1883
686.37
36%
ADF Amount
UA million
1082
1574.52
146%
UA million
%
%
NA
30%
20%
4.41
26%
30%
%
%
50%
20%
64%
16%
%
%
40%
40%
35%
50%
%
%
5%
5%
11%
1.34%
Months
Months
%
12
13
40%
12.1
12.9
96%
%
%
100%
100%
63%
84%
%
%
%
%
30%
26%
35%
11%
27%
26%
42%
15%
%
%
%
%
%
95%
17%
60%
70%
33%
73%
12%
54%
64%
65%
NTF Amount
Bank Group Disbursement Ratio (Investment only)
ADB Public Disbursement Ratio
ADB Private Disbursement Ratio
ADF Disbursement Ratio
Portfolio Management
Projects at Risk
Operations Supervised Twice a Year
Projects Managed by Field Offices
Impaired Loan Ratio (Non-Sovereign only)
Process Efficiency
Lapse of time between approval and first disbursement
Lapse of Time for Bidding Completion (3)
Timely PCR Coverage
Cross-cutting Areas
Gender Mainstreaming in Operations (4)
Climate Proofed Projects (5)
Human Resources (PL)
Field Based (6)
Gender Balance
Staff Age Diversity (7)
Staff Premature Attrition Rate (8)
Budget and Expenses
Administrative Budget Implementation
Field Offices Expenses
Operations Expenses (9)
Fixed Staff Costs (10)
Capital Budget Implementation**
*
Botswana - The Economic Diversification Support Programme: UA 969 Million
The Competitiveness and Public Sector Efficiency Programme (CPSE): UA 437 Million are excluded
** HQ renovation included
and
Mauritius
-
1/5
(1)
New RBCSPs includes: RBCSPs, Joint Assessment Strategy Papers and Interim Review
Strategy Papers.
(2)
CSPs related Documents are: Mid-Term Review CSPs, Updated CSPs and Completion Reports.
(3)
This KPI will not be measured in the near future. ORPF department will refine the definition
and collect the relevant data.
(4)
% of new projects and new RBCSPs which identify at least 1 gender equality outcome indicator
in the logframe.
(5)
Percentage of Projects classified as climate sensitive which become climate proofed (their
climate resilience is increased by reducing their climate vulnerability).
(6)
Considered as % of Operational PL staff (PL staff in the 3 Operations Complexes + ECON PL
staff + PL staff in 100% Operational Units outside Operations Complexes
(ADB/BD/IF/99/330)).
(7)
% of PL staff under 45 years of age (excluding Board Officers)
(8)
% of PL leaving the Bank within the first 3 years of Contract in comparison to total PL leaving
the Bank in the same period.
(9)
Operations defined as ORVP, OIVP, OSVP, ECON, and 100% Operational Units outside
Operations Complexes (OPEV, GECL.1, FFMA.2, FTRY.4 and FFCO.3)
(10)
Fixed Staff Cost comprises salaries and benefits expenses.
2/5
Annex 1(b): Operations Complexes KPIs and Performance as at end of November 2009
Unit
2009
Target
Achievement
Nov. 2009
Implementation
Rate Nov. 2009
Number
Number
10
15
16
7
160%
47%
Number of CPRs
Number
21
19
90%
Number of ESWs and Flagship Reports
Sector Operations (OSVP)
ADB Public Lending
Number
27
23
85%
UA million
670
384.49
57%
ADF Financing
UA million
754
470.25
62%
ADB Public Disbursement Ratio
%
25%
30%
ADF Disbursement Ratio
%
20%
18%
%
50%
56%
Number
20
17
Indicator
Regional and Country Programs (ORVP)
New RBCSPs
CSPs Related Documents
Disbursement ratio for Policy Based Operations
ESWs and Flagship Reports
Projects Managed by Field Offices
%
7%
12%
Timely PCR Coverage
%
40%
77%
PCRs Backlog
%
75%
136%
Gender Mainstreaming in Operations
Climate Proofed Projects
%
%
15%
5%
84%
100%
Operations Supervised Twice a Year
%
40%
54%
% of Ageing projects (=> 8years)
%
10%
11.6%
Months
12
9.5
Lapse of time between approval and first disbursement
85%
Problematic Projects
%
8%
7%
Fragile States Assistance-Supplemental Support Window
%
33%
42%
Fragile States Assistance-Arrears Clearance Window
%
33%
83%
Fragile States Assistance-Targeted Support Window
%
33%
59%
UA million
747
2207.39
296%
Infrastructure, Private Sector and Regional Integration (OIVP)
ADB Public Lending
Private Sector Lending
UA million
840
1074.25
128%
ADF Financing
UA million
1703
1179.79
69%
15%
ESWs and Related Papers
Number
45
7
ADB Public Disbursement Ratio
%
25%
31%
ADB Private Disbursement Ratio
%
50%
64%
ADF Disbursement Ratio
%
17%
17%
Operations Supervised Twice a Year
%
40%
55%
Projects Managed by Field Offices
%
7%
25%
Impaired Loan Ratio (Non-Sovereign only)
%
>5%
>5%
Timely PCR Coverage
%
40%
100%
Gender Mainstreaming in Operations
%
15%
81%
Climate Proofed Projects*
%
5%
56%
Problematic Projects
%
7%
10%
Months
6
9.3
Months
12
18.5
Lapse of time between approval and first disbursement (for Private
Sector Projects)
Lapse of time between approval and first disbursement (for Public
Sector Projects)
* Projects as supplementary loans, rural electrification and transmission line categories are NON-RESILIENT, therefore not
applicable to this indicator.
3/5
Annex 1(c ): ECON and Support Complexes KPIs and Performance as at end of November
2009
Unit
2009
Target
Achievement
November
2009
Implementation
Rate November
2009
Knowledge Management and Research (ECON)
Lead in the assessment of economic performance and development
challenges
Number of countries covered
Number
143
100
70%
Participation by RMC's and other stakeholders in production
Number
31
25
81%
Partnership with RMC's and other stakeholders in dissemination
Number
12
12
100%
Enhancing knowledge sharing, dissemination and policy support
Number of seminars/conferences
Participation of Policy Makers and other stakeholders from RMC's
Number
Number
41
620
53
936
129%
151%
Benchmarking development outcomes ( N° of evaluated projects)
Number
30
29
97%
Mainstreaming results measurement and knowledge in Bank operations
(CSPs, ESW, Projects with results framework)
Number
19
17
89%
Number
Number
Number
12
5
10
18
13
7
150
260%
70%
Financial crisis weekly & quarterly reports
Number
52
97
187%
Briefs on financial crisis
Number
13
13
100%
Number
3
3
100%
Number
52
49
94%
Number
52
49
94%
Number
300
500
167%
Number of workshops
Number
20
18
90%
Number of RMC's personnel trained
95%
Indicator
Improving quality at entry; operational and development effectiveness
(ADOA/CSP/ESW)
Generate knowledge to assist the RMCs and the Bank in policy and
strategic planning Measurement and knowledge in Bank Operations
( CSP and ESW supported)
Number of studies, books and WPS
Policy briefs
Number of RMC statistical strategies & profiles prepared
Providing deeper understanding on issues surrounding global
economic and financial crisis
Primary source of key development data on RMCs (number of
primary databases developed and maintained in national accounts,
purchasing power parities, infrastructure statistics etc)
Number of new primary databases developed and maintained in national
accounts, purchasing power parities, infrastructure statistics etc
Provide leadership for statistical development work in RMCs
Number of RMCs requesting and receiving AfDB technical assistance in
various statistical domains
Number of RMCs adopting ADB methodological approaches
Enhance data dissemination within the Bank (intranet) and for
external clients (internet) via the web-based Data Platform
Number of users per month accessing Platform
Enhance quality of Bank Group operations And sensitization of
RMC's members on economic development issues
Number
755
715
Financial Management (FNVP)
Process loan applications received without any defect within 10 working
days
Process and send loan bills 6 to 8 weeks before their due dates
%
80%
67.85%
%
85%
100%
Settlement failure rate
%
1%
Cost of funds – base on US$ 6 Month Libor
%
Timely preparation of monthly financial highlights
%
0.32%
$Libor +5.75
bps
Base Rate+10bps Euribor -5 bps
CHF Libor
+29.75bps
95%
95%
4/5
Achievement
November
2009
1.34%
Implementation
Rate November
2009
Unit
2009
Target
%
5%
Gender Balance Index (PL staff)
%
26%
26%
Vacancy Rate (PL staff at post only)
Vacancy Rate (PL at post excluding elected personnel and staff attached to
the Board)
Vacancy Rate (PL staff at post and offers made and positions committed)
%
5%
13%
%
5%
13%
%
5%
4%
Field Based PL Staff
%
30%
27%
Operational PL Staff
%
60%
66%
HR Costs Per Capita
UA Thousand
10
9
90%
IT Costs Per Capita
UA Thousand
9
7.2
80%
Facility Management Costs Per Capita
UA Thousand
12
8.9
74%
Indicator
Impaired Loan Ratio (Non-Sovereign only)
Corporate Services (CSVP)
5/5
ANNEX 2
PROPOSED 2010 LENDING PROGRAMME
(Amounts in UA million)
Item
Country
Name
Sector
Dept
REGIO
NAL
DEPT
Project Title
Sector
Code
Sector Description
ADB
Public
ADB
Private
MIC
SRF
ADF
Loan
ADF
Grant
NTF
FSF
CoFinancing
Other
Trust
Funds
Total
Cost
Fin.
Instruments
I - PUBLIC SECTOR OPERATIONS - COUNTRIES
1
Algeria
ORNB
Assistance technique 1
KF0
Institutional Support
0.6
0.6
2
Algeria
ORNB
Assistance technique 2
KF0
Institutional Support
0.6
0.6
3
Angola
OINF
ORSB
Economic Infrastructure
Management Support Program
KF0
Institutional Support
10
10
LGA
4
Angola
OWAS
ORSB
RWSSI
E00
Water supply and
Sanitation
14
14
LLP
5
Benin
OINF
ORWA
Projet Ouidah-allada ndali
nikki chikandou
DB0
Transport
33.68
33.68
LLP
6
Benin
OSGE
ORWA
APPUI INSTITUTIONNEL
KF0
Institutional Support
5
GGI
7
Botswana
OSAN
ORSA
Agriculture Infrastructure
project
AA0
Agriculture
30
LLP
8
Botswana
OSGE
ORSA
Institutional Support to
NBFIRA
KF0
Institutional Support
1
1
MIC
9
Botswana
OSHD
ORSA
SUPPORT TO TVET AND
TERTIARY SCIENCE
EDUCATION (MIC)
IAE
Technical / Vocational
Education
0.6
0.6
MIC
10
Burkina
Faso
OSAN
ORWA
PPF-PAGERN-MOCOP
AA0
Agriculture
1
PPF
PROGRAMME D'APPUI A
LA STRATEGIE DE
REDUCTION DE LA
PAUVRETE (PSRP V)
K00
Multi-Sector
35
LSL
33
GLP
5
30
1
LGA
11
Burkina
Faso
OSGE
ORWA
12
Burundi
OINF
OREA
Gitega-Ngozi road project
DB0
Transport
K00
Multi-Sector
10
10
LSL
26
26
LSI
7
7
LSL
13.3
LLP
1
GGS
13
Burundi
OSGE
OREA
PROGRAMME D'APPUI
AUX REFORMES
ECONOMIQUES PARE III
14
Cameroon
OINF
ORCE
Programme d'électrification
FA0
Power Supply Electricity
15
Cameroon
OSGE
ORCE
PROJET DE
MODERNISATION DU
CADASTRE
KA0
Multi-Sector
OINF
ORWB
Extension Aéroport de Praia
DA0
Transport
OSAN
ORWB
Etudes Bassin Versant II
AA0
Agriculture
16
17
Cape
Verde
Cape
Verde
35
3
30
13.3
1
1/11
ANNEX 2
PROPOSED 2010 LENDING PROGRAMME
(Amounts in UA million)
Item
Country
Name
Sector
Dept
REGIO
NAL
DEPT
Project Title
Sector
Code
Sector Description
18
Centrafriq
ue
OSAN
ORCE
Projet d'appui à la
réhabilitation des
infrastructures rurales
AA0
Agriculture
19
Centrafriq
ue
OSGE
ORCE
Projet d'Appui Institutionnel
Multisecteur
KF0
Institutional Support
20
Chad
OSGE
ORCE
PROJET D'APPUI A LA
BALANCE DES
PAIEMENTS
KA0
Public Sector
Management
21
Comoros
OSHD
OREB
TRAINING FOR PRIVATE
SECTOR EMPLOYEES
IAE
Technical / Vocational
Education
22
Congo
OSGE
ORCE
Projet à l'amélioration du
Climat des affaires
KF0
Institutional Support
23
Côte
d'Ivoire
OSHD
ORWA
PROJET DE
DEVELOPPEMENT DES
RESSOURCES HUMAINES
IAD
Higher Education
24
Dem Rep
Congo
OINF
ORCE
Projet d'electricité
FA0
Power Supply Electricity
25
Dem Rep
Congo
OWAS
ORCE
RWSSI
E00
Water supply and
Sanitation
26
Dem Rep
Congo
OSGE
ORCE
K00
27
Dem Rep
Congo
OSGE
ORCE
28
Egypt
OINF
ORNA
29
Egypt
OWAS
30
Egypt
31
ADB
Public
ADB
Private
MIC
SRF
ADF
Loan
ADF
Grant
NTF
FSF
Other
Trust
Funds
Total
Cost
Fin.
Instruments
3.85
GLP
2.4
2.448
GGI
10
10
GSL
1
1
GLP
3.3
3.3
GGI
18.2
LLP
68.84
GLP
69
69
LLP
Multi-Sector
20
20
GSL
KF0
Institutional Support
10
10
GGI
Power Project 2010
FA0
Power Supply Electricity
200
LLP
ORNA
WSS Study
E00
Water supply and
Sanitation
0.6
MIC
OSAN
ORNA
West Delta Project - Phase II
AAC
Irrigation And Drainage
20
20
LLP
Egypt
OSAN
ORNA
Costal Protection Project
C00
Environment
20
20
LLP
32
Egypt
OSAN
ORNA
Pumping Stations
Rehabilitation Project
AAC
Agriculture and Rural
Development
100
100
LLP
33
Egypt
OSGE
ORNA
ECONOMIC POLICY
REVIEW- MIC
KA0
Public Sector
Management
1
MIC
34
Egypt
OSHD
ORNA
NURSING TRAINING
IB0
Health
50
LLP
Projet d'Urgence de
Renforcement des Ressources
Humaines
APPUI INSTITUTIONNEL A LA
DECENTRALIZATION
3.85
CoFinancing
18.2
8.84
200
0.6
1
50
60
2/11
ANNEX 2
PROPOSED 2010 LENDING PROGRAMME
(Amounts in UA million)
Item
Country
Name
Sector
Dept
REGIO
NAL
DEPT
Project Title
Sector
Code
Sector Description
K00
Multi-Sector
35
Egypt
OSGE
OREB
Financial Sector Reform
Support
36
Eq Guinea
OWAS
ORCE
RWSSI
E00
37
Eq Guinea
OSAN
ORCE
Support to Rural Infrastructure
Development Project
38
Eritrea
OSHD
OREB
OINF
39
Ethiopia
ADB
Public
ADB
Private
MIC
SRF
ADF
Loan
ADF
Grant
NTF
FSF
CoFinancing
Other
Trust
Funds
Total
Cost
Fin.
Instruments
645
645
LSL
Water supply and
Sanitation
30
30
LLP
A00
Agriculture and Rural
Development
30
30
LLP
Support to Higher Education
Development Project
IAD
Higher Education
14
14
GLP
OREB
Project Gilgel-Gibe Hydro
F00
Energy
61
232.5
LLP
K00
Multi-Sector
2
2
GGI
DB0
Transport
140
LSI
0.6
MIC
20
LSL
1
GGI
40
Ethiopia
OSGE
OREB
FINANCIAL SECTOR
TECHNICAL ASSISTANCE
PROJECT
41
Gabon
OINF
ORCE
Programme Routier - phase 2
42
Gabon
OWAS
ORCE
WSS Study
E00
Water supply and
Sanitation
43
Gabon
OSGE
ORCE
PARCI
K00
Multi-Sector
KF0
Institutional Support
171.5
140
0.6
20
44
Gambia
OSGE
ORWB
INSTITUTIONAL SUPPORT
PROJECT ADDITIONAL
45
Ghana
OINF
ORWA
Reconstruction of the Fulfuso
Juntion - Sawla Road)
DB0
Transport
65
65
LLP
46
Ghana
OINF
ORWA
GEDAP II
FA0
Power Supply Electricity
38
38
LLP
47
Kenya
OINF
OREA
Nairobi Light-Rail Transit
System
DC0
Transport
35
35
LLP
48
Kenya
OWAS
OREA
Nairobi River
E00
Water supply and
Sanitation
35
35
LLP
49
Liberia
OSAN
ORWB
Rice Value chain
AA0
Agriculture
5.72
GLP
KA0
Public Sector
Management
0.5
0.5
MIC
0.5
0.5
MIC
50
50
LSI
13.2
13.2
LLP
50
Libya
OSGE
ORNA
TECHNICAL ASSISTANCE
PROGRAM FOR ECON AND
FINANCIAL
MANAGEMENT
51
Libya
OSHD
ORNA
MIC- Technical Skills
Development for
Competitiveness
IAD
Higher Education
52
Madagasca
r
OINF
ORSB
Programme Routier 1
DB0
Transport
ORSB
PROJET DES JEUNES
ENTREPRENEURS
RUREAUX II
AA0
Agriculture
53
Madagasca
r
OSAN
1
5.72
3/11
ANNEX 2
PROPOSED 2010 LENDING PROGRAMME
(Amounts in UA million)
Item
Country
Name
Sector
Dept
REGIO
NAL
DEPT
Project Title
APPUI INSTITUTIONNEL PRIBG II
KF0
Sector
Code
Sector Description
54
Madagasca
r
OSGE
ORSB
55
Malawi
OINF
ORSB
Nkhata Bay-Muzuzu Rehab
DB0
Transport
A00
Agriculture and Rural
Development
ADB
Public
ADB
Private
MIC
Institutional Support
SRF
ADF
Loan
ADF
Grant
NTF
FSF
CoFinancing
Other
Trust
Funds
Total
Cost
Fin.
Instruments
11.5
11.5
GGI
14
14
LLP
5
5
LGS
20
20
GLP
8
8
LLP
20
20
LLP
56
Malawi
OSAN
ORSB
Shire Valley Irrigation ProjectFeasibility Study
57
Malawi
OSGE
ORSB
Poverty Reduction Support
Grant II (PRSG II)
KA0
Public Sector
Management
58
Mali
OINF
ORWB
Projet Carrefour de la Paix
point Y
DB0
Transport
59
Mali
OSAN
ORWB
Projet Sucrier de Markala
A00
Agriculture and Rural
Development
60
Mauritius
OSGE
ORSB
CAPACITY BUILDING
PROGRAMME FOR ADSL
K00
Multi-Sector
0.5
0.5
MIC
61
Mauritius
OSHD
ORSB
MIC - Regional
Multidisciplinary Centre of
Excellence
IAD
Higher Education
0.2
0.2
MIC
62
Mauritius
OSHD
ORSB
Health Sector Project
IB0
Health
63
Morocco
OINF
ORNB
Projet Extension Port
DD0
Transport
64
Morocco
OINF
ORNB
Référentiel des emplois et
compétences logistique &
transport
DZ0
Transport
65
Morocco
OWAS
ORNB
Projet de renforcement de
l'AEP de l'axe Rabat-Casa
E00
Water supply and
Sanitation
66
Morocco
OSGE
ORNB
PARAP IV
K00
Multi-Sector
67
Morocco
OSHD
ORNB
MIC- Etude 1 Strategique sur
le Secteur Education
IAD
Higher Education
68
Mozambiq
ue
OWAS
ORSB
RWSSI
EA0
Water Supply
69
Namibia
OSAN
ORSA
TANDJIESKOPPE GREEN
SCHEME PROJECT
A00
Agriculture and Rural
Development
70
Namibia
OSAN
ORSA
Acquaculture Development
Project
AA0
Agriculture
71
Namibia
OSGE
ORSA
MIC - Private Sector
Development Project
KB0
Private Sector
Management
72
Namibia
OSGE
ORSA
Budget Support
K00
Multi-Sector
ORSA
Support to ICT Skills
Development
IAD
Higher Education
73
Namibia
OSHD
20
20
LLP
100
100
LLP
0.6
MIC
180
180
LLP
90
90
LSL
0.6
MIC
5.7
LLP
30
30
LLP
10
10
LLP
1
MIC
400
400
LSL
15
15
LLP
0.6
0.6
5.7
1
4/11
ANNEX 2
PROPOSED 2010 LENDING PROGRAMME
(Amounts in UA million)
Item
Country
Name
Sector
Dept
REGIO
NAL
DEPT
Project Title
APPUI A
L'ENSEIGNEMENT
TECHNIQUE ET A LA
FORMATION
PROFESSIONNELLE
PROJET DE
DEVELOPPEMENT DES
INFRASTRUCTURES DE
SANTE
Sector
Code
Sector Description
ADB
Public
ADB
Private
MIC
SRF
ADF
Loan
IAE
Technical / Vocational
Education
IB0
Health
Capacity Building PPP
FA0
Power Supply Electricity
10
ORWB
RWSSI PROGRAMME
E00
Water supply and
Sanitation
3.5
OWAS
ORWB
TOWNS WATER &
SANITATION PROJECT
E00
Water supply and
Sanitation
Swaziland
OWAS
ORSA
Lavumisa Corridor Rural
Water Supply and Sanitation
Project
E00
Water supply and
Sanitation
Swaziland
OSHD
ORSA
Youth Employment Creation
I00
74
Niger
OSHD
ORWA
75
Niger
OSHD
ORWA
76
Nigeria
OINF
ORWA
77
Sao Tome
OWAS
78
Sierra
Leone
79
80
ADF
Grant
NTF
FSF
CoFinancing
Other
Trust
Funds
Total
Cost
Fin.
Instruments
15.83
6.17
22
LLP
5.63
5
10.63
LLP
10
LLP
2.5
6
LSI
4.2
19
GLP
20
20
LLP
Social
6
6
LLP
IB0
Health
2
2
LLP
45.5
45.5
LLP
14.8
81
Swaziland
OSHD
ORSA
Health Sector Development
Project
82
Tanzania
OINF
OREA
TRANSMISSION LINES
FAC
Power Supply Electricity
83
Tanzania
OWAS
OREA
RWSSI Phase II
E00
Water supply and
Sanitation
60
60
LLP
84
Tanzania
OSGE
OREA
KF0
Institutional Support
5.2
5.2
LGI
85
Tanzania
OSHD
OREA
I00
Social
20
20
GLP
KF0
Institutional Support
4.4
GGI
86
Togo
OSGE
ORWA
INSTITUTIONAL SUPPORT
TO GOOD GOVERNANCE
II
Small Entrepreneurs Loan
Facility Phase II
APPUI INSTITUTIONNEL
POUR LES REFORMES
ECONOMIQUES ET DE LA
GOUVERNANCE
4.4
87
Tunisia
OINF
ORNA
Etude TGV Nord Sud
DC0
Transport
1.2
MIC
88
Tunisia
OINF
ORNA
Railway Modernisation III
DC0
Transport
60
1.2
60
LLP
89
Tunisia
OINF
ORNA
Etude Electrification Ligne de
Borg Cedria-Gabes
DC0
Transport
4
4
MIC
90
Tunisia
OINF
ORNA
Etude Desserte Ferroviaire
Kairouan
DC0
Transport
0.6
MIC
91
Tunisia
OINF
ORNA
Road Project VI
DB0
Transport
175
LLP
0.6
175
5/11
ANNEX 2
PROPOSED 2010 LENDING PROGRAMME
(Amounts in UA million)
Item
Country
Name
Sector
Dept
REGIO
NAL
DEPT
Project Title
92
Tunisia
OINF
ORNA
CENTRE D'EXCELLENCE
GD0
Information and
Communica-tion
Technologies
20
20
LLP
93
Tunisia
OWAS
ORNA
Projet de Renforcement des
Capacités des Eaux de Sfax
E00
Water supply and
Sanitation
50
50
LLP
94
Tunisia
OSAN
ORNA
PDAI II
AA0
Agriculture
15
15
LLP
IAD
Higher Education
0.2
MIC
IB0
Health
50
50
LSI
I00
Social
20
20
LLP
I00
Social
20
20
LLP
MIC-Etude Strategique sur le
developpement des industries
culturelles
Appui aux Réformes du
Secteur de la Santé
Lutte contre les Maladies
Emergentes
Sector
Code
Sector Description
ADB
Public
ADB
Private
MIC
ADF
Loan
SRF
ADF
Grant
NTF
CoFinancing
FSF
Other
Trust
Funds
Fin.
Instruments
95
Tunisia
OSHD
ORNA
96
Tunisia
OSHD
ORNA
97
Tunisia
OSHD
ORNA
98
Tunisia
OSHD
ORNA
99
Uganda
OSHD
OREA
Support to Mulago Hospital
IB0
Health
40
40
LLP
100
Zambia
OINF
ORSB
Nacala Corridor Phase II
DB0
Transport
18
18
LLP
FAC
Power Supply Electricity
19
19
LLP
23
23
GSL
10
10
LLP
2
2
LGA
Promotion Exportation des
Services de Santé
101
Zambia
OINF
ORSB
Ithesi-Thezi transmission
Lines
102
Zambia
OSGE
ORSB
POVERTY REDUCTION
BUDGET SUPPORT III
K00
Multi-Sector
103
Zimbabwe
OINF
ORSA
Road Support Project
DB0
Transport
E00
Water supply and
Sanitation
104
Zimbabwe
OWAS
ORSA
RWSSI/ Power Studies
SUB-TOTAL I
0.2
Total
Cost
2585
0
10.9
0
911.4
247.7
0
105.9
0
7.7
3869
I I - PUBLIC SECTOR OPERATIONS - MULTINATIONAL
105
Multinational
OINF
ORWB
Construction Pont / fleuve
senegal a Rosso
106
Multinational
OINF
ORSB
Nacala Corridor Project
(Mozambique/Malawi)
DB0
Transport
107
Multinational
_ORCE
OINF
ORCE
Etude du projet Routier
Ouesso-Bangui-Ndamena
DB0
Transport
108
Multinational
_ORCE
OINF
ORCE
Etude Navigation fluviale
Oubangui-Congo-Sangha
DD0
Transport
DB0
Transport
30
30
GLP
100
LLP
4
4
GGS
4
4
GGS
100
6/11
ANNEX 2
PROPOSED 2010 LENDING PROGRAMME
(Amounts in UA million)
Item
Country
Name
Sector
Dept
REGIO
NAL
DEPT
Project Title
Sector
Code
Sector Description
109
Multinational
_OREA
OWAS
OREA
Lake Victoria Water and
Sanitation Program
E00
Water supply and
Sanitation
110
Multinational
_OREA
OSHD
OREA
SUPPORT TO REGIONAL
ICT CENTERS OF
EXCELLENCE
IAD
Higher Education
111
Multinational
_ORNA
OINF
ORNA
Center of ExcellenceTunisie
GD0
Information and
Communica-tion
Technologies
112
Multinational
_ORNA
OINF
ORNA
North Africa Backbone
GD0
Information and
Communica-tion
Technologies
SUB-TOTAL II
ADB
Public
ADB
Private
MIC
SRF
ADF
Loan
ADF
Grant
50
NTF
FSF
CoFinancing
Other
Trust
Funds
Total
Cost
Fin.
Instruments
50
LLP
15
GLP
15
15
LLP
10
10
LLP
15
25
150
53
228
III - PRIVATE SECTOR OPERTIONS
113
114
115
116
117
118
119
120
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
OPSM2
Social / Education
IA0
Education
14
14
LLP
OPSM2
Social / Health
IB0
Health
14
14
LLP
OPSM2
Agriculture and Rural
Development
A00
Agriculture and Rural
Development
10
10
LLP
OPSM2
Agriculture and Rural
Development
A00
Agriculture and Rural
Development
10
10
LLP
OPSM2
Agriculture and Rural
Development
A00
Agriculture and Rural
Development
10
10
LLP
OPSM2
Agriculture and Rural
Development
A00
Agriculture and Rural
Development
10
10
LLP
OPSM2
Agriculture and Rural
Development
A00
Agriculture and Rural
Development
10
10
LLP
OPSM2
Agriculture and Rural
Development
A00
Agriculture and Rural
Development
10
10
LLP
7/11
ANNEX 2
PROPOSED 2010 LENDING PROGRAMME
(Amounts in UA million)
Item
121
122
123
124
125
126
127
128
129
130
131
132
133
Country
Name
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Sector
Dept
REGIO
NAL
DEPT
ADB
Public
ADB
Private
OPSM2
Industry, Mining & Quarrying
B00
Industry, Mining &
Quarrying
25
25
LLP
OPSM2
Industry, Mining & Quarrying
B00
Industry, Mining &
Quarrying
25
25
LLP
OPSM2
Industry, Mining & Quarrying
B00
Industry, Mining &
Quarrying
25
25
LLP
OPSM2
Industry, Mining & Quarrying
B00
Industry, Mining &
Quarrying
25
25
LLP
OPSM2
Industry, Mining & Quarrying
B00
Industry, Mining &
Quarrying
25
25
LLP
OPSM2
Industry, Mining & Quarrying
B00
Industry, Mining &
Quarrying
25
25
LLP
OPSM2
Industry, Mining & Quarrying
B00
Industry, Mining &
Quarrying
25
25
LLP
OPSM2
Industry, Mining & Quarrying
B00
Industry, Mining &
Quarrying
25
25
LLP
OPSM3
Infrastructure/ Transport
D00
Transport
25
25
LLP
OPSM3
Infrastructure/ Transport
D00
Transport
25
25
LLP
OPSM3
Infrastructure/ Transport
D00
Transport
25
25
EQY
OPSM3
Infrastructure/ Transport
D00
Transport
25
25
EQY
OPSM3
Infrastructure/ Transport
D00
Transport
25
25
EQY
NTF
FSF
Total
Cost
Fin.
Instruments
Sector Description
SRF
ADF
Grant
Other
Trust
Funds
Sector
Code
MIC
ADF
Loan
CoFinancing
Project Title
8/11
ANNEX 2
PROPOSED 2010 LENDING PROGRAMME
(Amounts in UA million)
Item
134
135
136
137
138
139
140
141
142
143
144
145
146
Country
Name
Africa Low
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Middle
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Sector
Dept
REGIO
NAL
DEPT
ADB
Public
ADB
Private
OPSM3
Infrastructure/ Transport
D00
Transport
25
25
EQY
OPSM3
Infrastructure/ water supply
and sanitation
E00
Water supply and
Sanitation
15
15
LLP
OPSM3
Infrastructure/ water supply
and sanitation
E00
Water supply and
Sanitation
15
15
LLP
OPSM3
Infrastructure/ Power supply
F00
Energy
30
30
EQY
OPSM3
Infrastructure/ Power supply
F00
Energy
30
30
EQY
OPSM3
Infrastructure/ Power supply
FA0
Power Supply Electricity
30
30
LLP
OPSM3
Infrastructure/ Power supply
F00
Energy
30
30
LLP
OPSM3
Infrastructure/ Power supply
FA0
Power Supply Electricity
30
30
LLP
OPSM3
Infrastructure/ Power supply
FA0
Power Supply Electricity
30
30
LLP
OPSM3
Infrastructure/ Power supply
FA0
Power Supply Electricity
30
30
LLP
OPSM3
Infrastructure/ Power supply
KB0
Private Sector
Management
30
30
LLP
OPSM3
Infrastructure/ Power supply
FA0
Power Supply Electricity
30
30
LLP
OPSM3
Infrastructure /
Communications
G00
Communications
20
20
EQY
NTF
FSF
Total
Cost
Fin.
Instruments
Sector Description
SRF
ADF
Grant
Other
Trust
Funds
Sector
Code
MIC
ADF
Loan
CoFinancing
Project Title
9/11
ANNEX 2
PROPOSED 2010 LENDING PROGRAMME
(Amounts in UA million)
Item
Country
Name
147
Afrique
OPSM3
148
Afrique
OPSM3
149
Afrique
OPSM3
150
Afrique
OPSM3
151
Afrique
OPSM3
152
153
154
155
156
157
158
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Africa Low
Income
Countries
Sector
Dept
REGIO
NAL
DEPT
Project Title
Infrastructure /
Communications
Infrastructure /
Communications
Infrastructure /
Communications
Infrastructure /
Communications
Infrastructure /
Communications
ADB
Public
ADB
Private
Communications
20
20
EQY
G00
Communications
20
20
EQY
G00
Communications
20
20
EQY
G00
Communications
20
20
EQY
G00
Communications
20
20
EQY
NTF
FSF
Total
Cost
Fin.
Instruments
G00
SRF
ADF
Grant
Other
Trust
Funds
Sector Description
MIC
ADF
Loan
CoFinancing
Sector
Code
OPSM4
Finance
H00
Finance
18
18
LLC
OPSM4
Finance
H00
Finance
18
18
LLC
OPSM4
Finance
H00
Finance
18
18
GTE
OPSM4
Finance
H00
Finance
18
18
EQY
OPSM4
Finance
H00
Finance
18
18
LLC
OPSM4
Finance
H00
Finance
18
18
LLC
OPSM4
Finance
H00
Finance
18
18
LLC
159
Afrique
OPSM4
Finance
H00
Finance
18
23
LLC
160
Afrique
OPSM4
Finance
H00
Finance
18
5
18
LLC
161
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
162
Afrique
OPSM4
Finance
H00
Finance
18
18
EQY
163
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
164
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
165
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
166
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
10/11
ANNEX 2
PROPOSED 2010 LENDING PROGRAMME
(Amounts in UA million)
Item
Country
Name
Sector
Dept
REGIO
NAL
DEPT
Project Title
Sector
Code
Sector Description
ADB
Public
ADB
Private
MIC
ADF
Loan
SRF
ADF
Grant
NTF
FSF
CoFinancing
Other
Trust
Funds
Total
Cost
Fin.
Instruments
167
Afrique
OPSM4
Finance
H00
Finance
18
18
EQY
168
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
169
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
170
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
171
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
172
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
173
Afrique
OPSM4
Finance
H00
Finance
18
18
GTE
174
Afrique
OPSM4
Finance
H00
Finance
18
18
GTE
175
Afrique
OPSM4
Finance
H00
Finance
18
18
GTE
176
Afrique
OPSM4
Finance
H00
Finance
18
18
EQY
177
Afrique
OPSM4
Finance
H00
Finance
18
18
EQY
178
Afrique
OPSM4
Finance
H00
Finance
18
18
EQY
179
Afrique
OPSM4
Finance
H00
Finance
18
18
EQY
180
Afrique
OPSM4
Finance
H00
Finance
18
18
EQY
181
Afrique
OPSM4
Finance
H00
Finance
18
18
GTE
182
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
183
Afrique
OPSM4
Finance
H00
Finance
18
18
LLC
SUB-TOTAL III
GRAND TOTAL
1,434
2,610
1,434
11
-
1,061
301
-
106
-
5
1,439
13
5,536
11/11
ANNEX 3
Detailed Sector Distribution of the Proposed 2010 Indicative Lending Programme (Amounts in UA million)
ADB Public
Sector
Infrastructure
Transport
Water Supply and Sanitation
Power
Communications
Finance
Social
Higher Education and Vocational Training**
Primary and Secondary Education
Health**
Other Social
Multisector (Including Budget support, Support to
reforms and Governance Support Projects)
Industry, Mining and Quarrying
Agriculture and Rural Development
Environment
Nbr
Amount
14
6
4
1
3
1,017
492
280
200
45
8
1
183
15
5
2
142
26
4
1,155
7
1
235
20
ADB Private
Nbr
Total ADB
Amount
22
6
2
8
6
32
2
540
150
30
240
120
576
28
1
1
14
14
1
8
6
Nbr
Amount
Other
ADF
Nbr
Grand Total
Amount
Nbr
Amount
Nbr*
Amount
Percent
73
29
18
17
9
33
25
12
1
9
3
2,666
1,049
572
880
165
581
354
87
14
207
46
48.2%
19.0%
10.3%
15.9%
3.0%
10.5%
6.4%
1.6%
0.3%
3.7%
0.8%
36
12
6
9
9
32
10
1
1
6
2
1,557
642
310
440
165
576
211
15
14
156
26
26
12
7
7
997
365
252
380
11
5
5
1
112
42
10
60
10
6
141
70
1
5
5
5
2
2
3
1
51
20
30
5
1,185
17
180
7
5
29
1,370
24.7%
200
60
8
13
1
200
295
20
5
45
2
5
8
20
1
200
345
20
3.6%
6.2%
0.4%
4,044
58
1,362
26
129
189
5,536
100.0%
TOTAL
34
2,610
71
1,434
105
* The number of loans and grants is higher than the real number of operations, due to some co-financing schemes.
** In the social sectors, Health appears to be favoured in 2010 as compared to Higher Education and Vocational Training. This is due to relatively important requests submitted by ADB countries such
as Tunisia and ADF countries such as Uganda. There is also one business opportunity in Health for the Private Sector Window. One should also note that, although Higher Education is a priority under
the MTS, it is not among the top priorities of ADF-11. Nonetheless, efforts are underway to prepare more Higher Education projects in both ADB and ADF countries and this will certainly result in an
increased demand further down the road.
1/1
ANNEX 4
Progress Made on Approved Budget Reforms
UA Budgeting and Fungibility: The key objective of the UA Budgeting framework is to
introduce greater efficiency, transparency and flexibility in the allocation and management of
resources. Presently, fungible budget expenditures include; staff salaries, mission,
consultancy, hospitality – bank staff, entertainment – non employees, and short term staff
expenses. However, till end of 2009, validation by COBS is a prerequisite for transfers within
these budget categories. With the introduction of UA budgeting from January 2010, COBS
will no longer validate transfers; instead, COBS will concentrate its attention on monitoring
efficiency and cost effectiveness of resources utilization. Given broader responsibilities,
VPUs are required to sharpen their resource management and monitoring skills.
Headcount Control: As outlined in Management’s last update to the Board on UA Budgeting
in July 200921 , the Board is requested to approve the elimination of headcount control from
January 2010. In its place; staff planning will be reinforced and fixed cost ratio (FCR)
introduced as compensating controls. These instruments will enable VPUs determine their
staffing needs and actions required to meet those needs, and, at the same time, mitigate the
potential risk of overspending on staff costs. The SMCC will provide oversight at the
institutional level.
Staff Planning: Undue restrictive controls (over authorized positions and expenditure lineitem budgets) will be removed so that Management can have more flexibility to decide on the
best use and mix of resources within allocated budget envelope. However, VPUs will be able
to hire staff subject to: (i) adherence with their staffing plans; (ii) availability of funds within
their allocated budget; and (iii) compliance with established FCR over the duration of a fiscal
year. Effective from January 2010, VPUs’ staffing plans will be updated monthly to cover the
next 12 months on a rolling basis, in order to determine budget availability and compliance
with FCR.22
In preparing and updating a staffing plan, VPUs will take the following into account: (i)
staffing needs of Work Programmes, in terms of the number, skills, experience, and grade
levels; (ii) expected turnover of staff on board arising from normal departures and retirement;
(iii) timing of expected turnover, and planned promotions and hires, taking into account the
expected time needed to complete hiring process; and (iv) CHRM guidelines on average
salaries for planned new hires and promotions.
In the unexpected circumstance of a request for unplanned additional staffing, the following
steps will be taken (before deciding on recruitment action):
a. update the VPU’s Staffing Plan;
b. recalculate the VPU’s FCR to confirm whether or not there is any change;
c. in case of change in the VPU’s FCR, recalculate Bank-wide FCR to ensure that there
is no change as shown in Annex 8(b); and
d. obtain SMCC approval.
21 Ref: ADB/BD/WP/2009/138 and ADF/BD/WP/2009/103
22
VPUs will be expected to prepare staffing plans covering 36 months, to support their strategic staffing objectives and the 3-year rolling budget framework.
1/3
Fixed Cost Ratio (FCR): Fixed costs are staff salaries and benefits, with overhead (i.e. rent,
occupancy, IT equipment, office furniture) that have direct correlation to staffing level. Fixed
costs, unlike variable costs (such as mission, consultancy and representation) do not, in the
short run, vary with Work Programme delivery. Fixed Cost Ratio (FCR) will, therefore,
determine the proportion of fixed costs to total budget (i.e. salary, benefits, overhead,
consultancy, mission, representation and STS). It is calculated as follows:
The FCR will be used as the primary tool, together with staff planning, to ensure that VPUs
maintain close oversight on staffing changes and total staff costs, and will also serve as a
forecasting tool to enable VPUs maintain flexibility and a reasonable balance between staff
related costs and other costs in utilizing their budget.
As a control mechanism, FCR will be calculated and managed annually at VPU levels and
will not be changed during 2010 unless there are exceptional changes in Work Programmes
and business conditions approved by the Board of Directors. Management will, therefore,
ensure that intra-VPU changes (if any) are compensated for within the VPU; and inter-VPU
changes compensated for in a manner that the Bank-wide FCR (as shown in Annex 8(b))
remains unchanged.
Time Recording System (TRS): Time recording system will be reintroduced with effect from
2010 to assist Management obtain more credible data on the cost of outputs, (i.e. products and
processes). To succeed, there is need for staff buy-in whilst the tool itself must be user
friendly and web enabled, and will record staff time against output codes. As a start, the TRS
will be implemented for PL staff in Operations Departments (including those in the Field
Offices). Once stabilized in this area, it will be extended to other staff and the NonOperations Departments. The intention is not to control or monitor how staff spend their
time, but to have reasonable costing data on Bank outputs and non-output-related activities.
With meaningful costing data, Cost Centre Managers will be assisted to; i) reasonably plan
and monitor costs of activities and outputs; ii) better understand spending patterns; and, iii)
facilitate identification of opportunities for efficiency improvements. It will also provide
support for budget management and as well as serve as an important tool for managerial
accountability.
Outstanding Deliverables
As we move towards the completion of the Budget Reforms approved by the Board in June
2007, the following are still outstanding, including highlights of issues that will be addressed
to ensure timely delivery:
Expansion of budget fungibility:
Decentralize benefits – Management is still reviewing the possibility of decentralizing, in the
future, part of staff benefits to the VPUs. Prior to this, Management will ensure there is strong
evidence of: (i) discipline on staff planning & recruitment procedures; and (ii) VPU budget
and resource management capacity.
2/3
Charge back system – This system will decentralize budget for some centrally managed
expenses to VPUs. This will require: (i) further cost/benefit analysis; and (ii) a more robust
information management system. As above, this is also subject to ongoing review by
Management.
Country budget management:
Under this arrangement, Country Work Programme related budgets will be managed by the
Regional Directors. This is conditional to: (i) further changes to the business processes; (ii)
significant restructuring of the delegation of authority matrix; (iii) better coordination across
Operations Complexes; and, (iv) strong resource management capacity Bank-wide.
3/3
ANNEX 5
Historical Quarterly Budget Implementation 2000 – 2009 (UA Million)
*2009 Q4 Forecast
1/1
ANNEX 6
List of Institutional KPIs and Targets for 2010-2012
Indicators
Unit
Baseline
UA million
Targets 2010-2012
2010
2011
2012
4087
4617
5340
6042
UA million
UA million
UA million
1347
840
1900
2500
1000
1117
1840
1050
2450
2202
1090
2750
Number
Number
Number
Number
10
15
21
92
21
25
22
42
16
11
28
34
9
26
14
29
Bank Group Amount (provisional targets)
UA million
3558
3500
4200
4800
ADB Public Amount
ADB Private Amount
ADF Amount
Bank Group Ratio (Investment only)
UA million
UA million
UA million
593
1883
1082
1300
700
1500
1600
800
1800
1900
800
2100
%
%
%
20%
50%
20%
20%
50%
20%
20%
50%
20%
25%
50%
25%
%
%
%
%
40%
40%
5%
<5%
40%
40%
14%
<5%
35%
40%
15%
<5%
30%
40%
20%
<5%
Months
Months
%
12
13
96%
12
10
75%
12
10
75%
12
10
75%
%
%
100%
100%
100%
100%
100%
100%
100%
100%
%
%
%
%
30%
26%
35%
11%
30%
27%
40%
11%
32%
28%
45%
11%
35%
30%
45%
10%
%
%
%
%
UA Million
%
%
95%
17%
60%
70%
95%
17%
60%
70%
100
55%
33%
95%
18%
60%
70%
125
55%
33%
95%
20%
60%
70%
150
55%
33%
I - Development Financing Operations
Total Bank Group Financing (1)
ADB Public Lending
ADB Private Lending
ADF Financing
II - Knowledge Management Products
New RBCSPs (2)
CSPs Related Documents (3)
CPRs
ESWs and Related Papers
III - Disbursements
ADB Public Disbursement Ratio
ADB Private Disbursement Ratio
ADF Disbursement Ratio
IV - Portfolio Management
Projects at Risk
Operations Supervised Twice a Year
Projects Managed by Field Offices
Impaired Loan Ratio (Non-Sovereign only)
V - Process Efficiency
Lapse of time between approval and first disbursement
Lapse of Time for Procurement
Timely PCR Coverage
VI - Cross-cutting Areas
Gender Mainstreaming in Operations (4)
Climate Proofed Projects (5)
VII - Human Resources (PL)
Field Based (6)
Gender Balance
Staff Age Diversity (7)
Staff Attrition Rate (8)
VIII - Budget and Expenses
Administrative Budget Implementation
Field Offices Expenses
Operations (9) Expenses
Fixed Staff Costs (10)
New untied trust funds (bilateral/multilateral)
% of Bank Operational consultancy committed by Trust Funds
Capital Budget Implementation
53%
33%
1/2
(1)
Excluding HIPC and ADB special assistance SRF& Other Grants.
(2)
New RBCSPs includes: RBCSPs, Joint Assessment Strategy Papers and Interim Review
Strategy Papers.
(3)
CSPs related Documents are: Mid-Term Review CSPs, Updated CSPs and Completion Reports.
(4)
% of new projects and new RBCSPs which identify at least 1 gender equality outcome indicator
in the log-frame.
(5)
% of new projects classified as climate sensitive which become climate proofed (their climate
resilience is increased by reducing their climate vulnerability).
(6)
Considered as % of Operational PL staff (PL staff in the 3 Operations Complexes + ECON PL
staff + PL staff in 100% Operational Units outside Operations Complexes
(ADB/BD/IF/99/330)).
(7)
% of PL staff under 45 years of age (excluding Board Officers)
(8)
% of PL leaving the Bank within the first 3 years of Contract in comparison to total PL leaving
the Bank in the same period.
(9)
Operations defined as ORVP, OIVP, OSVP, ECON, and 100% Operational Units outside
Operations Complexes (OPEV, GECL.1, FFMA.2, FTRY.4 and FFCO.3)
(10)
Fixed Staff Cost comprises salaries and benefits expenses.
2/2
ANNEX 7
Comparison with Other MDBs
2007 Data
Table 1.1
2008 Data
Table 2.1
MDB
No of
Staff
AsDB
2,443
No. in
Field
Offices
479
No of
Field
Offices
26
Field Office
Percent
Female
Percent
19.60%
29% PL
EBRD
1,349
297
32
22%
37%
IADB
1,745
516
26
29.60%
41.6% PL
AfDB
1,142
252
23
16.63%
23% PL
MDB
No of
Staff
No. in Field
Offices
AsDB
EBRD
IADB
AfDB
2,412
1,407
1,755
1,491
519
308
520
269
No of
Field
Offices
26
34
26
23
Field
Office
Percent
21.52%
21.89%
29.63%
18.04%
Female
Percent
Loans
value
(‘000UA)
Disbursement
(‘000UA)
Administrative cost
('000 UA)
per UA 1
Mill. Loan
Administr
a-tive cost
('000 UA)
per UA 1
Mill.
Disbursed
28%
33%
41
24% PL
Table 2.2
MDB
Table 1.2
MDB
Administrative
Expenses
(‘000UA)
No. of
New
Projects
AsDB
205
82
6,352*
4,276
EBRD
233
353
12,818
IADB
355
127
5,596
AfDB
176
100
Loans
value
(‘000UA)
3,100
57
15
571
WBMENA
Exchange rate: US $ and Euro to UA as at 12/2007
*Excluding bilateral and multilateral Trust Funds loans
Disbursement
(‘000UA)
Administrative cost ('000
UA) per UA 1
Mill. Loan
Administrative
Expenses
(‘000UA)
No. of
New
Projects
AsDB
234
86
7,052
5,914
33.18
39.57
32.27
Administrative cost ('000
UA) per UA 1
Mill.
Disbursed
47.94
EBRD
194
302
11,024
4,277
17.60
45.36
3,650
18.18
63.84
IADB
306
131
7,460
4,772
41.02
64.12
4,464
63.44
79.53
AfDB
186
133
3,528
1,861
52.72
99.95
69
17
1,008
492
68.45
140.24
1,616
63.65
108.91
409
99.82
139.36
WB-MENA
Exchange rate: US $ and Euro to UA as at 12/2007
*Excluding bilateral and multilateral Trust Funds loans
2008 Increased efficency* in Lending and Disbursing (2007 = 0)
WB‐MENA
AfDB
IADB
EBRD
AsDB
‐35.00
Administrative cost ('000 UA) x
UA 1 Mill. Disbursed
‐30.00
‐25.00
‐20.00
‐15.00
‐10.00
‐5.00
0.00
5.00
AsDB
EBRD
IADB
AfDB
WB‐MENA
‐8.37
‐18.48
‐15.41
‐8.96
0.88
* Measured as reduced costs x million Disbursed and Loaned between 2007 and 2008
1/1
ANNEX 8
STAFFING LEVEL BY COMPLEX
Annex 8(a): Charts of 2009 Staffing Level by Complex
Chart 2: Staffing Levels ‐ By Location
Chart 1: Staffing Levels ‐ Bank‐wide
1,914
1,776
1,914
1,776
1,593 MTS Line
1,479
1,492
1,376
1,186
1,086
728
690
400
422
2008
2008
2009
PL
GS
Total Staffing
2009
TRA/HQ
Field Office
Total Staffing
MTS Trajectory
Chart 4: Staffing levels - Operational Complexes
Chart 3: Staffing Level (Bankwide) ‐ By Grade and Location
430
1,914
1,776
234
248
213
986
235
73
222
79
506
477
OIVP
2008
HQ/TRA Based
213
200
187
899
433
2009
Field Based
Total Staffing
ORVP
2008
OSVP
ECON
2009
1/3
Chart 5: Staffing Levels - Other
Complexes
342
285
306
283
188
CSVP
199
FNVP
2008
OTHERS **
220
200
180
160
140
120
100
80
60
40
20
0
Chart 6: PL Staffing by Operational Priority Areas
78
82
73
32
79
39
14
13
2008
2009
Infrastructure
Higher Education
Knowledge Management
Governance
Private Sector
2009
Footnote: '** Includes all other complexes except BDIR
166
156
Chart 8: Operational PL Staff by Location
755
687
606MTS Line
567
556
503
199
184
2008
2009
TRA/HQ
Field Office
Total Operational PL
MTS Trajectory
** These include ORVP, OSVP, OIVP, ECON, and units and divisions
of non-operational Complexes whose work programmes are fully
operational namely: (i) OPEV, (ii) CRMU, (iii) GECL1, (iv) FFMA2, (v)
FFCO3, and (vi) FTRY4.
2/3
Annex 8(b): Fixed Cost Ratios by Complex
COMPLEX As of November 2009 2010 BDIR 92%
90% CSVP 86%
86% ECON 78%
84% FNVP 90%
93% OIVP 72%
80% ORVP 82%
86% OSVP 74%
77% OTHERS 87%
99% PRST & UPRST 82%
89% URBD 63%
71% BANK WIDE 80%
85% 3/3
ANNEX 9
Staff Allocation by Complex
HQ
GS
PL
Boards of Governors
Boards of Directors
Operation Evaluation
Sub-Total Special Appropriations
2009 Staffing (05/11/2009)
FO
PL
GS
HQ
Total
PL
2010 Projected Staffing
FO
GS
PL
GS
Total
54
17
71
18
9
27
-
-
72
26
98
54
19
73
18
10
28
-
-
Regional & Country Programs
Regional Departments
Policy and compliance
Procurement and Fiduciary Services
Sector Operations
Infrastructure, PS & Regional Integration
Sub-Total Operations
Knowledge Management & Research
Sub-Total Operations and Office of Chief Economist
118
66
31
21
152
166
436
52
488
37
26
6
5
40
32
109
27
136
104
84
20
43
50
197
197
174
153
21
174
174
433
329
37
67
235
248
916
79
995
123
69
33
21
157
172
452
55
507
41
27
7
7
40
33
114
28
142
133
98
35
46
55
234
234
179
157
22
179
179
Financial Management
Corporate Services
Institutional Governance & Corporate Management
Presidency
Communication Unit
Legal & Advisory Services
Other Units Reporting to PRST
& the Board*
Sub-Total Complexes staffing
88
137
131
8
11
36
85
149
103
9
8
12
5
-
21
25
-
199
311
234
17
19
48
92
138
152
8
15
41
88
150
108
9
8
13
5
-
21
25
-
72
29
101
476
351
40
85
243
260
979
83
1,062
206
313
260
17
23
54
76
74
-
-
150
88
78
-
-
166
356
337
5
46
744
382
346
5
46
70
6
-
1
77
91
6
-
1
985
506
202
221
1,914
1,053
522
239
226
779
98
2,040
Others (Incl.YPP,SCOU...)
Total
* Office of the COO, SEGL, OAGL, CRMU, SECU, TRIB, OPEV, COEO, COBS, OMBU
1/2
ANNEX 9
Staff Allocation by Complex
2011 Projected Staffing
HQ
FO
PL
GS
PL
Boards of Governors
Boards of Directors
Operation Evaluation
Sub-Total Special Appropriations
FO
GS
2012 Projected Staffing
HQ
FO
PL
GS
PL
Total
54
22
76
18
15
33
-
-
Regional & Country Programs
Regional Departments
Policy and compliance
Procurement and Fiduciary Services
Sector Operations
Infrastructure, PS & Regional Integration
Sub-Total Operations
Knowledge Management & Research
Sub-Total Operations and Office of Chief Economist
156
88
47
21
166
181
503
61
564
49
31
9
9
41
34
124
29
153
206
171
35
46
55
307
307
194
172
22
194
194
Financial Management
Corporate Services
Institutional Governance & Corporate Management
Presidency
Communication Unit
Legal & Advisory Services
100
146
192
8
22
47
90
158
120
9
10
14
5
-
21
25
-
72
37
109
605
462
56
87
253
270
1,128
90
1,218
216
329
312
17
32
61
115
87
-
-
Sub-Total Complexes staffing
438
368
5
46
Others (Incl.YPP,SCOU...)
112
6
-
1
1,190
560
312
241
Other Units Reporting to
PRST & the Board*
Total
FO
GS
Total
54
25
79
18
20
38
-
-
191
109
61
21
175
184
550
67
617
59
37
11
11
42
35
136
30
166
285
250
35
46
55
386
386
212
190
22
212
212
107
154
235
8
33
53
92
166
133
9
12
15
5
-
21
25
-
72
45
117
747
586
72
89
263
274
1,284
97
1,381
225
345
368
17
45
68
202
141
97
-
-
238
857
119
2,303
496
391
5
46
133
6
-
1
1,325
601
391
259
938
140
2,576
* Office of the COO, SEGL, OAGL, CRMU, SECU, TRIB, OPEV, COEO, COBS, OMBU
2/2
ANNEX 10
2010-2012 Budget Proposals by Category of Expenses (in UA Million)
Major Components
Direct Operating Expenses
Staff Related Cost of Which
2009.
Adjusted
Budget
2010
Budget
Increase
Over
2009
Increase
%
Contribution to the
Increase
2011
Budget
Increase
Over
2010
Increase
%
Contribution to the
Increase
2012
Budget
Increase
Over
2011
Increase
%
Contribution to the
Increase
(a)
(b )
(c=b-a)
(d=c/a)
(e=c/∑a)
(f )
(g=f-b)
(h=g/b)
(i=g/∑b)
(j )
(k=j-f)
(l=k/g)
(m=k/∑f)
196.95
204.20
7.26
3.68%
2.87%
220.26
16.06
7.87%
6.08%
224.93
4.66
2.12%
1.66%
5.93%
179.75
12.62
7.55%
4.78%
180.06
0.31
0.17%
0.11%
107.29
7.96
8.02%
107.47
0.18
0.17%
72.47
4.65
6.86%
72.59
0.13
0.17%
40.51
3.45
9.30%
44.87
4.36
10.75%
152.12
167.14
15.02
9.87%
Salaries
87.83
99.32
11.50
13.09%
Benefits
64.29
67.81
3.52
5.47%
Workload
44.83
37.07
(7.76)
-17.31%
21.35
14.55
(6.81)
-31.87%
14.26
(0.22)
-1.51%
19.62
5.36
37.61%
Short Term Staff
1.31
0.74
(0.57)
-43.57%
1.20
0.46
62.63%
1.20
(0.01)
-0.73%
Business Travel
20.92
20.36
(0.55)
-2.64%
23.53
3.10
15.16%
22.28
(1.25)
-5.31%
1.24
1.41
0.17
13.56%
1.52
0.10
7.42%
1.77
0.25
16.58%
44.80
45.87
1.07
2.39%
46.42
0.56
1.21%
53.95
7.53
16.21%
Human Resource Management
16.87
15.87
(1.00)
-5.90%
14.58
(1.29)
-8.12%
18.98
4.39
30.13%
Facility Management
17.26
19.11
1.84
10.68%
20.47
1.36
7.14%
23.49
3.02
14.73%
IT & Treasury Information System Mgt.
7.32
7.71
0.38
5.22%
8.08
0.37
4.79%
8.17
0.10
1.23%
Other Overhead (Publishing, Reproduction, etc)
3.34
3.18
(0.16)
-4.85%
3.29
0.11
3.46%
3.31
0.02
0.50%
11.33
13.94
2.60
22.96%
13.88
-0.06
-0.44%
14.80
0.93
6.67%
Meeting Bank Business
5.00
6.70
1.70
33.95%
6.35
(0.35)
-5.19%
6.80
0.45
7.09%
Audit, Legal & Advisory Service Fees
1.28
1.21
(0.07)
-5.56%
1.19
(0.02)
-1.94%
1.22
0.03
2.86%
Indirect Borrowing Expenses & Hedging Premium
1.01
1.02
0.01
0.99%
0.98
(0.03)
-3.19%
0.98
0.00
0.06%
RMC Training & Other Institutional Expenses
4.04
5.01
0.97
23.90%
5.35
0.34
6.83%
5.79
0.44
8.24%
253.08
264.00
10.93
4.32%
280.56
16.56
6.27%
293.68
13.11
4.67%
Consultants
Other Direct Expenses
Support Cost
Other Institutional General Expenses
TOTAL BUDGET
-3.07%
0.42%
1.03%
4.32%
1.31%
0.21%
-0.02%
6.27%
1.55%
2.68%
0.33%
4.67%
1/1
ANNEX 11
2010 – 2012 Budget Proposals by Complex (in UA Million)
2009 Adjusted Budget
Staff
Costs
Workload
Overhead
Total
Staff
Costs
Workload
2010 Proposed Budget
Increase in
Overhead Total
amount
Increase
%
Boards of Governors
Boards of Directors
Operation Evaluation
Staff Retirement Plan
Sub-Total Special Appropriations
9.95
1.82
17.65
29.41
1.37
1.69
3.06
3.54
0.86
0.57
4.98
3.54
12.18
4.08
17.65
37.45
10.57
2.36
19.76
32.69
1.35
1.16
2.50
5.20
0.82
0.56
6.57
5.20
12.74
4.07
19.76
41.77
1.65
0.55
(0.00)
2.11
4.32
47%
5%
0%
12%
12%
Regional & Country Programs
Regional Departments
Policy and compliance
Procurement and Fiduciary Services
Sector Operations
Infrastructure, PS & Regional Integration
Sub-Total Operations
Knowledge Management & Research
Sub-Total Operations and Office of Chief Economist
30.18
22.66
3.38
4.14
18.06
21.33
69.56
6.26
75.82
7.35
5.79
1.08
0.47
9.59
9.40
26.33
2.10
28.43
13.43
11.38
0.81
1.24
4.66
4.36
22.45
5.01
27.46
50.95
39.83
5.27
5.85
32.31
35.08
118.34
13.38
131.72
31.55
22.61
3.93
5.00
20.37
22.79
74.70
6.84
81.54
6.19
4.69
1.06
0.44
7.75
7.85
21.79
1.82
23.62
13.75
11.44
0.79
1.52
4.51
4.67
22.92
5.04
27.97
51.49
38.74
5.78
6.97
32.63
35.31
119.42
13.70
133.13
0.54
(1.09)
0.51
1.12
0.32
0.23
1.08
0.33
1.41
1%
-3%
10%
19%
1%
1%
1%
2%
1%
Financial Management
Corporate Services
Institutional Governance & Corporate Management
Presidency
Legal & Advisory Services
Communication Unit
12.23
19.44
16.73
1.85
3.87
1.20
9.82
48.39
1.54
3.63
5.75
1.01
1.59
0.83
2.32
10.92
5.77
5.29
5.40
0.50
1.44
0.36
3.10
16.46
19.54
28.36
27.87
3.36
6.90
2.38
15.23
75.77
13.28
20.14
20.27
2.10
4.79
1.71
11.68
53.70
1.30
3.54
3.88
0.64
0.79
0.73
1.73
8.73
5.31
4.88
5.61
0.46
1.38
0.69
3.09
15.80
19.89
28.57
29.77
3.19
6.96
3.13
16.49
78.23
0.35
0.21
1.90
(0.17)
0.06
0.74
1.26
2.46
2%
1%
7%
-5%
1%
31%
8%
3%
6.35
-
0.45
-
1.34
-
8.14
-
8.34
-
0.00
-
2.55
-
10.89
-
2.75
-
34%
-
159.99
42.85
50.24
253.08
176.27
34.85
52.89
264.01
10.93
4%
Other Units Reporting to PRST & the Board*
Sub-Total Complexes Budget
Institutional Cost (Incl. YPP, SCOU, Study Leaves,...)
Separation Package
Total Reference Budget
* Office of the COO, SEGL, OAGL, CRMU, SECU, TRIB, OPEV, COEO, COBS, OMBU
1/3
ANNEX 11
2010 – 2012 Budget Proposals by Complex (in UA Million)
2010 Proposed Budget
Staff
Costs
Workload
Overhead
2011 Proposed Budget
Total
Staff
Costs
Workload
Overhead
Total
Increase
in amount
Increase
%
Boards of Governors
Boards of Directors
Operation Evaluation
Staff Retirement Plan
Sub-Total Special Appropriations
10.57
2.36
19.76
32.69
1.35
1.09
2.43
5.20
0.82
0.56
6.57
5.20
12.74
4.00
19.76
41.70
9.78
2.52
20.99
33.30
1.35
2.20
3.55
4.61
0.76
0.61
5.98
4.61
11.89
5.33
20.99
42.83
(0.59)
(0.84)
1.33
1.23
1.13
-11%
-7%
33%
6%
3%
Regional & Country Programs
Regional Departments
Policy and compliance
Procurement and Fiduciary Services
Sector Operations
Infrastructure, PS & Regional Integration
Sub-Total Operations
Knowledge Management & Research
Sub-Total Operations and Office of Chief Economist
31.55
22.61
3.93
5.00
20.37
22.79
74.70
6.84
81.54
6.19
4.69
1.06
0.44
8.27
7.40
21.86
1.82
23.69
13.75
11.44
0.79
1.52
4.51
4.67
22.92
5.04
27.97
51.49
38.74
5.78
6.97
33.15
34.86
119.49
13.70
133.20
36.18
24.89
5.07
6.22
20.57
22.81
79.56
7.08
86.64
7.27
5.43
1.34
0.51
6.64
9.32
23.23
2.09
25.32
15.38
12.37
1.05
1.96
4.17
4.49
24.04
5.36
29.40
58.83
42.69
7.46
8.68
31.38
36.62
126.83
14.53
141.36
7.34
3.95
1.68
1.71
(1.76)
1.76
7.34
0.82
8.16
14%
10%
29%
25%
-5%
5%
6%
6%
6%
Financial Management
Corporate Services
Institutional Governance & Corporate Management
Presidency
Legal & Advisory Services
Communication Unit
Other Units Reporting to PRST & the Board*
Sub-Total Complexes Budget
13.28
20.14
20.27
2.10
4.79
1.71
11.68
53.70
1.30
3.54
3.88
0.64
0.79
0.73
1.73
8.73
5.31
4.88
5.61
0.46
1.38
0.69
3.09
15.80
19.89
28.57
29.77
3.19
6.96
3.13
16.49
78.23
13.48
20.74
21.98
2.07
4.83
2.02
13.06
56.21
1.65
2.26
4.76
0.70
1.35
0.47
2.24
8.66
5.17
4.90
6.11
0.44
1.32
0.96
3.39
16.17
20.30
27.90
32.85
3.21
7.50
3.46
18.69
81.05
0.41
(0.67)
3.08
0.02
0.54
0.33
2.19
2.82
2%
-2%
10%
1%
8%
11%
13%
4%
8.34
-
0.00
-
2.55
-
10.89
-
12.94
-
0.05
-
2.34
-
15.33
-
4.44
-
41%
-
176.27
34.85
52.89
264.01
189.09
37.58
53.89
280.56
16.55
6%
Institutional Cost (Incl. YPP, SCOU, Study Leaves,...)
Separation Package
Total Reference Budget
* Office of the COO, SEGL, OAGL, CRMU, SECU, TRIB, OPEV, COEO, COBS, OMBU
2/3
ANNEX 11
2010 – 2012 Budget Proposals by Complex (in UA Million)
2011 Proposed Budget
Staff
Costs
Workload
Overhead
2012 Proposed Budget
Total
Staff
Costs
Workload
Overhead
Total
Increase in
amount
Increase
%
Boards of Governors
Boards of Directors
Operation Evaluation
Staff Retirement Plan
Sub-Total Special Appropriations
9.78
2.52
20.99
33.30
1.35
2.20
3.55
4.61
0.76
0.61
5.98
4.61
11.89
5.33
20.99
42.83
9.88
2.54
21.03
33.45
1.35
2.86
4.21
4.97
0.83
0.75
6.55
4.97
12.06
6.15
21.03
44.21
0.36
0.17
0.81
0.04
1.38
8%
1%
15%
0%
3%
Regional & Country Programs
Regional Departments
Policy and compliance
Procurement and Fiduciary Services
Sector Operations
Infrastructure, PS & Regional Integration
Sub-Total Operations
Knowledge Management & Research
Sub-Total Operations and Office of Chief Economist
36.18
24.89
5.07
6.22
20.57
22.81
79.56
7.08
86.64
7.27
5.43
1.34
0.51
6.64
9.32
23.23
2.09
25.32
15.38
12.37
1.05
1.96
4.17
4.49
24.04
5.36
29.40
58.83
42.69
7.46
8.68
31.38
36.62
126.83
14.53
141.36
37.51
25.78
5.09
6.63
20.70
22.30
80.51
7.12
87.64
7.80
5.74
1.99
0.07
8.66
8.19
24.65
2.50
27.15
17.58
13.78
1.25
2.54
4.82
4.97
27.37
5.85
33.22
62.89
45.30
8.34
9.25
34.17
35.47
132.53
15.47
148.00
4.05
2.61
0.88
0.57
2.79
(1.15)
5.70
0.95
6.64
7%
6%
12%
7%
9%
-3%
4%
7%
5%
Financial Management
Corporate Services
Institutional Governance & Corporate Management
Presidency
Legal & Advisory Services
Communication Unit
Other Units Reporting to PRST & the Board*
Sub-Total Complexes Budget
13.48
20.74
21.98
2.07
4.83
2.02
13.06
56.21
1.65
2.26
4.76
0.70
1.35
0.47
2.24
8.66
5.17
4.90
6.11
0.44
1.32
0.96
3.39
16.17
20.30
27.90
32.85
3.21
7.50
3.46
18.69
81.05
13.47
20.89
22.49
2.08
4.87
2.41
13.13
56.85
1.94
2.58
5.59
0.80
1.58
0.57
2.64
10.11
5.74
5.69
7.20
0.50
1.52
1.20
3.99
18.63
21.15
29.16
35.28
3.38
7.96
4.18
19.76
85.59
0.85
1.26
2.43
0.17
0.46
0.72
1.07
4.54
4%
5%
7%
5%
6%
21%
6%
6%
Institutional Cost (Incl. YPP, SCOU, Study Leaves,...)
Separation Package
12.94
-
0.05
-
2.34
-
15.33
-
13.22
-
0.05
-
2.61
-
15.87
-
0.54
-
4%
-
189.09
37.58
53.89
280.56
191.16
41.51
61.00
293.68
13.11
5%
Total Reference Budget
* Office of the COO, SEGL, OAGL, CRMU, SECU, TRIB, OPEV, COEO, COBS, OMBU
3/3
ANNEX 12
Proposed Capital Budget
2010-2012 Bank Proposed Capital Investment Program (UA Thousand)
2010
TRA
HQ
FO
2011
IT
Total
2010
TRA
HQ
FO
2012
IT
Total
2011
TRA
HQ
FO
Total
IT
Total
2012
TRA
HQ
FO
IT
Proposed
(20102012)
IO
Section 16 OFFICE EQUIPMENT
100
-
-
100
150
-
-
150
100
-
-
100
350
-
-
350
100921
CGSP1-TRA Office Equipment
100
-
-
100
150
-
-
150
100
-
-
100
350
-
-
350
-
-
-
100916
Section 17 OFFICE FURNITURE
400
-
-
400
300
-
-
300
250
-
-
250
950
-
-
950
CGSP1-TRA Office Furniture
400
-
-
400
300
-
-
300
250
-
-
250
950
-
-
950
-
-
-
Section 19 IT & COMMUNICATIONS EQUIPMENT
-
-
-
3,701
3,701
-
-
-
8,909
8,909
-
-
-
5,394
5,394
-
-
-
18,004
100945
P8 FILENET Plateform DARMS Migration
-
-
-
50
50
-
-
-
-
-
-
-
-
-
-
-
-
-
50
18,004
50
100946
SERVER CONSOLIDATION PROJECT
-
-
-
-
-
-
-
-
378
378
-
-
-
100
100
-
-
-
478
478
100947
ADB CLIENT DESKTOP AUTOMATIC BACKUP
-
-
-
175
175
-
-
-
50
50
-
-
-
-
-
-
-
-
225
225
100942
ADB CORPORATE CONFERENCE SERVICES
-
-
-
-
-
-
-
-
291
291
-
-
-
111
111
-
-
-
402
402
100944
DEPLOYMENT OF IT EQUIPMENT
-
-
-
-
-
-
-
-
800
800
-
-
-
800
800
-
-
-
1,600
1,600
100934
Security Enhancement
-
-
-
-
-
-
-
-
64
64
-
-
-
64
64
-
-
-
129
129
100939
Telecom (PABX & VSAT) Enhancement
-
-
-
780
780
-
-
-
400
400
-
-
-
450
450
-
-
-
1,630
1,630
100940
Special Depts Hardware & Software acq
-
-
-
161
161
-
-
-
129
129
-
-
-
150
150
-
-
-
440
440
100935
KNOWLEDGE Mangt &Datawarehouse
-
-
-
-
-
-
-
-
225
225
-
-
-
258
258
-
-
-
483
483
100931
INTERNET/INTRANET
-
-
-
-
-
-
-
-
161
161
-
-
-
225
225
-
-
-
387
387
100932
CIMM0 - Enhancmnt of E-Recruitment & NPO
-
-
-
137
137
-
-
-
100
100
-
-
-
-
-
-
-
-
237
237
100933
GENERAL BANK SOFTWARE
-
-
-
-
-
-
-
-
64
64
-
-
-
64
64
-
-
-
129
129
100941
BROADBAND INTEGRATED TELECOMMUNICATIONS
-
-
-
-
-
-
-
-
900
900
-
-
-
400
400
-
-
-
1,300
1,300
100954
INTEX / ADCO
-
-
-
322
322
-
-
-
-
-
-
-
-
-
-
-
-
-
322
322
100951
Project Risk & Rating Assessment
-
-
-
-
-
-
-
-
150
150
-
-
-
150
150
-
-
-
300
300
100928
SAP FONCTIONNAL UPGRADE
-
-
-
-
-
-
-
-
500
500
-
-
-
934
934
-
-
-
1,434
1,434
100929
SURVEILLANCE &VERIFICATION SOFTWARE-OAGL
-
-
-
-
-
-
-
-
54
54
-
-
-
-
-
-
-
-
54
54
100938
NETWORK CABLING AND MONITORING
-
-
-
-
-
-
-
-
500
500
-
-
-
546
546
-
-
-
1,046
1,046
100930
ENHANCEMENT TO THE DDP System for ESTA
-
-
-
-
-
-
-
-
91
91
-
-
-
91
91
-
-
-
182
182
1N0023
Server for grid computing
-
-
-
26
26
-
-
-
-
-
-
-
-
-
-
-
-
-
26
26
1N0029
ABD IT Enterprise Architecture five prio
-
-
-
-
-
-
-
-
2,000
2,000
-
-
-
-
-
-
-
-
2,000
2,000
1N0030
IMPLEMENTATION OF OUTSOURCING
-
-
-
250
250
-
-
-
250
250
-
-
-
250
250
-
-
-
750
750
1N0026
INFRASTRUCTURE IMPROVEMENTS
-
-
-
800
800
-
-
-
1,000
1,000
-
-
-
300
300
-
-
-
2,100
2,100
1N0022
STORAGE AREA NETWORKING
-
-
-
1,000
1,000
-
-
-
800
800
-
-
-
500
500
-
-
-
2,300
2,300
1/2
2010
TRA
Section 20 BUILDINGS & CIVIL WORKS
2011
IT
Total
2010
TRA
HQ
FO
500
15,200
8,050
23,750
-
15,000
-
15,000
2012
IT
Total
2011
TRA
HQ
FO
400
16,500
7,900
24,800
-
15,000
-
15,000
Total
IT
Total
2012
TRA
HQ
FO
300
8,200
4,700
13,200
-
6,000
-
6,000
IT
Proposed
(20102012)
HQ
FO
1,200
39,900
20,650
61,750
-
36,000
-
36,000
1N0020
HQ - Renovation
100920
CGSP1-TRA Heating and AC systems
200
-
-
200
100
-
-
100
-
-
-
-
300
-
-
300
100918
CGSP1-TRA Office Building Outfitting
200
-
-
200
200
-
-
200
200
-
-
200
600
-
-
600
100913
CGSP1-TRA Electrical Works and Cabling
100
-
-
100
100
-
-
100
100
-
-
100
300
-
-
300
100925
Construction of NGFO Office
-
-
3,000
3,000
-
-
-
-
-
-
-
-
-
3,000
3,000
1N0032
Construction of AOFO Office
-
-
5,050
5,050
-
-
-
-
-
-
-
1N0018
FO-Buidling Acquis./construction-Phase2
-
-
-
-
-
-
7,900
7,900
-
-
4,700
4,700
1N0028
HQ-Rehabilitation Villas and Cité BAD
-
200
-
200
-
1,500
-
1,500
-
2,200
-
2,200
Section 23 OTHER PROJECTS
-
-
5,005
5,050
-
-
12,600
12,600
3,900
-
3,900
-
-
-
-
190
-
635
825
130
-
930
1,060
50
-
300
350
370
-
1,865
2,235
100958
SECU0-Security Warden/Cores System
90
-
-
90
80
-
-
80
50
-
-
50
220
-
-
220
100959
SECU0-FO Security equipment Batch 5
-
-
150
150
-
-
80
80
-
-
150
150
-
-
380
380
100917
CGSP1-TRA Building Fire Security
100
-
-
100
50
-
-
50
-
-
-
-
150
-
-
150
100912
CGSP1-FO Vehicles
-
-
100
100
-
-
600
600
-
-
-
-
-
-
700
700
1N0024
SECU0 ATR Security Equipment
-
-
185
185
-
-
100
100
-
-
50
50
-
-
335
335
1N0025
Information Security Protection Program
-
-
200
200
-
-
150
150
-
-
100
100
-
-
450
450
700
8,200
5,000
19,294
2,870
39,900
22,515
1,190
15,200
8,685
3,701
28,776
980
16,500
8,830
8,909
35,219
5,394
18,004
83,289
2/2
ANNEX 13:
OPERATIONAL AND NET INCOME ESTIMATES
Annex 13(a):
Assumption for Bank Group’s Net Income Estimates
The rate of return on ADB and ADF investments for each year is the weighted average
return on the held to maturity investment portfolio and the liquid investment portfolio. The
projected investment income for the Bank Group reflects future prospects based on current
volatile market conditions. For 2009, valuation gains were estimated taking into account the
September year to date valuation gains on the trading portfolio which were estimated to be
maintained until the end of 2009. Regarding the HTM portfolio, impairment estimate of
approximately UA 23 million was taken into account to reflect the credit deterioration of
some securities. This estimated impairment is subject to continuous review to reflect
ongoing changes in market conditions. Fair value gains or losses on borrowings and
associated derivatives were not taken into account in these projections.
The financial projections for ADF incorporate the estimated foregone income effect of the
MDRI debt cancellation initiative, but assume continued special purpose reporting.
The share of grants in ADF operations is assumed to remain at 30% through the period.
Future loan disbursements will be based on the historical disbursement profiles.
All borrowers in default status as at 30 September 2009 are assumed to remain in that status
throughout the period 2009-2012.
Provisioning for loan losses for ADB and NTF shall be calculated according to the revised
IAS 39 implemented as at January 1, 2005. ADF presents special purpose financial
statements and is not subject to provisioning.
1/4
Annex 13(b): Projected Bank Group Lending (UA millions)
2010
2011
2012
ADB
Public Sector
Private Sector
Total
2 645
1 500
4 145
1 780
1 110
2 890
2 016
1 276
3 292
ADF
1 441
2 450
2 750
NTF
20
20
20
Annex 13(c): Bank Group Cost Sharing Formula
2009
2010
2011
2012
ADB
ADF
26.89
71.60
27.03
71.48
26.97
71.54
26.97
71.55
NTF
1.51
1.49
1.49
1.48
Annex 13(d):
Allocation of Bank Group Administrative Expenses for 2010 (UA million)
Total
Budget
BUDGET PART
Total Bank Group Administrative Expenses Budget
Less Direct Administrative Expenses
ADB
ADF
NTF(*)
264.00
6.13
257.87
69.70
184.33
3.84
4.83
1.31
3.46
0.06
262.70
71.01
187.79
3.90
Direct Administrative Expenses
6.13
5.98
0.15
0.00
Non Shareable Depreciation (ADB only)
0.37
0.37
-
-
269.20
77.36
187.94
3.90
Sub-Total
Shared Depreciation
Total Shareable Expenses
Plus Direct Expenses:
Total Administrative Expenses
(*) In the event that the share of actual Bank Group Administrative expenditure attributable to NTF exceeds 20% of NTF gross income, the
excess over such percentage is borne by ADB.
2/4
Annex 13 (e)
Projected Net Operational & Net Income 2009-2012 (UA Million)
2009
ADB
ADF
2010
NTF
Total
ADB
ADF
2011
NTF
Total
ADB
ADF
2012
NTF
Total
Loan Income
325.1 67.1 0.9 393.1 363.3 85.7 1.2 450.2 391.8 93.6 1.6 487 Interest Inc. On Investments
1.1 264.2 182.2 71.1 1.1 254.4 - - - - - - 194.3 142.4 2 338.7 186.4 76.7 Net Loss/Gain from Investment &
Macro Hedge Swap
29.8 4.4 - 34.2 - - - Impairment on HTM Portfolio
-21.5 -10 - -31.5 - - 12 - - Other Income
Total Income
539.7 203.9 Financial Charges
Provision for Loan Losses
0 - 0.5 - 0.5 Operational Income
296.1 203.9 Total Admin. Expenditures
Net Income
9 243.6 Depreciation
2.9 234.6 Total Operational Expenses
Share of Administrative Expenses
2.4 12 - 12 746.5 561.7 162.4 - 12 - 12 726.4 586.0 164.7 2.7 - - 12 ADF
404.9 108.5 191 70 Total
2.1 515.5 1 262 - - - - - - - 12 3.1 789.5 0 331.6 12 753.4 607.9 178.5 NTF
- - 262.2 292.2 292.2 331.6 11.1 - 0.5 11.6 10.4 - 0.5 10.9 - 0.5 9.7 244.1 273.3 - 0.5 273.8 302.6 - 0.5 303.1 340.8 - 0.5 341.3 234.6 262.2 9.5 2.3 - ADB
502.4 288.4 162.4 0 1.8 452.6 283.4 164.7 0 2.2 9.2 450.3 267.1 178.5 2.6 448.2 72.1 180.6 0.6 253.3 75.6 187.9 0.5 264 80.9 199 0.6 280.5 84.5 208.5 0.7 293.7 5.2 - 5.2 5.2 - 5.2 5.2 - 5.2 5.2 - 5.2 77.3 180.6 0.6 258.5 80.8 187.9 0.5 269.2 86.1 199 0.6 285.7 89.7 208.5 0.7 298.9 218.8 23.3 1.8 -25.5 1.3 -34.3 1.6 -30 1.9 149.3 243.9 207.6 183.4 197.3 164.6 177.4 3/4
4/4
ANNEX 14
Trust Fund Utilization
Annex 14(a): Approvals by Donors 01 January - 4 November 2009
N°
1
2
3
4
5
6
7
8
9
10
11
12
13
14
DONOR
Denmark
Sweden
Nigeria
Canada
China
Spain
India
France
United Kingdom
Korea
Portugal
Japan
Finland
Switzerland
TOTAL
AMOUNT (UA)
95,213
137,321
286,485
666,966
246,453
211,373
485,429
796,503
1,014,545
1,094,010
669,833
1,237,728
1,386,246
118,323
8,446,427
PERCENTAGE
1.13%
1.63%
3.39%
7.90%
2.92%
2.50%
5.75%
9.43%
12.01%
12.95%
7.93%
14.65%
16.41%
1.40%
100%
NUMBER OF
REQUESTS
1
2
4
8
3
1
3
5
5
7
6
5
6
1
57
Annex 14 (b): Commitments by Organizational Units 01 January - 4 November 2009 N°
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
User Department
EADI
EDRE
ERCU
ESTA
ICT4D
OINF
OPSM
OREA
ORCE
ORPC
ORPF
ORQR
ORRU
ORSB
OSAN
OSGE
OSHD
OSUS
OWAS
TBD
ORVP
TOTAL
Approved
Amount (UA)
705,199
700,707
149,866
10,520
401,319
1,388,676
433,787
520,147
651,992
134,554
142,521
290,673
224,447
136,149
874,517
534,335
64,158
742,210
118,323
190,400
31,927
8,446,427
Percentage
8.35%
8.30%
1.77%
0.12%
4.75%
16.44%
5.14%
6.16%
7.72%
1.59%
1.69%
3.44%
2.66%
1.61%
10.35%
6.33%
0.76%
8.79%
1.40%
2.25%
0.38%
100%
Number of
Approved Requests
5
5
1
1
2
6
4
2
3
2
2
3
2
1
4
5
1
4
1
2
1
57
1/2
Annex 14(c ): Approvals by Thematic Funds (as of November 04th, 2009)
DONOR
N°
1
AWF (African Water facility) Fund
2
3
AMOUNT (UA)
Percentage
Number of
Requests
11,168 030
45.89%
8
NEPAD IPPF (Infrastructure Project Preparation Fund)
2,948,301
12.12%
9
FAPA (Fund For African Private Sector Assistance)
3,619,795
14.87%
7
4
RWSSI (Rural water Supply and Sanitation Initiative)
6,358,595
26.13%
1
5
MDWPP (Multidonor Water Partnership Programme)
240,044
0.99%
1
24,334,765
100%
26
TOTAL
Annex 14(d): Breakdown of the Above Approvals by Coordinating Technical Department
(As of November 4th, 2009)
Coordinating
Department
N°
AMOUNT (UA)
Percentage
Number of
Requests
1
OWAS
17,766,669
73.01%
10
2
ONRI
2,948,301
12.12%
9
3
OPSM
3,619,795
14.87%
7
24,334,765
100%
26
TOTAL
2/2
Download