SECTION 01270 MEASUREMENT AND PAYMENT PART 1 1.01 SECTION INCLUDES A. 1.02 GENERAL The work performed under this Agreement shall be paid for as described in Section 500, Article 5 based on the Bid Proposal and the Total Bid Price. All costs incurred shall comply with the provisions of these Specifications and shall be included in the Total Bid Price for the project. Except as may be otherwise stipulated, no material, labor or equipment will be furnished by the OWNER. The following provides a general listing of items of Work along with a brief summary of the work and materials included. Refer to the Specifications and Drawings for additional information and all requirements for each item of Work. ITEMS OF WORK 1. Mobilization No unit measurement for payment will be made for any of the work, materials and equipment required for mobilization. This work consists of the mobilization of personnel, equipment and supplies at the project site in preparation for work on the project. This item shall include the establishment of the CONTRACTOR’S offices, buildings and other necessary facilities, and all other costs incurred or labor and operations which must be performed prior to beginning the other items under the Contract. This item shall also include temporary fencing around project work areas, and any other fencing/security items as deemed necessary by the CONTRACTOR. Removal of the CONTRACTOR’s equipment, supplies, excess materials, and cleanup of the site are also included in this item. 2. Traffic Control No unit measurement for payment shall be made for any of the materials, work, and equipment required. The payment shall be total compensation for all labor, equipment, materials, maintenance, and all incidentals necessary to prepare, implement, and maintain the approved Traffic Control Plan in accordance with the Drawings and accepted Traffic Control Plan. 3. Surveying No unit measurement shall be made for this item. Work includes providing all equipment, labor, and materials required to provide Surveying for construction of all work items for the project including: Staking of horizontal and vertical alignments; overlot grading; subgrade elevations; off-sets; temporary control points; re-establishment of land monuments; and, all appurtenance features of the work. 4. Remove Turf Sod No unit measurement for payment shall be made for this item. The Total Bid Price shall include all of the CONTRACTOR’s cost of whatsoever nature to complete the turf sod removal: furnishing and transporting all materials, labor, and equipment; Werner Elem. 01270-1 Measurement and Payment excavation, removal disposal of sod; backfilling, grading and compacting; removal and/or moving of sprinkler equipment; and, all other related and necessary materials, work, and equipment required to perform the work in accordance with the Drawings and Specifications. 5. 6. Remove Concrete Remove Asphalt Speed Humps No unit measurement for payment shall be made for this item. The Total Bid Price shall include full compensation for sawing, removing, hauling and disposal of such items including existing cable/conduit, pipe, concrete, asphalt, and excavation and subsequent backfill with suitable material associated with the removal of these items, and all other work necessary to remove these items in accordance with the Drawings and Specifications. Replacement of asphalt; curb, gutter and sidewalk; storm sewer and pipe outside of the pay lines due to the CONTRACTOR’s failure to protect existing, undisturbed materials shall not be paid for and shall be replaced at the CONTRACTOR’s expense. 7. Remove Asphalt Pavement No unit measurement for payment shall be made for this item. The Total Bid Price shall include full compensation for sawing, removing, hauling and disposal of such items including existing cable/conduit, pipe, concrete, asphalt, and excavation and subsequent backfill with suitable material associated with the removal of these items, and all other work necessary to remove these items in accordance with the Drawings and Specifications. Replacement of asphalt; curb, gutter and sidewalk; storm sewer and pipe outside of the pay lines due to the CONTRACTOR’s failure to protect existing, undisturbed materials shall not be paid for and shall be replaced at the CONTRACTOR’s expense. 8. Concrete Speed Humps No unit measurement for payment shall be made for this item. No payment will be made for items placed outside of the dimensions as shown on the Drawings unless directed by the ENGINEER OWNER. The Total Bid Price shall include all of the CONTRACTOR’s costs of whatsoever nature associated with Concrete Speed Humps. The price bid shall include: furnishing and placing the concrete; forming; furnishing and applying curing compounds; finishing the edging the concrete surfaces; joints and joint materials; furnishing and compacting all materials required for preparation of a stable subbase; backfilling; curb painting; and all other related and necessary materials, work, and equipment required to construct the concrete curb and gutter in accordance with the Drawings and Specifications. No payment shall be made for replacement of materials damaged by the CONTRACTOR in his operations. 9. Vertical Curb and Gutter No unit measurement for payment shall be made for this item. No payment will be made for items placed outside of the dimensions as shown on the Drawings unless directed by the ENGINEER OWNER. The Total Bid Price shall include all of the CONTRACTOR’s costs of whatsoever nature associated with Vertical Curb and Gutter. The price bid shall include: furnishing and placing the concrete; forming; Werner Elem. 01270-2 Measurement and Payment furnishing and applying curing compounds; finishing the edging the concrete surfaces; joints and joint materials; furnishing and compacting all materials required for preparation of a stable subbase; backfilling; curb painting; and all other related and necessary materials, work, and equipment required to construct the concrete curb and gutter in accordance with the Drawings and Specifications. No payment shall be made for replacement of materials damaged by the CONTRACTOR in his operations. 10. 11. 12. Concrete Drain Pans (4-ft wide), Apron and Transition Concrete Drain Pan (3.5-ft wide) Concrete Drain Pan (6-ft wide), Apron and Ramp Transition No unit measurement for payment shall be made for this item. No payment will be made for items placed outside of the dimensions as shown on the Drawings unless directed by the ENGINEER OWNER. The Total Bid Price shall include all of the CONTRACTOR’s costs of whatsoever nature associated with Concrete Drain Pan, Apron and Ramp Transition. The price bid shall include: furnishing and placing the concrete; forming; furnishing coloring; furnishing expansion joints; furnishing and applying the curing compounds; sawcutting existing concrete as required; sawcutting control joints; finishing and edging the concrete surface; furnishing and compacting all materials required for preparation of a stable subbase; backfilling; and, all other related and necessary materials, work, and equipment required to construct the concrete pan in accordance with the Drawings and Specifications. 13. Concrete Sidewalk No unit measurement for payment shall be made for this item. Payment will be made as work progresses. No payment will be made for items placed outside of the dimensions as shown on the Drawings unless directed by the ENGINEER OWNER. The Total Bid Price shall include all of the CONTRACTOR’s costs of whatsoever nature associated with Concrete Sidewalk. The price bid shall include: furnishing and placing the concrete; forming; furnishing and applying curing compounds; finishing the edging the concrete surfaces; joints and joint materials; furnishing and compacting all materials required for preparation of a stable subbase; backfilling; and, all other related and necessary materials, work, and equipment required to construct the concrete flatwork in accordance with the Drawings and Specifications. No measurement for payment shall be made for replacement of materials damaged by the CONTRACTOR in his operations. 14. Aggregate Base Course No unit measurement for payment shall be made for this item. The Total Bid Price shall include full compensation for furnishing all labor, materials, equipment, and incidentals and for doing all work involved in Aggregate Base Course, complete-inplace, including supplying, placing and compacting aggregate base course at proper moisture in accordance with the Drawings and Specifications or as otherwise directed by the ENGINEER. 15. Hot Bituminous Pavement-Grades S and SX (including striping) No unit measurement for payment shall be made for this item. The Total Bid Price shall include full compensation for furnishing all labor, materials, equipment, and Werner Elem. 01270-3 Measurement and Payment any other incidentals to Hot Bituminous Pavement-Grade S and SX in accordance with the Contract Documents, complete-in-place; haul from the suppliers source; placement of pavement to design dimensions; subgrade preparation, excavation and embankment, including that required for Aggregate Base Course and Fly Ash installation; placement; compaction; striping; striping on concrete pavement; and, any other miscellaneous items and work shown or reasonably implied on the Drawings and in the Specifications for this work, and elsewhere in the Contract Documents. 16. Fly Ash Stabilization No unit measurement for payment shall be made for this item. The Lump Sum Bid Price for Fly Ash Stabilization shall include full compensation for furnishing all labor, materials, equipment, and incidentals and for placement, amendment, compaction, and all incidental work involved in Fly Ash Stabilization complete-inplace, including supplying and placing this item in accordance with the Drawings and Specifications or as otherwise directed by the ENGINEER OWNER. 17. 18. Rock Socks Straw Wattles No unit measurement for payment shall be made for this item. The Total Bid Price shall include all of the contractor’s costs of whatsoever nature required for supplying, installing, maintaining, removing the erosion control BMPs (filters, rock socks, wattles, etc.), and all other related and necessary materials, work, and equipment required to install erosion control BMPs in accordance with the Drawings and Specifications. 19. Playground Equipment - Remove and Replace Basketball and Tetherball Poles and Benches No unit measurement for payment shall be made for this item. The Total Bid Price shall include all of the CONTRACTOR’S costs of whatsoever nature. The bid price shall include; removal, storage, excavation; backfill; concrete pole and bench leg base; steel reinforcing; testing, asphalt patching and all other related and necessary materials, work, and equipment required to remove and reinstall playground poles and metal benches in accordance with the Drawings and Specifications. No measurement for payment shall be made for the replacement of materials damaged by the CONTRACTOR outside of this operation. Existing basketball and tetherball posts shall be reinstalled to the same height to rim and top, respectively, as they had at removal. 20. Signage – Handicap Parking Signs No unit measurement for payment shall be made for this item. The Total Bid Price shall include all of the CONTRACTOR’s cost of whatsoever nature to complete the sign installation including: furnishing and transporting all materials, labor, and equipment; furnishing and installing new signs; backfilling and compaction topsoil replacement; and, all other related and necessary materials, work, and equipment required to perform the work in accordance with the Drawings and Specifications. END OF SECTION Werner Elem. 01270-4 Measurement and Payment