CAMPUS PHYSICAL DEVELOPMENT PLAN 2011 – 13 Capital Budget UW-Stout Campus Physical Development Plan 2009-11 TABLE OF CONTENTS Chancellor’s Introduction .......................................................................... 1-1 Executive Summary ................................................................................... 2-1 I. Background ............................................................................................ I-1 A. Institution Profile ....................................................................................................... IA-1 B. Existing Conditions Map ............................................................................................ IB-1 C. Mission Statement .................................................................................................... IC-1 D. Strategic Goals.......................................................................................................... ID-1 E. Program Trends ........................................................................................................ IE-1 F. Planning Issues and Themes .................................................................................... IF-1 G. Space Needs Summary ............................................................................................. IG-1 II. Implementation Plan ............................................................................. II-1 A. B. C. D. Near Term Development Plan ................................................................................... IIA-1 Prioritized Project Requests ...................................................................................... IIB-1 Project Sequence Chart ............................................................................................ IIC-1 Origin/Destination Chart ............................................................................................ IID-1 III. Facilities Profiles .................................................................................. III-1 A. Building Profiles ........................................................................................................ IIIA-1 B. Site Development Profile ........................................................................................... IIIB-1 C. Site Utility Profile ....................................................................................................... IIIC-1 5/20/2010 Table of Contents TOC - 1 CHANCELLOR’S INTRODUCTION The University of Wisconsin-Stout has been designated as Wisconsin’s Polytechnic University by the UW System Board of Regents. I am proud to say that the university has incorporated that designation into its strategic planning and we are seeing tangible results already. The four pillars of that transformation are: The Discovery Center. This center opened in July 2009 with the help of an endowed chair established by a generous donor. It is harnessing the tremendous research and innovation potential of our faculty, staff and students to help business and industry solve their problems and grow Wisconsin’s economy. I am confident our Discovery Center will be model for other similar efforts in Wisconsin and the Midwest. The Center for Applied Ethics: This center, again with the help of an endowed chair established by a generous donor, is intended to assist our faculty in infusing ethical instruction into their curriculum. This is the only Ethics Center of its kind among Wisconsin comprehensive universities and is addressing a critical need in today’s society. The UW-Stout Curriculum Incubation Center: This center brings faculty and staff together to develop new undergraduate and graduate majors for UW-Stout. At the outset, UW-Stout had a very limited program array; thanks in large part to the center, we now offer undergraduates choices from among 40 majors, including some very innovative programs that are attracting high-achieving high school graduates. A revitalized Honors Program: We are building our Honors Program rapidly and have begun discussions about whether this program should become a stand-alone college. The polytechnic designation followed two decades of inspired innovation at UW-Stout that also included the university becoming the only UW System institution to provide a laptop computer to all undergraduate students. We offer modern, mediated learning centers, and we are committed to using modern technology for all education and business functions. Lab-based experiences are provided for the majority of students in all programs. We are now in the process of growing our applied sciences programs far beyond what has been seen on campus previously. We opened a brand new Jarvis Hall Science Wing in September 2009 and will have a remodeled part of that wing for the 2010-11 academic year. We are attracting hundreds of applied science majors to campus to study in the new science building and to prepare for exciting careers in medicine, pharmacy, dentistry and other professions. Our campus has seen many other physical changes recently, including a remodeled Price Commons cafeteria; Hovlid Hall Renovation and Dining Addition; and Harvey Hall Theatre Renovation. We are now preparing final plans for an $18 million remodeling of the Memorial Student Center. To ensure that UW-Stout remains at the forefront of innovation, we use an open, participatory strategic planning system that fosters continuous quality improvement. The campus recently concluded a Campus Master Planning Process that coordinated the planning of facilities, academic programs, utility infrastructure, land acquisition and campus services. We have prepared this Campus Physical Development Plan to help us continue with the type of inspired innovation that will be necessary for UW-Stout to thrive in the future. Charles W. Sorensen Chancellor UW-Stout Campus Physical Development Plan 2011-17 EXECUTIVE SUMMARY UW-Stout, Wisconsin’s Polytechnic University and 2001 Malcolm Baldridge National Quality Award recipient, is pleased to present its 2011-2017 Campus Physical Development Plan (CPDP). This plan is the result of much discussion, analysis, review and revision. The observations and recommendations included in the 2011-2017 Campus Physical Development Plan reflect this process and effort. Paramount to the development of the 2011-2017 Campus Physical Development Plan was the commitment of the campus to its goals; academic plan; issues and themes; and space needs. These are briefly summarized as follows: Strategic Goals UW-Stout is committed to its strategic goals. These include Enduring Goals and Focus 2015 (refer to Background Section D: Strategic Goals). The Enduring Goals, as evident in their name, reflect the campus’ continuous efforts to maintain and promote its challenging academic programs; active learning principles; excellence in teaching, research, scholarship and service; recruitment and retention of a diverse university population; fostering of a collegial, trusting and tolerant campus climate; safe, accessible, effective, efficient and inviting physical facilities; and responsive, efficient and cost-effective educational support programs and services. Focus 2015 concentrates on the preparation of students and graduates for success; the creation of a learning community that supports and encourages the engagement of its members in active learning; achieving national leadership and excellence in educating students in the theory and application of a broad range of technologies; strengthening on-campus organization by focusing on UW-Stout’s unique mission with the UW System; and creating a school outside the school enterprise that serves learners statewide, nationally and internationally. Program Trends UW-Stout is committed to its academic plan. An Academic Program Realignment became effective on July 1, 2008 and consists of four colleges: College of Arts, Humanities and Social Sciences (CAHSS); College of Education, Health and Human Sciences (CEHHS); College of Management (COM); and College of Science, Technology, Engineering and Mathematics (CSTEM). There are five (5) outcomes of this realignment: 1. Group similar programs, departments and disciplines together in units so they are better able to address common issues, share curriculum and resources, develop new programs, maximize capabilities, minimize duplication and work under common leadership. 2. Capitalize on trends and opportunities that have emerged over the past decade and position the campus for growth. 3. Align programs with an administrative structure that will strengthen UW-Stout’s mission and polytechnic identity and position UW-Stout among its national polytechnic peers. Expand technology transfer and outreach efforts to more fully realize regional economic growth and strengthen ties with external partners and stakeholders. 4. Develop an administrative structure of units that is more descriptive and understandable to both internal and external audiences, including potential faculty and staff hires, and provide greater brand identity to administrative and academic units. It is desirable to have an organizational structure that clearly explains who we are and what we do as an institution. 5. Provide a more coordinated approach to facilitate efforts of faculty and staff interested in interdisciplinary and collaborative programs including the Curriculum Incubation Center, Learning Communities, First Year Experience, Project Lead the Way and the University Honors Program. 5/20/2010 Executive Summary 2-1 UW-Stout Campus Physical Development Plan 2011-17 A coordinated approach is also needed to facilitate joint appointments, team teaching, facultystudent research initiatives and faculty involvement in Student Services initiatives. While academic planning is constantly evolving, it aids in the development of the Campus Physical Development Plan by identifying academic and space program needs. UW-Stout offers many unique programs not available at other UW System campuses. There are currently forty (40) undergraduate and nineteen (19) graduate programs at UW-Stout. There are four (4) developing programs (refer to Background Section E: Program Trends). A developing trend is the implementation of a customized instruction program which offers courses to students who are primarily on line or at a distance from campus. This “school outside the school” program is delivered in more non-traditional methods and formats and is customized for the student. Planning Issues and Themes UW-Stout is committed to addressing its planning issues and themes. Nine (9) major issues and six (6) continuing themes have been identified by the campus. The issues primarily focus on major building renovation and addition projects including: Harvey Hall; Bowman Hall; Home Economics; Recreation and Athletic Facilities; Student Health Services; Robert S. Swanson Learning Center; residence halls; University Centers (Memorial Student Center and Merle M. Price Commons); and campus parking. Continuing themes include: classroom size, quality and adequacy; older building infrastructure; consolidation of similar functions and availability to the public; telecommunications infrastructure; sustainability; and life safety and accessibility (refer to Background Section F: Planning Issues and Themes). Space Needs UW-Stout has identified, documented and planned its space needs by focusing on utilization and efficiency. A Campus Space Audit, Inventory and Utilization Study was completed by campus planning in the spring of 2007 and addressed facility use of all buildings relating to efficiency, availability, appropriateness, condition and flexibility of space. By improving general assignment utilization of classrooms and laboratories, much square footage will become available to address other space needs. The campus feels that this will allow anticipated space growth needs to be accommodated within existing building space. This includes programmatic space for the Masters of Fine Arts in Design, Discovery Center and Military Science. The exception to this is the demand for additional space in the Sports and Fitness Center. This has been estimated to be 100,000 ASF (refer to Background Section G: Space Needs Summary). Near Term Development Proposed Major projects include: 2011-2013: Harvey Hall Renovation – Phase II Infrastructure Fleming Hall Renovation 2013-2015: Bowman Hall Remodel North Hall Renovation 2015-2017: Home Economics Building Renovation and Infrastructure South Hall Renovation 5/20/2010 Executive Summary 2-2 UW-Stout Campus Physical Development Plan 2011-17 I. BACKGROUND A. Institution Profile .................................................................................. IA-1 Background and History ................................................................................................. IA-2 Character ........................................................................................................................ IA-3 Main Campus Property ................................................................................................... IA-4 Non-Contiguous Property ............................................................................................... IA-4 B. Existing Conditions Map ...................................................................... IB-1 C. Mission Statement ................................................................................ IC-1 Core Mission Statement ................................................................................................. IC-1 Select Mission Statement ............................................................................................... IC-2 D. Strategic Goals...................................................................................... ID-1 E. Program Trends .................................................................................... IE-1 Current Programs ........................................................................................................... IE-1 Recently Approved and Developing Programs .............................................................. IE-2 F. Planning Issues and Themes ............................................................... IF General Purpose Revenue (GPR) Supported Facilities and Functions ......................... IF-1 Program Revenue (PR) Supported Facilities and Functions ......................................... IF-1 Continuing Themes ........................................................................................................ IF-2 G. Space Needs Summary ........................................................................ IG-1 100 Classroom Facilities ................................................................................................ IG-2 200 Laboratory Facilities ................................................................................................ IG-2 300 Office Facilities ........................................................................................................ IG-3 400 Study Facilities ........................................................................................................ IG-3 500 Special Use Facilities .............................................................................................. IG-3 600 General Use Facilities ............................................................................................. IG-4 700 Support Facilities ..................................................................................................... IG-5 800 Health Care Facilities .............................................................................................. IG-6 900 Residential Facilities ................................................................................................ IG-6 5/20/2010 Table of Contents I-1 UW-Stout Campus Physical Development Plan 2011-17 A. INSTITUTION PROFILE Academic Profile Physical Profile Student Profile 58 Majors and Degrees 86 Acres (Main Campus) 7,512 53 Minor Programs 45 Acres (Non-Contiguous) – North Campus 9,015 Full Time Equivalent (FTE) Headcount 90 Concentration Areas 64 Buildings (Total) 2,792 Non-Residents 16 Certificate Programs 2,519,327 Gross Square Feet (Total) 6,223 Residents (Total) 1,726 Graduates (Annual Average) 3,015 Parking Spaces (Total) 3,127 Residents (On Campus) BACKGROUND AND HISTORY UW-Stout is one of 13 four-year campuses and 13 two-year campuses in the University of Wisconsin System. The UW System designates UW-Stout as a special mission institution, forged from the heritage of its founder, James Huff Stout, a Wisconsin industrialist. Mr. Stout believed that people needed advanced education to prepare them for America’s developing industrial society. To implement this vision, Mr. Stout founded a private institution called the Stout Manual Training School in 1891. In 1911, the training school became a public institution named Stout Institute and received teacher-training accreditation in 1928 with programs centered on industrial arts and home economics. In 1932, Stout was accredited as a college and received Master’s degree accreditation in 1948. The campus became Stout State College in 1955, Stout State University in 1964, and in 1971, UW-Stout became part of the UW System when the two public university systems were combined under one Board of Regents. In 2001, UW-Stout became the first university to receive the Malcolm Baldridge National Quality Award in recognition of its history of performance excellence in higher education. In 2007, UW-Stout received designation as Wisconsin’s Polytechnic University. 5/20/2010 A polytechnic university offers a comprehensive curriculum that prepares graduates for professional careers. A polytechnic university blends theory with practice to produce innovative solutions to real world problems. A polytechnic university works closely with business, industry and other educational institutions to benefit students and grow the economy. Institution Profile IA - 2 UW-Stout Campus Physical Development Plan 2011-17 CHARACTER UW-Stout is located in the city of Menomonie, Wisconsin, a traditional, yet progressive city with a population of 15,940. Menomonie is in west central Wisconsin about 30 miles west of Eau Claire and 75 miles east of Minneapolis, Minnesota. UW-Stout is located approximately half way between UW-River Falls and UW-Eau Claire. The UW-Stout campus, which consists of 131 acres on two campuses – Main Campus and North Campus, is situated in Menomonie’s downtown, south of Lake Menomin, and has been since the institution’s founding in 1891. Main Street, which fronts Main Campus on the north, has been designated a national Downtown Historic District, and is anchored by the Victorian-era Mabel Tainter Memorial Theater. The location of UW-Stout in Menomonie’s downtown provides the university with unique opportunities and challenges within the Menomonie community as it serves not only as an institution of higher education, but also as a neighbor, resource and employer. With the opening of the Stout Technology Park in 1990, the Stout University Foundation Inc. has realized its goal of providing a "highly specialized environment" for the university and technically-oriented private businesses to work together and to take advantage of the resources each has to offer. The park is designed to attract firms that specialize in areas where Stout has strong expertise, including packaging, plastics, graphic arts, food service, home economics, product development, computer science, industrial technology, plant engineering, and hotel and restaurant management. In 1967, a $50,000 private donation to the foundation was used as a down payment to purchase more than 700 acres of land on U.S. 12 to benefit the university. Of the 385 acres still owned by the foundation, 113 were deeded to the Stout Technology Park Development Corp. In partnership with the foundation, Northern States Power Company (now Xcel Energy) and the City of Menomonie invested $1 million in the park for utilities and roads. Wisconsin Bell (now AT&T) has provided the groundwork for the latest in telecommunications. 5/20/2010 Institution Profile IA - 2 UW-Stout Campus Physical Development Plan 2011-17 An industrial park located in northeast Menomonie provides a thriving base of industries including 3M, Ford Motor Company, Wal-Mart Distribution Center, Cardinal FG, Andersen Windows, Phillips Plastics Corporation and others. UW-Stout associates with these industries by providing services through programs such as: Northwest Wisconsin Manufacturing Outreach Center (NWMOC) which provides expertise in manufacturing management and the Stout Technology Transfer Institute (STTI) which promotes technology transfer between UW-Stout and industry. Its 9,015 students are enrolled in one of four colleges: College of Arts, Humanities and Social Sciences (CAHSS); College of Education, Health and Human Sciences (CEHHS); College of Management (COM) or College of Science, Technology, Engineering and Mathematics (CSTEM). A distinctive array of 39 undergraduate and 19 graduate programs are offered at UW-Stout. These programs lead to the following degrees: Bachelor’s of Science (BS), Bachelor’s of Arts (BA), Bachelor’s of Fine Arts (BFA), Master’s of Science (MS), Master’s of Science in Education (MSE), and the Education Specialist degree (Ed S). In 2008-09, 1,262 faculty and staff were employed at UW-Stout. Of the 285 faculty, 84 (29%) were professors, 79 (28%) were associate professors, and 122 (43%) were assistant professors. 58% of all employees were women and 5% were minorities. 40% of the faculty were women and 15% were minorities. 49% of the executive/director/administrators were women and 4% were minorities. 50% of the instructional academic staff were women and 5% were minorities. 59% of the professional (noninstructional) academic staff were women and 6% were minorities. 68% of the classified staff were women and 4% were minorities. In 2005, UW-Stout received Board of Regents and State Building Commission approval to expand campus boundaries on both Main Campus and North Campus. 5/20/2010 Institution Profile IA - 2 UW-Stout Campus Physical Development Plan 2011-17 In 2006, UW-Stout received Board of Regents and State Building Commission approval for multiple property acquisition on both Main Campus and North Campus, as properties became available. All of these properties are within current campus boundaries. CAMPUS PROPERTY UW-Stout consists of 131 acres on two campuses – Main Campus and North Campus. Main Campus The Main Campus, which contains 86 acres, includes all academic and administrative functions and facilities. Five of the ten residence halls are located on Main Campus and house 70% of all student residents. All athletic, recreation and intramural events and facilities are located on Main Campus. Main Campus has distinct zones for academic, administrative, residential and athletic/recreational functions. The academic functions are primarily situated in the northeast and east central areas; administrative in the north and west areas; residential in the west central area; and athletic/recreational in the south area. Main Campus has is bounded by State Highway 29/Main Street to the north; State Highways 25/29/Broadway Street to the west; and residential areas, primarily privately-owned student housing, to the south and east. Through the years, UW-Stout has acquired many properties within or adjacent to campus boundaries. The university continues to frequently review opportunities to acquire properties from private landowners within or contiguous to campus boundaries. The major landmark building on Main Campus is Bowman Hall. It was built in 1897 and is the oldest building on campus. Its most distinguishing feature is the Clock Tower, which also houses a carillon. The Clock Tower is a highly visible landmark in downtown Menomonie and is also visible from Interstate 94 which runs approximately two miles north of campus. In fall 2009, the Jarvis Hall Science Wing Addition was completed and opened. The existing Jarvis Hall Science Wing is currently being renovated and is scheduled for completion in fall 2010. Parking Services manages the 2,399 parking spaces in twenty-four lots on Main Campus. Permits are available for commuter, resident, disabled and visitor use. 5/20/2010 Institution Profile IA - 2 UW-Stout Campus Physical Development Plan 2011-17 North Campus North Campus, which contains 45 acres and is located four blocks north of Main Campus, has five of the ten residence halls at UW-Stout, housing 30% of all student residents. The residence halls include: Fleming Hall, Wigen Hall, Hovlid Hall, Jeter-Tainter-Callahan (JTC) and Red Cedar Hall. Red Cedar Hall is the newest of all campus residence halls having been constructed in 2005. It is also the most prominent residence hall on North Campus. A dining facility, including a large kitchen and convenience store, is located within one of the residence halls (Tainter Hall). The Hovlid Hall Renovation and Addition project is scheduled for completion in fall 2010 and includes a new dining facility to replace the one in Tainter Hall. The JTC complex will be vacated and demolished after completion of the Hovlid Hall project. The Student Health Center and Louis Smith Tainter House (LST House) are also located on North Campus. University Advancement and Marketing is in the Louis Smith Tainter house. North Campus is bounded by residential areas, primarily privately-owned, and the Red Cedar River to the north; residential areas, primarily privately-owned student housing, to the south and west; and Lake Menomin to the east. State Highway 25/Broadway Street dissects the North Campus in a north-south direction. Parking Services manages the 616 parking spaces provided on North Campus in ten parking lots. Most parking spaces are for student residents. 5/20/2010 Institution Profile IA - 2 UW-Stout Campus Physical Development Plan 2011-17 B. EXISTING CONDITIONS MAP BUILDING LEGEND 1 Harvey Hall 2 Fryklund Hall 3 Bowman Hall 5 Sports & Fitness Center 5A Sports & Fitness Center (A) 5B Sports & Fitness Center (B) 7 Vocational Rehabilitation 8 Child & Family Study Center 9 Child & Family Study Center (Storage) 10 Home Economics Building 11 Millennium Hall 12 Robert S. Swanson Learning Center 15 Jarvis Hall Science Addition 16 Jarvis Hall Science Wing 16A Jarvis Hall Technology Wing 17 Micheels Hall 18 Administration Building 19 Applied Arts Building 36 Heating Plant 45 Memorial Student Center 46 Communication Technologies 47 Merle M. Price Commons 48 Student Health Center 61 Tainter Hall 61A Jeter Hall 61B Callahan Hall 62 Louis Smith Tainter House 63 Red Cedar Hall 64 Wigen Hall 65 Hovlid Hall 65A Hovlid Hall Dining 66 Fleming Hall 67 McCalmont Hall 67A Antrim Hall 67B Froggatt Hall 68 Hansen Hall 68A Keith Hall 68B Milnes Hall 68C Chinnock Hall 69 Curran Hall 69A Kranzusch Hall 69B Tustison Hall 69C Oetting Hall 72 North Hall 73 South Hall 74 Maintenance Storage Building 75 Maintenance Storage Building 85 Williams Stadium 89 General Services Building 91 University Services Building 93 Nelson Field Restrooms 5/20/2010 Existing Conditions Map IB - 1 UW-Stout Campus Physical Development Plan 2011-17 C. MISSION STATEMENT University of Wisconsin System Mission Statement The mission of the system is to develop human resources, to discover and disseminate knowledge, to extend knowledge and its application beyond the boundaries of its campuses and to serve and stimulate society by developing in students’ heightened intellectual, cultural and humane sensitivities, scientific, professional and technological expertise and a sense of purpose. Inherent in this broad mission are methods of instruction, research, extended training and public service designed to educate people and improve the human condition. Basic to every purpose of the system is the search for truth. CORE MISSION STATEMENT As institutions in the University Cluster of the University of Wisconsin System, the University of Wisconsin-Eau Claire, the University of Wisconsin-Green Bay, the University of Wisconsin-La Crosse, the University of Wisconsin-Oshkosh, the University of Wisconsin-Parkside, the University of WisconsinPlatteville, the University of Wisconsin-River Falls, the University of Wisconsin-Stevens Point, the University of Wisconsin-Stout, the University of Wisconsin-Superior and the University of WisconsinWhitewater share the following core mission. Within the approved differentiation stated in their select missions, each university in the cluster shall: a. Offer associate and baccalaureate degree level and selected graduate programs within the context of its approved mission statement. b. Offer an environment that emphasizes teaching excellence and meets the educational and personal needs of students through effective teaching, academic advising, counseling and through university-sponsored cultural, recreational and extra-curricular programs. c. Offer a core of liberal studies that supports university degrees in the arts, letters and sciences, as well as specialized professional/technical degrees at the associate and baccalaureate level. d. Offer a program of pre-professional curricular offerings consistent with the university's mission. e. Expect scholarly activity, including research, scholarship and creative endeavor, that support its programs at the associate and baccalaureate degree level, its selected graduate programs and its approved mission statement. f. Promote the integration of the extension function, assist the University of Wisconsin-Extension in meeting its responsibility for statewide coordination, and encourage faculty and staff participation in outreach activity. g. Participate in interinstitutional relationships in order to maximize educational opportunity for the people of the state effectively and efficiently through the sharing of resources. h. Serve the needs of women, minority, disadvantaged, disabled and non-traditional students and seek racial and ethnic diversification of the student body and the professional faculty and staff. i. 5/20/2010 Support activities designed to promote the economic development of the state. Mission Statement IC - 1 UW-Stout Campus Physical Development Plan 2011-17 SELECT MISSION STATEMENT University of Wisconsin-Stout is a career-focused, comprehensive polytechnic university where diverse students, faculty and staff integrate applied learning, scientific theory, humanistic understanding, creativity and research to solve real-world problems, grow the economy and serve a global society. a. The University offers undergraduate and graduate programs in manufacturing engineering and undergraduate and graduate programs leading to professional careers in industry, commerce, education and human services through the study of technology, applied science, art, industrial management, human behavior and home economics. b. The University integrates the humanities; arts; and natural, physical and social sciences into its undergraduate programs. Experiences in these areas provide a foundation for the major field of study, promote continuing personal and professional growth, and prepare the students to deal constructively with issues and opportunities of the future. The University places special emphasis upon student development. c. The University's programs center on human development and interpersonal relationships, efficient and effective practices in industry, commerce, education and human services, and the relationships of individuals to their environment and to society. d. The University develops new educational strategies, provides opportunities to learn through involvement and experimentation, and creates a climate of inquiry. The University experiments with new instructional methods in the interest of improving the learning process. e. The University expects scholarly activity including research, scholarship, development and creative endeavor that supports its programs at the baccalaureate level, its select graduate programs and its select mission. f. The University, through outreach and public service, addresses the needs of society and contributes to the welfare of the state and to its economic and technological development and cooperates with University of Wisconsin-Extension. g. The University cooperates with the other University of Wisconsin System institutions; the Wisconsin Technical College System, and other state and national agencies; and participates in state-wide, national and international programs. 5/20/2010 Mission Statement IC - 2 UW-Stout Campus Physical Development Plan 2011-17 D. STRATEGIC GOALS UW-Stout is engaged in a continuing process of identifying, reviewing and revising its goals. Values The advancement of academic excellence; The nobility of spirit, a diversity of people, respect and inclusion for all; The pursuit of innovation, technology and sustainability with a constant eye to the future; The ideals of collaboration, competence and continuous improvement; The commitment to education as a means to illuminate the lives of all. Enduring Goals Goal 1: Offer high quality, challenging academic programs that influence and respond to a changing society. Goal 2: Preserve and enhance our educational processes through the application of active learning principles. Goal 3: Promote excellence in teaching, research, scholarship and service. Goal 4: Recruit and retain a diverse university population. Goal 5: Foster a collegial, trusting and tolerant campus climate. Goal 6: Provide safe, accessible, effective, efficient and inviting physical facilities. Goal 7: Provide responsive, efficient, and cost-effective educational support programs and services. Focus 2015 Goals Develop knowledge, respect and validation of differing values, cultures and beliefs in students, faculty and staff. Expand early and ongoing experiential learning opportunities including undergraduate applied research and entrepreneurship. Further develop and execute integrated enrollment management. Focus on Sustainability: Implement key elements of the president’s Climate Commitment and Educational and Applied Research Initiatives. University Priorities 5/20/2010 Develop a multi-year recruitment and retention plan which supplements current efforts with specific focus on students of color (particularly Hmong and Hispanic), veterans, and nontraditional populations. Strategic Goals ID-1 UW-Stout Campus Physical Development Plan 2011-17 Assert/demonstrate leadership in sustainability, including campus policy development and active participation in regional initiatives and groups. Develop and implement a pilot program to increase participation in faculty, staff and student exchange programs Fully integrate experiential learning into the curriculum and institutionalize it into the culture and identity. Campus Master Plan In 2007, UW-Stout began a Campus Master Plan process. The master plan is intended to be a dynamic and interactive working document that will provide long-term guidance and direction. Periodic evaluation of the Campus Master Plan will be necessary to ensure its continuity and to accommodate change. The Campus Master Plan is designed to comprehensively incorporate the planning of facilities, academic programs, utility infrastructure, land acquisition and campus services. UW-Stout presented the Campus Master Plan to the Board of Regents in October 2009. 5/20/2010 Strategic Goals ID-1 UW-Stout Campus Physical Development Plan 2011-17 E. PROGRAM TRENDS There are four colleges at UW-Stout: College of Arts, Humanities and Social Sciences (CAHSS); College of Education, Health and Human Sciences (CEHHS); College of Management (COM); and College of Science, Technology, Engineering and Mathematics (CSTEM). There are five (5) intended outcomes of this alignment: 1. Group similar programs, departments and disciplines together in units so they are better able to address common issues, share curriculum and resources, develop new programs, maximize capabilities, minimize duplication and work under common leadership. 2. Capitalize on trends and opportunities that have emerged over the past decade and position the campus for growth. 3. Align programs with an administrative structure that will strengthen UW-Stout’s mission and polytechnic identity and position UW-Stout among its national polytechnic peers. Expand technology transfer and outreach efforts to more fully realize regional economic growth and strengthen ties with external partners and stakeholders. 4. Develop an administrative structure of units that is more descriptive and understandable to both internal and external audiences, including potential faculty and staff hires, and provide greater brand identity to administrative and academic units. It is desirable to have an organizational structure that clearly explains who we are and what we do as an institution. 5. Provide a more coordinated approach to facilitate efforts of faculty and staff interested in interdisciplinary and collaborative programs including the Curriculum Incubation Center, Learning Communities, First Year Experience, Project Lead the Way and the University Honors Program. CURRENT PROGRAMS Undergraduate Degree Programs Undergraduate Degree Programs (cont.) Graduate Degree Programs CAHSS: Applied Social Science, B.S.* Art, B.F.A. Game Design and Development, B.S. Technical Communication, B.S. COM: Business Administration, B.S. Golf Enterprise Management, B.S. Hotel, Restaurant and Tourism Management, B.S. Management, B.S. Property Management, B.S. Retail, Merchandising and Management, B.S. Service Management, B.S. Supply Chain Management, B.S. Sustainable Management, B.S. CAHHS: Technical and Professional Communication, M.S. CEHHS: Art Education, B.S. Career, Technical Education and Training, B.S. Dietetics, B.S. Early Childhood Education, B.S. Family and Consumer Sciences Education, B.S. Food Systems and Technology, B.S. Human Development and Family Studies, B.S. Marketing and Business Education, B.S. Psychology, B.A. Science Education, B.S. Special Education, B.S. Technology and Science Education, B.S. Technology Education, B.S. Vocational Rehabilitation, B.S. CSTEM: Apparel Design and Development, B.S. Applied Mathematics and Computer Science, B.S. Applied Science, B.S. Computer Engineering, B.S. Construction, B.S. Engineering Technology, B.S. Game Design and Development, B.S. Graphic Communications Management, B.S. Information and CommunicationTechnologies, B.S. Information Technology Management, B.S. Manufacturing Engineering, B.S. Packaging, B.S. Plastics Engineering, B.S. CEHHS: Applied Psychology, M.S. Career and Technical Education, M.S. Career and Technical Education, Ed.S Education, M.S. Family Studies and Human Development, M.S. Food and Nutritional Sciences, M.S. Marriage and Family Therapy, M.S. Mental Health Counseling, M.S. School Counseling, M.S. School Psychology, M.S. School Psychology Ed.S. Technology Education, M.S. Vocational Rehabilitation, M.S. COM: Risk Control, M.S. Technology Management, M.S. Training and Development, M.S. CSTEM: Information and Communication Technologies, M.S. Manufacturing Engineering, M.S. * To be implemented in fall 2010 5/20/2010 Program Trends IE - 1 UW-Stout Campus Physical Development Plan 2011-17 UW-Stout offers a distinctive array of 39 undergraduate and 19 graduate programs. These programs lead to the following degrees: Bachelor’s of Science (BS), Bachelor’s of Arts (BA), Bachelor’s of Fine Arts (BFA), Master’s of Science (MS), Master’s of Science in Education (MSE), and the Education Specialist degree (Ed S). In fall 2009, the undergraduate programs with the largest enrollments were: art; business administration; hotel, restaurant and tourism management; construction; and management. The graduate programs with the largest enrollments were: education; vocational rehabilitation; and training and development. The University Honors Program offers enhanced learning opportunities to students with high academic potential. The curriculum stresses learning and activity through integrated and complementary honors courses in the arts and sciences, family studies, education, and technology. UW-Stout offers unique programs not available at other UW System campuses: Applied Math and Computer Science; Applied Science; Career, Technical Education and Training; Construction; Engineering Technology; Golf Enterprise Management; Graphic Communication Management; Hotel, Restaurant and Tourism Management; Information and Communication Technology; Information Technology Management; Manufacturing Engineering; Packaging; Service Management; Technical Communications; and Vocational Rehabilitation. RECENTLY APPROVED AND DEVELOPING PROGRAMS New programs are developed to be consistent with UW-Stout’s select mission, providing an approach to learning that involves combining theory, practice and experimentation to address the changing needs of society. UW-Stout’s designation as Wisconsin’s Polytechnic University supports the development of new programs that emphasize the tenets of using applied learning, scientific theory and research to solve real world problems, and collaborating with business and industry to grow the state economy. UW-Stout’s Academic Plan includes the following proposed programs: College of Arts, Humanities and Social Sciences (CAHSS) o Master of Fine Arts in Design: Entitlement to Plan approved by UW System Fall 2007 o A.A. in Arts and Sciences: To be submitted Fall 2009 College of Education, Health and Human Sciences (CEHHS) o B.S. in Health, Wellness and Fitness : Entitlement to Plan submitted to UW System Fall 2009 o M.S. in Gerontology : Entitlement to Plan approved by UW System Fall 2009 College of Management (COM) o M.S. in Homeland Security: Entitlement to Plan to be submitted to UW System Spring 2010 College of Science, Technology, Engineering and Mathematics (CSTEM) o M.S. in Industrial and Applied Mathematics: Entitlement to Plan to be submitted to UW System Summer 2010 o M.S. in Biomedical Sciences: Entitlement to Plan under discussion It is anticipated that the Masters of Fine Arts in Design program will require significant square feet and appropriate building systems infrastructure to support the program. UW-Stout is currently investigating options for its location in close proximity to the art facilities in Micheels Hall and the Applied Arts building. 5/20/2010 Program Trends IE - 2 UW-Stout Campus Physical Development Plan 2011-17 F. PLANNING ISSUES AND THEMES GENERAL PURPOSE REVENUE (GPR) SUPPORTED FACILITIES & FUNCTIONS Priority 1. 2. 3. 4. 5. 6. Issue Description Harvey Hall Renovation – Phase II Remodel The building infrastructure is functionally poor, deteriorating and obsolete. This includes: mechanical, HVAC, plumbing, electrical, telecommunications, life safety, ADA accessibility and elevators. The building has low efficiency, inherent of its 1916 design and results in many disconnected small offices and classrooms with poor aspect ratios. Changing Needs in Student Services Support Areas – Bowman Hall Prospective and current students are currently inconvenienced with disconnected student service support areas for students. Changing Programs and Infrastructure Upgrade – Home Economics Building There is inadequate space for evolving and changing academic programs. These programs cannot be accommodated with deteriorating and obsolete building infrastructure including: mechanical, HVAC, plumbing, electrical, telecommunications, life safety, ADA and elevators. Growing and Changing Programs in Communication Technologies Building This building is a second-use facility, originally constructed as a student union, and provides inadequate and inefficient space for program growth and increased technology requirements. Recreation and Athletic Facilities Recreational and athletic space is inadequate to meet the ever-growing demands of students and student-athletes. Appropriate Facilities and Location for Student Health Services The Student Health Center, located on North Campus, suffers from the deterioration of an older facility and a location that is inconvenient for most students, specifically the freshmen living on Main Campus. Robert S. Swanson Learning Center This building does not provide appropriate and proper facilities for studentfocused and faculty/staff services. Students frequently request for more group study rooms which promote collaboration and interaction. PROGRAM REVENUE (PR) SUPPORTED FACILITIES AND FUNCTIONS Priority 1. 2. 5/20/2010 Issue Description Residence Hall Infrastructure and Ability of Aging Residence Halls to Remain Competitive Physical systems in campus residence halls built in the late 1950’s through 1970 are reaching the end of their expected life. Continuous problems with leaking plumbing, ruptured buried steam piping, outmoded and inadequate electrical power distribution systems and excessive heat loss through deteriorated windows are, and will continue to be, very costly. Life safety issues are also a concern. Buildings of that era lack elevators and ADAcomplying toilet and shower rooms. Serious consideration must be given to the solutions to these issues and the impact improvements will have on the fee paid by all students who reside in residence halls. University Centers The Memorial Student Center and Merle M. Price Commons lack appropriate and proper facilities for student-focused services and conference/meeting space. Current facilities do not meet the technological, social and aesthetic expectations of students. The building system infrastructure, including Planning Issues and Themes IF - 1 UW-Stout Campus Physical Development Plan 3. 2011-17 mechanical, HVAC, plumbing, electrical, telecommunications, life safety, ADA accessibility and elevators, is deteriorating. Campus Parking Current and future building construction projects impact the number, capacity and location of parking lots. Parking is not proportionately provided (e.g., some North Campus residents have to park in Main Campus lots). Stormwater management requirements will reduce the number of available parking spaces. CONTINUING THEMES In addition to the planning issues listed above, UW-Stout has identified six continuing themes that are an integral part of all applicable projects on the issues list. They are listed separately as they need to be integrated into many projects and cannot be fully addressed in one project. Theme 1. 2. 3. 5/20/2010 Theme Description Classroom Size, Quality and Adequacy New academic programs have raised the expectation for technologyenabled instruction. The campus’ commitment to technology (e.g., the laptop e-Scholar program) has made it more difficult to provide adequate electrical and data capabilities in classrooms. Almost one quarter of the campus’ general assignment classrooms are located in Harvey Hall, an older building in which it is very difficult to provide these services. HVAC system inadequacies exist in many older buildings. Poor aesthetic issues, including, flooring, paint, ceiling, lighting and furniture also exist. There is a classroom demand imbalance – too many small classrooms, not enough medium-sized classrooms. Infrastructure Concerns Related to Older Buildings Building envelopes on campus require renovations of the existing systems which have exceeded their life expectancies, failing roof systems, inefficient and inoperable windows, metal doors and frames are deteriorating due to corrosion, tuckpointing and caulking failures and through-wall flashing replacements. The majority of mechanical systems on campus are constant volume air with pneumatic control systems which are energy inefficient, provide over heating and under heating spaces with limited control to areas within the facility. Fire dampers are missing in several HVAC systems which are required with current fire codes. The electrical substation, which serves the campus, is reaching capacity on one of two banks during routine maintenance or an emergency condition. The secondary distribution systems within buildings are at capacity and have obsolete breakers. The UPS systems are at capacity or are approaching their designed life cycle. The Heating Plant and Millennium Hall are the two buildings which require replacement and upgrades. Plumbing systems across campus have reached their life expectancies. The waste system was constructed of galvanized piping and is routinely failing along with valving which is non-operational. Twenty percent of the drinking fountains on campus are nonoperational. Random leaking is a normal occurrence. The Right Space: Consolidation of Similar Functions and Availability to the Public Operational inefficiencies and ineffectiveness result from the disconnectivity of departments. Departments that are located in different buildings are difficult for students and visitors to find. Planning Issues and Themes IF - 2 UW-Stout Campus Physical Development Plan 4. 5. 6. 5/20/2010 2011-17 Telecommunications Closets and Wiring Needs Telecommunication needs have expanded and exceed the space available in existing Main Distribution Frames (MDF). This is partially a result of the implementation of the e-Scholar (laptop) program. Connectivity and power distribution for laptops is inadequate. There is a lack of dedicated building MDF’s and some have been constructed in non-compliant spaces. Existing MDF’s suffer from inadequate HVAC systems resulting in the overheating of equipment. Non-labeled and abandoned cables are installed directly on ceiling grids and tile. These need to be installed to comply with current standards. Sustainability Energy efficiency and stormwater management requirements impact budget and operations. Life Safety and Accessibility Fire stopping is missing in all buildings except for Red Cedar Hall and the Administration Building. Elevators across campus require ADA upgrading to meet current standards. Restrooms across campus require ADA upgrading to meet current standards. Fire alarm systems are at capacity and we are unable to get replacement parts for obsolete systems. These systems are unable to be adapted to meet current codes. Emergency generators across campus are requiring additional maintenance and parts are becoming difficult to obtain. They have all exceeded their life expectancy. Planning Issues and Themes IF - 3 UW-Stout Campus Physical Development Plan 2011-17 G. SPACE NEEDS SUMMARY The UW-Stout campus consists of 2,497,267 gross square feet (GSF)/1,408,584 assignable square feet (ASF). Of its 64 buildings, 21 are academic, 20 are residential and 23 are service (administrative, physical plant, heating plant, general services, storage, etc.) buildings. UW-Stout has identified the need for additional space as follows: Sports and Fitness Center Military Science/ROTC Masters of Fine Arts and Design Discovery Center 100,000 ASF 3,280 ASF 9,580 ASF 15,050 ASF 127,910 ASF Special Use and Office Laboratory and Office Laboratory and Office Laboratory and Office UW-Stout is addressing concerns with building interior space utilization and efficiency. A Campus Space Audit, Inventory and Utilization Study was completed by campus planning in the spring of 2007 and addressed facility use of all buildings relating to efficiency, availability, appropriateness, condition and flexibility of space. Building efficiency is based on UW System Administration (UWSA) and the Division of State Facilities (DSF) space standards and guidelines. The objectives of this Space Audit, Inventory and Utilization Study were to: 1. Review all rooms on the UW-Stout campus 2. Accurately document room use and assignment 3. Identify campus space issues for inclusion in the Campus Physical Development Plan process 4. Provide recommendations to better utilize existing campus space 5. Provide information to assist in the development of a Campus Master Plan In addition to classroom, laboratory and office standards and utilization, building efficiency is analyzed. The Division of State Facilities (DSF) has established efficiency standards for a variety of building types. To assist in the identification and categorizing of space on campus, UW-Stout used the Postsecondary Education Facilities Inventory and Classification Manual (FICM) – 2006 Edition. 5/20/2010 Space Needs Summary IG - 1 UW-Stout 100 Campus Physical Development Plan 2011-17 CLASSROOM FACILITIES A Classroom Survey and Assessment was completed in 2006 for general assignment classrooms. Its purpose was to allow UWSA to better understand the conditions of existing classrooms and address the remodeling, technology and furniture requirements and costs to maintain high-level instructional facilities system-wide. This survey and assessment has better positioned the campus in repurposing substandard classrooms, such as substandard classrooms. In addition, it provides valuable planning information for campus-funded projects such as the e-Scholar (laptop) program. This process included the identification of general assignment classrooms and site surveys of each classroom. The surveys included data collection of room dimensions, ceiling height, assignable square feet (ASF), aspect ratio, room type (A: functional; B: substandard), capacity, seating type, technology levels, remodeling needs, funding timeframe, 2007-09 budget information and funding sources. Please note that the general assignment classrooms in the Jarvis Hall Science Wing are included as the survey and assessment reflect current classroom data. These classrooms are proposed to be replaced in the Jarvis Hall Science Wing Renovation and Addition project. With the completion of this project there is no identified need for additional classrooms. However, there will be an ongoing need to update existing classrooms. Summary of Findings General Assignment Classrooms: Room Type (totals): Total Room Capacity: Average Seats per Classroom: Seating Type: Technology Level: Classrooms requiring remodeling: Classrooms requiring tech: Classrooms requiring new furniture: Total classroom upgrade cost: 200 91 Total 83,488 ASF 918 ASF/classroom A (functional): 54 (59%) B (substandard) : 37 (41%) 4,388 total 48 Moveable tables and chairs/Fixed and Moveable tablet arm chairs Primarily Level 3 71 (78%) through 2013 / $1,571,555 (2007-2009 dollars) 31 (34%) through 2013 / $309,000 (expressed in 2007-2009 dollars) 27 (30%) through 2013 / $378,650 (expressed in 2007-2009 dollars) $2,259,205 LABORATORY FACILITIES In the fall of 2007, the Chancellor charged that a Laboratory Audit be conducted as a follow up to the Campus Space Audit, Inventory and Utilization Study. The intent of the audit is to accurately define, identify and document laboratory spaces and distinguish them from lab prep, supply and other rooms. At the time of this writing, all tours of laboratory and laboratory service areas have been completed. Final approval of the Laboratory Audit is anticipated in summer 2008 for implementation in the fall 2008 semester. In addition to the Laboratory Audit, the Chancellor has also charged that a Laboratory Modernization Renewal Plan be conducted as a follow up to the Laboratory Audit. The intent of this plan is to identify and document dates and descriptions of laboratory modifications. This information is critical to members of the Campus Space Committee as they review annual Laboratory Modernization Requests so as not to ignore the need for modernization of labs which might not be submitted for lab mod funding. The schedule calls for its completion in the 2008-09 academic year. Additional laboratory/laboratory service space, totaling 22,510 ASF, has been identified by Military Science (2,000 ASF); Masters of Fine Arts (7,840 ASF); and the Discovery Center (12,670 ASF). There will be an ongoing need to update existing laboratories. 5/20/2010 Space Needs Summary IG - 1 UW-Stout 300 Campus Physical Development Plan 2011-17 OFFICE FACILITIES Office facility space utilization and efficiency concerns were identified in the Campus Space Audit, Inventory and Utilization Study which was completed in the spring of 2007. In the fall of 2006, UW-Stout had 906 offices totaling 156,558 ASF. The average size of a campus office is 173 ASF. This equates to 11.4% of the total campus ASF. There is no identified need for additional office space although requests for office space are occasionally submitted. There are many opportunities to accommodate these requests within some departments or units. Additional office/office service space, totaling 5,400 ASF, has been identified by Military Science (1,280 ASF); Masters of Fine Arts (1,740 ASF); and the Discovery Center (2,380 ASF). 400 STUDY FACILITIES UW-Stout fosters and promotes collaboration between students and faculty. Students at UW-Stout have been requesting more study space around campus. Included in this request is a 24/7 study room. The Robert S. Swanson Learning Center, formerly the Library Learning Center, provides some student study rooms, but the demand exceeds the supply. Campus Planning is currently engaged in building space use studies in the Robert S. Swanson Learning Center and Millennium Hall. These studies will identify potential locations for student study space in both formal and informal settings. The Jarvis Hall Science Wing Renovation and Addition project will provide many opportunities for formal and informal study space. In addition to open tutor and instructional labs, open spaces throughout the building will be provided to promote collaboration between students and students; students and faculty; and faculty and faculty. All undergraduate students at UW-Stout are provided a laptop computer. While they can be powered by battery and network access is provided through wireless systems across campus, the university understands the limits of power and network access. The campus has undertaken an aggressive stance in providing electrical power receptacles and data ports in many areas where students study or lounge. The Jarvis Hall Science Wing Renovation and Addition project will provide many power and data sources throughout the building for easy and reliable access. 500 520 SPECIAL USE FACILITIES Athletic and Physical Education Facilities The Sports and Fitness Center (SFC) provides 136,635 ASF/187,016 GSF of athletic, physical education, recreation and intramural space. There is a need to expand the current physical area of the Sports and Fitness Center to accommodate continued growth in recreation and intramural activities; provide more flexibility to accommodate the demand for athletic, physical education, recreation and intramural space; and provide much needed storage space. A space study has determined that an additional of 100,000 ASF is necessary to meet the projected demand. This additional area includes a multi-purpose room, locker rooms, weight room, offices, lounge and storage. The current outdoor facilities including Williams Stadium (football), Alumni Field (NCAA women’s and intramural softball), Nelson Field (soccer), baseball field, multi-purpose field, track, ropes course and tennis courts, are in heavy demand. The fields are difficult to maintain due to high demand. 5/20/2010 Space Needs Summary IG - 1 UW-Stout 570 Campus Physical Development Plan 2011-17 Animal Facilities UW-Stout currently conducts instructional research of animals in the Jarvis Hall Science Wing. The only animals used in these studies are zebra fish. The Jarvis Hall Science Wing Renovation and Addition project will provide expanded space and technology for the continued studies of zebra fish in an aquatics complex. In addition, a mammalian complex is included in the project for studies involving the potential use of animals. 580 Greenhouse In fall 2009, a new expanded greenhouse was opened in the on the third floor of the Jarvis Hall Science Wing Addition. It will provide technology for continued growth in biological/botanical studies. It will be more accessible space and will also be more visible to the campus community. 600 610 GENERAL USE FACILITIES Assembly Harvey Hall was constructed in 1916 as part of the Stout Manual Training Institute, and is the second oldest building on Main Campus. In 1986 it was listed on the National Register of Historic Places as a contributing building in the Menomonie Downtown Historic District. It has served throughout its life as an important and heavily used academic building, and is expected to continue in this use for the foreseeable future. An important component of Harvey Hall is its theatre, which seats approximately 600, and has always been the only theatre at UW-Stout. The Harvey Hall Renovation – Phase I Theatre project was included in the 2007-2009 Capital Budget. 630 Food Facility The Memorial Student Center currently has three food service venues. These venues may change in the future based on planning currently underway for upgrades and improvements to the Memorial Student Center. The Merle M. Price Commons houses a large dining facility of 12,453 ASF primarily catering to student residents. It is directly connected to a kitchen. It does not provide for any other assembly of many persons, although there are several meeting rooms in the building. Tainter Hall, located on North Campus, houses a large dining room of 6,881 ASF and is directly connected to a kitchen. This dining facility will be removed with the demolition of the Jeter-TainterCallahan (JTC) residence hall upon completion of the Hovlid Hall Renovation and Addition project, which will construct a replacement food service facility for North Campus. JTC demolition is anticipated in 2010. 640 Day Care Day care services are provided in both the Child and Family Study Center (pre-school) and the Home Economics building (infant and toddler). Day care primarily serves as an instructional laboratory in the Early Childhood Education program. It is the desire of the campus to combine both of these functions in the Home Economics building. 5/20/2010 Space Needs Summary IG - 1 UW-Stout 650 Campus Physical Development Plan 2011-17 Lounge In general, there is a lack of lounge space on campus. Highly trafficked buildings which provide little lounge space include the Memorial Student Center, Merle M. Price Commons, Robert S. Swanson Learning Center, and Sports and Fitness Center. The Jarvis Hall Science Wing Renovation and Addition project will provide many lounges/student study spaces throughout the building. It is desirable to provide additional and more appealing lounge spaces in other buildings, specifically Harvey Hall, Bowman Hall and Applied Arts. 670 Recreation The Multi-Purpose Room in the Sports and Fitness Center is occasionally used for assembly purposes, both for the campus and the outside community. 680 Meeting Room University Centers includes two buildings which provide assembly space for large groups and includes the Memorial Student Center (MSC) and Merle M. Price Commons (PC), both of which are located on Main Campus. The Memorial Student Center specifically provides large assembly spaces including the Great Hall and the Crystal Ballrooms. These rooms are heavily used not only by the campus, but also by the Menomonie community. The Great Hall contains 6,768 ASF of space used for performances, presentations, conferences and other special events. The Crystal Ballrooms (A, B and C) contain 5,076 ASF of space used for presentations, conferences, meetings and other special events. After twenty-three years, the Great Hall and Crystal Ballrooms have shown deteriorating signs of aging in its mechanical, electrical and telecommunications infrastructure. They require remodeling to improve aesthetics, functionality and provide an attractive and appealing environment. The campus is currently engaged with architects in a University Centers Renovation Pre-Planning Study for the Memorial Student Center. This study primarily focuses on student-related spaces and does not include any renovation work in the Great Hall or Crystal Ballrooms. 700 710 SUPPORT FACILITIES Central Computer or Telecommunications Millennium Hall hosts the central computer and telecommunication systems for the UW-Stout campus. A building use plan is currently being developed for Millennium Hall to address space and accessibility concerns for the laptop program. Laptop service is provided on the third floor of Millennium Hall in a constricted space that is remote, inconvenient and unappealing to students. 720 Shop Manufacture, repair and maintenance space is provided in the General Services building located on Main Campus. This 27,335 ASF/35,433 GSF building houses the campus physical plant including building maintenance, campus engineering, custodial services, grounds maintenance, fleet vehicles, key control, recycling and administrative offices. 730 Central Storage Purchasing Services is located in the University Services building located on Main Campus. The University Services building contains 31,938 ASF/39,846 GSF of which 8,906 square feet is used for central storage. 5/20/2010 Space Needs Summary IG - 1 UW-Stout 760 Campus Physical Development Plan 2011-17 Hazardous Materials Storage 775 square feet of hazardous materials storage is provided in the University Services building. While other hazardous materials are kept in other buildings such as the Jarvis Hall Science Wing and Applied Arts, this central storage facility is used for the receiving, shipping and disposal of chemicals and other hazardous materials. 800 HEALTH CARE FACILITIES Student Health Services is located in the Student Health Center on North Campus. This facility, circa 1957, consists of 8,005 ASF/11,572 GSF of examination, laboratory and office space. This building was originally constructed as a health care facility for the city of Menomonie. Through acquisition, it became the Student Health Center for UW-Stout. Although the allocation of space seems appropriate for its function, the condition and location of the building is a concern. The building is over fifty years old and its residential quality infrastructure requires much maintenance. Its location on North Campus makes it very inconvenient for Main Campus residents (all freshmen and many sophomores). It is the intent of the Campus Master Plan to identify the appropriate size and location of the Student Health Center and if it should be in physical association with other campus departments such as University Counseling. 900 RESIDENTIAL FACILITIES University Housing maintains 356,148 ASF of student housing space in ten (10) residence halls in twenty (20) buildings on Main and North campus. This ASF does not include office, study, recreation, meeting and other spaces assigned different room categories. There is a total capacity of 3,159 beds (2,199 beds on Main Campus and 960 beds on North Campus). The residence halls are summarized below. Residence Hall Capacity Antrim-Froggatt-McCalmont (AFM) 300 Curran-Kranzusch-Tustison-Oetting (CKTO) 478 Fleming Hall 205 Hansen-Keith-Milnes-Chinnock (HKMC) 482 Hovlid Hall 194 Jeter-Tainter-Callahan (JTC) 319 North Hall 366 Red Cedar Hall 205 South Hall 368 Wigen Hall 242 Location Main Campus Main Campus North Campus Main Campus North Campus North Campus Main Campus North Campus Main Campus North Campus Hovlid Hall, located on North Campus, is currently in construction for a renovation and addition project. The addition will include a new dining facility and service space to replace those facilities in Tainter Hall. All residence halls on Main and North Campus, with the exception of Red Cedar Hall, were constructed in the late 1950’s through 1970. All of these residence halls show signs of infrastructure age and fatigue. Jeter-Tainter-Callahan (JTC), the oldest residence facility on the UW-Stout campus, is planned for demolition following the completion of the North Campus Remodeling program resulting in a reduction of 55,490 ASF/86,120 GSF. There is no planned construction of a new residence hall to replace JTC. UW-Stout has completed a residence hall renewal plan study to identify and document the existing building system conditions in all residence halls except for Red Cedar Hall. This information has been analyzed and its findings were prioritized as to determine which residence halls will receive renovation, at what time and at what cost. 5/20/2010 Space Needs Summary IG - 1 UW-Stout Campus Physical Development Plan 2011-17 II. IMPLEMENTATION PLAN A. Near Term Development Plan .............................................................. IIA-1 B. Prioritized Project Requests ................................................................ IIB General Purpose Revenue (GPR) Supported Requests ................................................ IIB-1 Program Revenue (PR) Supported Requests ................................................................ IIB-2 C. Project Sequence Chart ....................................................................... IIC-1 D. Origin-Destination Chart ...................................................................... IID-1 5/20/2010 Table of Contents II - 1 UW-Stout Campus Physical Development Plan 2011-17 A. NEAR TERM DEVELOPMENT PLAN Campus Building EMS Upgrade (All Buildings) ADA Restroom Upgrade Applied Arts Home Economics Chilled Water Project – Phase III: Sports and Fitness Center General Services University Services Nelson Field Lighting Replacement Pedestrian Corridor Sports and Fitness Center: Bleacher Replacement Multi-Purpose Room (MPR) Floor Replacement Storage Addition Harvey Hall Renovation – Phase II Remodel Bowman Hall: Clock Tower Repair South Hall Remodel Jeter-Tainter-Callahan (JTC) Demolition North Hall Remodel Fleming Hall Remodel 5/20/2010 General Services Building Remodel Near Term Development Plan IIA - 1 UW-Stout Campus Physical Development Plan 2011-17 B. PRIORITIZED PROJECT REQUESTS GENERAL PURPOSE REVENUE (GPR) SUPPORTED REQUESTS 1. Project Title: Estimated Cost: Harvey Hall Renovation – Phase II Remodel $ $ 2. Project Title: Estimated Cost: Estimated Cost: $ Estimated Cost: $ Estimated Cost: $ Estimated Cost: $ General Fund Supported Borrowing Program Revenue Supported Borrowing Building Trust Funds Gift/Grant Funds Program Revenue - Cash Total 48,467,000 0 0 0 0 48,467,000 General Fund Supported Borrowing Program Revenue Supported Borrowing Building Trust Funds Gift/Grant Funds Program Revenue - Cash Total 18,700,000 0 0 0 0 18,700,000 General Fund Supported Borrowing Program Revenue Supported Borrowing Building Trust Funds Gift/Grant Funds Program Revenue - Cash Total Fryklund Hall Remodel $ $ 5/20/2010 16,754,000 0 0 0 0 16,754,000 Applied Arts Remodel $ 6. Project Title: General Fund Supported Borrowing Program Revenue Supported Borrowing Building Trust Funds Gift/Grant Funds Program Revenue - Cash Total Sports and Fitness Center Remodel and Addition $ 5. Project Title: 7,345,000 0 0 0 0 7,345,000 Home Economics Building Remodel $ 4. Project Title: General Fund Supported Borrowing Program Revenue Supported Borrowing Building Trust Funds Gift/Grant Funds Program Revenue - Cash Total Bowman Hall Remodel $ 3. Project Title: 28,176,000 0 0 0 0 28,176,000 7,090,000 0 0 0 0 7,090,000 General Fund Supported Borrowing Program Revenue Supported Borrowing Building Trust Funds Gift/Grant Funds Program Revenue - Cash Total Prioritized Project Requests IIB - 1 UW-Stout Campus Physical Development Plan 2011-17 PROGRAM REVENUE (PR) AND GIFT/GRANT SUPPORTED REQUESTS 2011-13 BIENNIUM 1. Project Title: Action Requested: Estimated Cost: Fleming Hall Residence Hall Renovation Planning and Construction $ $ 6,599,000 0 0 6,599,000 Program Revenue Supported Borrowing Gift/Grant Funds Program Revenue - Cash Total 2013-15 BIENNIUM 2. Project Title: Action Requested: Estimated Cost: North Residence Hall Renovation Planning and Construction $ $ 13,250,000 0 0 13,250,000 Program Revenue Supported Borrowing Gift/Grant Funds Program Revenue - Cash Total 2015-17 BIENNIUM 3. Project Title: Action Requested: Estimated Cost: South Residence Hall Renovation Planning and Construction $ $ 5/20/2010 14,130,176 0 0 14,130,176 Program Revenue Supported Borrowing Gift/Grant Funds Program Revenue - Cash Total Prioritized Project Requests IIB - 2 UW-Stout Campus Physical Development Plan 2011-17 C. PROJECT SEQUENCE CHART UNIVERSITY OF WISCONSIN - UW-STOUT CAMPUS PHYSICAL DEVELOPMENT PLAN PROJECT SEQUENCE CHART: 2011 - 2023 2011-13 NEAR TERM IMPLEMENTATION 2013-15 2015-17 MID-TERM IMPLEMENTATION 2019-21 2017-19 2021-23 KEY CAMPUS PHYSICAL DEVELOPMENT PLAN - PLANNED PROJECT SCHEDULE OF EVENTS $ 104.8 GPR $ 17.7 DURATION OF CAMPUS PHYSICAL DEVELOPMENT PLAN PR DURATION OF PROJECT HARVEY HALL RENOVATION - PHASE II $28.2M GPR $2.8M $25.4M DURATION OF PROJECT CONSTRUCTION DURATION OF PROJECT PLANNING FLEMING HALL $6.6 PR $0.6M $6.0M BOWMAN HALL RENOVATION/INFRA $7.4M GPR $0.8M $6.6M NORTH HALL A $4.2 PR $0.4M $3.8M NORTH HALL B, C $9.0 PR $0.9M $8.1M HOME ECONOMICS RENOVATION/INFRA $16.8M GPR $1.7M $15.1M SOUTH HALL (A, B) $9.6 PR $1.0M $8.6M SOUTH HALL (C) $4.6 PR $.5M $3.9M CKTO $19.1 PR $1.9M $17.2M ANTRIM/FROGGATT $10.8 PR $1.3M $11.7M McCALMONT HALL $6.5 PR $2.0M $18.0M SFC $14.4M GPR, $2.5M PR $1.4M $15.5M FRYKLUND HALL $7.1M GPR $0.6M $6.5M NEW ACADEMIC $58.5M GPR $5.9M $52.6M APPLIED ARTS $18.7M GPR $1.5M $17.2M HKMC $22.4 PR $2.2M $20.2M WIGEN HALL $8.3M PR $.9M $7.5M TOTAL GPR $ PR $ 2.8 $ 0.8 $ 8.3 $ 15.1 $ 14.4 $ 84.3 $ 125.7 M 6.6 $ 13.2 $ 14.2 $ 19.1 $ 19.8 $ 30.7 GIFT $ - $ - $ - $ - $ - $ - $ $ 103.6 M - M GRNT $ - $ - $ - $ - $ - $ - $ - M $ 229.3 M 5/20/2010 Project Sequence Chart IIC - 1 UW-Stout Campus Physical Development Plan 2011-17 UW-Stout’s Project Sequence Chart is based on its commitment that academics and facility condition are paramount to the continued excellence in instruction. Support services are next considered in the development of the chart. General Purpose Revenue (GPR) Priority Project Request Summary The Harvey Hall Renovation – Phase II Remodel project is considered UW-Stout’s top GPR priority based on the following issues: Harvey Hall was built in 1916 and its aged condition has resulted in deteriorating and obsolete building infrastructure systems such as: HVAC, plumbing, electrical, telecommunications and life safety. This building is very difficult to maintain. Harvey Hall houses almost one-quarter of the general assignment classrooms making it the most utilized classroom building on campus. These classrooms provide seating for almost 800 students. Harvey Hall uses space very inefficiently, inherent of its original design. The Jarvis Hall Science Wing Renovation and Addition project will allow the Mathematics, Statistics and Computer Science (MSCS) department to relocate from Harvey Hall to the Jarvis Hall Science Wing in fall 2010. The area vacated by MSCS will provide the campus with opportunities to address major space issues on campus, such as the relocation and/or consolidation of academic programs and/or departments. This is the first critical and necessary action for the campus to begin aligning academic programs with facilities and is key to the successful implementation of the Campus Physical Development Plan and Campus Master Plan. The Bowman Hall Remodel project addresses UW-Stout’s goal of providing prospective and current students with student service facilities that are convenient, accessible, welcoming and attractive. It is anticipated that operational efficiencies could be realized with improved alignment of departments which work together closely. The Home Economics Building Remodel project continues UW-Stout’s commitment to academics and facilities. This building houses three of the four colleges on campus: College of Education, Health and Human Sciences (CEHHS); College of Management (COM); and College of Science, Technology, Engineering and Mathematics (CSTEM). With the 2008 academic program realignment, the Home Economics building is not only in need of building infrastructure repair or replacement, but also programmatic reconfiguration to better consolidate similar functions and improve operational efficiencies. The Sports and Fitness Center Remodel and Addition project addresses UW-Stout’s most critical need for additional space. The current building, which provides facilities for physical education, recreation, intramurals and athletics, is experiencing deteriorating infrastructure such as air quality and plumbing. The current facilities do not meet the expectations of students and other users of the building in regards to adequate building systems and facilities to meet the demands of students and athletics. The Fryklund Hall Remodel project primarily addresses the deteriorating conditions of building infrastructure systems including HVAC, plumbing, electrical, telecommunications and life safety. The evolving and changing academic programs cannot be adequately served with aged building systems resulting in health and safety concerns. A new academic building will replace the deteriorating Communication Technologies and Vocational Rehabilitation buildings. Both of these buildings are second-hand use (Communication Technologies was originally designed as a student center and Vocational Rehabilitation was originally designed as a library). The new building will address academic, space management and building infrastructure concerns. The Applied Arts Remodel project primarily addresses the deteriorating conditions of building infrastructure systems including HVAC, plumbing, electrical, telecommunications and life safety. The evolving and changing academic programs cannot be adequately served with aged building systems resulting in health and safety concerns. 5/20/2010 Project Sequence Chart IIC - 2 UW-Stout Campus Physical Development Plan 2011-17 Program Revenue (PR) Priority Project Request Summary In fall 2009, UW-Stout completed a residence hall renewal plan study which identifies deficiencies in all residence halls on Main Campus and North Campus, except for Red Cedar Hall and Hovlid Hall. It provides facility condition reports (building system infrastructure, accessibility, and life safety), architectural recommendations, cost estimates and a schedule for implementation. As a result of this study, it is anticipated that projects will be proposed for residence hall remodels in each of the next five biennia beginning in 2011-13. 5/20/2010 Project Sequence Chart IIC - 3 UW-Stout Campus Physical Development Plan 2011-17 D. ORIGIN-DESTINATION CHART The Origin-Destination Chart indicates how department relocations and new academic programs will promote and foster the success of this realignment. Department relocations and academic programs, approved or proposed, are indicated in italics. Bowman Hall Admissions Registration and Records Financial Aid Dean of Students Graduate School University Counseling Disability Services International Education Career Advisement Center Veterans Center (VC) - New Educational Talent Search (ETS) Robert S. Swanson Learning Center ETS Millennium Hall Technology & Information Services Learning Technology Services Telecommunications & Networking Nakatani Teaching & Learning Center ASK5000 Help Desk Circulation and Reference University Archives and ARC Cataloging and Processing Periodicals and Serials Instructional Resource Services Educational Materials Center (EMC) Interlibrary Loan Center for Applied Ethics (CAE) University Honors (UH) Women & Gender Studies (WGS) UH/WGS/SAS/FS Senate of Academic Staff (SAS) Faculty Senate (FS) UH/WGS/SAS/FS McCalmont Hall Housing Stout Vocational Rehabilitation Institute (SVRI) School of Education (SOE) Psychology (PSYCH) SVRI New Academic Building Rehabilitation & Counseling (RC) Stout Vocational Rehabilitation Institute (SVRI) Apparel & Communication Technologies (ACT) Technical Education (TE) ACT Note: Replaces Communication Technologies and Vocational Rehabilitation buildings Harvey Hall College of Arts, Humanities and Social Sciences (CAHSS) English & Philosophy PSYCH Social Science SOE (Temp) Speech Communications, Foreign Languages, Theatre & Music University Honors (UH) Women & Gender Studies (WGS) SOE Senate of Academic Staff (SAS) (HMEC) Faculty Senate (FS) (Perm) Educational Talent Search (ETS) Mathematics, Statistics & Computer Science (MSCS) School of Education (SOE) Psychology (PSYCH) Military Science (MS/ROTC) ACT/TE RC/SVRI Communication Technologies Apparel & Communication Technologies (ACT) Technical Education (TE) Military Science (MS/ROTC) Vocational Rehabilitation Rehabilitation & Counseling (RC) Stout Vocational Rehabilitation Institute (SVRI) Note: Communication Technologies building will be vacated and demolished Note: Vocational Rehabilitation building will be vacated and demolished Student Health Center Student Health Services (SHS) Note: Student Health Center will be vacated 5/20/2010 MS/ROTC Sports & Fitness Center SHS Physical Education Athletics Recreation Intramurals Student Health Center (SHS) Origin-Destination Chart Jarvis Hall Science Wing MSCS Biology (BIO) Chemistry (CHEM) Physics (PHY) Risk Control (RC) People Process Culture (PPC) Business (BUS) Mathematics, Statistics & Computer Science (MSCS) Micheels Hall Art & Design (A&D) Business Operations & Management (O&M) Construction Masters of Fine Arts in Design New Child & Family Study Center Early Childhood Education (ECE) Day Care Center (DCC) Pre-School (PS) 4K Program (4K) Note: Child & Family Study Center (CFSC) will be vacated ECE/DCC/PS/4K Home Economics (HMEC) Food & Nutrition (F&N) Hospitality & Tourism (H&T) Apparel & Communication Technologies (ACT) Human Development & Family Studies (HDFS) Early Childhood Education (ECE) Day Care Center (DCC) Pre-School (PS) 4K Program (4K) SOE IID - 1 UW-Stout Campus Physical Development Plan 2011-17 UW-Stout consists of four colleges: College of Arts, Humanities and Social Sciences (CAHSS); College of Education, Health and Human Sciences (CEHHS); College of Management (COM); and College of Science, Technology, Engineering and Mathematics (CSTEM). Construction of the Jarvis Hall Science Wing Renovation and Addition project is scheduled for completion and occupation in August 2010. This project will provide state-of-the-art laboratories for biology, chemistry and physics; and general assignment classrooms. The Department of Mathematics, Statistics and Computer Science (MSCS) will relocate from Harvey Hall to the Jarvis Hall Science Wing. The relocation of MSCS will better facilitate the collaborative instruction of math and the sciences which are included in the new College of Science, Technology, Engineering and Mathematics (CSTEM). With the relocation of MSCS to the Jarvis Hall Science Wing, the Harvey Hall Renovation – Phase II Infrastructure project warrants greater consideration and opportunity. MSCS currently occupies approximately 8,000 ASF in Harvey Hall which will become available for other use. In addition, the MSCS relocation will result in less general assignment classroom demand in Harvey Hall. This will provide opportunity to take some poor quality general assignment classrooms off-line. There are twenty (20) general assignment classrooms in Harvey Hall. Five of these classrooms, totaling approximately 3,200 ASF, were graded as Type B, meaning that they are less than desirable instructional spaces and should be considered for being taken off-line. Combining the available MSCS area of 8,000 ASF and the classroom area of 3,200 ASF, results in 11,200 ASF of vacant space in Harvey Hall. McCalmont Hall, constructed originally as a residence hall, currently houses academic offices (Department of Psychology and School of Education) and laboratories (Department of Psychology), Stout Vocational Rehabilitation Institute (SVRI) clients and one floor of student housing (fifth floor). The Department of Psychology occupies 6,000 ASF and the School of Education (SOE) occupies 4,400 ASF for a total of 10,400 ASF. In late 2010/early 2011, Psychology will relocate to Harvey Hall in the 11,200 ASF of vacated space. University Housing could then reclaim half of the second floor and all of the third and fourth floors in McCalmont Hall for student housing. SVRI would remain in McCalmont Hall in the near term development plan. Potentially, SOE offices in McCalmont Hall could also relocate to Harvey Hall. This would be a temporary relocation until an addition is constructed next to the Home Economics building and all of SOE would be housed in the Home Economics building. The temporary relocation of SOE from McCalmont Hall to Harvey Hall cannot occur until the Harvey Hall Renovation – Phase II Infrastructure project is completed. Military Science is also being considered for relocation to Harvey Hall. This can only occur after other departments and programs are relocated from Harvey Hall. These include University Honors (considered for relocation to the Robert S. Swanson Learning Center); Women and Gender Studies; Faculty Senate; Senate of Academic Staff; and Educational Talent Search. A Veterans Center is being considered for location in Bowman Hall. The ASK5000 Help Desk was relocated to Millennium Hall from Micheels Hall 184. With the reassignment of two computer labs, the space vacated in Micheels Hall could be used to accommodate the new Master of Fine Arts in Design and, possibly, the Gaming and Design Development program. It is estimated that 7,500 ASF will be required for these two programs. The vacated area in Micheels Hall provides approximately 8,000 ASF. The Child and Family Study Center (CFSC) located on the east side of Main Campus and constructed in 1970, is a 4,639 ASF/7,270 GSF facility primarily used as a pre-school instructional laboratory in the Early Childhood Education program. The infant and toddler program is located in the Home Economics building, west of the CFSC. It is desirable to combine both of these functions in the Home Economics building to maximize building and operational efficiencies and minimize duplication of services. Student Health Services is located in the Student Health Center on North Campus. This facility, circa 1957, consists of 8,005 ASF/11,572 GSF of examination, laboratory and office space. This building was originally constructed as a health care facility for the city of Menomonie. Through acquisition, it became the Student Health Center for UW-Stout. Although the allocation of space seems appropriate for its function, the condition and location of the building is a concern. The building is over fifty years old and its infrastructure requires much maintenance. The basement level is unoccupiable due to health and safety 5/20/2010 Origin-Destination Chart IID - 2 UW-Stout Campus Physical Development Plan 2011-17 issues. Its location on North Campus makes it very inconvenient for Main Campus residents (all freshmen and many sophomores). Its relocation to the Sports and Fitness Center on Main Campus accomplishes two issues. First, it will provide easier and more convenient access for residents on Main Campus who are the primary users of the center. Secondly, it will foster the promotion of a Wellness Center at UW-Stout. In addition to the above referenced relocations, new academic programs on UW-Stout’s Academic Plan will be incorporated in existing academic areas (reference Background Section E. Program Trends). It is anticipated that these programs will not require additional square feet. Academic Program M.S. Gerontology Location Home Economics The Campus Master Plan has been approved and much of its findings, recommendations and direction are reflected in the Origin-Destination planning. Two existing buildings, Vocational Rehabilitation and Communication Technologies, are older, second-use facilities. The Campus Master Plan has proposed that these two buildings be vacated and demolished. The departments and programs currently in these two buildings will be relocated to a new academic building. Further investigation is required as to what departments and programs would be best suited for relocation in a new academic building. 5/20/2010 Origin-Destination Chart IID - 3 UW-Stout Campus Physical Development Plan 2011-17 III. FACILITIES PROFILES Facilities Summary..................................................................................... III-2 Building Summary........................................................................................................... III-4 Site Development Summary ........................................................................................... III-6 Site Utility Summary ....................................................................................................... III-7 A. Building Profiles ................................................................................... IIIA Academic Buildings Applied Arts .................................................................................................................... IIIA-1 Bowman Hall................................................................................................................... IIIA-2 Child and Family Study Center ....................................................................................... IIIA-3 Communication Technologies ........................................................................................ IIIA-4 Fryklund Hall ................................................................................................................... IIIA-5 Harvey Hall ..................................................................................................................... IIIA-6 Home Economics............................................................................................................ IIIA-7 Jarvis Hall Science Addition ........................................................................................... IIIA-8 Jarvis Hall Science Wing ................................................................................................ IIIA-9 Jarvis Hall Technology Wing .......................................................................................... IIIA-10 McCalmont Hall .............................................................................................................. IIIA-11 Micheels Hall .................................................................................................................. IIIA-12 Millennium Hall ............................................................................................................... IIIA-13 Robert S. Swanson Learning Center .............................................................................. IIIA-14 Sports and Fitness Center .............................................................................................. IIIA-15 Sports and Fitness Center Addition A ............................................................................ IIIA-16 Sports and Fitness Center Addition B ............................................................................ IIIA-17 Vocational Rehabilitation ................................................................................................ IIIA-18 Williams Stadium ............................................................................................................ IIIA-19 Administrative Buildings Administration ................................................................................................................. IIIA-20 General Services ............................................................................................................ IIIA-21 Heating Plant .................................................................................................................. IIIA-22 Heating Plant Addition .................................................................................................... IIIA-23 Heating Plant Electrical Substation ................................................................................ IIIA-24 Louis Smith Tainter House ............................................................................................. IIIA-25 Memorial Student Center ................................................................................................ IIIA-26 Merle M. Price Commons ............................................................................................... IIIA-27 Student Health Center .................................................................................................... IIIA-28 University Services ......................................................................................................... IIIA-29 Residence Halls Antrim Hall (AF) .............................................................................................................. IIIA-30 Callahan Hall (JTC) ........................................................................................................ IIIA-31 Chinnock Hall (HKMC) ................................................................................................... IIIA-32 Curran Hall (CKTO) ........................................................................................................ IIIA-33 Fleming Hall .................................................................................................................... IIIA-34 Froggatt Hall (AF) ........................................................................................................... IIIA-35 Hansen Hall (HKMC) ...................................................................................................... IIIA-36 Hovlid Hall ....................................................................................................................... IIIA-37 North Point Dining and Fitness Center ........................................................................... IIIA-38 Jeter Hall (JTC)............................................................................................................... IIIA-39 Keith Hall (HKMC) .......................................................................................................... IIIA-40 Kranzusch Hall (CKTO) .................................................................................................. IIIA-41 Milnes Hall (HKMC) ........................................................................................................ IIIA-42 North Hall ........................................................................................................................ IIIA-43 Oetting Hall (CKTO) ....................................................................................................... IIIA-44 5/21/2010 Table of Contents III - 1 UW-Stout Campus Physical Development Plan 2011-17 Red Cedar Hall ............................................................................................................... IIIA-45 South Hall ....................................................................................................................... IIIA-46 Tainter Hall (JTC) ........................................................................................................... IIIA-47 Tainter Hall Dining .......................................................................................................... IIIA-48 Tustison Hall (CKTO) ..................................................................................................... IIIA-49 Wigen Hall ...................................................................................................................... IIIA-50 B. Site Development Profile ...................................................................... IIIB-1 C. Site Utility Profile .................................................................................. IIIC-1 5/21/2010 Table of Contents III - 2 FACILITIES SUMMARY The UW-Stout campus consists of 1,465,903 ASF/2,181,608 NSF in sixty-six (66) academic, administrative and residential buildings. Total gross square feet (GSF) equates to 2,504,432 GSF. These numbers include the new square footage added with the Jarvis Hall Science Addition and Hovlid Hall Dining Addition which opened in 2009 and 2010, respectively. Buildings envelope systems on campus have many buildings with window systems of single panel, inoperable, and need of renovation. Window curtain walls have improper installation which leak and have no ability to get repaired or parts as the manufacture is out of business. Windows having insulated glazing have non thermo break in the metal frames provide a constant condensation issue. Masonry screen walls leak with failing masonry joints, broken bricks, missing caulking, failed vinyl flashing at lintels or base flashing. Roofing membranes (both EPDM and Built-up) and parapet wall flashing leaking. Hollow metal doors and frames are failing from corrosion. Foundations have moisture issues with failed water proofing or a lack of water proofing with a high ground water table on campus. Metal curtain wall leaking and rusting panels completed through. Older buildings do not have energy efficient designed HVAC systems. The majority of our systems are constant air flow systems with pneumatic controls. Pneumatic controls are the majority type used in monitoring our facilities which provides limited information and limited adjustment ability. None uniform heat/cooling through out the facilities producing overheated spaces and under heated locations with in the facilities. Mold and poor air quality complaints are a constant in are older buildings. A few facilities have fiber board ductwork mains which have failed, providing ventilation to the intestinal spaces verses the finished spaces. The HVAC system valves are unable to move or break off in the open position, prohibiting the ability to isolate, adjust and repair the system. HVAC piping system has continual water hammering, failures (rotting piping), plugged coils, blown diaphragms, and failed heat wheels. Several air handling units throughout campus have limited to no access ability to clean and service the existing coils, causing inefficient operations and premature failure of the coils. Cooling for the electronic equipment for the telecommunication systems in Millennium Hall are at capacity and unable to provide emergency back up for the campus information technology’s electronic equipment. Plumbing systems throughout campus have plumbing failures in the original piping materials used in our facilities; galvanized drain waste lines, drinking fountains, building isolation valves are nonfunctional, shower floor drains and lead safings leak. Existing wall hung configurations require completed replacement to match replacement toilet requirements. The majority of our roofing drainage systems are unable to meet the storm water management requirements as they currently drain into the city’s storm mains. Pool drain water is discharge noncompliant with current WDNR requirements. Existing piping systems for the pool are failing due to rotting piping and valving which is inoperable. The discharge is currently draining chlorinated water into the storm mains. Non-ADA compliant restrooms are in several facilities through out campus. Asbestos containing materials are a constant impediment in conducting maintenance activities on campus. Existing piping chases are full of ACM materials and have limited space to work in. VAT tile wear surface has worn off in a majority of offices producing dust within the space. Fire stopping installations, a Life safety code, is non existent in all but Red Cedar Residence Hall on our campus. Building electrical distribution panels are at capacity within the facilities. Emergency generators and their distribution panels have both life safety and non life safety circuitry on the same panels and switches. Generators are obsolete and replacement parts are impossible to obtain. Millennium halls generator is undersized to provide emergency backup when required for the information technology equipment. Field lighting systems around campus are non efficient with 5/21/2010 Facilities Summary III - 3 1000W metal halide lamps and 1500 W quartz lamps. Site lighting for the campus has non efficient lighting. The UPS systems are at capacity for the telecommunication equipment and need replacement for the heating plant as the system has met its recommended life capacity. Telecommunication closets throughout campus are undersized and have no ventilation serving these rooms or are sharing square footage with janitorial closets, mechanical spaces or electrical rooms. Cabling has been installed free form across ceilings with unlabeled and abandoned cable in place. The athletic/recreation fields (baseball, soccer and track) have improper grading and drainage issues. The Johnson Fieldhouse bleachers in the Sports and Fitness Center experience constant repair and failing electrical components. The bleachers do not provide ADA seating accommodations. Overall, Johnson Fieldhouse experiences electrical issues throughout the gymnasium and press box areas. Parking lots do not meet WDNR storm water management requirements. Grading and drainage changes are needed to meet the requirement. 5/21/2010 Facilities Summary III - 4 BUILDING SUMMARY Building Construction Chronology 1,800,000 3,000,000 1,600,000 2,500,000 1,200,000 2,000,000 1,000,000 1,500,000 800,000 600,000 1,000,000 400,000 CUMULATIVE SQUARE FEET (LINES) PERIOD SQUARE FEET (BARS) 1,400,000 500,000 200,000 0 1850-1875 1876-1900 1901-1925 1926-1950 1951-1975 1976-2000 2001-2025 184,030 ASF 0 33,011 51,935 0 934,827 262,100 GSF 0 66,118 136,814 0 1,552,739 400,693 348,068 ASF TOTAL 0 33,011 84,946 84,946 1,019,773 1,281,873 1,465,903 GSF TOTAL 0 66,118 202,932 202,932 1,755,671 2,156,364 2,504,432 0 CONSTRUCTION PERIOD Approximately 62% of building space was constructed in the 25-year time period of 1951-1975. This is a result of the aggressive construction program initiated by the state to address space deficiencies at its universities. These buildings are now all of an age and condition which warrants major renovation and/or replacement. Building infrastructure systems, such as HVAC, plumbing and electrical, are deteriorating due to failing and obsolete parts. Maintenance is more difficult and requires more time. Building functionality on the UW-Stout campus varies depending on the age, condition and use. For example, the Vocational Rehabilitation building was originally designed and constructed as a library in 1954. It is now used as an academic building and houses classrooms, laboratories and offices. This building is showing signs of system infrastructure fatigue due to its 54 years of age and the inherent inefficiencies of its repurposing as an academic building. The Communication Technologies building, constructed in 1959 suffers the same fate. It was originally designed and constructed as a student union. Harvey Hall is now 94 years old. No major renovation or remodel has ever been performed on this building. While it somewhat works as a classroom and office building, its system infrastructure and original design result in a very inefficient building in regards to configuration, HVAC, electrical, plumbing, telecommunications, ADA accessibility and life safety. The Sports and Fitness Center, in addition to the outdoor fields, is in heavy use. The increasing popularity of recreational programs has resulted in a high demand of indoor and outdoor facilities. Scheduling these facilities for intramural, recreation and athletic use is difficult. In addition, Menomonie High School uses campus facilities such as Williams Stadium, multi-purpose room, outdoor track and tennis courts for their athletic events. The Menomonie Thunderhawks, a semiprofessional football team, also use Williams Stadium for their games and practices. 5/21/2010 Facilities Summary III - 5 UW-Stout is also addressing the same needs in its residence halls. Most were built in the 1960’s and were constructed with little flexibility to accommodate the needs of today’s students. Paramount to resident concerns is power, telecommunications and updated restroom facilities. With the implementation of the e-Scholar (laptop) program, the campus has committed resources for providing technology-enabled facilities. However, this is difficult, and costly, to do in many buildings due to their age and lack of space for telecommunication closets. Harvey Hall is a prime example. Many interior walls in campus buildings are of masonry construction. This provides little flexibility and costly and time consuming reconfigurations of space. 5/21/2010 Facilities Summary III - 6 SITE DEVELOPMENT SUMMARY Most site development identified in the 2011-2017 Campus Physical Development Plan centers on the need for more athletic and recreational outdoor space. The Campus Master Plan, approved in 2009, has identified other site issues including: parking lot location and development; vehicle and pedestrian circulation; campus boundaries; and landscaping and site furnishings. All of these issues relate to the creation of a campus image used in the recruitment and retention of students. The campus has identified the following high priority issues to be addressed in the Campus Master Plan: University Profile o Polytechnic Designation o Academic Planning o Enrollment Trends o Classrooms and Laboratories o Campus Infrastructure North Campus Jeter-Tainter-Callahan (JTC) Residence Hall Site Energy Efficiency and Sustainability Campus Image o Campus “Gateway” o Circulation (pedestrian and vehicle) o Architectural Theme o Landscaping Some specific development opportunities include: 5/21/2010 Acquisition of properties on both Main Campus and North Campus to address parking needs o Campus boundary expansion to the west and east on Main Campus and west and south on North Campus o Parking lot development o Lighting Traffic th rd o Traffic calming ideas along Broadway Street/Highway 25, 10 Avenue and 3 Street Landscaping o Defining edges along Broadway Street/Highway 25 and east edge of campus Gateways o Defining entrances at the north, west and south ends of campus, including North Campus Athletic and Recreation Fields o Outdoor track replacement o Replacement of lights on Nelson Field (soccer field) o Installation of lights on the outdoor track o Regrading of Nelson Field to address drainage issues o Regrading of baseball field to address drainage issues o Shared press box/storage facility for outdoor track and soccer field o Installation of synthetic turf on Nelson Field (soccer field) o Installation of irrigation system on Nelson Field (soccer field) o Installation of synthetic turf on baseball field o Installation of irrigation system on baseball field o Ropes course expansion (including restrooms, storage and water) Facilities Summary III - 7 SITE UTILITY SUMMARY Campus distribution systems supply steam, condensate, electricity, chilled water, signal, clock, card access and building automation to the campus. Stand alone emergency generators serve specific facilities on the campus. The following table summarizes utility capacities and maximum loads for the past calendar year (January through December 2007). Utility Parameter Maximum Demand Total Capacity Firm Capacity Steam 70,000 215,000 115,000 PPH PPH PPH Chilled Water Electrical 1200 2400 5687 5954 Tons Tons KW KVA Notes: 1. 2. 3. Firm Capacity is the maximum steam output with the largest boiler out of service. Maximum Demand for Electrical Utility is based on monthly utility bills. Chilled water fields only apply to central and district systems. Individual building chillers are not included in these values. Campus steam distribution is high pressure steam to each building where it is reduced to medium and /or low pressure. The overall system is in satisfactory condition. A restriction of a bottleneck (reduced pipe) size prohibits the ability to provide the required steam capacity to the north campus. The steam distribution lacks the ability to redirect steam to provide a back up feed largest complex on campus; Jarvis Addition, Jarvis Science, Jarvis Technology, Micheels Hall and Applied Arts buildings. Campus primary electrical system is 4160V network of 5KV feeder cables which serve each campus building from two line-ups of switchgear located adjacent to the heating plant. The substation contains to 5MVA, 15V/5KV transformers served from separate distribution feeders. There is a tie circuit breaker between the east and west switch gear line-ups. The currently load balance is approximately 35% of the load on the east bank or transformer #2 , and approximately 65% of the load on the west bank, or transformer #1. The critical time for the electrical use is in May and September when the students are on campus and hot temperature spells are common. Metering components are burned out, switches with inoperable indicator signals verifying that the switches are locked into place. The substation due is nearing capacity and will lose the ability to operate on one distribution bank through the tie breaker. The central chiller water distribution system consists of three 800 Ton chillers which serve nine buildings. The central chiller water system is in excellent condition. The campus chilled water system has ten buildings which have stand alone chillers. These buildings have chillers, towers and associated pumps and controls have high energy usage, high chemical usage, scaling issues and plugged coils and tower corrosion failures. The stand alone chillers are in poor condition. City of Menomonie provides local utilities of water, sanitary, storm water to the campus. Campus is responsible for the management of the storm water laterals which serve each facility throughout the campus and connect to the Cities mains. Space limitations and the existing parking lot grading designs are the main obstacles to accomplishing the storm water management requirements. The system is in satisfactory condition. The campus signal system has a fiber optic backbone extending from the head–end equipment located in Millennium Hall through the campus distribution signal system into each building. The fiber back bone installation started in 1993. The system is in good working condition. The campus has a central 120v clock system serving the entire campus from the General Services building. This system was installed in 1975. The system is in poor working condition. 5/21/2010 Facilities Summary III - 8 The campus building automation system (BAS) is a Johnson Controls building automation system consisting of several generations of legacy DDC equipment. The second generation legacy DDC equipment is no longer supported and parts are only available through dealers that sell used equipment. The first generation DDC legacy supervisory control equipment is being phased out by the manufacturer and utilizes outdated Arcnet communication technology. The system is in poor condition. The central chilled water distribution plant, Administration building and the Jarvis Hall Science Wing Renovation and Addition will have web-based Ethernet communications and will be in good condition. Card access is installed in thirty-nine (39) buildings on campus: University Services, General Services, Williams Stadium, South Hall, North Hall, CKTO Hall, HKMC Hall, McCalmont Hall, Antrim Froggatt Hall, Fleming Hall, Hovlid Hall, Wigen Hall, Red Cedar Hall, JTC Hall, Student Health Center, Merle M. Price Commons, Communication Technologies, Memorial Student Center, Applied Arts, Administration, Robert S. Swanson Learning Center, Home Economics, Child and Family Study Center, Vocational Rehabilitation, Sports and Fitness Center, Fryklund Hall, Bowman Hall and Harvey Hall. Card access is in good working condition. Emergency generators are located in nineteen (19) buildings; Heating plant, Red Cedar Hall, Vocational Rehabilitation, Robert S. Swanson Learning Center, Millennium Hall, University Services, Memorial Student Center, Jarvis Hall Science Wing, Oetting Hall , Communication Technologies, Sports and Fitness Center, General Services, Fryklund Hall, Home Economics, Harvey Hall, Bowman Hall, Applied Arts, Merle M. Price Commons and Williams Stadium. Overall, the generators are in satisfactory condition. City of Menomonie provides local utilities of water, sanitary and storm water to the campus. Campus is responsible for the management of the storm water laterals which serve each facility throughout the campus and connect to the city’s mains. Space limitations and the existing parking lot grading designs are the main obstacles to accomplishing the storm water management requirements. The system is in satisfactory condition. Xcel energy provides gas distribution throughout campus. Local telephone is provides by AT&T and cable TV is provided by Charter Communications. The following lists utility type projects planned on campus. A building automation system (BAS) upgrade project would replace the existing Johnson Controls first generation application specific DDC controllers that are controlling existing air handling units. Other mechanical equipment will remain in place and be integrated into the new BAS. The existing Johnson Controls second generation Field Processing Unit (FPU) equipment controlling mechanical equipment will be replaced. The campus electrical substation upgrade project will replace the 1964 campus 5KV primary electrical service. Two 5 MVA, 13.3 – 4.16 KV utility owned transformers will be replaced by two 7.5/10.5 state owned units. Two line-ups of metal clad switchgear with bus tie will also be replaced. Each line up will include compartments for one main, one tie and seven feeder draw-out air magnetic vacuum circuit breakers along with AC power transformers/panel, DC control power supply and metering. The existing capacitor bank transclosure will also be replaced. The east side steam loop extension project is steam/condensate duct bank installation between pit #19 at the NE corner of the Robert S. Swanson Learning Center and pit #7 west of the Jarvis Hall Science Wing will provide a secondary feed to serve the southeast quadrant of campus. 5/21/2010 Facilities Summary III - 9 Phase II of the central chilled water project will extend the central chilled water piping distribution system to Vocational Rehabilitation, Harvey Hall, Fryklund Hall, Memorial Student Center, Merle M. Price Commons and McCalmont Hall and remove the building specific chillers. Phase III of the central chilled water project distribution will connect Sports and Fitness Center and Millennium Hall to complete the central chilled water project. Recently completed projects include construction of the central chiller water plant inside the Heating Plant along with phase I of the piping system. Phase I was completed in 2007 and included connections to Administration, Bowman Hall, Communication Technologies, Robert S. Swanson Learning Center, Home Economics, Jarvis Hall Science Wing, Jarvis Hall Technology Wing, Micheels Hall and Applied Arts went in to service in 2007. A primary electric upgrade project, serving Harvey Hall was completed in 2006. A 9,000 PPH gas/oil boiler (#1) in the heating plant was replaced with a 25,000 PPH boiler in 2006. 5/21/2010 Facilities Summary III - 10 UW-Stout Campus Physical Development Plan 2011-17 Red Cedar Hall ............................................................................................................... IIIA-45 South Hall ....................................................................................................................... IIIA-46 Tainter Hall (JTC) ........................................................................................................... IIIA-47 Tainter Hall Dining .......................................................................................................... IIIA-48 Tustison Hall (CKTO) ..................................................................................................... IIIA-49 Wigen Hall ...................................................................................................................... IIIA-50 B. Site Development Profile ...................................................................... IIIB-1 C. Site Utility Profile .................................................................................. IIIC-1 5/20/2010 Table of Contents III - 2 FACILITIES SUMMARY The UW-Stout campus consists of 1,465,903 ASF/2,181,608 NSF in sixty-six (66) academic, administrative and residential buildings. Total gross square feet (GSF) equates to 2,504,432 GSF. These numbers include the new square footage added with the Jarvis Hall Science Addition and Hovlid Hall Dining Addition which opened in 2009 and 2010, respectively. Buildings envelope systems on campus have many buildings with window systems of single panel, inoperable, and need of renovation. Window curtain walls have improper installation which leak and have no ability to get repaired or parts as the manufacture is out of business. Windows having insulated glazing have non thermo break in the metal frames provide a constant condensation issue. Masonry screen walls leak with failing masonry joints, broken bricks, missing caulking, failed vinyl flashing at lintels or base flashing. Roofing membranes (both EPDM and Built-up) and parapet wall flashing leaking. Hollow metal doors and frames are failing from corrosion. Foundations have moisture issues with failed water proofing or a lack of water proofing with a high ground water table on campus. Metal curtain wall leaking and rusting panels completed through. Older buildings do not have energy efficient designed HVAC systems. The majority of our systems are constant air flow systems with pneumatic controls. Pneumatic controls are the majority type used in monitoring our facilities which provides limited information and limited adjustment ability. None uniform heat/cooling through out the facilities producing overheated spaces and under heated locations with in the facilities. Mold and poor air quality complaints are a constant in are older buildings. A few facilities have fiber board ductwork mains which have failed, providing ventilation to the intestinal spaces verses the finished spaces. The HVAC system valves are unable to move or break off in the open position, prohibiting the ability to isolate, adjust and repair the system. HVAC piping system has continual water hammering, failures (rotting piping), plugged coils, blown diaphragms, and failed heat wheels. Several air handling units throughout campus have limited to no access ability to clean and service the existing coils, causing inefficient operations and premature failure of the coils. Cooling for the electronic equipment for the telecommunication systems in Millennium Hall are at capacity and unable to provide emergency back up for the campus information technology’s electronic equipment. Plumbing systems throughout campus have plumbing failures in the original piping materials used in our facilities; galvanized drain waste lines, drinking fountains, building isolation valves are nonfunctional, shower floor drains and lead safings leak. Existing wall hung configurations require completed replacement to match replacement toilet requirements. The majority of our roofing drainage systems are unable to meet the storm water management requirements as they currently drain into the city’s storm mains. Pool drain water is discharge noncompliant with current WDNR requirements. Existing piping systems for the pool are failing due to rotting piping and valving which is inoperable. The discharge is currently draining chlorinated water into the storm mains. Non-ADA compliant restrooms are in several facilities through out campus. Asbestos containing materials are a constant impediment in conducting maintenance activities on campus. Existing piping chases are full of ACM materials and have limited space to work in. VAT tile wear surface has worn off in a majority of offices producing dust within the space. Fire stopping installations, a Life safety code, is non existent in all but Red Cedar Residence Hall on our campus. Building electrical distribution panels are at capacity within the facilities. Emergency generators and their distribution panels have both life safety and non life safety circuitry on the same panels and switches. Generators are obsolete and replacement parts are impossible to obtain. Millennium halls generator is undersized to provide emergency backup when required for the information technology equipment. Field lighting systems around campus are non efficient with 5/20/2010 Facilities Summary III - 3 1000W metal halide lamps and 1500 W quartz lamps. Site lighting for the campus has non efficient lighting. The UPS systems are at capacity for the telecommunication equipment and need replacement for the heating plant as the system has met its recommended life capacity. Telecommunication closets throughout campus are undersized and have no ventilation serving these rooms or are sharing square footage with janitorial closets, mechanical spaces or electrical rooms. Cabling has been installed free form across ceilings with unlabeled and abandoned cable in place. The athletic/recreation fields (baseball, soccer and track) have improper grading and drainage issues. The Johnson Fieldhouse bleachers in the Sports and Fitness Center experience constant repair and failing electrical components. The bleachers do not provide ADA seating accommodations. Overall, Johnson Fieldhouse experiences electrical issues throughout the gymnasium and press box areas. Parking lots do not meet WDNR storm water management requirements. Grading and drainage changes are needed to meet the requirement. 5/20/2010 Facilities Summary III - 4 BUILDING SUMMARY Building Construction Chronology 1,800,000 3,000,000 1,600,000 2,500,000 1,200,000 2,000,000 1,000,000 1,500,000 800,000 600,000 1,000,000 400,000 CUMULATIVE SQUARE FEET (LINES) PERIOD SQUARE FEET (BARS) 1,400,000 500,000 200,000 0 1850-1875 1876-1900 1901-1925 1926-1950 1951-1975 1976-2000 2001-2025 184,030 ASF 0 33,011 51,935 0 934,827 262,100 GSF 0 66,118 136,814 0 1,552,739 400,693 348,068 ASF TOTAL 0 33,011 84,946 84,946 1,019,773 1,281,873 1,465,903 GSF TOTAL 0 66,118 202,932 202,932 1,755,671 2,156,364 2,504,432 0 CONSTRUCTION PERIOD Approximately 62% of building space was constructed in the 25-year time period of 1951-1975. This is a result of the aggressive construction program initiated by the state to address space deficiencies at its universities. These buildings are now all of an age and condition which warrants major renovation and/or replacement. Building infrastructure systems, such as HVAC, plumbing and electrical, are deteriorating due to failing and obsolete parts. Maintenance is more difficult and requires more time. Building functionality on the UW-Stout campus varies depending on the age, condition and use. For example, the Vocational Rehabilitation building was originally designed and constructed as a library in 1954. It is now used as an academic building and houses classrooms, laboratories and offices. This building is showing signs of system infrastructure fatigue due to its 54 years of age and the inherent inefficiencies of its repurposing as an academic building. The Communication Technologies building, constructed in 1959 suffers the same fate. It was originally designed and constructed as a student union. Harvey Hall is now 94 years old. No major renovation or remodel has ever been performed on this building. While it somewhat works as a classroom and office building, its system infrastructure and original design result in a very inefficient building in regards to configuration, HVAC, electrical, plumbing, telecommunications, ADA accessibility and life safety. The Sports and Fitness Center, in addition to the outdoor fields, is in heavy use. The increasing popularity of recreational programs has resulted in a high demand of indoor and outdoor facilities. Scheduling these facilities for intramural, recreation and athletic use is difficult. In addition, Menomonie High School uses campus facilities such as Williams Stadium, multi-purpose room, outdoor track and tennis courts for their athletic events. The Menomonie Thunderhawks, a semiprofessional football team, also use Williams Stadium for their games and practices. 5/20/2010 Facilities Summary III - 5 UW-Stout is also addressing the same needs in its residence halls. Most were built in the 1960’s and were constructed with little flexibility to accommodate the needs of today’s students. Paramount to resident concerns is power, telecommunications and updated restroom facilities. With the implementation of the e-Scholar (laptop) program, the campus has committed resources for providing technology-enabled facilities. However, this is difficult, and costly, to do in many buildings due to their age and lack of space for telecommunication closets. Harvey Hall is a prime example. Many interior walls in campus buildings are of masonry construction. This provides little flexibility and costly and time consuming reconfigurations of space. 5/20/2010 Facilities Summary III - 6 SITE DEVELOPMENT SUMMARY Most site development identified in the 2011-2017 Campus Physical Development Plan centers on the need for more athletic and recreational outdoor space. The Campus Master Plan, approved in 2009, has identified other site issues including: parking lot location and development; vehicle and pedestrian circulation; campus boundaries; and landscaping and site furnishings. All of these issues relate to the creation of a campus image used in the recruitment and retention of students. The campus has identified the following high priority issues to be addressed in the Campus Master Plan: University Profile o Polytechnic Designation o Academic Planning o Enrollment Trends o Classrooms and Laboratories o Campus Infrastructure North Campus Jeter-Tainter-Callahan (JTC) Residence Hall Site Energy Efficiency and Sustainability Campus Image o Campus “Gateway” o Circulation (pedestrian and vehicle) o Architectural Theme o Landscaping Some specific development opportunities include: 5/20/2010 Acquisition of properties on both Main Campus and North Campus to address parking needs o Campus boundary expansion to the west and east on Main Campus and west and south on North Campus o Parking lot development o Lighting Traffic th rd o Traffic calming ideas along Broadway Street/Highway 25, 10 Avenue and 3 Street Landscaping o Defining edges along Broadway Street/Highway 25 and east edge of campus Gateways o Defining entrances at the north, west and south ends of campus, including North Campus Athletic and Recreation Fields o Outdoor track replacement o Replacement of lights on Nelson Field (soccer field) o Installation of lights on the outdoor track o Regrading of Nelson Field to address drainage issues o Regrading of baseball field to address drainage issues o Shared press box/storage facility for outdoor track and soccer field o Installation of synthetic turf on Nelson Field (soccer field) o Installation of irrigation system on Nelson Field (soccer field) o Installation of synthetic turf on baseball field o Installation of irrigation system on baseball field o Ropes course expansion (including restrooms, storage and water) Facilities Summary III - 7 SITE UTILITY SUMMARY Campus distribution systems supply steam, condensate, electricity, chilled water, signal, clock, card access and building automation to the campus. Stand alone emergency generators serve specific facilities on the campus. The following table summarizes utility capacities and maximum loads for the past calendar year (January through December 2007). Utility Parameter Maximum Demand Total Capacity Firm Capacity Steam 70,000 215,000 115,000 PPH PPH PPH Chilled Water Electrical 1200 2400 5687 5954 Tons Tons KW KVA Notes: 1. 2. 3. Firm Capacity is the maximum steam output with the largest boiler out of service. Maximum Demand for Electrical Utility is based on monthly utility bills. Chilled water fields only apply to central and district systems. Individual building chillers are not included in these values. Campus steam distribution is high pressure steam to each building where it is reduced to medium and /or low pressure. The overall system is in satisfactory condition. A restriction of a bottleneck (reduced pipe) size prohibits the ability to provide the required steam capacity to the north campus. The steam distribution lacks the ability to redirect steam to provide a back up feed largest complex on campus; Jarvis Addition, Jarvis Science, Jarvis Technology, Micheels Hall and Applied Arts buildings. Campus primary electrical system is 4160V network of 5KV feeder cables which serve each campus building from two line-ups of switchgear located adjacent to the heating plant. The substation contains to 5MVA, 15V/5KV transformers served from separate distribution feeders. There is a tie circuit breaker between the east and west switch gear line-ups. The currently load balance is approximately 35% of the load on the east bank or transformer #2 , and approximately 65% of the load on the west bank, or transformer #1. The critical time for the electrical use is in May and September when the students are on campus and hot temperature spells are common. Metering components are burned out, switches with inoperable indicator signals verifying that the switches are locked into place. The substation due is nearing capacity and will lose the ability to operate on one distribution bank through the tie breaker. The central chiller water distribution system consists of three 800 Ton chillers which serve nine buildings. The central chiller water system is in excellent condition. The campus chilled water system has ten buildings which have stand alone chillers. These buildings have chillers, towers and associated pumps and controls have high energy usage, high chemical usage, scaling issues and plugged coils and tower corrosion failures. The stand alone chillers are in poor condition. City of Menomonie provides local utilities of water, sanitary, storm water to the campus. Campus is responsible for the management of the storm water laterals which serve each facility throughout the campus and connect to the Cities mains. Space limitations and the existing parking lot grading designs are the main obstacles to accomplishing the storm water management requirements. The system is in satisfactory condition. The campus signal system has a fiber optic backbone extending from the head–end equipment located in Millennium Hall through the campus distribution signal system into each building. The fiber back bone installation started in 1993. The system is in good working condition. The campus has a central 120v clock system serving the entire campus from the General Services building. This system was installed in 1975. The system is in poor working condition. 5/20/2010 Facilities Summary III - 8 The campus building automation system (BAS) is a Johnson Controls building automation system consisting of several generations of legacy DDC equipment. The second generation legacy DDC equipment is no longer supported and parts are only available through dealers that sell used equipment. The first generation DDC legacy supervisory control equipment is being phased out by the manufacturer and utilizes outdated Arcnet communication technology. The system is in poor condition. The central chilled water distribution plant, Administration building and the Jarvis Hall Science Wing Renovation and Addition will have web-based Ethernet communications and will be in good condition. Card access is installed in thirty-nine (39) buildings on campus: University Services, General Services, Williams Stadium, South Hall, North Hall, CKTO Hall, HKMC Hall, McCalmont Hall, Antrim Froggatt Hall, Fleming Hall, Hovlid Hall, Wigen Hall, Red Cedar Hall, JTC Hall, Student Health Center, Merle M. Price Commons, Communication Technologies, Memorial Student Center, Applied Arts, Administration, Robert S. Swanson Learning Center, Home Economics, Child and Family Study Center, Vocational Rehabilitation, Sports and Fitness Center, Fryklund Hall, Bowman Hall and Harvey Hall. Card access is in good working condition. Emergency generators are located in nineteen (19) buildings; Heating plant, Red Cedar Hall, Vocational Rehabilitation, Robert S. Swanson Learning Center, Millennium Hall, University Services, Memorial Student Center, Jarvis Hall Science Wing, Oetting Hall , Communication Technologies, Sports and Fitness Center, General Services, Fryklund Hall, Home Economics, Harvey Hall, Bowman Hall, Applied Arts, Merle M. Price Commons and Williams Stadium. Overall, the generators are in satisfactory condition. City of Menomonie provides local utilities of water, sanitary and storm water to the campus. Campus is responsible for the management of the storm water laterals which serve each facility throughout the campus and connect to the city’s mains. Space limitations and the existing parking lot grading designs are the main obstacles to accomplishing the storm water management requirements. The system is in satisfactory condition. Xcel energy provides gas distribution throughout campus. Local telephone is provides by AT&T and cable TV is provided by Charter Communications. The following lists utility type projects planned on campus. A building automation system (BAS) upgrade project would replace the existing Johnson Controls first generation application specific DDC controllers that are controlling existing air handling units. Other mechanical equipment will remain in place and be integrated into the new BAS. The existing Johnson Controls second generation Field Processing Unit (FPU) equipment controlling mechanical equipment will be replaced. The campus electrical substation upgrade project will replace the 1964 campus 5KV primary electrical service. Two 5 MVA, 13.3 – 4.16 KV utility owned transformers will be replaced by two 7.5/10.5 state owned units. Two line-ups of metal clad switchgear with bus tie will also be replaced. Each line up will include compartments for one main, one tie and seven feeder draw-out air magnetic vacuum circuit breakers along with AC power transformers/panel, DC control power supply and metering. The existing capacitor bank transclosure will also be replaced. The east side steam loop extension project is steam/condensate duct bank installation between pit #19 at the NE corner of the Robert S. Swanson Learning Center and pit #7 west of the Jarvis Hall Science Wing will provide a secondary feed to serve the southeast quadrant of campus. 5/20/2010 Facilities Summary III - 9 Phase II of the central chilled water project will extend the central chilled water piping distribution system to Vocational Rehabilitation, Harvey Hall, Fryklund Hall, Memorial Student Center, Merle M. Price Commons and McCalmont Hall and remove the building specific chillers. Phase III of the central chilled water project distribution will connect Sports and Fitness Center and Millennium Hall to complete the central chilled water project. Recently completed projects include construction of the central chiller water plant inside the Heating Plant along with phase I of the piping system. Phase I was completed in 2007 and included connections to Administration, Bowman Hall, Communication Technologies, Robert S. Swanson Learning Center, Home Economics, Jarvis Hall Science Wing, Jarvis Hall Technology Wing, Micheels Hall and Applied Arts went in to service in 2007. A primary electric upgrade project, serving Harvey Hall was completed in 2006. A 9,000 PPH gas/oil boiler (#1) in the heating plant was replaced with a 25,000 PPH boiler in 2006. 5/20/2010 Facilities Summary III - 10 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Applied Arts 285-0L-0019 Academic 1972 85,579 Floors GSF 140,346 GPR 100 % AG UG 3 0 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING vii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Applied Arts building has been used as an academic facility since its original construction. Occupant(s) and Use(s) Building envelope in good shape. Power operated door operators are aged. Mechanical Applied Arts houses the College of Arts, Humanities and Social Sciences (Art and Design) and College of Science, Technology, Engineering and Mathematics (Engineering and Technology). Classrooms, laboratories and faculty/staff offices support the academic needs. Condensate lines require metering added to the building. Control valves are old. AHU’s A3E, A4E and A5E are being replaced in the summer of 2010. AHU 3 has a bad heating coil. Electrical Functionality Assessment Electrical system in good working order. Card access in sixteen labs. Additional space to address programmatic needs. Other Building Issues Late hour access for students is necessary for project work. Future Building Plans A major project is proposed to remodel and renovate this building to address academic program and infrastructure deficiencies. All Agency Project Request to replace three air handling units in summer 2010. Communication Building cabling system is outdated. Plumbing Drinking fountains, sinks and faucets are deteriorating. Urinals rebuilt five years ago. Clay pits are filled. Conveying Freight/ passenger elevator is in satisfactory condition. Code and Health/Safety Sprinkled system for paint booths. 5/20/2010 Equipment and Furnishings Building Profile IIIA - 1 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Bowman Hall 285-0L-0003 Administration/Academic 1897 27,083 Floors GSF 51,406 GPR 100 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Bowman Hall is named for Clyde Bowman, who was the acting president following Lorenzo Dow Harvey. It has always been used as an academic facility. It is listed on the National Register of Historic Places and also lies within the Menomonie Historic Preservation Commission district. Limited remodeling or renovation has occurred in the past. Occupant(s) and Use(s) Bowman Hall currently houses Enrollment Services (Admissions, Financial Aid and Registration and Records); Graduate School, Counseling, Career Exploration, Dean of Students, International Education, Multicultural Student Services, Upward Bound and Disability Services. In addition, there are three (3) general assignment classrooms. Functionality Assessment Bowman Hall is used primarily for student services. Its inherent design and construction has resulted in inefficient and disconnected functionality. Building and floor accessibility is difficult. Other Building Issues Future Building Plans Bowman Hall has been identified as the second major project priority on the UW-Stout campus. The intent is to focus on its role as a complete student services building. Code and Health/Safety Building fire alarm system was upgrade in 1994. Significant building renovation was in completed in 1984. ADA rest rooms were added in 2004. Pigeon dropping in the bell tower require abatement. Building has significant ACM and limited lead base paint in the facility. Architectural Building envelope is in satisfactory condition. Bell tower requires significant work and repairs of wood flooring, stairs, windows, tuck pointing, iron works. Clockworks not working only the bells are operational. Loading dock retaining walls are in need of repair. Powered door operators require are deteriorating. The building has had various remodeling projects over the years. Finishes are worn. Interior spaces are outdated and worn. Hardware and doors in poor condition. Original plaster ceilings have been compromised by acoustical type ceilings support wires. Mechanical Building mechanical system HVAC systems are constant air volume systems and are in marginal condition. Noise complaints from various air systems. Controls are pneumatic, not DDC. Steam and condensate are outdated. Steam supply to Harvey Hall provided by Bowman. Perimeter heat loop systems with no controls for individual offices. Cold spots throughout the building. Electrical All panels; power, lighting, and emergency are at capacity. Fire alarm system has obsolete parts and cannot be expanded. Emergency generator is high maintenance and replacement parts not available. Communication Telecommunications are maximum capacity for the building. Building has no defined MDF room. Plumbing Plumbing waste stacks are galvanized and deteriorating. Conveying One passenger elevator serves the building. Last upgraded in 1984. High maintenance is required for this unit. Equipment and Furnishings Movable equipment in the building. Fixed seating in one lecture hall. 5/20/2010 Building Profile IIIA - 2 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Child and Family Study Center 285-0L-0008 Academic 1970 4,639 Floors GSF 7,270 GPR 100 % AG UG 2 0 PR CENTRAL UTILITY CONNECTIONS CW HPS I 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING vi Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Child and Family Study Center (CFSC) is used as an academic facility. Building envelop is in good shape; roof replaced in 1996, exterior doors window replaced in 2010. Interior finishes; some floor worn, rest room flooring being replaced in 2010. Walls require frequent painting due to heavy usage by occupants. Powered door operators are outdated. Occupant(s) and Use(s) The CFSC currently houses Early Childhood Education (preschool) and includes laboratories, faculty/staff offices and support space. Mechanical Building residential furnaces with AC replaced in 2001. Functionality Assessment The CFSC has accessibility issues as a result of its inherent design and construction. The building is deteriorating and requires much maintenance. Other Building Issues Electrical Original wiring system not supported separately from ceiling system; laying on grid and tile ceiling. Fire Alarm system twenty years old and outdated. Communication Cabling at capacity. No defined MDF room in facility. Future Building Plans A major project is proposed for the Home Economics building which currently houses other programs for Early Childhood Education. The intent is to provide an addition to the Home Economics building and relocate functions currently in the CFSC to Home Economics. Plumbing All piping in poor condition, fixtures are in good shape. Some plumbing repairs being completed in 2010. Conveying There is no elevator in this building. Code and Health/Safety Chair seat lift for access between first and basement. No fire protection within facility. 5/20/2010 Equipment and Furnishings Building Profile Moveable equipment within building. IIIA - 3 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Communication Technologies 285-0L-0046 Academic 1959 34,439 Floors GSF 57,064 GPR 100 % AG UG 2 1 PR CENTRAL UTILITY CONNECTIONS CW HPS I 2009-11 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING vi Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History The Communication Technologies building was originally designed as a student union. It was repurposed as an academic facility upon completion of the Memorial Student Center in 1985. Various building components have asbestos containing materials in thermal insulation, floor tile and carpet/tile mastic. The exterior doors and frames contain lead paint. Architectural Building envelope windows installed in 1985. Caulking is deteriorating due to sun exposure. Roof replaced in 2004. Interiors carpeted wall partitions are worn. Doors, hardware and powered door operators are deteriorating. Occupant(s) and Use(s) The Communication Technologies building houses the College of Education, Health and Human Sciences (School of Education in Career and Technical Education, Marketing and Business Education, Technology Education, Science Education); College of Management (Military Science/ROTC); and the College of Science, Technology, Engineering and Mathematics (Apparel and Communication Technologies). There are seven (7) general assignment classrooms and twenty-three (23) classroom laboratories in addition to twenty-eight (28) faculty and staff offices. Functionality Assessment As a result of its original design as a student union, this building functions poorly as an academic facility. There is inefficient use of space It is difficult to manage space within the building due to its varied occupants and uses. Some classrooms have been taken off-line due to air quality and noise concerns. Mechanical Mechanical HVAC upgraded in 1985. Automation controls outdated as the first generation of DDC legacy supervisory control equipment is being phased out by the manufacturer and utilizes outdated Arc net communication technology. The PRV is outdated on the secondary steam main. Air compressor replaced in 2010. Electrical Electrical system original and outdated. Electrical panels are at capacity and replacement breakers are obsolete and impossible to obtain. Card access at exterior south ADA door. Fire alarm replaced in 2009. Communication 120v campus clock system in most areas of building. Cat 5 and Cat 3 cabling should be upgraded to current standard. Ventilation of MDF room is required to remove heat from equipment in the room. Other Building Issues Future Building Plans The Communication Technologies building has aging and deteriorating building infrastructure systems including HVAC, plumbing, electrical, telecommunications and life safety. One option is to request a project which will address programmatic remodeling, life safety and building infrastructure issues. The Campus Master Plan has proposed the demolition of the Communication Technologies building. A new academic building is proposed on another site to accommodate displaced programs. Plumbing System is galvanized and copper piping, obsolete and subject to random failure. Isolation valves inoperable. Plumbing system at capacity for future expansion. Conveying The combination freight/passenger elevator has limited use, but has worn door parts due to age and has high maintenance calls. Equipment and Furnishings Code and Health/Safety The building has an automatic sprinkler system in parts. 5/20/2010 Building Profile IIIA - 4 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Fryklund Hall 285-0L-0002 Academic 1961 43,216 Floors GSF 73,464 GPR 100 % AG UG 3 0 PR CENTRAL UTILITY CONNECTIONS CW HPS C 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING iii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Electrical Fryklund Hall is named for Lieutenant Colonel Verne E. Fryklund, president of the Stout Institute. It has always been used as an academic facility. Original building 300KVA primary transformer and secondary 480-3 breaker in place. Transformer (750KVA), distribution panels and buss duct replaced in 1992. Current rooms power supply not meeting technology requirements. Master clock system for building in good working system. Fire alarm replaced in 1992. Card access at south entrance and eleven labs. Fire alarms upgraded in 2003. Occupant(s) and Use(s) Laboratories, classrooms, faculty/staff offices for the College of Science, Technology, Engineering and Mathematics (CSTEM) and building systems space. Communication Functionality Assessment Communications system preplaced in 1992. Current voice/data are at capacity. MDF rooms under sized for technology needs. Other Building Issues Plumbing Pluming system replaced in 1992. Added lab air, lab gas, three neutralizations tanks, and welding gas distribution system to building. Future Building Plans None Conveying Code and Health/Safety Elevator added in 1992 and is in good shape. There is limited ACM material within building; mastic for carpet, and tile, linoleum, assumed fire doors and duct connectors. No lead paint within building. Equipment and Furnishings Combination of fixed seating and moveable equipment throughout facility. Architectural Building renovated in 1992, exterior walls, structural floors, roof deck and columns only items reused, added new stairwells and elevator. Building has burnished block/ painted CMU interior walls. Acoustical ceilings, oak veneer doors, hardware and frames in good shape. Powered operated door operators are outdated. Card access at building entrances. Roof replaced in 2008. Mechanical System replaced in 1992 with VAV air systems, lab exhaust system, two AHU’s, radiant ceiling panel, steam, coils, pumps, shell and tube heat exchanger and chiller. Building has cooling issues. Building scheduled to be connected to central chilled water plant in 2010. Current room usage not meeting technology requirements. Third floor east has air flow issues. 5/20/2010 Building Profile IIIA - 5 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Harvey Hall 285-0L-0001 Academic 1916 1975 51,935 GSF Floors 136,814 GPR 100 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS F 2009-11 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING vi Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Harvey Hall is named for Lorenzo Dow Harvey, a leading advocate of the Stout Manual Training School. It has always been used as an academic facility. While not listed on the National Register of Historic Places, it lies within the Menomonie Historic Preservation Commission district. Besides a stairwell addition, no other major renovations have occurred. should be removed as it was abandoned in 1975 after a new interior stair was added. Terrazzo stair floor risers are worn. Powered door operators are outdated. Mechanical Steam system, which also feeds Bowman Hall, is original and obsolete. Condensate receivers are deteriorating. Steam system leaks and need high maintenance. Buried condensate lines and vacuum lines have failed. HVAC systems are obsolete. Building automation controls need upgrading to DDC to provide better control and metering of the systems. Chilled water needs to be tied into campus central system. Some air returns are original wood/plaster chases. Occupant(s) and Use(s) Harvey Hall houses the College of Arts, Humanities and Social Sciences (CAHSS): English and Philosophy; Social Science; and Speech Communications, Foreign Languages, Theatre and Music. Functionality Assessment Electrical New electrical primary service in 2006. Building secondary distribution is required from the new system. All existing panels for power, emergency and lighting are at capacity. Vintage light fixtures with ACM covered wiring. Master clock system serving this facility. Emergency generator is outdated. Card access at two exterior entrances and two labs. Card access will in increase with theater remodeling in 2010. Fire alarm system is outdated. The building layout is broken up and inefficient. Classroom and office space quality is poor. Other Building Issues All building components are aged and deteriorating. Future Building Plans The Harvey Hall Renovation – Phase I Theatre project is scheduled for completion in January 2011. The Harvey Hall Renovation – Phase II Infrastructure project request was submitted for inclusion in the 2009-2011 Capital Budget. This request will address programmatic renovation, life safety and building infrastructure issues. MSCS will relocate to the Jarvis Hall Science Wing upon its completion in 2010. Code and Health/Safety Communication Cat 3 cabling is not to current standard in order to provide the networking for laptop computers. Some classrooms have power and data at tables, overhead projectors and document cameras in class rooms. Improvements to ADA accessibility, fire egress, fire suppression, hazardous materials (asbestos, lead, mercury, PCB’s) and security are all needed. Building ADA compliant to 1986 standards for entrance and restrooms. Both ACM and lead based materials exist throughout the facility in a majority of building components. Occupants issue yearly complaints on air quality concerns. Except for the theatre and attic, the building has no automatic sprinkler system. Plumbing Building envelope, roof and windows display fatigue. Tuck pointing is deteriorating due to cracked brick, eroded mortar joints and failing caulking in the control joints. Original metal fire escapes to be demolished. Interior doors are deteriorating due to worn and obsolete hardware parts. Settlement at southeast stair and northeast stair requires restoration to historic nature. Emergency fire escape Equipment and Furnishings Architectural 5/20/2010 System is cast iron, galvanized and copper piping, obsolete and subject to frequent failures. Restrooms are in average condition from high usage and do not comply with ADA. Drinking fountains are outdated. Summer use water heater being added in 2010. Conveying Building Profile One passenger elevator serves this facility and was last upgraded in 1980. An elevator modernization is required. Food service activities need permanent service area. Fixed seating in the theater and remaining building movable equipment. IIIA - 6 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Home Economics 285-0L-0010 Academic 1973 78,957 Floors GSF 133,383 GPR 100 % AG UG 4 0 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2009-11 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Home Economics building was originally designed as an academic facility focusing on instructional programs. Building envelope Is in good shape. Play ground area upgraded in 2007 with rubber matting on sidewalks and play areas. Patios on the north and west entrances leak and have settling concerns. Powered door operators are outdated. Occupant(s) and Use(s) The Home Economic building houses the College of Education, Health and Human Sciences (departments of Human Development and Family Studies; Food and Nutrition, School of Education); College of Management (departments of Hospitality and Tourism; Business); and the College of Science, Technology, Engineering and Mathematics (Apparel and Communication Technologies). There are nineteen (19) general assignment classrooms and thirty-three (33) classroom and research laboratories in addition to eighty (80) faculty and staff offices. There are two (2) laboratory dining facilities (Rendezvous and Cedar Café). Functionality Assessment Three of the four colleges use space in this building, resulting in inefficient use of space and some duplication of operations. It is difficult to manage space within the building due to its varied occupants and uses. Some classrooms have been taken off-line due to air quality and noise concerns. Mechanical Mechanical system has air issues throughout facility. Building automation controls outdated as the first generation DDC legacy supervisory control equipment is being phased out by the manufacturer and utilizes outdated Arcnet communication technology. Condensing receivers are outdated. Leslie units are failing. Air handling unit ten replaced in 2010. Kitchen supply and exhaust system replaced in Room 306 in 2010. Electrical All panels are at capacity within the building. Motor control center should is outdated. Replacement parts no longer available. Generators are old but operate satisfactorily. Fire alarm is outdated. Communication 120v campus clock system in most areas of building. Cat 3 cabling is not to current standard. Building has only one MDF room. There are no separate distribution rooms on each floor. All vertical raceways are at capacity. No ventilation serving the MDF room which produces excessive heat from equipment. Other Building Issues Room 240 suite requires reconfiguration to meet accreditation requirements. Future Building Plans The Home Economics building has aging and deteriorating building infrastructure systems including HVAC, plumbing, electrical, telecommunications and life safety. This request will address programmatic remodeling, life safety and building infrastructure issues. Kitchen hoods and AHU service room 306 are being replaced in 2010. An addition to the east is proposed and will added classroom, laboratory, Child and Family Study Center, SOE faculty and staff and the Center for Intergenerational Studies and Services. Plumbing Asbestos containing materials (ACM) are present in thermal insulation on all piping systems. Potential PCB presence. Security (CPTED) should be addressed. There is no automatic sprinkler system except for a CO2 fire suppression system in Rooms 132 and 136. Underground tank removed in 2009. Equipment and Furnishings Code and Health/Safety 5/20/2010 Waste piping is galvanized and deteriorating. As system produces spermatic failures. Isolation valving is inoperable or the valve stems break off when in use. RO system is outdated. Urinals in building are outdated. Corner III piping leaks. Upgrading kitchen hoods fire protection system in 2010 in room 306. Conveying Building Profile High use passenger elevator requires above normal maintenance. Student lockers are undersized and do not accommodate larger backpacks. IIIA - 7 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Jarvis Hall Science Addition 285-0L-0015 Academic 2009 48,076 Floors GSF 78,990 GPR 100 % AG UG 3 1 PR CENTRAL UTILITY CONNECTIONS CW HPS A 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING i Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Jarvis Hall Science Addition (JHSA) is named after John A. Jarvis who served as a professor, dean, vice president and president. The addition was constructed to provide state of the art science facilities which replaced the antiquated science laboratories and classrooms in the existing Jarvis Hall Science Wing. New in 2009. Mechanical New in 2009. Issues with VFD motor on AHU two. Electrical New in 2009. Occupant(s) and Use(s) The Jarvis Hall Science Addition houses instructional laboratories for the departments of Biology, Chemistry and Physics. Research laboratories, aquatic, mammalian and virarium suites are provided to support instruction. A greenhouse is located on the third floor. It also has four (4) general assignment classrooms. Communication New in 2009. Plumbing New in 2009. Conveying Functionality Assessment JHSA has provides state of the art instructional and research facilities for the science programs. One passenger/ freight elevator serves this building. Equipment and Furnishings New fixed seating and moveable seating in building. New science equipment throughout the facility. Some existing equipment relocated into complex. Other Building Issues Future Building Plans None Code and Health/Safety Building constructed according to the 2000 IBC. Fire protection and command systems in this building control adjacent Jarvis Science buildings. Fire alarm master command center in facility and controls Jarvis Science, Jarvis Technology, Micheels Hall and Applied Arts buildings. 5/20/2010 Building Profile IIIA - 8 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Jarvis Hall Science Wing 285-0L-0016 Academic 1970 2009/2010 44,978 GSF Floors 66,201 GPR 100 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS A 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING i Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Jarvis Hall Science Wing (JHSW) is named after John A. Jarvis who served as a professor, dean, vice president and president. It has always been used as an academic facility. The JHSW was renovated in 2009/2010 to provide state of the art instructional facilities for the sciences. The Department of Mathematics, Statistics and Computer Science (MSCS) will relocate from Harvey Hall to the JHSW in fall 2010. The Jarvis Hall Science Addition was completed and occupied in fall 2009. A lecture hall replacement will be completed and occupied in fall 2010. Occupant(s) and Use(s) The JHSW houses instructional laboratories for Mathematics, Statistics and Computer Science (MSCS); Business; and Risk Control in addition to offices for faculty and staff. The College of Science, Technology, Engineering and Mathematics (CSTEM) office is located on the first floor. Functionality Assessment The building layout is broken up and inefficient. Classroom and office space quality is poor. Building is in excellent condition. Structural floors columns and exterior CMU walls reused. Replaced and added windows in offices and curtain wall window systems in all public areas and lecture halls. Mechanical Systems all replaced in 2010. Electrical All systems replaced in 2010. Communication All replaced in 2010. Cat 6 and wireless. Plumbing All new systems in 2010. DI added to the building plumbing systems. Conveying One passenger elevator serves this facility and modernization was included in the 2009/2010 renovation project. Other Building Issues None Equipment and Furnishings Science equipment (casement work, fume hoods, laminar flow hoods, etc.) Fixed and moveable equipment were added in the 2009/2010 renovation. Future Building Plans No plans for future major project work at this time. Code and Health/Safety Building renovated according to the 2000 IBC. Fire protection added to the building with its command center located in the Jarvis Science Addition. 5/20/2010 Building Profile IIIA - 9 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Jarvis Hall Technology Wing 285-0L-0016A Academic 1970 40,135 Floors GSF 63,839 GPR 100 % AG UG 2 0 PR CENTRAL UTILITY CONNECTIONS CW HPS C 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING iii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Jarvis Hall Technology Wing (JHT) is named after John A. Jarvis who served as a professor, dean, vice president and president. It has always been used as an academic facility. Occupant(s) and Use(s) Building envelop in good working condition. Building interiors in satisfactory condition. Powered door operators are outdated. Wood flooring high maintenance issue due to mastic containing ACM. Mechanical The JHSW currently houses laboratories for Engineering and Technology and Business. Offices for faculty and staff are located primarily on the second floor. Functionality Assessment Steam control valves on all AHU’s in bad condition and having difficulty getting replacement parts. Electrical In good condition. The first floor primarily houses large laboratories for construction programs. Building layout is broken up and inefficient. Classroom and office space quality is poor. Other Building Issues Communication Defined MDF room required in this building. Plumbing Drinking fountains, faucets, and sinks are deteriorating. Piping in fair condition. Plumbing system at capacity. Future Building Plans Conveying There are no plans at this time for major project work. One passenger elevator serves this facility. Code and Health/Safety Eye wash stations and back flow prevention required in areas of building. ACM through facility. Majority of flooring VAT throughout offices and classrooms. 5/20/2010 Equipment and Furnishings Building Profile IIIA - 10 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF McCalmont Hall 285-0L-0067 Academic/Residence 1963 21,156 Floors GSF 40,762 GPR 80 % AG UG 5 0 PR CENTRAL UTILITY CONNECTIONS CW HPS C 2011-17 ELEC FIBER C. AIR N. GAS 20 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History McCalmont Hall is named for Mary M. McCalmont who taught chemistry and was a department chair in her forty years at Stout. It was originally designed and used as a women’s dormitory until four floors were converted to office and laboratory space. entrance doors replaced in 2009. Roofing replacement scheduled for replacement in 2010/2011. Interior finishes are multi layers of paint on CMU walls. Doors, hardware are outdated. Sliding door for access to fist floor needs is deteriorating along with power operated door operator. Mechanical Occupant(s) and Use(s) The Stout Vocational Rehabilitation Institute (SVRI) currently occupies rooms on the first and second floors for program residents. Psychology occupies some second floor rooms and the third floor for laboratories and offices. The School of Education has faculty and staff offices on the fourth floor. University Housing uses the fifth floor for student residents. Mechanical systems; exhaust fans, controls, radiation, pumps, convertor, convectors, cabinets heaters, piping and valves are original to building and are obsolete. Steam distribution in room 1 and service to building are outdated. Chiller in poor condition. Scheduled to be tied into the central chiller water loop for air conditioning in 2010. Electrical Functionality Assessment Electrical systems are outdated. Larger electrical room will be required for any upgrade. Fire alarm installed in 1994 and is outdated. Card access at main doors. Card access at north building entrance, fifth floor and west stair and two rooms on second floor. Emergency generator power supplied from Vocational Rehabilitation building. The building layout is broken up and inefficient. Classroom and office space quality is poor. Other Building Issues All building components are aged and deteriorating. Communication Future Building Plans Long-term plans are to reassign all of McCalmont Hall to University Housing. In late 2010 or early 2011, the Department of Psychology will relocate to Harvey Hall in space vacated when Mathematics, Statistics and Computer Science (MSCS) relocates to the Jarvis Hall Science Wing in fall 2010. SOE will relocate from McCalmont Hall in the future. SVRI will vacate area on second floor for University Housing use. Code and Health/Safety Building added elevator in 1982 and connection link to Vocational rehabilitation. Fire alarm system installed in 1994. Fire protection is a stand pipe system only. Building has ACM floor tile, mastic, plumbing shower faucet gaskets, piping insulation throughout facility. No lead paint in the building. Voice and data are currently fed from Antrim Froggatt. MDF room required in building when building remodeled. Building has 5e cabling system. System is outdated. Plumbing All systems have outlived their useful lives and will continue to have failures. Fixtures, piping and valves, water heater, waste/vent are outdated. Roof drains can be modified and reused. Conveying One passenger elevator installed in 1982 serves this facility. Equipment and Furnishings Fifth floor has new furnishings in 2006. Architectural Building envelope is in good condition. In 2008 windows, tuck pointing and exterior sealants replaced. Building sliding 5/20/2010 Building Profile IIIA - 11 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Micheels Hall 285-0L-0017 Academic 1996 22,307 Floors GSF 42,768 GPR 100 % AG UG 2 0 PR CENTRAL UTILITY CONNECTIONS CW HPS B 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING ii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Micheels Hall was named for former Chancellor William J. Micheels and has been used as an academic facility since its original design and construction. A general access computer lab was removed in 2008 and this space is currently used as temporary science faculty/staff office space until the Jarvis Hall Science Wing Renovation and Addition project is completed in fall 2010. Building envelope and interiors finishes are in good shape. Roof 14 years old. First floor labs have plenum access floors for computer labs. Powered door operators are outdated. Mechanical Three AHU’s with VAV distribution installed in 1996. They are in satisfactory working order. Four computer room air conditioners (liebert units) sever the first floor raised access computer labs. Liebert unit in 184c has shaft and bearing high maintenance. BAS control should update to DDC. Steam valves are an old style and outdated. Occupant(s) and Use(s) Micheels Hall houses the College of Arts, Humanities and Social Sciences (Art and Design) and the College of Science, Technology, Engineering and Mathematics (Engineering and Technology). There are three (3) general assignment classrooms. Electrical Electrical system in good working condition. Fire alarm in good working system. Card access at east exterior entrance and room 184. Functionality Assessment The building functions well with its current departments. Other Building Issues Communication System should be upgrade to current standard. Future Building Plans Plumbing The former general access computer lab (Room 184) is being considered for future short and long-term use. Potential short-term occupants include Memorial Student Center (MSF) staff and/or events during the MSC renovation. Potential long-term occupants include the Masters of Fine Arts in Design. Room 184 is also the only large “swing” space currently available on campus. The potential relocation of Apparel and Design faculty and staff to Micheels Hall has been considered. System in good working order. Conveying Elevator starting mode has hydraulic hammering noise. Unable to resolve issue. Equipment and Furnishings Movable equipment with facility purchased in 1996. Code and Health/Safety No fire protection system in building. 5/20/2010 Building Profile IIIA - 12 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Millennium Hall 285-0L-0011 Administration 2001 23,625 Floors GSF 43,590 GPR 100 % AG UG 3 0 PR CENTRAL UTILITY CONNECTIONS CW HPS B 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING ii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Millennium Hall was designed and constructed to replace the Communications building which was razed. This building is the campus communications center. The ASK5000 Help Desk was relocated from Micheels Hall to Millennium Hall in 2008 to provide better support to students, faculty and staff. Occupant(s) and Use(s) Millennium Hall houses offices and support space for Learning and Information Technology (Learning Technology Services; Telecommunications and Networking; Enterprise Information Systems; Nakatani Center; e-Scholar; and ASK5000 Help Desk). There are distance education and video-conferencing facilities. Functionality Assessment Cooling system for building over sized for the environment with limited summer use and under capacity for electronic equipment server rooms cooling provided by roof top DX units. Electrical Communication In good working order. Plumbing Future Building Plans In good working order. Some functions of the building are being reviewed for appropriateness of location and will be considered for future project work. 5/20/2010 Mechanical UPS and emergency generator at capacity.. Other Building Issues Code and Health/Safety Building envelop has issues with window systems. Building single paned storm and room windows. Severe condensation annually during the heating system. Curtain wall on east side leaks. Manufacturers out of business no parts or color of frames available. Powered door operators are failing. Building room configuration not matching technology requirements. Conveying One passenger elevator serves this building. Equipment and Furnishings Building Profile IIIA - 13 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Robert S. Swanson Learning Center 285-0L-0012 Academic 1981 84,007 Floors GSF 125,520 GPR 100 % AG UG 7 0 PR CENTRAL UTILITY CONNECTIONS CW HPS B 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING ii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Robert S. Swanson Learning Center (RSLC) was renamed for former Chancellor Robert S. Swanson in 2007. It was originally designed and constructed as the university library. Building envelope in good condition. Portion of building had roof replaced in 2005. Powered operators are outdated. Mechanical All equipment original and obsolete. Steam PRV, traps and condensate receiver are outdated. Building has poor air circulation in various parts of building. Occupant(s) and Use(s) The RSLC currently houses the University Library (Library Systems, Library Instruction, Reference/Distance Education, Collection Development, Electronic Resources/Assistive Technology, Web Resources, Cataloging/Processing, Instructional Resources Service, Area Research Center and Archives, Access Services/Interlibrary Loan, and the Educational Materials Center). There is also the Instructional Laboratory in addition to administrative staff offices and support space. There is one general assignment classroom on the second floor. The Center for Applied Ethics is located on the third floor. The administrative offices for the College of Science, Technology, Engineering and Mathematics (CSTEM) are temporarily housed on the third floor until their relocation to the Jarvis Hall Science Wing in fall 2010. Electrical Electrical system original and has severe issues with light dimming systems. No replacement available. Motor control center in poor condition. Exterior lighting not on emergency power. Fire alarm replaced in 2009. Communication Building has under sized MDF rooms with no ventilation. Wireless throughout facility. Plumbing Drinking fountains have been replaced. Waster piping has required high maintenance due to leaks. Hot water heater replaced in 2007. Sinks and faucets are outdated. Functionality Assessment The RSLC lacks small group study rooms for students. Consideration has been given to combining the Circulation and Reference areas. Other Building Issues Conveying One passenger and one freight elevator serve the buildings which are in good working order for the heavy usage. Equipment and Furnishings Future Building Plans As the role and purpose of libraries continues to evolve, the campus routinely reviews the appropriateness of use by other programs and departments. It is currently proposed that the University Honors Program will be relocated from Harvey Hall to the fourth floor of the RSLC. Code and Health/Safety Fire protection in building 5/20/2010 Building Profile IIIA - 14 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Sports and Fitness Center 285-0L-0005 Academic 1964 1989/1998/2001 137,391 GSF 187,016 Floors GPR 85 % AG UG 2 0 PR CENTRAL UTILITY CONNECTIONS CW HPS C 2011-17 ELEC FIBER C. AIR N. GAS 15 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING iii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Sports and Fitness Center (SFC) is the only physical education, athletics and recreation facility on campus. It has had three additions since its original construction. Building envelop in good shape. Pool windows replaced in 2006. Roof replaced in 2005. Interiors cmu walls require frequent painting due to the high usage of the facility. Terrazzo stairs require high maintenance due to high traffic. Pool repainted in 2010. Gym floor replaced in 2002 and is being refinished 2010. Bleachers are original and failing. Men’s locker rooms are outdated. Lockers original and don’t meet current requirements. A storage addition was added to the north of the JFH gym in 1998. Occupant(s) and Use(s) The original SFC currently houses physical education, athletics and University Recreation (intramural sports, sport clubs, Stout Adventures, Health and Fitness Center and swimming pool) functions. It includes the Johnson Fieldhouse (athletic, recreation and events), swimming pool, women and men locker rooms, first aid/mat room, Hall of Champions (conference room), offices for faculty and staff, laundry room, storage and building support space. Mechanical Mechanical systems including BAS are outdated throughout facility. Lobby ductwork replaced in 2008. Office suite 217 and associated offices upgraded to VAV system in 2008. AHU still is outdated. Condensate receiver needs replacing.PRV in fair condition. Several isolation valves non-functioning in building. Functionality Assessment The increase in health and wellness, in addition to the continued growth in recreation and intramural programs, has resulted in great demand for the SFC. Electrical Other Building Issues Building system original. Transformers, switchgear and panels at capacity. Master clock system in facility in working condition. Lighting upgrades to main gym and pool in 2010. Lobby corridor lighting replaced in 2008. Fire alarm system upgrade in 2009. The increase in health and wellness, in addition to the continued growth in recreation and intramural programs, has resulted in great demand for the SFC Programs and events are scheduled into the late night/early morning. Communication Future Building Plans A major project is proposed to add 100,000 ASF to the facility to meet the demands of recreation, athletics and intramurals. This includes additional multi-purpose, fitness, locker rooms and support spaces. Part of the addition may include a new location for the Student Health Center currently located in an outdated facility on North Campus. Telecommunications are at capacity. Defined MDF room required in facility. Plumbing Plumbing in poor condition, worn and unable to get replacement parts in showers. Pool drain covers replaced in 2010. Pool piping replaced in 1996. Pool drainage system connected to storm waste not sanitary waste. Code and Health/Safety Fire protection in building. Pool drains in to storm system, not in compliance. Building contains ACM. No lead based paint is in facility. Conveying Original elevator serves the building. Equipment and Furnishings Diving boards replaced in 2008. 5/20/2010 Building Profile IIIA - 15 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Sports and Fitness Center – Addition A 285-0L-0005A Academic 1989 64,001 Floors GSF 83,656 GPR 85 % AG UG 2 1 PR CENTRAL UTILITY CONNECTIONS CW HPS B 2011-17 ELEC FIBER C. AIR N. GAS 15 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING ii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Sports and Fitness Center (SFC) Addition A is part of the only physical education, athletics and recreation facility on campus. It has had two additions since its original construction. Occupant(s) and Use(s) Building envelope in good condition. MRP room roof replaced in 2007. Locker rooms, weight rooms, offices and MPR room heavily used and showing wear. MPR outer track replaced in 2003. Mechanical The SFS Addition A currently houses physical education, athletics and University Recreation (intramural sports, sport clubs, Stout Adventures, Health and Fitness Center and swimming pool) functions. It includes the multipurpose gym/track, women and men locker rooms, weight room, racquetball courts/golf hitting room, offices for faculty and staff, laundry room, storage and building support space. In addition, three general assignment classrooms are located on the second floor. Mechanical system starting to require higher maintenance. Electrical In good working order. MPR power at capacity. Fire alarm system replaced in 2008. Communication Building required defined MDF room. Plumbing Functionality Assessment The increase in health and wellness, in addition to the continued growth in recreation and intramural programs, has resulted in great demand for the SFC. Other Building Issues The increase in health and wellness, in addition to the continued growth in recreation and intramural programs, has resulted in great demand for the SFC Programs and events are scheduled into the late night/early morning. Plumbing in good condition. Conveying One elevator serves the building. Equipment and Furnishings Moveable equipment in working order. Future Building Plans A storage addition is considered to the south of the SFC Addition A. Code and Health/Safety No fire protection within facility. 5/20/2010 Building Profile IIIA - 16 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Sports and Fitness Center – Addition B 285-0L-0005B Academic 2001 12,723 Floors GSF 17,759 GPR 85 % AG UG 2 1 PR CENTRAL UTILITY CONNECTIONS CW HPS A 2011-17 ELEC FIBER C. AIR N. GAS 15 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING i Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Sports and Fitness Center (SFC) Addition B is part of the only physical education, athletics and recreation facility on campus. Building envelope is in good condition. Mechanical Mechanical system in good condition. BAS should be upgraded to DDC. Occupant(s) and Use(s) The SFS Addition B currently houses physical education, athletics and University Recreation (intramural sports, sport clubs, Stout Adventures, Health and Fitness Center and swimming pool) functions. It includes the Fitness Center, West Gym/Group Fitness Gym, Stout Adventures (climbing wall, resource/service area and storage) and building support space. Functionality Assessment The increase in health and wellness, in addition to the continued growth in recreation and intramural programs, has resulted in great demand for the SFC. Other Building Issues The increase in health and wellness, in addition to the continued growth in recreation and intramural programs, has resulted in great demand for the SFC Programs and events are scheduled into the late night/early morning. Electrical Fire alarm replaced in 2008. Card access provided for seven interior rooms; locker, weight and treatment room. Communication Building requires own MDF room. Plumbing Plumbing system in good working order. Shut off valves should be added to building to isolate water distribution to minimize building outages. Conveying None, elevator in main building. Equipment and Furnishings Future Building Plans Moveable equipment, weight lifting equipment, sports equipment. No major projects are being considered at this time. Code and Health/Safety 5/20/2010 Building Profile IIIA - 17 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Vocational Rehabilitation 285-0L-0007 Academic 1954 1981 43,295 GSF Floors 82,309 GPR 100 % AG UG 3 0 PR CENTRAL UTILITY CONNECTIONS CW HPS F 2009-11 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING vi Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History The Vocational Rehabilitation building was originally designed as a library, but was repurposed as an academic facility upon completion of the Robert S. Swanson Learning Center (formerly Library Learning Center) in 1981. and dry mastic for carpet and tile. The painted exterior doors and frames contain lead paint. Architectural The building envelope is in good shape. West entrance marble stone and lead flashing deteriorating from moisture. Building waterproofing, foundation drainage in the 1954 section is leaking and plaster walls are in constant deterioration. Powered door operators are outdated. Occupant(s) and Use(s) The Vocational Rehabilitation building houses the College of Education, Health and Human Sciences (Rehabilitation and Counseling; Stout Vocational Rehabilitation Institute, Marriage and Family Therapy); It also houses Outreach Services and Customized Instruction. There are nine (9) general assignment classrooms and twenty-two (22) classroom, open and research laboratories in addition to sixty-nine (69) faculty and staff offices. Mechanical HVAC system is deteriorating. VAV controllers are failing. Building automation controls need upgrading as the first generation DDC legacy supervisory control equipment is being phased out by the manufacturer and utilizes outdated Arcnet communication technology. Building is scheduled to be tied into central chilled water system in 2010. Functionality Assessment As a result of its original design as a library, this building functions poorly as an academic facility. There is inefficient use of space It is difficult to manage space within the building due to its varied occupants and uses. Some classrooms have been taken off-line due to air quality and noise concerns. Other Building Issues Electrical Electrical system is outdated. All existing panels for power, emergency and lighting are at capacity. Master clock system with n facility in satisfactory condition. Emergency generator replaced in 2010. Generator also supplies emergency power to McCalmont Hall. Communication None 120v campus clock system in most areas of building. A mixture of Cat 5 and Cat 3 cabling should be upgraded to current standard. Card access at west entry and eight labs. Future Building Plans The Vocational Rehabilitation building has aging and deteriorating building infrastructure systems including HVAC, plumbing, electrical, telecommunications and life safety. Space is inefficiently used. The building is difficult to navigate. One option is to request a project which will address programmatic remodeling, life safety and building infrastructure issues. The Campus Master Plant has proposed demolition of the Vocational Rehabilitation building and a new academic building would be constructed on the current site. Code and Health/Safety Security (CPTED) should be addressed. There is some automatic sprinkler system within the building. Asbestos containing materials (ACM) in thermal insulation, floor tile 5/20/2010 Plumbing System is galvanized and copper piping which are obsolete and subject to failure. Restrooms are in average condition. Conveying Freight elevators are 53 years old but are in good shape due to infrequent use. Passenger elevator Is the third highest used elevator on campus and was last upgraded in 1980. Equipment and Furnishings Building Profile Movable equipment is of various ages. IIIA - 18 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Williams Stadium 285-0L-00085/0085A Academic 2001 15,990 Floors GSF 59,501 GPR 85 % AG UG 3 0 PR CENTRAL UTILITY CONNECTIONS CW HPS A 2011-17 ELEC FIBER C. AIR N. GAS 15 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING i Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Williams Stadium is named for Don and Nona Williams, donors for the stadium. The stadium was designed and constructed for football and university events. The football field turf was replaced in 2008. Building envelop has masonry issues. Brick veneer on west elevation failing. Stadium railings/ concrete pockets failing. Countertops worn. In 2010, windows on third floor are being added along with carpeting in the chancellor’s suite and corridor to elevator. Signage for press box being installed in 2010. Memorial pavers have vandalism to them and will be replaced in 2010. Field turf in excellent condition. Occupant(s) and Use(s) Williams Stadium houses support spaces (ticket booth, press box, Chancellor’s box, food service, restrooms and storage) for football games and university events. The stadium is also used by the Menomonie High School. Functionality Assessment Mechanical Mechanical system in good working order. Electrical Works well for programs. Electrical system in good working order. Replaced all sodium were replaced with quartz style lighting. Field lighting have quartz lights burned out. Fire alarm panel serves elevator mechanical room only. Other Building Issues None Future Building Plans Communication Communications are adequate for facility. There are no plans at this time for future project work. Code and Health/Safety Plumbing High maintenance yearly to drain and fill each spring and fall of the water distribution system. Conveying There is one passenger elevator serving this building. Equipment and Furnishings 5/20/2010 Building Profile IIIA - 19 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Administration Building 285-0L-0018 Administrative 1970 20,563 Floors GSF 34,417 GPR 100 % AG UG 3 1 PR CENTRAL UTILITY CONNECTIONS CW HPS A 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING i Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Administration Building was originally designed and constructed for university administration functions although other services have been provided throughout its existence. An HVAC renovation project was completed in 2008 and included programmatic renovation in some areas. Occupant(s) and Use(s) The Administration Building currently houses the Chancellor’s Office; Provost’s Office; ASLS Vice Chancellor’s Office; Business and Financial Services; Student Business Services; Career Services; Human Resources; University Communications; Budget, Planning and Analysis; and Internal Audit. Functionality Assessment Building envelope is in good condition. Roofs replaced in 2007 and 2009. Building interiors; painting, carpet, ceilings were updated in 2007. Powered door operators are outdated. Mechanical HVAC systems for floors 1-3 updated in 2007. Basement updated in 1999. Steam isolation valves are outdated. Electrical Lighting updated in 2007 throughout the building. Electrical service original to building. Card access to building entrances. Fire alarm system is outdated. Communication This building adequately accommodates the functions. Building dedicated MDF room and cabling replaced in 2007. Other Building Issues Plumbing None Plumbing piping original. Beginning to have maintenance issues. Future Building Plans There are no major project work plans at this time. A small project to remodeling of BPA area for HR and Affirmative Action offices. Code and Health/Safety Conveying Passenger elevator in good condition. Equipment and Furnishings No sprinkler system in facility. 5/20/2010 Building Profile IIIA - 20 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF General Services 285-0L-0089 Administration 1975 26,036 Floors GSF 35,433 GPR 100 % AG UG 1 0 PR CENTRAL UTILITY CONNECTIONS CW HPS C 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING iii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The General Services building is located west of Broadway Street/Highway 25. Building envelop is in satisfactory condition. Powered door operators are outdated. Metal roofing is worn over the shop area. Roof fasteners are failing. Built up roofing replaced in 2005. Lobby repainted in 2008. Occupant(s) and Use(s) Physical Plant functions are housed in the General Services building. Mechanical Mechanical systems original and outdated. Administrative offices cooling capacity under sized. Functionality Assessment Building continues to function as a support facility to the university. Space usage at capacity. Electrical Lighting master controller needs the ASCO relay replaced for outdoor lighting. Old relay is problematic and hard to find replacement parts. Shop lighting should be replaced along with lighting controls. Fire alarm system added to building in 2009. Other Building Issues None. Future Building Plans All Agency project to replace heating systems, lighting systems and ceiling to improve the energy efficiency of the building. Communication In good working condition. Plumbing Code and Health/Safety ACM materials throughout the building VAT tiles need abatement. Shop areas have fire protection. Hot water issue. Conveying None Equipment and Furnishings Moveable equipment is vintage, but in working condition. 5/20/2010 Building Profile IIIA - 21 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Heating Plant 285-0L-0036/0036A/0036B Administration 1965 1973/1974/2006 681 GSF 20,072 Floors GPR 100 % AG UG 2 1 PR CENTRAL UTILITY CONNECTIONS CW HPS B 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING i Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Heating Plant Window system is outdated. Roof replaced in 2009. Overhead door between the coal bunker and heating plant was replaced in 2009. Floor grating replaced with floor hatch in 2009. Plant office received a new ceiling and insulation above ceiling and paint in 2007. Occupant(s) and Use(s) Physical Plant staff. Functionality Assessment Mechanical Building adequately accommodates functions. Four boilers and associated equipment are in working condition. Gas boiler replaced in 2006. Boiler number four outlet breeching was replaced in 2008. Boiler number one is having the oil gun replaced during summer 2010. Other Building Issues Replacement of city water main and lateral into building, window curtain wall replacement, Breeching expansion joint replacement between boilers 3 and 4(affecting boilers 2, 3, 4), installing variable frequency drive on FD4 fan, catwalk installation from conveyor level to boiler 4 and from the burners level to upper drum levels at boiler 2 and 3 and the re-insulation of boilers 2and 3 outer skins. Future Building Plans Electrical service being replaced in the summer of 2010. Emergency generator replaced in 2005. Communication In working order. An electrical substation project is scheduled for construction in fall 2010. Code and Health/Safety Electrical Plumbing In satisfactory condition. Conveying Coal conveying system in working order. Equipment and Furnishings 5/20/2010 Building Profile IIIA - 22 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Heating Plant Electrical Substation 285-0L-0036B Administration 1974 0 Floors GSF 0 GPR 100 % AG UG 0 1 PR CENTRAL UTILITY CONNECTIONS CW HPS F 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Heating Plant Electrical Substation provides electrical service to the campus; except for the Child and Family Study Center and the Student Heath Center which have their own metered service. Masonry wall in good shape. Site to be re-graded in 2011 when equipment removed. Mechanical NA Occupant(s) and Use(s) Two 5MVA transformers owned by Xcel energy, two banks of switch gear, each fed from a separate utility line. Switch gear have a tie buss between the two banks. Functionality Assessment Substation has two feeders on one switch. System has had issues when resting switches to re-energize during outages. Other Building Issues Electrical Substation requires high maintenance. Equipment has trouble being rest once de-energized. Electrical substation being removed in 2011. Communication NA Plumbing None. Storm outlets to be retained and extended in 2011. Future Building Plans An electrical substation project is scheduled for construction in fall 2010 to replace this system on a new site and reserve this site for future heating plant expansion; possible bag house. Conveying NA Equipment and Furnishings NA Code and Health/Safety Existing grade into the substation very steep. 5/20/2010 Building Profile IIIA - 24 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Louis Smith Tainter House 285-0L-0062 Administration 1890 5,928 Floors GSF 14,712 GPR 100 % AG UG 2 1 PR CENTRAL UTILITY CONNECTIONS CW HPS B 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING ii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Louis Smith Tainter House is named after Louis Smith Tainter, an assistant with the Knapp, Stout & Co. It is listed on the National Register of Historic Places and lies within the Menomonie Historic Preservation Commission district. Building envelope in satisfactory condition. Roof replaced in 2004. Windows were replaced in 2008. Having warranty issues with the curved window sashes. Replacement scheduled for summer 2010. Interiors require carpet stretching and painting throughout the facility. North east archway beam is scheduled to be replaced in 2010. Building has no ADA door operators within facility. Occupant(s) and Use(s) University Advancement (Stout University Foundation and Stout Alumni Association) are housed in the Louis Smith Tainter House. Mechanical Mechanical AHUs are outdated. BAS control support an upgraded. Functionality Assessment This building adequately accommodates functions. Electrical Other Building Issues Electrical service is outdated. Currently power from JTC. None Communication Future Building Plans Cabling is adequate for facility. There is no major project work planned at this time. Plumbing Code and Health/Safety Toilets and flushing valves are outdated. Abatement of bat droppings required in attic. No ADA entrance in building. Conveying None. Equipment and Furnishings 5/20/2010 Building Profile IIIA - 25 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Memorial Student Center 285-0L-0045 Student Center/Union 1985 1993 59,193 GSF Floors 100,745 GPR 0 % AG UG 2 0 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2009-11 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING iii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Memorial Student Center (MSC) is dedicated to the students, faculty and staff who served and died in our country’s military conflicts. It is a “community center” for members of UW-Stout and provides opportunities to learn through involvement and experimentation. Since its original construction, no major renovations have occurred. Noise results from too much CMU and glass block. Exterior doors and hardware are original and need replacement due to heavy use, corrosion and worn parts. The exterior envelope has failing windows. Roofs are in good condition. Replace caulking due to failing joints and moisture infiltration. Settling at precast retaining wall on SE side. Water runoff from roof and glass canopies is an issue. Concentrated flooding occurs at southeast exterior entrances. Two elevated sidewalks have possible slab and structural concerns due to corrosion from salt. Occupant(s) and Use(s) Currently, the MSC houses many student life services including: student government (SSA); student organizations and club sports; University Dining Services; service and information center; bookstore; recreation; University Centers administrative offices; and general meeting space. Mechanical Fiberboard ductwork in main HVAC system failed in the facility. Interstitial spaces receive more air than designated rooms. Building automation controls need upgrading as the first generation DDC legacy supervisory control equipment is being phased out by the manufacturer and utilizes outdated Arcnet communication technology. Heating and cooling systems contain stop leak material resulting in premature replacement of valving, restricting flow which prohibits meeting temperature requirements. Remove chiller and connect building to central chilled water system. Food service water-cooled condensing units need replacement for better energy efficiency, meet current codes and conserve water usage. The out of service heat exchanger is plugged. Functionality Assessment The MSC lacks adequate meeting and student lounge space. The building is difficult to navigate horizontally and vertically due to its inherent design. Other Building Issues The Campus Master Plan will address such issues as the creation a more transparent and welcoming building. One area of significance is how the MSC better integrates the green space to the south. The building was constructed so that all entrances require going up or down an exterior ramp. This is a very dangerous in wet, snowy and icy conditions Electrical All panels; power, lighting and emergency are at capacity. Fire alarm system has obsolete parts and system cannot be expanded. Dimming and PA system are failing and have unobtainable parts. Future Building Plans A major project was considered to address programmatic renovation, life safety and building infrastructure issues for both Price Commons and the Memorial Student Center (MSC). Funding concerns limited the project scope to just the MSC. Future plans should consider Price Commons issues. Communication Campus clock system is original and failing. Cabling is outdated and a larger MDF room is needed. Plumbing Food service drain lines experience flow restrictions. Code and Health/Safety Conveying MSC has potential issues involving ADA accessibility and hazardous materials. The loading dock is undersized and has poor separation of food service and waste distribution. Passenger and freight elevators are original and have worn parts, no fire service and high use. Equipment and Furnishings Existing furniture needs upgrading or replacement. 5/20/2010 Building Profile IIIA - 26 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Merle M. Price Commons 285-0X-0047 B09 1967/ 44,672 Floors GSF 75,906 GPR 0 % AG UG 2 1 PR CENTRAL UTILITY CONNECTIONS CW HPS B 2009-11 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING ii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Price Commons (PC) is named for Merle M. Price who served UW-Stout for 42 years as dean of men and later dean of students. He also taught courses in social science and education. The Price Commons Second Floor Renovation project was completed in fall 2009 and included the removal of asbestos containing material (ACM) and renovation of the servery and dining areas of the cafeteria. Building envelop in good condition. The membrane roof was replaced in 2005. Second floor remodeled in 2009 and the addition of a server bay in the NE corner of the building. New coolers and freezers were replaced. First floor SE section of the building was fit-up in 2006 for SLS administration offices and card access. Housing and Dining offices were updated with new ceilings, painting and carpet in 2009. Occupant(s) and Use(s) Price Commons currently houses many student life services including: University Housing; University Dining Services; Campus Card; facilities management; Student Life Services administrative offices; student lounge space; and general meeting space. Mechanical AHU’s and exhaust hoods serving the kitchen, NE servery and seating spaces replaced in 2009. Electrical Second floor server bay added to the NE corner of the building in 2009. Fire alarm updated in 2009. Emergency generator replaced and relocated outside in 2009. Functionality Assessment This building adequately accommodates functions. Other Building Issues Communication None Cabling and wireless updated in 2009. Future Building Plans Replacement of loading dock drive way with storm drains in loading dock area in 2011. Plumbing Second floor piping and valving replaced in 2009. Second floor drains replaced in 2006. Remaining building original piping. Code and Health/Safety Price Commons has known asbestos abatement needs, and likely has mercury, PCB’s and other hazardous materials that need attention during renovations. Additional code and safety upgrades that are possible include ADA accessibility, fire code, fire suppression, and security / crime prevention items. Egress, hazardous materials, mold, new code requirements, security and crime prevention items. 5/20/2010 Conveying Passenger elevator in good condition. Freight elevator in satisfactory condition. Equipment and Furnishings Building Profile Kitchen equipment serves the second floor cafeteria. A loading dock provides direct access to the kitchen. IIIA - 27 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Student Health Center 285-0L-0048 Administration 1957 7,874 Floors GSF 11,573 GPR 100 % AG UG 1 1 PR CENTRAL UTILITY CONNECTIONS CW HPS F 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING vii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The Student Health Center is located on North Campus. Window replacement scheduled for summer of 2010. Roof replaced in 2008. Re-grading and landscaping revised in 2009. Building interiors at the main entrance were updated in 2007. Powered door operators are worn. Occupant(s) and Use(s) The Student Health Center houses all health services. Mechanical Functionality Assessment The location of the Student Health Center is at the northern most point of Main/North campus. This is often considered inconvenient for freshman and sophomores living on Main Campus. Other Building Issues Future Building Plans Fire alarm system is outdated. System in satisfactory condition. Plumbing In working order. The Campus Master Plan has identified potential new locations for the Student Health Center including the Sports and Fitness Center or the Memorial Student Center. 5/20/2010 Electrical Communication The basement is not occupied due to health related building issues. Code and Health/Safety Systems in satisfactory condition. Conveying None. Equipment and Furnishings Building Profile IIIA - 28 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF University Services 285-0L-0091 Administration 1988 31,052 Floors GSF 39,846 GPR 100 % AG UG 2 0 PR CENTRAL UTILITY CONNECTIONS CW HPS B 2011-17 ELEC FIBER C. AIR N. GAS 0 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING ii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The University Services building is located on the west side of Broadway Street/Highway 25. Building envelope in good condition. Major settlement of sub surface and pavement occurring around the west and south side of the building. Powered door operators require replacement. Occupant(s) and Use(s) The University Services building currently houses Health and Safety; Procurement and Materials Management; Police and Parking Services; Printing; Mail Services; and University Stores. Functionality Assessment Mechanical Mechanical systems at capacity. Electrical Electrical system at capacity. Fire Alarm replaced in 2009. This building adequately accommodates functions. Communication Other Building Issues At capacity. None Plumbing Future Building Plans In good working order. Sanitary building lateral replaced in 2008. There are no major project building plans at this time. Code and Health/Safety Conveying No sprinkler system in building. Halon system in hazardous waste storage area. 5/20/2010 None Equipment and Furnishings Building Profile IIIA - 29 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Antrim Hall 285-0L-0067A Residence 1966 - 16,870 GSF Floors 28,771 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Antrim Hall was originally designed and constructed for student residents in 1966 and was named after Sara Antrim who was the director of the women’s physical education program from 1936 to 1964. Antrim connects to McCalmont Hall and Froggatt Hall. It was an addition that was intended to provide a common front desk to McCalmont and Froggatt. Antrim roof was replaced in July of 2007. Antrim building envelope in satisfactory condition. Roof replaced in 2007. Interiors are in fair condition. Doors, hardware and power operated openers are outdated. Mechanical Original systems are outdated. Electrical Occupant(s) and Use(s) Original equipment is outdated. Transformers and medium voltage gear serves Antrim, Froggatt and CKTO. Emergency power by generator in Oetting of the CKTO complex. Antrim Hall contains 124 beds. Recreational, lounge, laundry and support services are also provided. Antrim is a First Year Experience Hall which houses the “Green” learning community. Communication Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety are outdated. Cabling to 5e standard. Plumbing Original system is outdated. Conveying None Other Building Issues The floor elevations of Antrim and Froggatt (1966) do not match the first floors of McCalmont. Equipment and Furnishings Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for Antrim and Froggatt Halls in the 2019-021 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants. Window replacement project summer 2010. Code and Health/Safety Building has ACM and some lead based paint throughout the facility. 5/20/2010 Building Profile IIIA - 30 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Callahan Hall 285-0L-0061B Residence 1958 - 11,524 GSF Floors 18,561 GPR 0 % AG UG 3 1 PR CENTRAL UTILITY CONNECTIONS CW HPS F 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING vii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Callahan Hall was originally designed and constructed for student residents. The building was named after Gertrude Callahan who served as Stout’s Chair of the English Department. Callahan Hall is a part of the Jeter-TainterCallahan residence hall complex that is located on Lake Menomin. Building envelope in poor condition. Interiors in poor condition. Mechanical Original systems with high maintenance activities. Electrical Occupant(s) and Use(s) Callahan Hall contains 65 beds. Recreational, lounge, laundry and support services are also provided. Callahan houses primarily sophomore students in single rooms. Original systems with panels at capacity. High maintenance issues. Communication Standard 5e cabling with facility. Functionality Assessment Following an assessment of the viability of the JTC complex, it was determined that the building elevations created ADA compliance problems and that in the long term the complex should be demolished instead of renovated. MEP capacity of the building is also a major functional issue that would need to be addressed if renovation were to be considered, which it is not. Plumbing Original systems and require high maintenance. Conveying None Equipment and Furnishings Other Building Issues Elevations between Tainter and Callahan create problems for accessibility and compliance with ADA regulations. Future Building Plans Callahan Hall is one building in the Jeter-Tainter-Callahan (JTC) complex on North Campus. Demolition of JTC is proposed following completion of the Fleming Hall Renovation project in the fall of 2012. Code and Health/Safety Building contains various forms of acm and no lead based paint. 5/20/2010 Building Profile IIIA - 31 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Chinnock Hall 285-0L-0068C Residence 1969 - 14,330 GSF Floors 26,616 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Chinnock Hall was originally designed and constructed for student residents. Chinnock Hall was an addition that was added to the halls or cubes that comprise Hanson, Miles and Keith Halls in 1969. HKM halls were constructed three years earlier in 1966. Occupant(s) and Use(s) Building envelope in satisfactory condition. Roofing replaced in 1998. Windows are outdated. Building interiors are in fair condition. Doors, hardware, and power operated openers are outdated. Mechanical Original systems and outdated. Chinnock Hall contains 118 beds. Recreational, lounge, laundry and support services are also provided. Chinnock is a First Year Experience Hall and houses the Art and Design Learning Community. Functionality Assessment All wall, floor and ceiling finishes outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Electrical Original systems and require replacement. Emergency power from CKTO. Fire alarm requires replacement. Communication Standard 53 cabling within building. Plumbing Original and outdated. Conveying Other Building Issues Interior of stairwells are constructed with structural glazed masonry tile. There might be asbestos under the carpeted areas. The water service is not large enough to supply a fire sprinkler system. None Equipment and Furnishings Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for the HKMC (Hansen/Keith/Milnes/Chinnock) residence hall complex in the 2021-23 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. .The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants. Code and Health/Safety Building has various forms of acm and no lead based paint. 5/20/2010 Building Profile IIIA - 32 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Curran Hall 285-0L-0069 Residence 1966 - 16,536 GSF Floors 26,360 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Curran Hall was originally designed and constructed for student residents. Curran Hall was named after Fredrick Curran who was the supervisor of the industrial education student teachers. The original block of Curran, Kranzusch and Tustison was constructed in 1966. Oetting was added to this complex in 1969 along with a similar addition to HKMC. No major additions have been occurred since 1969. Occupant(s) and Use(s) Curran Hall contains 128 beds. Curran houses freshman students as a part of the First Year Experience and houses the community service learning community. Recreational, lounge, laundry and support services are also provided. Building envelope in satisfactory condition. Roofing replaced in 2004. Windows are outdated. Building interiors are in fair condition. Doors, hardware and power operator are outdated. Mechanical Original systems are outdated. Electrical Original systems are outdated. Emergency power by generator in Oetting at a part of the CKTO complex. Communication Communications 5e cabling. Defined MDF room required. Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Other Building Issues Plumbing Original systems within building are outdated. New gas water heater for summer occupancy. Shared water service with Antrim Froggat. New building service required to minimize building outages during water shut downs. Conveying None None Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for the CKTO (Curran/Kranzusch/Tustison/Oetting) residence hall complex in the 2017-19 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. . The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants. Equipment and Furnishings Code and Health/Safety Building has acm and some lead based paint throughout the facility. 5/20/2010 Building Profile IIIA - 33 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Fleming Hall 285-0L-0066 Residence 1952 - 25,298 GSF Floors 40,298 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Fleming Hall, located on North Campus, was originally designed and constructed in 1961 for student residents. It was named after Thomas Fleming, Stout’s former Director of Public Relations. No major additions have been added to the building. Occupant(s) and Use(s) Building envelope in satisfactory condition. Roofing replaced in 2005. Windows are outdated. Building interiors are in fair condition. Doors, hardware and power operator are outdated. Mechanical Original systems are outdated. Fleming Hall contains 198 beds and houses primarily sophomore students. Recreational, lounge, laundry and support services are also provided Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Other Building Issues Minor work is currently (2010) be done to connect Fleming Hall with Hovlid Hall. The synergy of this connection will create a common front desk for the two buildings. Asbestos floor tile is likely below the carpeted areas. Electrical Original systems are outdated. Communication Cabling complies with the standards of 5e cabling. Plumbing Original systems within building are outdated. Electric water heater for summer occupancy. Conveying None Equipment and Furnishings Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for Fleming Hall in the 2011-13 biennium. Fleming Hall is project one of phase one of the renewal program. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. Code and Health/Safety Building has acm containing materials throughout and no lead based paint. 5/20/2010 Building Profile IIIA - 34 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Froggatt Hall 285-0L-0067B Residence 1966 - 13,834 GSF Floors 23,592 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Froggatt Hall was originally designed and constructed for student residents. Froggatt was named after Stout’s head librarian, Lillian Froggatt, who served in that capacity for 32 years. The Antrim-Froggatt addition was intended to provide a common front desk for the Antrim-Froggatt-McCalmont residence hall complex. Occupant(s) and Use(s) Froggatt Hall contains 128 beds. Froggatt Hall is a First Year Experience Residence Hall and houses the Green and Honors learning communities. Recreational, lounge, laundry and support services are also provided. Building envelope in satisfactory condition. Roof replaced in 2007. Interiors are in fair condition. Doors, hardware and power operated openers are outdated. Mechanical Original systems are outdated. Electrical Original systems are outdated. Main distribution for Antrim, Froggatt and CKTO. Emergency power from generator located in Oetting hall apart of CKTO complex. Communication Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Cabling to 5e standard. Plumbing Original and outdated. Conveying None Other Building Issues The floor elevations of Antrim and Froggatt (1966) do not match the first floors of McCalmont Equipment and Furnishings Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for Antrim and Froggatt Halls in the 2019-21 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants Code and Health/Safety Building contains various types of acm materials. 5/20/2010 Building Profile IIIA - 35 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Hansen Hall 285-0L-0068 Residence 1965 - 15,944 GSF Floors 26,166 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Hansen Hall was originally designed and constructed in 1966 for student residents. Hansen Hall was one of three cubes that comprise Hansen-Keith-Miles Halls; Chinnock was later added as an addition. It was named after H.M Hansen, a pioneer in building trades and a Stout instructor. Occupant(s) and Use(s) Building envelope in satisfactory condition. Roofing replaced in 1998. Windows are outdated. Building interiors are in fair condition. Doors, hardware and power operator are outdated. Mechanical Original systems are outdated. Hansen Hall contains 128 beds. Recreational, lounge, laundry and support services are also provided. Hansen if a First Year Experience hall that housing the Global learning community. Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Electrical Original system are outdated. Emergency power supplied by generator in Oetting apart of the CKTO complex. Communication Cabling meets standard 5e requirements. Plumbing Original systems are outdated. Conveying Other Building Issues None None Equipment and Furnishings Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for the HKMC (Hansen/Keith/Milnes/Chinnock) residence hall complex in the 2021-23 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants Code and Health/Safety Building has various forms of acm and no lead based paint. 5/20/2010 Building Profile IIIA - 36 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Hovlid Hall 285-0L-0065 Residence 1959 2010 28,322 GSF Floors 41,611 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS A 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING i Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Hovlid Hall was originally designed and constructed for student residents in 1959. The building was named after Leonard Hovlid who attended the Stout institute and grew up in Menomonie. The building envelope; masonry re-tuck pointed, the replacement of windows and roof was completes in 2010. Building envelope is in good condition. Building interiors received all new finishes and casework, reconfiguration of the toilet rooms, director’s suite, and the basement. Two designated ADA rooms, gender neutral rest rooms on each floor and a connection link to Fleming Hall and the Hovlid dining hall added in 2010. Occupant(s) and Use(s) Hovlid Hall contains 190 beds and houses primarily sophomore students. Mechanical Functionality Assessment Hovlid Hall was renovated in 2009-10. All wall, floor and ceiling finishes were replaced; interior doors and hardware were replaced; and the building mechanical, electrical and plumbing infrastructures were upgraded, including all new bathrooms. New windows were also installed and a new roof put on the building. The mechanical systems were replaced in 2010. Steam/condensate service to building replaced. The hall director apartment and connecting link added air conditioning. A/C system tapped off of by Hovlid dinning addition system. Electrical Other Building Issues Building electrical systems, fire alarm system, site lighting replaced in 2010. Emergency generator added to the facility. Communication Future Building Plans As a part of the renovation, Hovlid Hall was connected to Fleming Hall by an addition that combined service desks and mail counters. There is a similar desire to connect Hovlid Hall to Wigen Hall to the north and could become a consideration in the renewal plan for Wigen Hall. Hovlid Hall is also connected to the new dining facility via the Hovlid/Fleming addition. Code and Health/Safety Plumbing All plumbing systems replaced in 2010, except for the existing roof drains which are in good shape. Building main lateral new for facility. Conveying Facility constructed to IBC code 2006 code. Existing building type is equivalent to current Type IIA construction classification. Fire partitions and barrier (existing stairs, corridors and unit separation) are not noted/required as they are existing construction and this is not a change in use. Building has fire protection system included which is not required by code. Carbon monoxide dection system at gas operated equipment within building. Eye wash station added in janitor closets. Underground (abandoned in place) fuel tank removed in 2009 5/20/2010 All communications systems replaced in 2010. Wireless added to the facility. North campus hub located in building. Building added an elevator in 2010. Equipment and Furnishings Building Profile All residence room furniture, lounge, kitchen furniture was replaced in 2010. All moveable equipment was replaced in 2010. IIIA - 37 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF North Point Dining and Fitness Center 285-0L-0065A Residence 2010 - 9,870 GSF Floors 29,088 GPR 0 % AG UG 0 2 PR CENTRAL UTILITY CONNECTIONS CW HPS A 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING i Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural The North Point Dining and Fitness Center was originally designed and constructed for dining, convenience store and fitness center for student residents on North Campus. It opened in fall 2010. Constructed in 2009-2010. Natural day lighting, energy efficient building products used in the construction of facility. Mechanical New systems in August 2010. conditioning in building. Occupant(s) and Use(s) The North Point Dining and Fitness Center contains dining, food preparation, convenience store and fitness center facilities. Building support service space is also provided. Functionality Assessment Electrical New service in August2010. Communication Building occupied in fall 2010. New system in August 2010. Other Building Issues Plumbing None New system in August 2010. Future Building Plans Conveying None Passenger elevator new in August 2010. Code and Health/Safety Facility constructed to IBC code 2006 code. Building has fire protection system included which is not required by this code. Existing building type is equivalent to current Type IIA construction classification. 5/20/2010 Heat recovery and Air Equipment and Furnishings Building Profile New equipment and furnishings installed in August 2010. IIIA - 38 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Jeter Hall 285-0L-0061A Residence 1958 - 11,626 GSF Floors 18,771 GPR 0 % AG UG 3 1 PR CENTRAL UTILITY CONNECTIONS CW HPS F 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING vii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Jeter Hall was originally designed and constructed for student residents. Jeter Hall was named after Lillian Jeter who was the supervisor for student teachers in home economics. Jeter Hall is a part of the Jeter-Tainter-Callahan residence hall complex that is located on Lake Menomin. Occupant(s) and Use(s) Jeter Hall contains 68 beds. Recreational, lounge, laundry and support services are also provided. Jeter Hall houses primarily sophomore students in single rooms. Building envelope in poor condition. Interiors in poor condition. Mechanical Original systems with high maintenance activities. Electrical Original systems with panels at capacity. High maintenance issues. Communication Functionality Assessment Following an assessment of the viability of the JTC complex, it was determined that the building elevations created ADA compliance problems and that, in the long term, the complex should be demolished instead of renovated. MEP capacity of the building is also a major functional issue that would need to be addressed if renovation were to be considered. Other Building Issues Elevations between Jeter and Tainter create problems for accessibility and compliance with ADA regulations. Standard 5e cabling with facility. Plumbing Original systems and require high maintenance. Conveying None Equipment and Furnishings Future Building Plans Jeter Hall is scheduled to be demolished in 2012 following the completion of the Fleming Hall Renovation project. Code and Health/Safety Building contains various forms of acm and no lead based paint, except on a tan metal roof. 5/20/2010 Building Profile IIIA - 39 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Keith Hall 285-0L-0068A Residence 1965 - 14,052 GSF Floors 24,023 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Keith Hall was originally designed and constructed in 1966 for student residents. Keith Hall was named after Floyd Keith who served as the chair of the metals department for many years. Keith Hall is one of three cubes that comprise Hansen-Keith-Miles Halls; Chinnock was added as an addition in 1969. Building envelope in satisfactory condition. Roofing replaced in 1998. Windows are outdated. Building interiors are in fair condition. Doors, hardware, and power operated openers are outdated. Mechanical Original systems are outdated. Occupant(s) and Use(s) Keith Hall contains 112 beds. Keith Hall houses freshman students as a part of the freshman year experience program and has a Global learning community. Recreational, lounge, laundry and support services are also provided. Electrical Original systems and outdated. Emergency power from CKTO. Fire alarm outdated. Communication Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Standard 5e cabling system. Plumbing Original systems and outdated. Conveying None Other Building Issues None Equipment and Furnishings Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for the HKMC (Hansen/Keith/Milnes/Chinnock) residence hall complex in the 2021-23 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. .The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants. Code and Health/Safety Building has various forms of acm and no lead based paint. 5/20/2010 Building Profile IIIA - 40 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Kranzusch Hall 285-0L-0069A Residence 1966 - 14,028 GSF Floors 27,804 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Kranzusch Hall was originally designed and constructed for student residents. Kranzusch Hall was named after Ray Kranzusch who worked for 40 years in Stout’s industrial arts program. The original block of Curran, Kranzusch and Tustison was constructed in 1966. Oetting was added to this complex in 1969 along with a similar addition to HKMC. No major additions have occurred since 1969. Occupant(s) and Use(s) Kranzusch Hall contains 112 beds. Kranzusch Hall houses freshman students as a part of the First Year Experience Program. Recreational, lounge, laundry and support services are also provided. Building envelope in satisfactory condition. Roofing replaced in 2004. Windows are outdated. Building interiors are in fair condition. Doors, hardware and power operator are outdated. Mechanical Original systems and outdated. Electrical Original systems and outdated. Main service located in AF and connects to CKTO. Emergency power by generator in Oetting apart of the CKTO complex. Communication Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Plumbing Original systems and outdated. Conveying None Other Building Issues None Equipment and Furnishings Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for the CKTO (Curran/Kranzusch/Tustison/Oetting) residence hall complex in the 2017-19 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants. Code and Health/Safety Building has acm and some lead based paint throughout the facility. 5/20/2010 Building Profile IIIA - 41 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Milnes Hall 285-0L-0068B Residence 1965 - 16,265 GSF Floors 25,244 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Mechanical Milnes Hall was originally designed and constructed for student residents in 1966. Milnes was one of three cubes that comprise Hansen-Keith-Miles Halls; Chinnock was later added as an addition in 1969. Occupant(s) and Use(s) Milnes Hall contains 124 beds. Milnes Hall houses freshman students as a part of the First Year Experience program. Recreational, lounge, laundry and support services are also provided. Original systems and outdated. Electrical Original systems and outdated. Emergency power from Oetting halls apart of the CKTO. Fire alarm is outdated. Communication Cabling meets standard 5e requirements. Plumbing Original systems and outdated. Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety are outdated. Conveying None Equipment and Furnishings Other Building Issues None Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for the HKMC (Hansen/Keith/Milnes/Chinnock) residence hall complex in the 2021-23 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. .The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants. Code and Health/Safety Building has various forms of acm and no lead based paint. Architectural Building envelope in satisfactory condition. Roofing replaced in 1998. Windows are outdated. Building interiors are in fair condition. Doors, hardware and power operator are outdated. 5/20/2010 Building Profile IIIA - 42 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF North Hall 285-0L-0072 Residence 1967 - 43,874 GSF Floors 76,136 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural North Hall was originally designed and constructed for student residents. The residence hall was constructed in 1967 without any major subsequent additions other than an elevator addition in 1997. In 2007, an ADA remodeling project focused on the bathrooms was completed. In 2008 hall director’s apartment was completed. Building envelope in satisfactory condition. Roof replaced in cube A in 2005 and the remaining building in 2007. Doors, hardware, power operated operators are outdated. Interior walls in good conditions. Mechanical Original and outdated. Occupant(s) and Use(s) North Hall contains 371 beds. Recreational, lounge, laundry and support services are also provided. North Hall contains upper class students and is the home to the diversity focused learning community. Many of the residence hall students with disabilities live in this building. Electrical Original system outdated. Emergency generator installed in 2009, transfer switches installed. Communication Cabling is standard 5e and should be upgrade when the building is remodeled. Currently hub for Main Campus residence halls. Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Plumbing Original systems are outdated. Conveying Other Building Issues North Hall houses the technology core for the residence halls and for Student Life Services. Good working condition. Equipment and Furnishings Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for North Hall in the 2013-15 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. .The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants. Code and Health/Safety A portion of the building has had the acm abated. No lead based paint with in building. 5/20/2010 Building Profile IIIA - 43 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Oetting Hall 285-0L-0069C Residence 1969 - 13,737 GSF Floors 23,555 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Oetting Hall was originally designed and constructed for student residents. Oetting Hall was named after Erich Oetting who was the first dean of the school of education. The original block of Curran, Kranzusch and Tustison was constructed in 1966. Oetting was added to this complex in 1969 along with a similar addition to HKMC. No major additions have been occurred since 1969. Occupant(s) and Use(s) Oetting Hall contains 118 beds. Oetting houses freshman students as a part of the First Year Experience program. The Science and Engineering learning community is located there. Recreational, lounge, laundry and support services are also provided. Building envelope in satisfactory condition. Roofing replaced in 2004. Windows outdated. Building interiors are in fair condition. Doors, hardware and power operator are outdated. Mechanical Original systems and outdated. Electrical Original systems and outdated. Emergency generator provides service to the following building; CKTO, HKMC and AF. Communication Cabling complies with the standards of 5e cabling. Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Other Building Issues Plumbing Original systems and outdated. Conveying None Equipment and Furnishings None Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for the CKTO (Curran/Kranzusch/Tustison/Oetting) residence hall complex in the 2017-19 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants. Code and Health/Safety Building has acm and some lead based paint throughout the facility. 5/20/2010 Building Profile IIIA - 44 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Red Cedar Hall 285-0L-0063 Residence 2005 - 73,229 GSF Floors 119,439 GPR 0 % AG UG 6 1 PR CENTRAL UTILITY CONNECTIONS CW HPS A 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING i Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Red Cedar Hall was originally designed and constructed for student residents. Red Cedar Hall opened in the fall of 2005. It is a suite-style building, with each suite containing either 3 or 4 single bedrooms, a living area, kitchenette, and bathroom facilities consisting of a shower room separated from a toilet room and two sinks. Red Cedar was built at a cost of $16.7 million dollars. Building envelope and interiors are in excellent shape. Loading dock at facility. Mechanical Good working order. Electrical Good working order. Occupant(s) and Use(s) Red Cedar Hall contains 296 beds. Red Cedar houses primarily upper class students. Recreational, lounge, laundry and support services are also provided. The building has two elevators and is the only air conditioned hall at Stout. Each floor has a floor lounge and kitchen. Communication Cat 6 and in good working order. Plumbing Majority of systems in good working order. Hot water circulation system has had spermatic leaks, two per year since 2005. Functionality Assessment Building adequately accommodates functions. Conveying Other Building Issues Red Cedar was featured in the 2006 Architectural Portfolio and received a post-secondary citation. Two elevators are in good working order. Equipment and Furnishings All equipment and furnishings in good condition. Future Building Plans No future project work is considered at this time. Code and Health/Safety Building to have non acm materials with in facility. 5/20/2010 Building Profile IIIA - 45 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF South Hall 285-0L-0073 Residence 1967 - 44,791 GSF Floors 75,844 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural South Hall was originally designed and constructed for student residents. The residence hall was constructed in 1967 without any major subsequent additions. Occupant(s) and Use(s) Building envelope in satisfactory condition. Roof replaced in 1993. Interiors are in fair condition. Doors, hardware, power door operators outdated. Finishes are outdated. Mechanical South Hall contains 365 beds. Recreational, lounge, laundry and support services are also provided. South Hall is the home to first year experience students and houses the Stoutward Bound learning community. Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Other Building Issues Original systems and outdated. Electrical Original system and outdated. Emergency generator installed in 2009. Communication Cabling standard is 5e. Plumbing Original and outdated. Conveying None None. Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for South Hall in the 2015-17 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants. Equipment and Furnishings Code and Health/Safety Portions of building have been abated. Lead based paint is in areas within building. 5/20/2010 Building Profile IIIA - 46 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Tainter Hall 285-0L-0061 Residence 1952 - 25,342 GSF Floors 40,347 GPR 0 % AG UG 3 1 PR CENTRAL UTILITY CONNECTIONS CW HPS F 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING vii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Tainter Hall was originally designed and constructed for student residents. The building was named after Andrew Tainter who partnered with James Huff Stout in the lumber business. Tainter is a part of the Jeter/Tainter/Callahan (JTC) residential complex located on Lake Menomin. Occupant(s) and Use(s) Tainter Hall contains 136 beds. Recreational, lounge, laundry and support services are also provided. Tainter Hall houses primarily sophomore students in double and single rooms. Tainter Hall also contains the residential food service and dining facility on the ground level. Functionality Assessment Following an assessment of the viability of the JTC complex, it was determined that the building elevations created ADA compliance problems and that in the long term, the complex should be demolished instead of renovated. MEP capacity of the building is also a major functional issue that would need to be addressed if renovation were to be considered. Building envelope in poor condition. Interiors in poor condition. Mechanical Original systems with high maintenance activities. Electrical Original systems with panels at capacity. High maintenance issues. Communication Standard 5e cabling with facility. Plumbing Original systems and require high maintenance. Conveying None Equipment and Furnishings Other Building Issues Elevations between Jeter, Tainter and Callahan create problems for accessibility and compliance with ADA regulations. Future Building Plans Tainter Hall is scheduled to be demolished in 2013 following the completion of the North Campus Residence Hall renewal project. Code and Health/Safety Building has various types of acm and no lead based paint. 5/20/2010 Building Profile IIIA - 47 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Tainter Hall Dining 285-0L-0061C Residence 1962 - 6,998 GSF Floors 8,441 GPR 0 % AG UG 0 1 PR CENTRAL UTILITY CONNECTIONS CW HPS F 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING vii Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Tainter Hall Dining was originally designed and constructed for student residents. The building was named after Andrew Tainter who partnered with James Huff Stout in the lumber business. Tainter is a part of the Jeter/Tainter/Callahan (JTC) residential complex located on Lake Menomin. Building envelope and interiors on poor condition. Mechanical Original systems with high maintenance issues. Electrical Occupant(s) and Use(s) Original systems with systems at capacity. Tainter Hall Dining contains a dining hall and kitchen. Communication Functionality Assessment Following an assessment of the viability of the JTC complex, it was determined that building elevations created ADA compliance problems and that in the long term, the complex should be demolished instead of renovated. MEP capacity of the building is also a major functional issue that would need to be addressed if renovation were to be considered. Cabling at standard 5e. Plumbing Original systems with high maintenance issues. annual flushing of waste system serving kitchen. Semi- Conveying None Other Building Issues Elevations between Jeter, Tainter and Callahan create problems for accessibility and compliance with ADA regulations Equipment and Furnishings Future Building Plans Tainter Hall is one building scheduled to be demolished in 2013 following the completion of the North Campus Residence Hall renewal project Code and Health/Safety Building has various forms of acm and no lead based paint. 5/20/2010 Building Profile IIIA - 48 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Tustison Hall 285-0L-0069B Residence 1966 - 15,134 GSF Floors 26,755 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Tustison Hall was originally designed and constructed for student residents. Tustison Hall was named after Francis Tustison who was credited with developing the four-year program in physics and mathematics at Stout. The original block of Curran, Kranzusch and Tustison was constructed in 1966. Oetting was added to this complex in 1969 along with a similar addition to HKMC. An elevator was added to the building in the 1990s. No other major additions have been occurred since. Building envelope in satisfactory condition. Roofing replaced in 2004. Windows outdated. Building interiors are in fair condition. Doors, hardware and power operator are outdated. Mechanical Original systems and outdated. Electrical Original systems and outdated. generator in Oetting. Occupant(s) and Use(s) Tustison Hall contains 124 beds. Tustison Hall houses freshman students as a part of the First Year Experience program. Recreational, lounge, laundry and support services are also provided. Emergency power by Communication Communications 5e cabling. Defined MDF room required. Plumbing Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Original systems within building are outdated. New gas water heater for summer occupancy. Shared water service with Antrim Froggat. New building service required to minimize building outages during water shut downs. Conveying None Other Building Issues None Equipment and Furnishings Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for the CKTO (Curran/Kranzusch/Tustison/Oetting) residence hall complex in the 2017-19 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. The study suggests moving the bathrooms outside of the building footprint. The existing bathrooms will be demolished and replaced with common space for the occupants. Code and Health/Safety Building has acm and some lead based paint throughout the facility. 5/20/2010 Building Profile IIIA - 49 UW-Stout Campus Physical Development Plan Building Name Building No. Building Type Constructed Addition(s) ASF Wigen Hall 285-0L-0064 Residence 1970 - 27,499 GSF Floors 44,125 GPR 0 % AG UG 4 1 PR CENTRAL UTILITY CONNECTIONS CW HPS D 2011-17 ELEC FIBER C. AIR N. GAS 100 % HISTORICAL WATER SEWER US WI FUNCTIONAL RATING PHYSICAL RATING v Building Profile ratings based on the Postsecondary Education Facilities Inventory and Classification Manual (FICM): 2006 Edition Background and History Architectural Wigen Hall, located on North Campus, was originally designed and constructed in 1970 for student residents. The building was named after Ray Wigen who was the Dean of the Graduate College from 1946 to 1966. No major additions or renovations have been added to the building. Occupant(s) and Use(s) Wigen Hall contains 241 beds and houses primarily sophomore students. Recreational, lounge, laundry and support services are also provided. Wigen Hall houses an honors floor. Functionality Assessment All wall, floor and ceiling finishes are outdated and deteriorating. All interior doors and hardware are deteriorating. The building infrastructure is deteriorating and all building systems, including HVAC, plumbing, electrical, telecommunications and life safety need to be replaced. Building envelop and interiors in fair condition. Card access to building entrances. Mechanical Original systems and outdated. Electrical Building electrical system original. In 2009, new medium voltage 5KVA, 600 amps, 3phase, non-fused switchgear installed. Rough conduit from Hovlid Hall for future connection to Hovlid emergency generator. Communication Communications systems comply with 5e cabling throughout building. TV cabling coaxial through facility. Emergency call and cashless vending system in place. Plumbing All systems have out lived the useful life and will continue to have failures. Back flow preventers required at HVAC equipment. Other Building Issues None Future Building Plans Following a Residence Hall Study completed in 2009, a major renovation project is proposed for Wigen Hall in the 2021-23 biennium. Renovation will include, but not limited to, systems infrastructure upgrade, restroom upgrades, improved ADA accessibility, window replacement and site utility modifications. A moderate maintenance facility upgrade will occur in 2010 to help Wigen Hall last until the major renovation in 2021. In 2011 a window replacement and rest room remodeling is scheduled. Conveying None. Equipment and Furnishings Code and Health/Safety Fire protection system is a riser to each floor, current capped. 5/20/2010 Building Profile IIIA - 50 UW-Stout Campus Physical Development Plan 2011-17 B. SITE DEVELOPMENT PROFILE Campus Master Plan Proposals: Gateways to identify main entrances to campus Installation of traffic calming devices at major pedestrian crosswalks on campus Landscaping fences and plantings Campus boundary expansion Campus Boundary Expansion: Twenty-Four (24) Properties Parking Main Campus Gateway Traffic Calming Campus Boundary Expansion: Forty (40) Properties Parking, Recreation and Athletics Main Campus Gateway Traffic Calming Nelson Field Lighting Main Campus Gateway Outdoor Track Track Replacement Lighting Traffic Calming North Campus Gateway Main Campus Gateway Potential Realignment of 2nd Street Parking Lot #11 Development Long Term: Paved Landscaping Ornamental Fencing Plantings Parking Lot #9 Development Long Term: Paved Main Campus Gateway Campus Boundary Expansion: Sixteen (16) Properties Parking Parking Lot #15 Development Long Term: Paved 5/20/2010 Site Development Profile IIIB - 1 UW-Stout Campus Physical Development Plan 2011-17 C. SITE UTILITY PROFILE Stormwater Retention Issues Southeast corner of Nelson Field has stormwater runoff from 5th Street East resulting in severe erosion Stormwater Retention Issues Heavy rains cause flooding into Memorial Student Center. Existing storm inlets are undersized for roof runoff Central Chilled Water Loop Phase II Millennium Hall Central Chilled Water Loop Phase III Connect Sports and Fitness Center to central chilled water loop and remove existing chillers and towers Final chilled water loop to be determined Sanitary Improvements Grease receptor at Merle M. Price Commons was installed in 1967 Stormwater Retention Issues Parking lot #14 (south of Millennium Hall) has existing storm inlets not connected to city storm main and water backs up and drains on parking lot surface 5/20/2010 Site Utility Profile IIIC - 1